Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

cooling tower annual audit process by John A. Herbert

784 views

Published on

emsd cooling tower annual audit by John A. Herbert

Published in: Business
  • My brother found Custom Writing Service ⇒ www.HelpWriting.net ⇐ and ordered a couple of works. Their customer service is outstanding, never left a query unanswered.
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Don't forget another good way of simplifying your writing is using external resources (such as ⇒ www.WritePaper.info ⇐ ). This will definitely make your life more easier
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Writing a good research paper isn't easy and it's the fruit of hard work. For help you can check writing expert. Check out, please ⇒ www.HelpWriting.net ⇐ I think they are the best
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here

cooling tower annual audit process by John A. Herbert

  1. 1. EMSD COOLING TOWER AUDIT Hong Kong By John A. Herbert
  2. 2. Background There are approximately 9,000 cooling towers in Hong Kong. The EMSD Code of Practice forWater-cooled Air Conditioning Systems Part 2: Operation and Maintenance of CoolingTowers [ PDF link] requires an independent audit for Hong Kong CoolingTower installations.
  3. 3. Annual independent audits of operation and maintenance records of cooling tower systems shall be carried out by an independent and competent auditor. -- EMSD Code of Practice part 2, Jan 2007 edition, Clause 4.3.1
  4. 4. Annual Audit Procedure
  5. 5. CoolingTower Auditor Duties auditors to carry out the following tasks: a) Inspection on the validity of O&M manual, up-to-date water quality records, maintenance report and log book; b) Visual inspection of cooling tower system operating conditions; c) Risk and operational problem identification; d) Recommendation on remedial actions required; e) Preparation of audit report; f) Report and explain the conditions of the system to the system owner; and g) Submit annual audit report to EMSD.
  6. 6. On-site inspection
  7. 7. EMSD checking CoolingTowers EMSD conduct Legionella water sampling, and public notice for towers with excessive legionella are issued, refer to emsd website:
  8. 8. EMSD checking CoolingTowers http://www.emsd.gov.hk/filemanager/en/content_646/Building_List_CT_NN.pdf
  9. 9. Kelcroft E&M Limited unit 18, 5/F, Hope Sea Industrial Centre 26 Lam Hing Street Kowloon Bay, Hong Kong phone: +852 2335 9830 fax: +852 2335 9862 www.kelcroft.com.hk Kelcroft John A. Herbert BEAM Professional, REA

×