SlideShare a Scribd company logo
1 of 117
POWER HOLDING COMPANY OF NIGERIA PLC


NATIONAL CONTROL
      CENTRE
     OSOGBO
   GENERATION
       AND
  TRANSMISSION
 GRID OPERATIONS
                         2007
   (ANNUAL TECHNICAL REPORT)
                                ISSUED BY:
                       GENERAL MANAGER (S/O)

                    NATIONAL CONTROL CENTRE

                                    OSOGBO

                             FEBRUARY, 2008.


 Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
TABLE OF CONTENTS
                                                                               PAGES
   INTRODUCTION                                                                1

1.0 GRID OPERATIONS IN 2007                                                    1


   1.1   Hydrology and Lake Operation.                                         1
   1.2   Thermal Generation                                                    9
   1.3   Generation Ordering and Load Dispatching                              19
   1.4   Frequency Control                                                     19
   1.5   Voltage Control                                                       19
   1.6   Outage Planning                                                       22
   1.7   Energy Production                                                     29




2.0 CONSTRAINTS TO GRID OPERATIONS                                             41


   2.1 Constraints to Grid vis-a-vis System Communication                      41
   2.2 Generation Constraints                                                  49
   2.3 Transmission Constraints                                                49


3.0 REINFORCEMENT AND REHABILITATION OF
    NATIONAL GRID                                                              62

4.0 SYSTEM DISTURBANCES                                                        66

   4.1 Transmission System faults                                              66
   4.2 Generation System faults                                                66

5.0 ACCIDENTS AND MISHAPS                                                      66



6.0 CONCLUSIONS AND RECOMMENDATIONS                                            67



7.0 APPENDICES                                                                 71




                                (i)




   Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
NO.                   LIST OF TABLES                                                PAGE



1A.   HYDROLOGICAL SUMMARY                                                          3


1B    COMP. AVE.INFLOW AND TURB.DISCH.                                              6


2     AVERAGE MONTHLY MW AVAILABILITY                                               12


3     SUMMARY OF GENERATION CAPABILITIES OF PHCN POWER                              20
      STATIONS AS OPERATED IN 2007


4.    PHCN POWER SYSTEM FREQUENCY                                                   27


5A.   2007 OUTAGES STATISTICAL SUMMARY 330KV LINE                                   29


5B.   2006 OUTAGES STATISTICAL SUMMARY 330KV LINE                                   29


6A.   2007 OUTAGES STATISTICAL SUMMARY 132KV LINE                                   30


6B.   2006 OUTAGES STATISTICAL SUMMARY 132KV LINE                                   30


7.    ENERGY GENERATED (MWH)                                                        38


8.    HYDRO & THERMAL ENERGY GENERATED(MWH)                                         39


9.    ENERGY GENERATION & POWER CONSUMPTION RECORDS                                 43


10.   MONTHLY ENERGY BALANCE SUMMARY                                                46


11    ENERGY AVAILABLE FOR SALES PLUS DISTRIBUTION LOSSES
      IN EACH REGION (MW)                                                           47


12    TOTAL GAS CONSUMED                                                            48


13    COST OF GAS (NAIRA) AGAINST ENERGY GENERATED 2007                             49


14    OPERATING FUEL COST (NAIRA/KWh)                                               50


15    MONTHLY MAXIMUM DEMAND/GENERATION ANALYSIS (MWH)                              84


16    SYSTEM GENERATION PEAK LOAD (FORECAST & ACTUAL)                               85


17    SUMMARY OF OCCURRENCE MAXIMUM PEAK LOAD                                       86


18    SUMMARY OF SYSTEM DISTUBANCES                                                 107


19A   SUMMARY OF SYSTEM DISTUBANCES OF INTEGRATED GRID                              108


19B   SUMMARY OF GRID COLLAPSES                                                     109


19C   SUMMARY OF SYSTEM DISTURBANCES OF INTEGRATED GRID OPERATIONS                  110

                                         (ii)




      Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
NO.                        CHARTS                                                          PAGE

1.    KAINJI AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW                                    4

2.    KAINJI HYDROGRAPH                                                                    4

3.    JEBBA AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW                                     8

4.    JEBBA HYDROGRAPH                                                                     8

5.    SHIRORO AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW                                   9

6.    SHIRORO HYDROGRAPH                                                                   9

7.    2007 AVERAGE MONTHLY MW AVAILABILITY                                                 14

8.    POWER STATIONS AVAILABILITY FACTOR                                                   14

9     POWER STATIONS AVERAGE MW AVAILABILITY                                               21

10    POWER STATIONS INSTALLED CAPACITY                                                    21

11    ANNUAL ENERGY GENERATED.                                                             25

12    SIMULTANEOUS NATIONAL PEAK DEMAND (MW)                                               25

13    330KV FORCED OUTAGES (2006 & 2007)                                                   32

14    132KV FORCED OUTAGES (2006 & 2007)                                                   32

15    COMBINED 2006 & 2007 330KV OUTAGES.                                                  33

16    COMBINED 2006 & 2007 132KV OUTAGES.                                                  33

17    330KV PLANNED, URGENT AND EMERGENCY OUTAGES                                          34

18    132KV PLANNED,URGENT & EMERGENCY OUTAGES                                             34

19    PERCENTAGE ENERGY USED IN POWER STATIONS                                             40

20    HYDRO, THERMAL AND TOTAL ENERGY GENERATED                                            40

21    ENERGY GENERATED IN HYDRO POWER STATIONS                                             42

22    ENERGY GENERATED IN MAJOR THERMAL POWER STATIONS                                     42

23    AVAILABLE ENERGY FOR SALES                                                           44

24    TOTAL MONTHLY ENERGY AVAILABLE FOR SALE                                              44

25    TRANSMISSION REGIONS: MONTHLY ENERGY AVAILABLE FOR SALE                              51


                                           (iii)




        Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
NO.                    CHARTS                                                     PAGE

 26    REGIONAL ENERGY AVAILABLE FOR SALE                                          51

 27    MAJOR THERMAL STATIONS FUEL COST                                            52

 28    MONTHLY UNIT PROD. COST (NAIRA/UNIT)                                        53

 29    STATIONS AVE. PROD. COSTS (NAIRA/UNIT)                                      54

 30    MONTHLY PEAK DEMAND FORECAST AND ACTUAL GENERATION                          87

 31    WEEKLY PEAK GENERATION                                                      87

 32    KAINJI G.S. USABLE GEN. CAP. SPECTOGRAPH PLOT AVAILABLE                     88

 33    JEBBA G.S. USABLE GEN. CAP. SPECTOGRAPH PLOT AVAILABLE                      88

 34    SHIRORO P.S. USABLE GEN. CAP. SPECTOGRAPH                                   89

 35    EGBIN P.S. USABLE GEN. CAP. SPECTOGRAPH                                     89

 36    DELTA P.S. USABLE GEN. CAP. SPECTOGRAPH                                     90

 37    AFAM P.S. USABLE GEN. CAP. SPECTOGRAPH                                      90

 38    SAPELE P.S. USABLE GEN. CAP. SPECTOGRAPH                                    91

 39    OMOTOSHO P.S. USABLE GEN. CAP. SPECTOGRAPH                                  91

 40    AES P.S. USABLE GEN. CAP. SPECTOGRAPH                                       92

 41    OKPAI P.S. USABLE GEN. CAP. SPECTOGRAPH                                     92

 42    GEREGU G.S. USABLE GEN. CAP. SPECTOGRAPH                                    93

 43    OMOTOSHO G.S. USABLE GEN. CAP. SPECTOGRAPH                                  93

 44    OMOKU P.S. USABLE GEN. CAP. SPECTOGRAPH                                     94

 45    AJAOKUTA P.S. USABLE GEN. CAP. SPECTOGRAPH                                  94

 46    OLORUNSOGO P.S. USABLE GEN. CAP. SPECTOGRAPH                                95

 47    DAILY TOTAL GRID GEN. AVAILABILITY STATUS                                   95

 48    GRAPHICAL REPRESENTATION OF SYSTEM COLLAPSE (DAYS)                          111

 49    GRAPHICAL REPRESENTATION OF SYSTEM COLLAPSE (MONTHS)                        111

 50    SUMMARY OF SYSTEM DISTURBANCES 2007                                         112

 51    LOAD LOSS DUE TO SYSTEM DISTURBANCES                                        112


                                          (iv)




Generation and Transmission Grid Operations-2006-National Control Centre, Osogbo
lNTRODUCTION

T
his Technical Report, an annual publication of Power Holding Company Nigeria Plc
(PHCN), covered the National Generation and Transmission Grid Operations in 2007. It
was collated from NCC electronics data bank. Among the major headings elaborated on
were:

    •   1.0 Grid Operations in 2007.

    •   2.0 Constraints to Grid Operations in 2007.

    •   3.0 Reinforcements to the National Grid in 2007.

    •   4.0 System Disturbances, Accidents and Mishaps in 2007.

    •   5.0 Accidents and Mishaps

    •   6.0 Conclusions and Recommendations.

Grid Operations in 2007 was compared with the preceding year 2006 and the previous
years through tables and graphs.

Also presented are detailed analyses of plant and equipment outages, energy generated,
transmitted and available to the distribution network.

Depicted also are supplementary charts, graphs and other significant details that aid
comprehension of the report.

1.0 GRID OPERATIONS IN 2007
The plant average availability at Kainji Power Station in 2007 was 524.1MW. This was
115.3MW higher than 2006 figure of 408.8MW.

Jebba’s plant availability ranged between 578.4MW and 559.1MW in 2007 with average
availability of 572.3MW. This was greater than 2006 average availability of 554.2MW
by 4.9MW.


At Shiroro Power Station plant availability throughout the year was little less than 2006.
The availability varied between 600MW and 444.4MW in 2007. It stood at an average of
524.8MW. This was just 5.1MW lower than 2006 figure of 529.9MW.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
1.1      HYDROLOGY AND LAKE OPERATIONS

1.1.1.   Kainji Lake

The average computed inflow of the 2006/2007 black flood yield into the Kainji Lake
was higher than the average forecast inflow by 8.98%.

When the black flood inflow was compared with the figures of immediate past five years
the 2006/2007 black flood was higher than the 2005/2006 by 14.6%, higher than
2004/2005 by 34.54%, lower than 2003/2004 by 14.78%, higher than 2002/2003 by
22.21%, lower that 2001/2002 by 9.4%.

The fairly, good flood yield, brought the head water elevation to 141.69 meters
corresponding to a volume of 11.95 billion cubic metres of water at the beginning of the
hydro year, January 1st 2007.

The black flood peaked on 8th December 2006, with a value of 1724 cubic metres per
second (m3/sec).

This was (2.78%) higher than the peak daily computed black flood inflow of 2005/2006.

At the Joint Operations/Generation Planning meeting held in Jebba Hydroelectric
Business Unit on the 7th - 8th March 2007, the planned turbine discharges and the
expected inflow into the Kainji Lake from the months of March through August were as
in the Table1B. The importance of the meeting was to agree on the draw down
trajectory.

The forecast inflow between January and June 2007 was 26.85% lower than the actual
computed inflow. It was noted that the actual turbine discharge during the period fell
short by (1.24%) of the planned discharge, in spite of the fairly robust inflow. This was a
result of fall in Kainji MW availability.

Also during this period while the Kainji MW was low and Jebba MW availability was
higher, hence the amount of inflow into the Jebba Lake was not good enough to keep the
head water elevation high for efficient Power Generation. It became necessary to engage
on controlled spillage, to sustain Jebba Operations. Between January and April a total
average volume of water spilled was 1405.56 cubic metres per second.

The difference of 641.66 m3/sec between the average computed total station discharge of
1213.61 m3/sec and the average total computed inflow rate of 571.95 m3/sec resulted in
the drawing down of the Lake to an elevation of 130.44 metres by June 28, 2007.

This corresponded to a storage balance of 1.38 billion cubic metres of water. This
volume was 0.37 billion cubic metres lower than the lowest volume attained on July 24,
2006. It was observed that, the volume attained in 2007 was the lowest ever since the
inception of the Kainji Lake Operations 1968.




           Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                2
TABLE 1A: HYDROLOGICAL SUMMARY. JANUARY - DECEMBER 2007
             AVE.TURB.DISCH.               AVE.SPILLAGE        STATION AVE.TOT. DISCH          COMP.AVE. INFLOW                AVE.DAILY ENERGY
                   (CUB.M/SEC)              (CUB.M/SEC)              (CUB.M/SEC)       RATE (CUB.M/SEC)                              (MWH)
MONTH     KAINJI     JEBBASHIROROKAINJI JEBBASHIRORO KAINJI JEBBA SHIRORO KAINJI JEBBASHIRORO KAINJI                                 JEBBA SHIRORO
 JAN.     856.13     1419.48   368.84   457.10   0.00   0.00   1313.23   1419.48   368.84    1294.61   1353.77   54.39    7321.87    7864.77    8222.48




                                                                                                                                                           Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
 FEB.     774.86     1372.57   319.25   541.43   0.00   0.00   1316.29   1372.57   319.25    1069.07   1347.79   27.96    6680.48    7608.39    6921.00
 MAR.     1189.32    1288.23   214.81   275.90   0.00   0.00   1465.22   1288.23   214.81    399.74    1379.55   13.19    9670.42    7212.52    4434.10
 APR.     1345.23    1669.67   144.73   131.13   0.00   0.00   1476.36   1669.67   144.73    277.80    1572.60   31.47    9938.73    9026.90    3058.93
 MAY.     1176.13    1381.16   168.51    0.00    0.00   0.00   1176.13   1381.16   168.51    179.94    1287.84   69.13    8132.87    7544.32    3354.00
 JUN.     534.43     653.67    232.17    0.00    0.00   0.00    534.43   653.67    232.17    210.53    676.83    200.43   3608.41    3619.00    4380.87
JAN-JUN
          5876.10    7784.78   1448.31 1405.56   0.00   0.00   7281.66   7784.78   1448.31   3431.69   7618.38   396.57   45352.78 42875.90     30371.38
 TOTAL
JAN-JUN
          979.35     1297.46   241.39   234.26   0.00   0.00   1213.61   1297.46   241.39    571.95    1269.73   66.10    7558.80    7145.98    5061.90
AVERAG




                                                                                                                                                                                                                                              3
 JUL.     324.03     451.48    362.16    0.00    0.00   0.00    324.03   451.48    362.16    562.48    451.87    527.71   2168.61    2528.77    6870.13
 AUG.     833.68     1027.81   376.71    0.00    0.00   0.00    833.68   1027.81   376.71    2209.19   1342.35 1048.87    5366.56    6112.32    7765.71
 SEP.     1152.17    2078.80   444.00    0.00    0.00   0.00   1152.17   2078.80   444.00    2620.27   2171.87   951.50   8214.07    12028.07   9532.90
 OCT.     1267.74    1988.65   321.29    0.00    0.00   0.00   1267.74   1988.65   321.29    1457.19   1709.45   249.32   9901.06    11106.97   7487.29
 NOV.     1248.93    1394.10   321.23   192.50   0.00   0.00   1441.43   1394.10   321.23    1213.2    1514.80   96.17    9876.63    7655.13    7362.63
 DEC.     1392.26    1240.23   194.97    0.00    0.00   0.00   1392.26   1240.23   194.97    1307.77   1422.39   38.52    10722.55   7324.00    4356.03
JUL-DEC
         6218.81 8181.06 2020.36 192.50          0.00   0.00   6411.31   8181.06   2020.36   9370.10   8612.73 2912.09 46249.48 46755.26        43374.70
 TOTAL
JUL-DEC
         1036.47 1363.51 336.73    32.08         0.00   0.00   1068.55   1363.51   336.73    1561.68   1435.46   485.35   7708.25    7792.54    7229.12
AVERAG
ANNUAL
        12094.91 15965.84 3468.67 1598.06        0.00   0.00   13692.97 15965.84 3468.67 12801.79 16231.11 3308.66 91602.26 89631.16            73746.08
 TOTAL
AVERAG
         1007.91 1330.49 289.06 133.17           0.00   0.00   1141.08   1330.49   289.06    1066.82   1352.59   275.72   7633.52    7469.26    6145.51
   E
KAINJI AVE.MONTHLY TOT. DISCHARGE & INFLOW
                                                                                                    JANUARY-DECEMBER 2007, CHART 1 (SEE TABLE 1)
                                           2800




                                           2400
                FLOW IN CUBIC METRES/SEC




                                           2000




                                           1600




                                           1200




                                           800




                                           400




                                             0
                                                     JAN.         FEB.         MAR.         APR.         MAY.         JUN.         JUL.      AUG.      SEP.      OCT.    NOV.    DEC.
                                                                                                                      MONTHS

                                                                                                           DISCHARGE          INFLOW




                                                                                              KAINJI HYDROGRAPH
                                                                                                         1994-2007 CHART 2
                                            144




                                            142
HEAD WATER ELEVATION IN METRES




                                            140




                                            138




                                            136




                                            134




                                            132




                                            130
                                              JAN.          FEB          MAR          APR          MAY          JUN          JUL       AUG       SEP      OCT      NOV     DEC
                                                                                                                        MONTHS

                                                                     2007ACTUAL             2006ACTUAL          2005ACTUAL         2004ACTUAL       2003ACTUAL
                                                                     2002ACTUAL             2001ACTUAL          2000ACTUAL         1999ACTUAL       1998ACTUAL
                                                                     1997ACTUAL             1996ACTUAL          1995 ACTUAL        1994 ACTUAL




                                                      Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                                                 4
The fast draw down was as a result of National demand as the gas supply to the Thermal
Power Stations was unstable. To maintain supply during the nationwide elections and
subsequent inaugurations, all available water was used to generate power.

At the Joint Operations/Generation Planning meeting held in Shiroro Hydro Electric
PLC, between 5th and 6th September 2007, the impoundment program from September
2007 – February 2008 for the white flood and subsequent black flood was agreed on.
Normally, it was convenient to fill the Kainji Lake to an elevation of 140.06 metres
corresponding to a volume of 10 billion cubic metres of water by the end of the white
flood usually October ending.

Records showed that the actual average computed inflow was slightly higher than
forecast inflow by 0.76%. The average actual turbine discharge during the white flood
was (17.65%) lower than the planned turbine discharge, because Kainji 1G6 which was
expected to be on the grid in September was surprisingly unavailable.

The peak of the computed white flood occurred on 1st September 2007, with a magnitude
of 4660 m3/sec. That magnitude was 1.75% higher than the peak value of 4580 m3/sec of
the previous year which occurred on September 8, 2006.

All the available units in Kainji Power station were kept running to avoid spillage. It has
to be mentioned that, if the Kainji Lake was not drawn down to the lowest elevation ever,
spillage was would have been inevitable.

At that period, spillage in Kainji would have been undesirable for Jebba Lake whose head
water elevation was above 102.5 metres already.

By the end October 2007, the Kainji Lake head water elevation was 140.04 metres,
corresponding to almost 10.00 billion cubic metres as planned.

Before the end of October, Jebba Lake head water was observed to have to be reduced
drastically, because Kainji turbine discharge was not high enough as the lateral inflow
into the Jebba Lake has dropped significantly.

By October 30, 2007, the Jebba Lake head water elevation had dropped to 99.9 metres.
For 13 days, from 1st – 13th November 2007, controlled spillage was embarked on Kainji
spillway gate. An average of 192.50 m3/sec was spilled, to boost Jebba Lake.

The head water elevation of the Kainji Lake was at 139.24 metres, corresponding to 9.08

billion cubic metres by the month of December 31st, 2007. This volume was lower

(31.61%) than the volume obtained by the same time 2006.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               5
TABLE1B: PLAN/ACTUAL COMP. AVE. INFLOW AND AVE. TURB. DISCH. (CUB.M/SEC). JANUARY - DECEMBER 2007.
                     KAINJI                                        JEBBA                                    SHIRORO
                                                                              AVER.
MON           ACTUAL       PLAN      ACTUAL    PLAN      ACTUAL     PLAN            ACTUAL      PLAN     ACTUAL    PLAN     ACTUAL
    PLAN INF.                                                                LATERA
 TH             INF.       DISC.      DISC.     INF.       INF.     DISC.            DISC.       INF.      INF.    DISC.     DISC.
                                                                              L INF
JAN.   1121.00   1294.61   900.00    856.13    891.00    1353.77    920.00    49.84   1419.48   15.00     54.39    200.00   368.84




                                                                                                                                     Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
FEB.   568.00    1069.07   900.00    774.86    883.00    1347.79    950.00    11.07   1372.57   12.00     27.96    200.00   319.25
MAR.   572.00    399.74    1200.00   1189.32   994.00    1379.55    900.00    22.65   1288.23   15.00     13.19    200.00   214.81
APR.   200.00    277.80    1200.00   1345.23   1007.00   1572.60    850.00    96.97   1669.67   25.00     31.47    200.00   144.73
MAY.   102.00    179.94    1000.00   1176.13   778.00    1287.84    758.00    90.97   1381.16   108.00    69.13    200.00   168.51
JUN.   142.00    210.53    750.00    534.43    864.00    676.83     864.00   119.97   653.67    192.00   200.43    200.00   232.17




                                                                                                                                                                                                                        6
JUL.   333.00    652.48    700.00    324.03    1307.00   451.87    1320.00   135.13   451.48    442.00   527.71    300.00   362.16
AUG.   1629.00   2209.19   1080.00   833.68    1363.00   1342.35   1380.00   528.90   1027.81   794.00   1048.87   300.00   376.71
SEP.   2526.00   2620.27   1374.00   1152.17   2311.00   2171.87   2020.00 1019.67 2078.80 1191.00       951.50    500.00   444.00
OCT.   2084.00   1457.19   1374.00   1267.74   2109.00   1709.45   1909.00   449.48   1988.65   510.00   249.32    450.00   321.29
NOV.   1556.00   1213.20   1410.00   1248.93   1492.00   1514.80   1492.00    62.63   1394.10   88.00     96.17    300.00   321.23
DEC.   1644.00   1307.77   1410.00   1392.26   1434.00   1422.39   1500.00    44.97   1240.23   35.00     38.52    200.00   194.97
Overall Kainji MW availability was better (28.2%) than the figure of the previous year
(see chart 1&2)

1.1.2   Jebba Lake

At the beginning of the hydro year, 1st January 2007, the head water elevation at Jebba
lake was at 100.96 metres, corresponding to 3.2875 billion cubic metres. This was
slightly higher (0.23%) than the storage balance of 3.28 billion cubic metres of water
recorded at the beginning of 2006 hydro year.

Appreciable lateral inflow into the Jebba Lake started on 25th August 2007, with a value
of 1223 m3/sec. It peaked on 28th August 2007 with a value of 1813 m3/sec and ebbed
out after the second week of October. The peak value was higher (39.68%) than the peak
lateral inflow recorded on September 17th, 2006.

During the year, the minimum head water recorded, was 99.02 metres which occurred on
June 26th, 2007.

The maximum station turbine discharge of 2266 m3/sec occurred on September 10, 2007,
and the maximum computed inflow of 2876 m3/sec occurred on August 28, 2007.

When the head water elevation was 102.73 metres on September 9th, 2007, the six units
were run for 24 hours for almost 12 days.

Due to unstable gas supply to the Thermal Power Plants, great demand was on the hydro
plants. This head water elevation (102.73metres) corresponded to a storage balance of
3.803 billion cubic metres (see chart 3 &4)

From Table 2, Jebba MW availability was higher than the previous year by 3.27%. Even
though Kainji MW availability improved this year, it was evident from Table 1A the
monthly average turbine discharge which was the primary source of inflows into Jebba
Lake was always lower than Jebba turbine discharge because of its MW availability. For
this reason the head water elevation in Jebba lake was always drawn down early in the
year.

By the end of the year, December 31st 2007, the head water elevation in Jebba was
102.74 metres, corresponding to 3.805 billion cubic metres of water. This was 15.65%
higher than the headwater of the Lake at the same period 2006.

1.1.3   Shiroro Lake

At the beginning of the hydro year, January 1st 2007, the reservoir head water elevation
was 376.29 metres corresponding to a storage balance of 4.2678 billion cubic metres of
water. This volume was lower (6.68%) than the storage balance at the same time 2006.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               7
JEBBA AVE. MONTHLY TOTAL DISCHARGE & INFLOW
                                                                                               JANUARY-DECEMBER 2007, CHART 3 (SEE TABLE 1)
                                                            2500




                                                            2000
                                 FLOW IN CUBIC METRES/SEC




                                                            1500




                                                            1000




                                                             500




                                                               0
                                                                   JAN.     FEB.     MAR.     APR.      MAY.          JUN.         JUL.         AUG.         SEP.         OCT.         NOV.         DEC.
                                                                                                                        MONTHS

                                                                                                                     DISCHARGE      INFLOW




                                                                                              JEBBA HYDROGRAPH
                                                                                                       1994-2007 CHART 4
                                        103.5



                                                        103
HEAD WATER ELEVATION IN METRES




                                        102.5



                                                        102



                                        101.5



                                                        101



                                        100.5



                                                        100



                                                  99.5
                                                     JAN.             FEB      MAR      APR      MAY           JUN           JUL          AUG          SEP          OCT          NOV          DEC
                                                                                                                         MONTHS


                                                                                                       2007ACTUAL            2006ACTUAL         2005ACTUAL           2004ACTUAL
                                                                                                       2003ACTUAL            2002ACTUAL         2001ACTUAL           2000ACTUAL
                                                                                                       1999ACTUAL            1998ACTUAL         1997ACTUAL           1996ACTUAL
                                                                                                       1995 ACTUAL           1994 ACTUAL




                                                                     Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                                               8
SHIRORO AV. MONTHLY TOT. DISCHARGE & INFLOW
                                                                       JANUARY-DECEMBER 2007 CHART 5 (SEE TABLE 1 ).
                                 1300

                                 1200

                                 1100

                                 1000
     FLOW IN CUBIC METRES/SEC




                                 900

                                 800

                                 700

                                 600

                                 500

                                 400

                                 300

                                 200

                                 100

                                   0
                                         JAN.         FEB.     MAR.         APR.         MAY.         JUN.         JUL.         AUG.         SEP.         OCT.         NOV.         DEC.


                                                                                                    MONTHS
                                                                                     DISCHARGE                        INFLOW


                                                                              SHIRORO HYDROGRAPH
                                                                                            1994-2007, CHART 6
                                   385




                                   380
HEAD WATER ELEVATION IN METRES




                                   375




                                   370




                                   365




                                   360




                                   355
                                     JAN.       FEB          MAR      APR          MAY          JUN          JUL          AUG          SEP          OCT          NOV          DEC

                                                                                                      MONTHS
                                                         2007ACTUAL          2006 ACTUAL            2005 ACTUAL           2004 ACTUAL           2003ACTUAL
                                                         2002ACTUAL          2001ACTUAL             2000ACTUAL            1999ACTUAL            1998ACTUAL
                                                         1997ACTUAL          1996ACTUAL             1995ACTUAL            1994ACTUAL




                                            Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                                9
The draw down plan of the Shiroro Lake between March and August 2007 was agreed
upon at the Joint Operations/Generation Planning meeting held in Jebba Hydroelectric
Business Unit on the 7th & 8th March 2007, as displayed in table 1B.

The actual computed inflow during the period was higher than the forecast inflow by
19.97%. Total station turbine discharge exceeded the total computed by 1079.89 m3/sec.
This resulted in drawing down the lake to an elevation 358.41 metres by July 13, 2007.

The unstable gas supply from the Nigerian Gas Company forced the Operation to draw
down the lake to that all time low head water elevation. This elevation was lower the
previous year minimum elevation of 359.65 metres on July 15, 2006 by 0.1427 billion
cubic metres.

The pattern of flood yield into the Shiroro Lake this year can be described as sporadic.
The flood peaked in August and substantial inflow was for short duration about three
weeks precisely. The peak value of computed inflow recorded was 3175 m3/sec on
August 28, 2007. The forecast inflow was 794 m3/sec, while the actual computed inflow
was 1048.87 m3/sec. Hope rose that definitely the Lake will be filled during the flood
season.

After the first twelve days in September the inflow ebbed out. The hope was suddenly
dashed.

Usually, it was planned to fill the lake within the first two weeks in October every year,
but the disappointing inflow yield of September, torpedoed the plan.

Maximum head water elevation attained during the flood was 379.37 metres on
September 30, 2007.

When it became obvious that the lake could not be filled, water regulation started. The
head water elevation improved 379.49 metres corresponding to 4.987 billion cubic metres
on October 12, 2007.

Since appreciable inflows were not expected into the Shiroro Lake, plans were drawn out,
in order to manage the available water resource from October 2007 till mid-July 2008.

Overall Shiroro MW availability throughout 2007, dropped slightly by 0.97%, when
compared with 2006 figure.

By December 31st 2007, the head water elevation stood at 373.68 metres corresponding
to a storage balance of 3.7188 billion cubic metres. This balance was 14.76% lower than
the storage balance at the same time 2006. (See chart 5&6).




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              10
1.2.    THERMAL GENERATION

1.20.   GENERATION AVAILABILITY

In table 2, the average Power(MW) availability was depicted. Analysis of the year’s
thermal availability was conducted employing the popular relevant statistical measures.

Thermal plant average availability was 2535.0MW in 2007. Of this figure 699.5MW
(27.59%) was contributed by the 3 Independent Power Producers (IPP). The thermal
availability was 60.99% of aggregate of Hydro and thermal availability of 4156.2MW in
2007. It surpassed 2006 figure of 2396.4MW by 138.6MW.

1.21 SAPELE G. S.

Sapele ST1 generated from January to 23rd May, when it was on forced outage.
Restored back on 26th, the unit remained synchronized to the grid till 6th September when
it tripped on high vibration.

Between 13th September and 25th October the unit was available. It then went through a 3
week outage to clear serious oil leakage on the generator. Tripped on 20th November on
supper heater very high temperature the unit was restored by November ending and
generated through out December, 2007.

Sapele ST2 which had been on outage since September, 2002 due to high bearing
problem was restored to the grid in August, 2007. It tripped on turbine high vibration on
6th August. After a week of outage the unit was available till 31st August when it was
forced out of the grid for a week due to restricted earth fault. It generated throughout
September until it tripped during the system disturbance early October.

From 30th October to the 2nd week of November, the unit was available. It then tripped on
control oil pressure and remained unavailable throughout December, 2007.

Sapele ST3 was unavailable since 28th May, 2006 due to faulty generator transformers.
By 31st December, 2007, the unit was still unavailable.

Sapele ST4 was forced out of the grid due to high winding temperature fault since the
third quarters of 1994. It was still unavailable by 31st December, 2007.

Sapele ST5 has been on outage since 2nd March, 1986 when its unit transformer and
associated switchgear got burnt. The unit was unavailable by December, 31st 2007.

Sapele ST6 tripped following System disturbance on the 29th September, 2005. The
ensuing fire outbreak in the station destroyed the governor control cable.




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              11
TABLE 2 AVERAGE MONTHLY MW AVAILABILITY JAN. TO DEC. 2007
                                                                                                                                 THERMAL
                                                                                                                                         THERMAL THERMA HYDRO GRAND
         KAINJI JEBBA SHIROR EGBIN AJAOKU A.E.S SAPEL OKPAI                   AFAM     DELTA GEREGU OMOK OMOTOS PAPALANT          TOTAL
MONTHS                                                                                                                                     TOTAL L TOTAL TOTAL TOTAL
          MW     MW    O MW   MW    TA MW  MW   E MW   MW                      MW       MW     MW   U MW  HO MW   O MW            (PHCN)
                                                                                                                                         (IPP) MW  MW     MW    MW
                                                                                                                                    MW
 JAN.    421.9   578.4    595.2    997.4    80.5    256.3    108.4   444.5    166.9    474.5     0.0     34.8     0.0     0.0     1827.6   735.5    2563.2    1595.5   4158.7
 FEB.    375.6   561.2    444.4    831.1    91.7    212.4     0.0     91.7    447.4     57.0    435.7     0.0    67.2     0.0     1930.1   304.1    2234.2    1381.3   3615.5
 MAR.    522.2   566.4    520.3    641.1    90.9    172.1    112.5   366.1     73.3    427.1     76.3    86.0     0.0     0.0     1421.2   624.1    2045.3    1608.9   3654.2




                                                                                                                                                                                 Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
 APR.    580.8   569.1    517.7    709.7    92.6    166.1    116.1   314.5    106.8    334.2     96.8    230.5    0.0     0.0     1456.3   711.1    2167.4    1667.6   3835.0
 MAY.    601.1   578.4    454.8    752.3    94.0    200.5    85.2    387.1    232.6    346.1    330.8    72.5     0.0     0.0     1840.9   660.1    2501.0    1634.4   4135.4
 JUN.    479.2   578.4    520.0    689.3    91.7    198.1    112.0   330.2    205.9    330.9    350.1    88.3    40.4     0.0     1820.3   616.6    2436.9    1577.6   4014.4
JAN-JUN
        2980.9   3431.9   3052.5   4620.9   541.4   1205.5   534.2   1934.0   1232.9   1969.7   1289.7   512.0   107.7    0.0    10296.5   3651.5   13948.0   9465.2   23413.2
 TOTAL
JAN-JUN
AVERAG 496.8     572.0    508.7    770.1    90.2    200.9    89.0    322.3    205.5    328.3    214.9    85.3    17.9     0.0     1716.1   608.6    2324.7    1577.5   3902.2
   E
 JUL.    596.8   578.4    469.4    794.8    110.0   198.3    127.7   479.2    204.8    363.0    284.7    100.0   22.3     0.0     1907.4   777.5    2684.9    1644.5   4329.4




                                                                                                                                                                                                                                                                    12
 AUG.    545.2   562.9    585.5    709.7    110.0   238.0    197.4   479.2    204.8    311.8    392.4    96.0    67.0     0.0     1993.1   813.1    2806.2    1693.5   4499.7
 SEP.    492.3   578.4    540.0    814.0    89.8    229.2    176.2   437.2    243.2    370.3    255.7    94.2    138.6    0.0     2087.9   760.6    2848.5    1610.7   4459.2
 OCT.    555.3   578.4    595.5    660.0     5.0    234.2    81.8    456.0    265.8    381.7    276.0    75.0    153.9    0.0     1824.2   765.2    2589.4    1729.2   4318.6
 NOV.    548.7   559.1    600.0    566.9    60.0    267.9    137.7   472.1    290.8    358.0    276.0    75.8    200.0    0.0     1889.3   815.9    2705.2    1707.7   4412.9
 DEC.    570.6   578.4    454.8    660.0    55.0    266.3    120.0   468.9    295.2    311.0    230.5    75.0    231.9   123.4    2027.0   810.2    2837.2    1603.9   4441.1
JUL-DEC
        3308.9   3435.5   3245.1   4205.4   429.8   1434.0   840.9   2792.6   1504.4   2095.8   1715.3   516.0   813.8   123.4   11729.0   4742.6   16471.5   9989.5   26461.0
 TOTAL
JUL-DEC
AVERAG 551.5     572.6    540.9    700.9    71.6    239.0    140.1   465.4    250.7    349.3    285.9    86.0    135.6   20.6     1954.8   790.4    2745.3    1664.9   4410.2
   E
ANNUAL
 STN.
       524.1     572.3    524.8    735.5    80.9    220.0    114.6   393.9    228.1    338.8    250.4    85.7    76.8    10.3     1835.5   699.5    2535.0    1621.2   4156.2
AVERAG
   E
The unit was restored on the 3rd week of September, 2006. By November, 2006 it
developed bearing vibration trouble. It was virtually out of service in 2007 due to crack
on the turbine blade and high vibration.

1.22    AFAM P. S.

Afam GT1 was out of service since last quarter of 1993. It remained out of service by
December, 2007.

Afam GT2 - scrapped.

Afam GT3 out of service since February 1990 on damaged exciter and generator bearing
problem, still maintained its enoperatable state by December, 2007.

Afam GT4 was unavailable due to rotor balancing and labyrinth seal problem since 1998.

Afam GT5 was on outage due to excessive oil leakage from the generator between
January and the third week of February. It ran for only a week and was then shut down
due to smoke on the exciter.

Tied in the first week of August, it rolled generation into the grid till 28th September,
2007. It was on bars for 9 days before it tripped as a result of system disturbance.
Having generated the last week of September, the unit tripped again on turbine main lube
oil low pressure. By 31st December, 2007, the unit was still out of service.

Afam GT6 was unavailable throughout the year with the exception of the first five days
of January, having developed high turbine inlet temperature.

Afam GT7 was unavailable in the year on burnt generator breaker and control cable
faults.

Afam GT8 had been on outage since 3rd April, 1988 on damaged turbine and turbine
blade failure.

GT9’s major overhaul was suspended in the last quarter of 1995 and still on breakdown
outage since.

GT10 supposed to be on rehabilitation since 2002 was still unavailable by December, 31st
2007.

GT11 was out of service in September 1997 due to the fatal fire outbreak at Afam P.S.
though it was restored to service 2 weeks after, it sooned tripped on oil drain high
temperature and still out by 31st December, 2007.

Afam GT12 was shutdown in August 1998 due to compressor blade failure. It was still
out of service at the expiration of 2007.




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              13
2007 AVE. MONTHLY MW AVAILABILITY
                                                                JANUARY-DECEMBER 2007 CHART 7(SEE TABLE2)
                             2500


                             2000
MONTHLY AVAILABILITY




                             1500


                             1000


                                         500


                                           0
                                                  J      F        M       A        M       J        J       A        S       O           N   D


                                                                                         MONTHS

                                           KAINJI            JEBBA            SHIRORO           SAP.TOT           AFAM              EGBIN
                                           DELTA             IJORA            CALABAR           AES               OKPAI             AJAOKU
                                           THMAL PHCN        THMAL IPP                          HYDRO TOT         GRAND TOT         OMOKU



                                                             POWER STATIONS AVAILABILITY FACTOR
                                                                JANUARY-DECEMBER 2007, CHART 8(SEE TABLE 3)
                                           1.20
                   AVAILABILITY FACTOR




                                           1.00

                                           0.80

                                           0.60

                                           0.40

                                           0.20

                                           0.00
                                                           )




                                                          O


                                                          O
                                                          O


                                                          O

                                                         RO


                                                          M




                                                         ST


                                                            /




                                                           )

                                                           T
                                                           )




                                                           )
                                                         TA




                                                        AS


                                                        AS




                                                        AS
                                                        AS




                                                        AS




                                                         G
                                                         R


                                                         R




                                                       SH


                                                        G
                                                       EA

                                                      KU
                                                     YD


                                                     YD


                                                       O




                                                     LE




                                                     SO
                                                      G




                                                     (G
                                                     (G




                                                     (G




                                                     KU
                                                     (G
                                                   ST




                                                   TO
                                                    IR




                                                   AI
                                                 AO




                                                 PE
                                                   H
                                                   H




                                                   N
                                                AM
                                                   S




                                                   O
                                                 TA
                                                SH




                                                  U




                                                 O
                                               KP
                                                E.
                                                 N




                                                 U
                                                M
                                                JI


                                                A




                                              EG
                                              SA
                                              AJ




                                               M
                                             EL
                                              BI




                                               R
                                             AF
                                             BB
                                             IN




                                             A.




                                              O
                                             O




                                            O

                                           LO
                                           EG




                                          ER
                                            D
                                          KA


                                          JE




                                          O
                                         G




                                                                                  POWER STATIONS



                                                      Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                           14
Afam GT13 had been on outage due to turbine failure since February 1997. By the end
of 2007, the unit was still unavailable.

Afam GT14 which had been on outage due to compressor blade failure since April 1992
was on outage by December, 2007.

Afam GT15 had been out of service since 1995 and required major overhaul to come
back on stream.

Afam GT16 which had compressor blades failure in 1992 was still unavailable by 31st
December, 2007.

Afam GT17 was out of service on ignition failure from January to October 21, 2007. It
came back on stream briefly and was later shutdown for reliability test. By November,
when the reliability test was over, it only generated for 2 days following which it was
shutdown due to bearing oil leakage. It was still on outage by December, 2007.

GT18 was shutdown from January to 15th October to clear the accumulated condensates
on the gas pipeline. It generated in the 2nd weekend, shutdown thereafter on low gas
pressure. Returned to the grid in early November, the unit tripped a week after on low
gas pressure. Attempts to restore it failed as condensate problems surfaced. By 31st
December, 2007, the unit was out of service.

GT19 was out of service on high air intake differential pressure. The unit was
synchronized to the grid a week after. Between 14th and 23rd January, it went out of
service on dirty air inlet filters. From 8th April to end of June, the unit was available.
Out for a week on underfrequency, the unit was available thereafter till the expiration of
2007.

GT20 generated into the grid in the first 14 days of January. It was then shutdown due to
dirty air inlet filters till 16th March. On 25th March, it shutdown again due to air intake
filter leakages.

The unit was available then till the end of 2007 except the third week of June when it
tripped on high inlet temperature.

Afam average plant availability was 166.9 MW in January 2007. The first half annual
peak of 232.6 MW was attained February.

In the second half of the year, the peak average demand was 295.2 MW, recorded in
December. The year’s average MW availability was 228.1MW. It was 147.8MW
(189%) greater than 2006 figure of 80.30 MW.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               15
1.23   DELTA P.S.

Delta GT1 & GT2 had been scrapped.

Delta GT3, 4 & 5 were out of service due to non-availability of the 81MVA 11/132kV
transformer since January 2006 and remained unavailable by the end of 2007.

Delta GT6 was generally available in 2007. It only went out on a week outage on
excitation fault.

Delta GT7 was available from January to mid May when it was on a week outage. It ran
thereafter till the 3rd week in July when it was on forced outage for a week. By the 2nd
week of November, the unit developed compressor bleed valve trouble and was still
unavailable by 31st December, 2007.

Delta GT8 was in service from January to 17th April. It developed serious oil leakage
from reduction gear for a week and run till the 2nd week of September when it shutdown
due to faulty generator bleed valve position trouble. It thereafter generated in the 3rd and
4th week of October but tripped in early November. It was thereafter synchronized to the
grid till the end of December, 2007.

Delta GT9 was generally available through out the year except the outage to seal the oil
leakage on its unit transformer between 7th and 18th February, 2007.

Delta GT10 was available from January to 7th February. It then went on outage to seal
the oil leakage on the unit transformer. Returned to the grid by 18th February, the unit ran
till the 1st week in September when it tripped on excitation trouble. After a week outage
the unit remained on the grid till 31st December, 2007.

Delta GT11 was on the grid from January to 7th February when it was shutdown on
planned outage to seal oil leakage on its unit transformer. Restored to the grid on 18th
February, the generating unit was available till the end of 2007.

Delta GT12 was available through out the year except the planned outage on the 3rd week
of July, 2007.

Delta GT13 was available in the year 2007 except the 3rd week in July when it was on
planned outage and the last week of December when the unit was shutdown due to
abnormal bearing problem.

Delta GT14 was on the grid from January to the 3rd week of July when it was on planned
outage. It then generated till mid October when it tripped on exhaust over temperature.
By 31st December, 2007, the unit was still unavailable.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               16
Delta GT15 was available from January to March 2007. It developed starting problem
and remained out of service by 31st December, 2007.

Delta GT16 was still undergoing rehabilitation in 2007.

Delta GT17 was out of service from January to 31st July 2007. It ran for 13 days in
August. Thereafter, it was shutdown due to fire in the turbine accessory.

Delta GT18 was available throughout 2007 except the last 3 weeks of August when it
was on outage due to high exhaust temperature.

Delta GT19 had been on outage since April 1998 on combustion trouble. Rehabilitation
was still in been awaited by 31st December, 2007.

Delta GT20 generated into the grid from January to 19th February 2007, when it
developed hydrogen gas leakage. By February 28 the unit was tied to the grid. It tripped
again by 1st April on faulty crank motor. Synchronized back on 14th April, the unit
generated till 18th May when it tripped on ignition problem. The unit was then available
from mid June till 31st December, 2007.

Delta monthly average availability was 474.5 MW in January 2007. That was the mid
year peak generation. In the second half of the year, the peak demand was 381.7 MW
recorded in October, 2007.

The Station’s annual average availability was 338.8MW. It was 31.21% lower than
2006 value of 492.5 MW.

1.24.   EGBIN P.S.

Egbin ST1 was available from January to April 2007. It was shutdown from 1st to 17th
May for condenser cleaning. The unit was then available till the last week of July when it
tripped on control system failure. By the third week of September the unit was out for
inspection.

Restored to the grid by the 2nd week of November, the unit generated for a week. It was
thence available till 31st December, 2007 except a week of outage to clear its control
valve problem.

Egbin ST2 was available throughout the year except a week outage each in April and
June 2007.

Egbin ST3 was on the grid from January to the tail end of January when it developed
boiler problem. By 31st December, 2007 the unit was still unavailable

Egbin ST4 generated from January to the first week in March, 2007. It then went on
planned outage till 21st March. It was shutdown for condenser cleaning in the third week




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              17
of June and went on planted outage in the last week of August. It was thereafter available
till 31st December, 2007.

Egbin ST5 was available from January to 20th March when it went on outage due to
generator breaker fault. It remained on bars thence.

Egbin ST6 which tripped on 13th March, 2006 on furnace distortion remained unavailable
by 31st December, 2007.

Egbin plant generation availability was 997.4 MW in January, 2007. That was the peak
availability for the 1st half of the year (January to June). In the second half of the year,
the peak plant generation availability of 814.0 MW was attained in September. Annual
average generation availability was 735.5 MW. It fell short of 2006 value of 1005.5 MW
by 26.80%.

1.25   IJORA P.S.

Ijora GT4 was awaiting commissioning throughout the year 2007.

GT5 which had been on breakdown outage due to exhaust plenum fault since the third
week of March, 2006 was still unavailable by 31st December, 2007

1.26 CALABAR P.S.

Calabar EE1 was unavailable since the 2nd week of March, 2002 on burnt bearing. By
31st December, 2007 the unit was still unavailable.

Calabar EE2 has been out of service due to abnormal noise since 31st March, 2005. It
was still unavailable by 31 December, 2007

GM2’s starting problem that commenced in June 2004, continued throughout 2007.

1.27   AES – INDEPENDENT POWER PRODUCERS (IPP)

AES Barge 202 was tied to the grid from January to December 2007, safe a week outage
in the last week of January and the 2nd week of April when it was shutdown due to the
Nigeria Gas Company (NGC) pigging work.

Barge 203 ran from January to 9th March. It then tripped on high bearing vibration. Tied
back in the 1st week of April, it generated for only 3 days after which it was shutdown
due to condensate problem. From early May to the 3rd week of July, it was unavailable
due to bearing, it failure and lube oil leakage.

The unit was synchronized to the grid from 4th week in July to 31st December, 2007.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               18
Barge 204 was on the grid between January and 5th April when it was shutdown due to
condensate problem. It was tied back on 12th April and ran till 22nd May when it tripped
on high frequency. Between June and December 2007, the unit went on outage thrice
viz: 1st to 8th September on maintenance outage; third week of September due to water
leakage from cooling water pump and 26th October to the first week of November due to
rotating pump problem.

AES 205 barge went on outage six times in 2007. Between 22nd and 9th February it was
shutdown to reposition its circuit. From 1st to 22nd March it was unavailable on diesel
main starting problem. In second week of April, it was shutdown due to condensate
problem.

From the first week in September to 19th October, a major combustion inspection was
carried out on the unit. By 31st December 2007, the unit was still available and
synchronized to the grid.

Barge 207 ran from January to 5th February. It was on planned outage thence till the tail
end of February. On the 2nd week of April it had starting problem. Synchronized on 18th
April, it ran till 8th May when it was shutdown 7 weeks for compressor washing. It later
went on outage from 3rd July to the 2nd week of August on generator fault.

The unit was however available thereafter till 31st December, 2007.

Barge 208 generated in the first 3 weeks of January, tripped on turbine bearing high
vibration and remained out of service till 10th May. It generated thence till 31st December
except outage in June (15th – 13th); August (1st week maintenance) and November (1st
week due to serious water leakage.

Barge 209 was mostly available in 2007. It was shutdown only once in the third week of
March due to condensate problem.

Barge 210 was available from January to December, 2007 except a week outage in the 2nd
week of April due to condensate problem.

Barge 211 was on outage due to transformer fault. It ran till 2nd week in April when it
was shutdown due to condensate problem. From then till 31st December, 2007, the unit
produced energy into the grid.

1.28   OKPAI IPP

Okpai ST1 was synchronized to the grid from January to 10th April when it went on
outage due to steam leakages. Restored on 29th April, the unit was available till 31st
December except the first week of June when it tripped on fault and the third week of
December when it was shutdown for generator maintenance.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               19
TABLE 3. SUMMARY OF GENERATION CAPABILITIES OF PHCN POWER

      STATIONS AS OPERATED IN THE YEAR 2007( JANUARY - DECEMBER )


                                       AVAILABILIT AVERAGE
                                                                                           INSTALLED
       POWER STATION                    Y FACTOR AVAILABILIT
                                                                                         CAPACITY (MW)
                                           (MW)     Y (MW)

        KAINJI HYDRO                          0.69                 524.14                           760.00
        JEBBA HYDRO                           0.99                 572.28                           578.40
           SHIRORO                            0.87                 524.80                           600.00
         EGBIN STEAM                          0.56                 735.53                          1320.00
          AJAOKUTA                            0.90                  80.94                            90.00
          A.E.S (GAS)                         0.81                 219.96                           270.00
          SAPELE ST                           0.11                 114.59                          1020.00
          OKPAI GAS/                          0.88                 393.88                           450.00
          AFAM (GAS)                          0.37                 228.11                           623.00
         DELTA (GAS)                          0.38                 338.80                           882.00
        GEREGU (GAS)                          0.60                 250.42                           414.00
          OMOKU GT                            0.86                  85.67                           100.00
          OMOTOSHO                            0.23                  76.79                           335.00
        OLORUNSOGO                            0.03                  10.29                           335.00
            TOTAL                             0.53                4156.19                          7777.40


DEFINITIONS:-


1. AVAILABILITY FACTOR                          =            AVERAGE MW. AVAILABILITY
                                                                      PI

2.                 PI                           =            The sum of current site rating of
                                                             commissioned units installed in the
                                                             station for the year.

3. AVERAGE MW. AVAILABIL                        =            This is a measure of average
                                                             usable MW capacity of each station
                                                             putting gas pressure constraints
                                                             and other external factors into
                                                             consideration.




                Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                     20
POWER STATIONS AVERAGE MW AVAILABILITY
                                                                           JANUARY-DECEMBER 2007, CHART 9 (SEE TABLE 3)
                                        800.00
                                        700.00
AVERAGE MW AVAILABILITY (MW)




                                        600.00
                                        500.00
                                        400.00
                                        300.00
                                        200.00
                                        100.00
                                          0.00
                                                                                 TA




                                                                                  S)


                                                                                  S)
                                                                                  S)




                                                                                  S/
                                                                                RO




                                                                                  S)
                                                        O




                                                                                  M




                                                                                 ST




                                                                                  O
                                                                                  O
                                                                                RO




                                                                                   T
                                                                                G
                                                    R




                                                                                G
                                                                              SH
                                                                              EA




                                                                                A


                                                                                A
                                                                                A




                                                                                A


                                                                                A
                                                                               U
                                                             YD
                                                   YD




                                                                              O




                                                                            LE




                                                                            SO
                                                                            IG


                                                                             (G
                                                                             (G




                                                                             (G


                                                                            (G


                                                                              U
                                                                             K




                                                                          TO
                                                                          ST
                                                                           IR




                                                                            K
                                                                          O




                                                                        PE
                                                  H


                                                            H




                                                                        PA




                                                                          N
                                                                         M
                                                                         .S




                                                                        TA




                                                                         O
                                                                       SH




                                                                         U
                                                                       JA




                                                                        O

                                                                      RU
                                                                       IN




                                                                      FA
                                                         A
                                               JI




                                                                       M
                                                                      .E




                                                                     EG
                                                                     SA


                                                                      K




                                                                      M
                                                                    EL
                                                        B
                                           IN




                                                                     A




                                                                     O
                                                                     B




                                                                     A




                                                                    O


                                                                    A




                                                                    O

                                                                   LO
                                                     B




                                                                  EG




                                                                  ER
                                                                   D
                                          A

                                                  JE
                                         K




                                                                 O
                                                                 G
                                                                                           POWER STATIONS

                                                                           POWER STATIONS INTALLED CAPACITIES
                                                                           JANUARY-DECEMBER 2007, CHART 10 (SEE TABLE3)
                                        1400


                                        1200
             INSTALLED CAPACITIES(MW)




                                        1000


                                         800


                                         600


                                         400


                                         200


                                          0
                                                                        O


                                                                        AF




                                                                        G
                                                   KA


                                                                JE


                                                                        SH


                                                                        EG


                                                                        AJ


                                                                        A.


                                                                        SA




                                                                        D




                                                                        O


                                                                        O
                                                                        O
                                                                         EL
                                                                          KP




                                                                          ER




                                                                          M


                                                                          LO
                                                                          E.




                                                                           M
                                                                   B




                                                                           AO




                                                                           AM
                                                     IN




                                                                           PE
                                                                           IR


                                                                           BI




                                                                            O
                                                                   BA




                                                                             S




                                                                             O
                                                                             TA
                                                                             AI




                                                                             R
                                                                             EG
                                                       JI




                                                                              O


                                                                              N




                                                                              TO
                                                                               KU




                                                                               LE




                                                                               KU
                                                                               (G




                                                                               U
                                                                                (G
                                                                                RO




                                                                                 G
                                                             H




                                                                                 ST
                                                                       H




                                                                                 (G




                                                                                 N
                                                                                 U




                                                                                  SH
                                                                                  AS
                                                                                  TA




                                                                                   AS
                                                             YD




                                                                                   AS
                                                                                   YD




                                                                                   ST




                                                                                   SO
                                                                                   G
                                                                                    AS
                                                                                    EA




                                                                                    (G


                                                                                     T


                                                                                     O
                                                                                     )




                                                                                      /


                                                                                      )
                                                                 R


                                                                                      R




                                                                                        G
                                                                                        )


                                                                                        AS
                                                                                        M
                                                                  O


                                                                                         O




                                                                                          O
                                                                                            )




                                                                                        POWER STATIONS



                                                                Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                                     21
GT11 was available throughout the year except a five week outage between the 2nd week
of May and 3rd week of June (20th) when the unit was shutdown for overhaul.

GT12 was synchronized to the grid from January to 22nd March. It then went on
inspection and restored by the end of April 2007. The unit pooled power to the grid till
31st December except the last week of September 2007.

1.29.   AJAOKUTA P.S.

Ajaokuta ST1 produced from January to 9th February when it was shutdown for routine
maintenance. It was restored by 17th February but tripped again by 12th March as the
H.P. side of the unit. The unit was then available for 10 weeks after which it tripped on
axial shifts problem in the 2nd week of June. It ran in the next 13 weeks and then tripped
due to System Disturbance. The unit generated into the grid in November and December
2007, except the last week of November when it was out due to low gas pressure.

ST2 was available in the first 3 weeks of January. After a week outage the unit stayed on
grid till the last week of May when it tripped on fault. In the next 13 weeks June to the
1st week in September, the unit generated into the grid following which it tripped and
remained out of service for 10 days. It barely ran for a week when it developed
hydrologic trouble.

From October to 31st December, 2007, the unit was unavailable.

1.30    OMOKU P.S.

Omoku GT1 was available throughout 2007 except 17th to 23rd January when the causes
of its tripping could not be ascertained and the last week in May when it was out of
service on reverse power problem.

Omoku GT2 was available through out 2007.

Omoku GT3 was available throughout 2007 with exception of the 2nd to 4th week of
January when it tripped on fault.

Omoku GT4 was unavailable from January to the 3rd week of March, It then generated till
the 1st week of May when it was shutdown on planned outage. Restored back by 5th June,
the unit was synchronized to the grid. It remained available until the last week of
September when it was on annual maintenance. The unit was still out-of-service by 31st
December, 2007.

1.31    OMOTOSHO P.S.

Commissioning of Omotosho GT1 commenced on 23rd June, 2007. 1st July, the unit
was shutdown for continuation of commissioning test. Tied back to the grid by the 3rd
week of July, GT1 generated till 6th August when it developed starting problem for about




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              22
a week. On 14th August it could not run due to low gas pressure that spanned 10 days.
The unit was however available from 24th August to 31st December, 2007.

Omotosho GT3 was commissioned in the first week of December. It tripped on D.C.
ground fault but was restored by the 2nd week and remained available by 31st December,
2007.

Omotosho GT6 commissioning and commenced in mid October. It generated till 21st
when it tripped due to system disturbance, restored back by the last week of October, it
generated thereafter till 31st December, 2007.

Omotosho GT7 was commissioned tied to the grid on 2nd September 2007. It generated
till 7th October when it tripped on fault. Tied back in the 2nd week of October, the unit
was synchronized to the grid up till 31st December, 2007.

Omotosho GT8 commenced generation by 15th August and was available till 31st
December, 2007.

1.32   GEREGU P. S.

GT1 was commissioned on 9th March 2007. It was shutdown by 18th March for checks.
Restored on 21st March, the unit ran till 26th June when it was shutdown for gas
restoration. Between 1st to 23rd July, the unit generated into the grid.

Thereafter it was on outage due to faulty natural gas unloading valve. From then the unit
was available except 10 days outage on mid September caused by low water pressure and
an 11 – day maintenance outage in early December. The unit was however
synchronously tied to grid by 31st December, 2007.

GT1 started production on 5th April, 2007. Its was on a 4 day outage for gas pipe
restoration on 26th June. From 1st July to August, the unit was tied to the grid.

For almost a month of September the unit was on outage due to vent fan oil leakage.

It generated on October and November but unavailable through out December on faulty
cooling system.

GT13 came on stream in early June. It was however shutdown in order to restore gas
pipe line. Between 7th to 25th July, the unit developed faulty fan motor. From 25th July to
28th September it generated into the grid.

It then went on a week outage to repair the generator transformer tap changer. The unit
was on the grid throughout December, 2007.

1.33   OLORUNSOGO P.S.




          Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                               23
Commissioning of the units commenced in December, 2007.

GT1’s commissioning commenced on 7th. It ran for the rest of December, 2007.

GT2’s commissioning began on 17th December, 2007. It was on the grid for the rest of
December, 2007.

GT3 was commissioned on 10th December, 2007. The unit was still generating by 31st
December, 2007.

GT5 was commissioned on 16th December. It generated for the remaining days of
December, 2007.

1.40   GENERATION ORDERING AND LOAD DISPATCH

An integrated grid was operated in 2007, pooling generation from Kainji, Jebba and
Shiroro Hydro Power Station and Egbin, Delta, Afam, Sapele, AES, Okpai, Omotosho,
Omoku and Olorunsogo thermal Stations.

Inadequate gas supply from the Nigerian Gas Company (NGC) and incessant low gas
pressure militated against full thermal capacity generation into the grid. Among the
affected Stations were: Egbin and AES which although capable of an average generation
of 955.0MW was frequently confined between 200 and 700 MW.

There was a time that the combined stations could only pooled less than 100 MW into the
grid. Likewise, Geregu, Omotosho and Olorunsogo output to the grid was often limited
by gas availability to about 30% of available capacity.

Since generation availability was grossly inadequate to meet the ever increasing load
demand, load shedding continued through out the year in order to maintain power
balance.

1.50   FREQUENCY CONTROL

Due to generation shortage, the grid was operated outside the frequency control policy of
50Hz + 0.40% i.e. 49.80Hz to 50.20Hz, resulting in frequency excursions outside the
operational limits.

Most of the gas turbines on the grid were operated on temperature control mode. Hence
they were often insensitive to vagaries of system frequency.

The automatic voltage regulator (AVRs) and governor system of Kainji, Kaplan units
(variable blades) were not functional. All the other machines in the system were
considered base load, except Jebba units that regulate occasionally.




         Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                              24
ANNUAL ENERGY GENERATED (GWH)
                                                                                 1973-2007 CHART 11
                   07                                                                                                                                                23,187
                   06                                                                                                                                                 23,300
                   05                                                                                                                                                     24,077
                   04                                                                                                                                                      24,132
                   03                                                                                                                                             22,612
                   02                                                                                                                                       21,544
                   01                                                                                                                         17,637
                   00                                                                                                          15,227
                   99                                                                                                                16,291
                   98                                                                                                                16,253
                   97                                                                                                           15,416
                   96                                                                                                              15,971
                   95                                                                                                             15,793
                   94                                                                                                      14,557
                   93                                                                                                      14,617
YEAR




                   92                                                                                                         15,066
                   91                                                                                                    14,212
                   90                                                                                               13,364
                   89                                                                                           12,700
                   88                                                                                  11,471
                   87                                                                                11,141
                   86                                                                             10,665
                   85                                                                          10,155
                   84                                                                 8,927
                   83                                                              8,456
                   82                                                    7,102
                   81                                                  6,766
                   80                                          5,724
                   79                                       5,151
                   78                                  4,359
                   77                                 4,195
                   76                              3,750
                   75                           3,322
                   74                        2,780
                   73                      2,493


                        0                          5000                             10000                            15000                          20000                25000                        30000
                        73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07
       ENERGY(GWH) 24 27 33 37 41 43 51 57 67 71 84 89 10 10 11 11 12 13 14 15 14 14 15 15 15 16 16 15 17 21 22 24 24 23 23

                                                                                 ENERGY GENERATED (GWH)


                                                    SIMULTANEOUS NATIONAL PEAK (MW)
                                                           1973-2007 CHART 12
          07                                                                                                                                                                                   3,600
          06                                                                                                                                                                                       3,682
          05                                                                                                                                                                                            3,774.1
          04                                                                                                                                                                          3,427.5
          03                                                                                                                                                                             3,479.3
          02                                                                                                                                                                3,223.4
          01                                                                                                                                                  2,934.49
          00                                                                                                                                       2,499
          99                                                                                                                                    2,458
          98                                                                                                                                   2,448
          97                                                                                                                                   2,457
          96                                                                                                                                     2,470
          95                                                                                                                                   2,452
          94                                                                                                                                   2,446
          93
YEAR




                                                                                                                                        2,330
          92                                                                                                                               2,382
          91                                                                                                                        2,246
          90                                                                                                                       2,219
          89                                                                                                              2,008
          88                                                                                                           1,952
          87                                                                                                      1,855
          86                                                                                             1,730
          85                                                                                             1,720
          84                                                                                     1,532
          83                                                                                1,434
          82                                                                                 1,448
          81                                                                        1,323
          80                                                               1,181
          79                                                           1,095
          78                                              887
          77                                        767
          76                                     708
          75                               579
          74                         457
          73                   385



               0               500                        1000                         1500                        2000                       2500          3000                      3500                   4000
               73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07
        PEAK 385 457 579 708 767 887 109 118 132 144 143 153 172 173 185 195 200 221 224 238 233 244 245 247 245 244 245 249 293 322 347 342 377 368 360

                                                                                             PEAK DEMAND (MW)




                            Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
                                                                                                    25
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid
Grid

More Related Content

Similar to Grid

Full Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFull Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFernando Penarroyo
 
Calpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALCalpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALfinance29
 
Calpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALCalpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALfinance29
 
The Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory CommissionThe Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory Commissionelectricitygovernance
 
Renewables 2050-presentation
Renewables 2050-presentationRenewables 2050-presentation
Renewables 2050-presentationJaume Satorra
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libreAbanihi
 
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportationsOFFSHORE VN
 
Sierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerSierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerRhys Gerholdt
 
Ee479 -renewable_system_designs,_inc_-_final
Ee479  -renewable_system_designs,_inc_-_finalEe479  -renewable_system_designs,_inc_-_final
Ee479 -renewable_system_designs,_inc_-_finalLoren Schwappach
 
Grid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergyGrid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergySonia Large
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary ServicesIPPAI
 
Presentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfPresentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfHASSAN527910
 

Similar to Grid (20)

Syria
SyriaSyria
Syria
 
Full Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal EnergyFull Steam Ahead For Philippine Geothermal Energy
Full Steam Ahead For Philippine Geothermal Energy
 
Calpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALCalpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINAL
 
Calpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINALCalpine2Q08_Earnings_Presentation_vFINAL
Calpine2Q08_Earnings_Presentation_vFINAL
 
Carl Lenox | SunPower
Carl Lenox | SunPowerCarl Lenox | SunPower
Carl Lenox | SunPower
 
The Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory CommissionThe Experience of the Energy Regulatory Commission
The Experience of the Energy Regulatory Commission
 
Renewables 2050-presentation
Renewables 2050-presentationRenewables 2050-presentation
Renewables 2050-presentation
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre
 
B.praveen kumar
B.praveen kumarB.praveen kumar
B.praveen kumar
 
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations
0030 ndi rev 3 - 15 april 2009 guidelines for marine transportations
 
Sierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local PowerSierra Club: Making the World Safer with Local Power
Sierra Club: Making the World Safer with Local Power
 
Ee479 -renewable_system_designs,_inc_-_final
Ee479  -renewable_system_designs,_inc_-_finalEe479  -renewable_system_designs,_inc_-_final
Ee479 -renewable_system_designs,_inc_-_final
 
Grid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest EnergyGrid Connections And PPAs: Tim Foster, Smartest Energy
Grid Connections And PPAs: Tim Foster, Smartest Energy
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary Services
 
Fort Bragg Energy Briefing
Fort Bragg Energy BriefingFort Bragg Energy Briefing
Fort Bragg Energy Briefing
 
Presentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfPresentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdf
 
Powering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity gridPowering Europe - Wind energy and the electricity grid
Powering Europe - Wind energy and the electricity grid
 
Panasonic 2173
Panasonic 2173Panasonic 2173
Panasonic 2173
 
Managing the Winds of Change – California Experiences
Managing the Winds of Change – California ExperiencesManaging the Winds of Change – California Experiences
Managing the Winds of Change – California Experiences
 
Jnnsm november 2012
Jnnsm november 2012Jnnsm november 2012
Jnnsm november 2012
 

Recently uploaded

Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 

Recently uploaded (20)

Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 

Grid

  • 1. POWER HOLDING COMPANY OF NIGERIA PLC NATIONAL CONTROL CENTRE OSOGBO GENERATION AND TRANSMISSION GRID OPERATIONS 2007 (ANNUAL TECHNICAL REPORT) ISSUED BY: GENERAL MANAGER (S/O) NATIONAL CONTROL CENTRE OSOGBO FEBRUARY, 2008. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
  • 2. TABLE OF CONTENTS PAGES INTRODUCTION 1 1.0 GRID OPERATIONS IN 2007 1 1.1 Hydrology and Lake Operation. 1 1.2 Thermal Generation 9 1.3 Generation Ordering and Load Dispatching 19 1.4 Frequency Control 19 1.5 Voltage Control 19 1.6 Outage Planning 22 1.7 Energy Production 29 2.0 CONSTRAINTS TO GRID OPERATIONS 41 2.1 Constraints to Grid vis-a-vis System Communication 41 2.2 Generation Constraints 49 2.3 Transmission Constraints 49 3.0 REINFORCEMENT AND REHABILITATION OF NATIONAL GRID 62 4.0 SYSTEM DISTURBANCES 66 4.1 Transmission System faults 66 4.2 Generation System faults 66 5.0 ACCIDENTS AND MISHAPS 66 6.0 CONCLUSIONS AND RECOMMENDATIONS 67 7.0 APPENDICES 71 (i) Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
  • 3. NO. LIST OF TABLES PAGE 1A. HYDROLOGICAL SUMMARY 3 1B COMP. AVE.INFLOW AND TURB.DISCH. 6 2 AVERAGE MONTHLY MW AVAILABILITY 12 3 SUMMARY OF GENERATION CAPABILITIES OF PHCN POWER 20 STATIONS AS OPERATED IN 2007 4. PHCN POWER SYSTEM FREQUENCY 27 5A. 2007 OUTAGES STATISTICAL SUMMARY 330KV LINE 29 5B. 2006 OUTAGES STATISTICAL SUMMARY 330KV LINE 29 6A. 2007 OUTAGES STATISTICAL SUMMARY 132KV LINE 30 6B. 2006 OUTAGES STATISTICAL SUMMARY 132KV LINE 30 7. ENERGY GENERATED (MWH) 38 8. HYDRO & THERMAL ENERGY GENERATED(MWH) 39 9. ENERGY GENERATION & POWER CONSUMPTION RECORDS 43 10. MONTHLY ENERGY BALANCE SUMMARY 46 11 ENERGY AVAILABLE FOR SALES PLUS DISTRIBUTION LOSSES IN EACH REGION (MW) 47 12 TOTAL GAS CONSUMED 48 13 COST OF GAS (NAIRA) AGAINST ENERGY GENERATED 2007 49 14 OPERATING FUEL COST (NAIRA/KWh) 50 15 MONTHLY MAXIMUM DEMAND/GENERATION ANALYSIS (MWH) 84 16 SYSTEM GENERATION PEAK LOAD (FORECAST & ACTUAL) 85 17 SUMMARY OF OCCURRENCE MAXIMUM PEAK LOAD 86 18 SUMMARY OF SYSTEM DISTUBANCES 107 19A SUMMARY OF SYSTEM DISTUBANCES OF INTEGRATED GRID 108 19B SUMMARY OF GRID COLLAPSES 109 19C SUMMARY OF SYSTEM DISTURBANCES OF INTEGRATED GRID OPERATIONS 110 (ii) Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
  • 4. NO. CHARTS PAGE 1. KAINJI AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW 4 2. KAINJI HYDROGRAPH 4 3. JEBBA AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW 8 4. JEBBA HYDROGRAPH 8 5. SHIRORO AVERAGE MONTHLY TOTAL DISCHARGE AND INFLOW 9 6. SHIRORO HYDROGRAPH 9 7. 2007 AVERAGE MONTHLY MW AVAILABILITY 14 8. POWER STATIONS AVAILABILITY FACTOR 14 9 POWER STATIONS AVERAGE MW AVAILABILITY 21 10 POWER STATIONS INSTALLED CAPACITY 21 11 ANNUAL ENERGY GENERATED. 25 12 SIMULTANEOUS NATIONAL PEAK DEMAND (MW) 25 13 330KV FORCED OUTAGES (2006 & 2007) 32 14 132KV FORCED OUTAGES (2006 & 2007) 32 15 COMBINED 2006 & 2007 330KV OUTAGES. 33 16 COMBINED 2006 & 2007 132KV OUTAGES. 33 17 330KV PLANNED, URGENT AND EMERGENCY OUTAGES 34 18 132KV PLANNED,URGENT & EMERGENCY OUTAGES 34 19 PERCENTAGE ENERGY USED IN POWER STATIONS 40 20 HYDRO, THERMAL AND TOTAL ENERGY GENERATED 40 21 ENERGY GENERATED IN HYDRO POWER STATIONS 42 22 ENERGY GENERATED IN MAJOR THERMAL POWER STATIONS 42 23 AVAILABLE ENERGY FOR SALES 44 24 TOTAL MONTHLY ENERGY AVAILABLE FOR SALE 44 25 TRANSMISSION REGIONS: MONTHLY ENERGY AVAILABLE FOR SALE 51 (iii) Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
  • 5. NO. CHARTS PAGE 26 REGIONAL ENERGY AVAILABLE FOR SALE 51 27 MAJOR THERMAL STATIONS FUEL COST 52 28 MONTHLY UNIT PROD. COST (NAIRA/UNIT) 53 29 STATIONS AVE. PROD. COSTS (NAIRA/UNIT) 54 30 MONTHLY PEAK DEMAND FORECAST AND ACTUAL GENERATION 87 31 WEEKLY PEAK GENERATION 87 32 KAINJI G.S. USABLE GEN. CAP. SPECTOGRAPH PLOT AVAILABLE 88 33 JEBBA G.S. USABLE GEN. CAP. SPECTOGRAPH PLOT AVAILABLE 88 34 SHIRORO P.S. USABLE GEN. CAP. SPECTOGRAPH 89 35 EGBIN P.S. USABLE GEN. CAP. SPECTOGRAPH 89 36 DELTA P.S. USABLE GEN. CAP. SPECTOGRAPH 90 37 AFAM P.S. USABLE GEN. CAP. SPECTOGRAPH 90 38 SAPELE P.S. USABLE GEN. CAP. SPECTOGRAPH 91 39 OMOTOSHO P.S. USABLE GEN. CAP. SPECTOGRAPH 91 40 AES P.S. USABLE GEN. CAP. SPECTOGRAPH 92 41 OKPAI P.S. USABLE GEN. CAP. SPECTOGRAPH 92 42 GEREGU G.S. USABLE GEN. CAP. SPECTOGRAPH 93 43 OMOTOSHO G.S. USABLE GEN. CAP. SPECTOGRAPH 93 44 OMOKU P.S. USABLE GEN. CAP. SPECTOGRAPH 94 45 AJAOKUTA P.S. USABLE GEN. CAP. SPECTOGRAPH 94 46 OLORUNSOGO P.S. USABLE GEN. CAP. SPECTOGRAPH 95 47 DAILY TOTAL GRID GEN. AVAILABILITY STATUS 95 48 GRAPHICAL REPRESENTATION OF SYSTEM COLLAPSE (DAYS) 111 49 GRAPHICAL REPRESENTATION OF SYSTEM COLLAPSE (MONTHS) 111 50 SUMMARY OF SYSTEM DISTURBANCES 2007 112 51 LOAD LOSS DUE TO SYSTEM DISTURBANCES 112 (iv) Generation and Transmission Grid Operations-2006-National Control Centre, Osogbo
  • 6. lNTRODUCTION T his Technical Report, an annual publication of Power Holding Company Nigeria Plc (PHCN), covered the National Generation and Transmission Grid Operations in 2007. It was collated from NCC electronics data bank. Among the major headings elaborated on were: • 1.0 Grid Operations in 2007. • 2.0 Constraints to Grid Operations in 2007. • 3.0 Reinforcements to the National Grid in 2007. • 4.0 System Disturbances, Accidents and Mishaps in 2007. • 5.0 Accidents and Mishaps • 6.0 Conclusions and Recommendations. Grid Operations in 2007 was compared with the preceding year 2006 and the previous years through tables and graphs. Also presented are detailed analyses of plant and equipment outages, energy generated, transmitted and available to the distribution network. Depicted also are supplementary charts, graphs and other significant details that aid comprehension of the report. 1.0 GRID OPERATIONS IN 2007 The plant average availability at Kainji Power Station in 2007 was 524.1MW. This was 115.3MW higher than 2006 figure of 408.8MW. Jebba’s plant availability ranged between 578.4MW and 559.1MW in 2007 with average availability of 572.3MW. This was greater than 2006 average availability of 554.2MW by 4.9MW. At Shiroro Power Station plant availability throughout the year was little less than 2006. The availability varied between 600MW and 444.4MW in 2007. It stood at an average of 524.8MW. This was just 5.1MW lower than 2006 figure of 529.9MW. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo
  • 7. 1.1 HYDROLOGY AND LAKE OPERATIONS 1.1.1. Kainji Lake The average computed inflow of the 2006/2007 black flood yield into the Kainji Lake was higher than the average forecast inflow by 8.98%. When the black flood inflow was compared with the figures of immediate past five years the 2006/2007 black flood was higher than the 2005/2006 by 14.6%, higher than 2004/2005 by 34.54%, lower than 2003/2004 by 14.78%, higher than 2002/2003 by 22.21%, lower that 2001/2002 by 9.4%. The fairly, good flood yield, brought the head water elevation to 141.69 meters corresponding to a volume of 11.95 billion cubic metres of water at the beginning of the hydro year, January 1st 2007. The black flood peaked on 8th December 2006, with a value of 1724 cubic metres per second (m3/sec). This was (2.78%) higher than the peak daily computed black flood inflow of 2005/2006. At the Joint Operations/Generation Planning meeting held in Jebba Hydroelectric Business Unit on the 7th - 8th March 2007, the planned turbine discharges and the expected inflow into the Kainji Lake from the months of March through August were as in the Table1B. The importance of the meeting was to agree on the draw down trajectory. The forecast inflow between January and June 2007 was 26.85% lower than the actual computed inflow. It was noted that the actual turbine discharge during the period fell short by (1.24%) of the planned discharge, in spite of the fairly robust inflow. This was a result of fall in Kainji MW availability. Also during this period while the Kainji MW was low and Jebba MW availability was higher, hence the amount of inflow into the Jebba Lake was not good enough to keep the head water elevation high for efficient Power Generation. It became necessary to engage on controlled spillage, to sustain Jebba Operations. Between January and April a total average volume of water spilled was 1405.56 cubic metres per second. The difference of 641.66 m3/sec between the average computed total station discharge of 1213.61 m3/sec and the average total computed inflow rate of 571.95 m3/sec resulted in the drawing down of the Lake to an elevation of 130.44 metres by June 28, 2007. This corresponded to a storage balance of 1.38 billion cubic metres of water. This volume was 0.37 billion cubic metres lower than the lowest volume attained on July 24, 2006. It was observed that, the volume attained in 2007 was the lowest ever since the inception of the Kainji Lake Operations 1968. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 2
  • 8. TABLE 1A: HYDROLOGICAL SUMMARY. JANUARY - DECEMBER 2007 AVE.TURB.DISCH. AVE.SPILLAGE STATION AVE.TOT. DISCH COMP.AVE. INFLOW AVE.DAILY ENERGY (CUB.M/SEC) (CUB.M/SEC) (CUB.M/SEC) RATE (CUB.M/SEC) (MWH) MONTH KAINJI JEBBASHIROROKAINJI JEBBASHIRORO KAINJI JEBBA SHIRORO KAINJI JEBBASHIRORO KAINJI JEBBA SHIRORO JAN. 856.13 1419.48 368.84 457.10 0.00 0.00 1313.23 1419.48 368.84 1294.61 1353.77 54.39 7321.87 7864.77 8222.48 Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo FEB. 774.86 1372.57 319.25 541.43 0.00 0.00 1316.29 1372.57 319.25 1069.07 1347.79 27.96 6680.48 7608.39 6921.00 MAR. 1189.32 1288.23 214.81 275.90 0.00 0.00 1465.22 1288.23 214.81 399.74 1379.55 13.19 9670.42 7212.52 4434.10 APR. 1345.23 1669.67 144.73 131.13 0.00 0.00 1476.36 1669.67 144.73 277.80 1572.60 31.47 9938.73 9026.90 3058.93 MAY. 1176.13 1381.16 168.51 0.00 0.00 0.00 1176.13 1381.16 168.51 179.94 1287.84 69.13 8132.87 7544.32 3354.00 JUN. 534.43 653.67 232.17 0.00 0.00 0.00 534.43 653.67 232.17 210.53 676.83 200.43 3608.41 3619.00 4380.87 JAN-JUN 5876.10 7784.78 1448.31 1405.56 0.00 0.00 7281.66 7784.78 1448.31 3431.69 7618.38 396.57 45352.78 42875.90 30371.38 TOTAL JAN-JUN 979.35 1297.46 241.39 234.26 0.00 0.00 1213.61 1297.46 241.39 571.95 1269.73 66.10 7558.80 7145.98 5061.90 AVERAG 3 JUL. 324.03 451.48 362.16 0.00 0.00 0.00 324.03 451.48 362.16 562.48 451.87 527.71 2168.61 2528.77 6870.13 AUG. 833.68 1027.81 376.71 0.00 0.00 0.00 833.68 1027.81 376.71 2209.19 1342.35 1048.87 5366.56 6112.32 7765.71 SEP. 1152.17 2078.80 444.00 0.00 0.00 0.00 1152.17 2078.80 444.00 2620.27 2171.87 951.50 8214.07 12028.07 9532.90 OCT. 1267.74 1988.65 321.29 0.00 0.00 0.00 1267.74 1988.65 321.29 1457.19 1709.45 249.32 9901.06 11106.97 7487.29 NOV. 1248.93 1394.10 321.23 192.50 0.00 0.00 1441.43 1394.10 321.23 1213.2 1514.80 96.17 9876.63 7655.13 7362.63 DEC. 1392.26 1240.23 194.97 0.00 0.00 0.00 1392.26 1240.23 194.97 1307.77 1422.39 38.52 10722.55 7324.00 4356.03 JUL-DEC 6218.81 8181.06 2020.36 192.50 0.00 0.00 6411.31 8181.06 2020.36 9370.10 8612.73 2912.09 46249.48 46755.26 43374.70 TOTAL JUL-DEC 1036.47 1363.51 336.73 32.08 0.00 0.00 1068.55 1363.51 336.73 1561.68 1435.46 485.35 7708.25 7792.54 7229.12 AVERAG ANNUAL 12094.91 15965.84 3468.67 1598.06 0.00 0.00 13692.97 15965.84 3468.67 12801.79 16231.11 3308.66 91602.26 89631.16 73746.08 TOTAL AVERAG 1007.91 1330.49 289.06 133.17 0.00 0.00 1141.08 1330.49 289.06 1066.82 1352.59 275.72 7633.52 7469.26 6145.51 E
  • 9. KAINJI AVE.MONTHLY TOT. DISCHARGE & INFLOW JANUARY-DECEMBER 2007, CHART 1 (SEE TABLE 1) 2800 2400 FLOW IN CUBIC METRES/SEC 2000 1600 1200 800 400 0 JAN. FEB. MAR. APR. MAY. JUN. JUL. AUG. SEP. OCT. NOV. DEC. MONTHS DISCHARGE INFLOW KAINJI HYDROGRAPH 1994-2007 CHART 2 144 142 HEAD WATER ELEVATION IN METRES 140 138 136 134 132 130 JAN. FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MONTHS 2007ACTUAL 2006ACTUAL 2005ACTUAL 2004ACTUAL 2003ACTUAL 2002ACTUAL 2001ACTUAL 2000ACTUAL 1999ACTUAL 1998ACTUAL 1997ACTUAL 1996ACTUAL 1995 ACTUAL 1994 ACTUAL Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 4
  • 10. The fast draw down was as a result of National demand as the gas supply to the Thermal Power Stations was unstable. To maintain supply during the nationwide elections and subsequent inaugurations, all available water was used to generate power. At the Joint Operations/Generation Planning meeting held in Shiroro Hydro Electric PLC, between 5th and 6th September 2007, the impoundment program from September 2007 – February 2008 for the white flood and subsequent black flood was agreed on. Normally, it was convenient to fill the Kainji Lake to an elevation of 140.06 metres corresponding to a volume of 10 billion cubic metres of water by the end of the white flood usually October ending. Records showed that the actual average computed inflow was slightly higher than forecast inflow by 0.76%. The average actual turbine discharge during the white flood was (17.65%) lower than the planned turbine discharge, because Kainji 1G6 which was expected to be on the grid in September was surprisingly unavailable. The peak of the computed white flood occurred on 1st September 2007, with a magnitude of 4660 m3/sec. That magnitude was 1.75% higher than the peak value of 4580 m3/sec of the previous year which occurred on September 8, 2006. All the available units in Kainji Power station were kept running to avoid spillage. It has to be mentioned that, if the Kainji Lake was not drawn down to the lowest elevation ever, spillage was would have been inevitable. At that period, spillage in Kainji would have been undesirable for Jebba Lake whose head water elevation was above 102.5 metres already. By the end October 2007, the Kainji Lake head water elevation was 140.04 metres, corresponding to almost 10.00 billion cubic metres as planned. Before the end of October, Jebba Lake head water was observed to have to be reduced drastically, because Kainji turbine discharge was not high enough as the lateral inflow into the Jebba Lake has dropped significantly. By October 30, 2007, the Jebba Lake head water elevation had dropped to 99.9 metres. For 13 days, from 1st – 13th November 2007, controlled spillage was embarked on Kainji spillway gate. An average of 192.50 m3/sec was spilled, to boost Jebba Lake. The head water elevation of the Kainji Lake was at 139.24 metres, corresponding to 9.08 billion cubic metres by the month of December 31st, 2007. This volume was lower (31.61%) than the volume obtained by the same time 2006. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 5
  • 11. TABLE1B: PLAN/ACTUAL COMP. AVE. INFLOW AND AVE. TURB. DISCH. (CUB.M/SEC). JANUARY - DECEMBER 2007. KAINJI JEBBA SHIRORO AVER. MON ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN INF. LATERA TH INF. DISC. DISC. INF. INF. DISC. DISC. INF. INF. DISC. DISC. L INF JAN. 1121.00 1294.61 900.00 856.13 891.00 1353.77 920.00 49.84 1419.48 15.00 54.39 200.00 368.84 Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo FEB. 568.00 1069.07 900.00 774.86 883.00 1347.79 950.00 11.07 1372.57 12.00 27.96 200.00 319.25 MAR. 572.00 399.74 1200.00 1189.32 994.00 1379.55 900.00 22.65 1288.23 15.00 13.19 200.00 214.81 APR. 200.00 277.80 1200.00 1345.23 1007.00 1572.60 850.00 96.97 1669.67 25.00 31.47 200.00 144.73 MAY. 102.00 179.94 1000.00 1176.13 778.00 1287.84 758.00 90.97 1381.16 108.00 69.13 200.00 168.51 JUN. 142.00 210.53 750.00 534.43 864.00 676.83 864.00 119.97 653.67 192.00 200.43 200.00 232.17 6 JUL. 333.00 652.48 700.00 324.03 1307.00 451.87 1320.00 135.13 451.48 442.00 527.71 300.00 362.16 AUG. 1629.00 2209.19 1080.00 833.68 1363.00 1342.35 1380.00 528.90 1027.81 794.00 1048.87 300.00 376.71 SEP. 2526.00 2620.27 1374.00 1152.17 2311.00 2171.87 2020.00 1019.67 2078.80 1191.00 951.50 500.00 444.00 OCT. 2084.00 1457.19 1374.00 1267.74 2109.00 1709.45 1909.00 449.48 1988.65 510.00 249.32 450.00 321.29 NOV. 1556.00 1213.20 1410.00 1248.93 1492.00 1514.80 1492.00 62.63 1394.10 88.00 96.17 300.00 321.23 DEC. 1644.00 1307.77 1410.00 1392.26 1434.00 1422.39 1500.00 44.97 1240.23 35.00 38.52 200.00 194.97
  • 12. Overall Kainji MW availability was better (28.2%) than the figure of the previous year (see chart 1&2) 1.1.2 Jebba Lake At the beginning of the hydro year, 1st January 2007, the head water elevation at Jebba lake was at 100.96 metres, corresponding to 3.2875 billion cubic metres. This was slightly higher (0.23%) than the storage balance of 3.28 billion cubic metres of water recorded at the beginning of 2006 hydro year. Appreciable lateral inflow into the Jebba Lake started on 25th August 2007, with a value of 1223 m3/sec. It peaked on 28th August 2007 with a value of 1813 m3/sec and ebbed out after the second week of October. The peak value was higher (39.68%) than the peak lateral inflow recorded on September 17th, 2006. During the year, the minimum head water recorded, was 99.02 metres which occurred on June 26th, 2007. The maximum station turbine discharge of 2266 m3/sec occurred on September 10, 2007, and the maximum computed inflow of 2876 m3/sec occurred on August 28, 2007. When the head water elevation was 102.73 metres on September 9th, 2007, the six units were run for 24 hours for almost 12 days. Due to unstable gas supply to the Thermal Power Plants, great demand was on the hydro plants. This head water elevation (102.73metres) corresponded to a storage balance of 3.803 billion cubic metres (see chart 3 &4) From Table 2, Jebba MW availability was higher than the previous year by 3.27%. Even though Kainji MW availability improved this year, it was evident from Table 1A the monthly average turbine discharge which was the primary source of inflows into Jebba Lake was always lower than Jebba turbine discharge because of its MW availability. For this reason the head water elevation in Jebba lake was always drawn down early in the year. By the end of the year, December 31st 2007, the head water elevation in Jebba was 102.74 metres, corresponding to 3.805 billion cubic metres of water. This was 15.65% higher than the headwater of the Lake at the same period 2006. 1.1.3 Shiroro Lake At the beginning of the hydro year, January 1st 2007, the reservoir head water elevation was 376.29 metres corresponding to a storage balance of 4.2678 billion cubic metres of water. This volume was lower (6.68%) than the storage balance at the same time 2006. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 7
  • 13. JEBBA AVE. MONTHLY TOTAL DISCHARGE & INFLOW JANUARY-DECEMBER 2007, CHART 3 (SEE TABLE 1) 2500 2000 FLOW IN CUBIC METRES/SEC 1500 1000 500 0 JAN. FEB. MAR. APR. MAY. JUN. JUL. AUG. SEP. OCT. NOV. DEC. MONTHS DISCHARGE INFLOW JEBBA HYDROGRAPH 1994-2007 CHART 4 103.5 103 HEAD WATER ELEVATION IN METRES 102.5 102 101.5 101 100.5 100 99.5 JAN. FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MONTHS 2007ACTUAL 2006ACTUAL 2005ACTUAL 2004ACTUAL 2003ACTUAL 2002ACTUAL 2001ACTUAL 2000ACTUAL 1999ACTUAL 1998ACTUAL 1997ACTUAL 1996ACTUAL 1995 ACTUAL 1994 ACTUAL Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 8
  • 14. SHIRORO AV. MONTHLY TOT. DISCHARGE & INFLOW JANUARY-DECEMBER 2007 CHART 5 (SEE TABLE 1 ). 1300 1200 1100 1000 FLOW IN CUBIC METRES/SEC 900 800 700 600 500 400 300 200 100 0 JAN. FEB. MAR. APR. MAY. JUN. JUL. AUG. SEP. OCT. NOV. DEC. MONTHS DISCHARGE INFLOW SHIRORO HYDROGRAPH 1994-2007, CHART 6 385 380 HEAD WATER ELEVATION IN METRES 375 370 365 360 355 JAN. FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MONTHS 2007ACTUAL 2006 ACTUAL 2005 ACTUAL 2004 ACTUAL 2003ACTUAL 2002ACTUAL 2001ACTUAL 2000ACTUAL 1999ACTUAL 1998ACTUAL 1997ACTUAL 1996ACTUAL 1995ACTUAL 1994ACTUAL Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 9
  • 15. The draw down plan of the Shiroro Lake between March and August 2007 was agreed upon at the Joint Operations/Generation Planning meeting held in Jebba Hydroelectric Business Unit on the 7th & 8th March 2007, as displayed in table 1B. The actual computed inflow during the period was higher than the forecast inflow by 19.97%. Total station turbine discharge exceeded the total computed by 1079.89 m3/sec. This resulted in drawing down the lake to an elevation 358.41 metres by July 13, 2007. The unstable gas supply from the Nigerian Gas Company forced the Operation to draw down the lake to that all time low head water elevation. This elevation was lower the previous year minimum elevation of 359.65 metres on July 15, 2006 by 0.1427 billion cubic metres. The pattern of flood yield into the Shiroro Lake this year can be described as sporadic. The flood peaked in August and substantial inflow was for short duration about three weeks precisely. The peak value of computed inflow recorded was 3175 m3/sec on August 28, 2007. The forecast inflow was 794 m3/sec, while the actual computed inflow was 1048.87 m3/sec. Hope rose that definitely the Lake will be filled during the flood season. After the first twelve days in September the inflow ebbed out. The hope was suddenly dashed. Usually, it was planned to fill the lake within the first two weeks in October every year, but the disappointing inflow yield of September, torpedoed the plan. Maximum head water elevation attained during the flood was 379.37 metres on September 30, 2007. When it became obvious that the lake could not be filled, water regulation started. The head water elevation improved 379.49 metres corresponding to 4.987 billion cubic metres on October 12, 2007. Since appreciable inflows were not expected into the Shiroro Lake, plans were drawn out, in order to manage the available water resource from October 2007 till mid-July 2008. Overall Shiroro MW availability throughout 2007, dropped slightly by 0.97%, when compared with 2006 figure. By December 31st 2007, the head water elevation stood at 373.68 metres corresponding to a storage balance of 3.7188 billion cubic metres. This balance was 14.76% lower than the storage balance at the same time 2006. (See chart 5&6). Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 10
  • 16. 1.2. THERMAL GENERATION 1.20. GENERATION AVAILABILITY In table 2, the average Power(MW) availability was depicted. Analysis of the year’s thermal availability was conducted employing the popular relevant statistical measures. Thermal plant average availability was 2535.0MW in 2007. Of this figure 699.5MW (27.59%) was contributed by the 3 Independent Power Producers (IPP). The thermal availability was 60.99% of aggregate of Hydro and thermal availability of 4156.2MW in 2007. It surpassed 2006 figure of 2396.4MW by 138.6MW. 1.21 SAPELE G. S. Sapele ST1 generated from January to 23rd May, when it was on forced outage. Restored back on 26th, the unit remained synchronized to the grid till 6th September when it tripped on high vibration. Between 13th September and 25th October the unit was available. It then went through a 3 week outage to clear serious oil leakage on the generator. Tripped on 20th November on supper heater very high temperature the unit was restored by November ending and generated through out December, 2007. Sapele ST2 which had been on outage since September, 2002 due to high bearing problem was restored to the grid in August, 2007. It tripped on turbine high vibration on 6th August. After a week of outage the unit was available till 31st August when it was forced out of the grid for a week due to restricted earth fault. It generated throughout September until it tripped during the system disturbance early October. From 30th October to the 2nd week of November, the unit was available. It then tripped on control oil pressure and remained unavailable throughout December, 2007. Sapele ST3 was unavailable since 28th May, 2006 due to faulty generator transformers. By 31st December, 2007, the unit was still unavailable. Sapele ST4 was forced out of the grid due to high winding temperature fault since the third quarters of 1994. It was still unavailable by 31st December, 2007. Sapele ST5 has been on outage since 2nd March, 1986 when its unit transformer and associated switchgear got burnt. The unit was unavailable by December, 31st 2007. Sapele ST6 tripped following System disturbance on the 29th September, 2005. The ensuing fire outbreak in the station destroyed the governor control cable. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 11
  • 17. TABLE 2 AVERAGE MONTHLY MW AVAILABILITY JAN. TO DEC. 2007 THERMAL THERMAL THERMA HYDRO GRAND KAINJI JEBBA SHIROR EGBIN AJAOKU A.E.S SAPEL OKPAI AFAM DELTA GEREGU OMOK OMOTOS PAPALANT TOTAL MONTHS TOTAL L TOTAL TOTAL TOTAL MW MW O MW MW TA MW MW E MW MW MW MW MW U MW HO MW O MW (PHCN) (IPP) MW MW MW MW MW JAN. 421.9 578.4 595.2 997.4 80.5 256.3 108.4 444.5 166.9 474.5 0.0 34.8 0.0 0.0 1827.6 735.5 2563.2 1595.5 4158.7 FEB. 375.6 561.2 444.4 831.1 91.7 212.4 0.0 91.7 447.4 57.0 435.7 0.0 67.2 0.0 1930.1 304.1 2234.2 1381.3 3615.5 MAR. 522.2 566.4 520.3 641.1 90.9 172.1 112.5 366.1 73.3 427.1 76.3 86.0 0.0 0.0 1421.2 624.1 2045.3 1608.9 3654.2 Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo APR. 580.8 569.1 517.7 709.7 92.6 166.1 116.1 314.5 106.8 334.2 96.8 230.5 0.0 0.0 1456.3 711.1 2167.4 1667.6 3835.0 MAY. 601.1 578.4 454.8 752.3 94.0 200.5 85.2 387.1 232.6 346.1 330.8 72.5 0.0 0.0 1840.9 660.1 2501.0 1634.4 4135.4 JUN. 479.2 578.4 520.0 689.3 91.7 198.1 112.0 330.2 205.9 330.9 350.1 88.3 40.4 0.0 1820.3 616.6 2436.9 1577.6 4014.4 JAN-JUN 2980.9 3431.9 3052.5 4620.9 541.4 1205.5 534.2 1934.0 1232.9 1969.7 1289.7 512.0 107.7 0.0 10296.5 3651.5 13948.0 9465.2 23413.2 TOTAL JAN-JUN AVERAG 496.8 572.0 508.7 770.1 90.2 200.9 89.0 322.3 205.5 328.3 214.9 85.3 17.9 0.0 1716.1 608.6 2324.7 1577.5 3902.2 E JUL. 596.8 578.4 469.4 794.8 110.0 198.3 127.7 479.2 204.8 363.0 284.7 100.0 22.3 0.0 1907.4 777.5 2684.9 1644.5 4329.4 12 AUG. 545.2 562.9 585.5 709.7 110.0 238.0 197.4 479.2 204.8 311.8 392.4 96.0 67.0 0.0 1993.1 813.1 2806.2 1693.5 4499.7 SEP. 492.3 578.4 540.0 814.0 89.8 229.2 176.2 437.2 243.2 370.3 255.7 94.2 138.6 0.0 2087.9 760.6 2848.5 1610.7 4459.2 OCT. 555.3 578.4 595.5 660.0 5.0 234.2 81.8 456.0 265.8 381.7 276.0 75.0 153.9 0.0 1824.2 765.2 2589.4 1729.2 4318.6 NOV. 548.7 559.1 600.0 566.9 60.0 267.9 137.7 472.1 290.8 358.0 276.0 75.8 200.0 0.0 1889.3 815.9 2705.2 1707.7 4412.9 DEC. 570.6 578.4 454.8 660.0 55.0 266.3 120.0 468.9 295.2 311.0 230.5 75.0 231.9 123.4 2027.0 810.2 2837.2 1603.9 4441.1 JUL-DEC 3308.9 3435.5 3245.1 4205.4 429.8 1434.0 840.9 2792.6 1504.4 2095.8 1715.3 516.0 813.8 123.4 11729.0 4742.6 16471.5 9989.5 26461.0 TOTAL JUL-DEC AVERAG 551.5 572.6 540.9 700.9 71.6 239.0 140.1 465.4 250.7 349.3 285.9 86.0 135.6 20.6 1954.8 790.4 2745.3 1664.9 4410.2 E ANNUAL STN. 524.1 572.3 524.8 735.5 80.9 220.0 114.6 393.9 228.1 338.8 250.4 85.7 76.8 10.3 1835.5 699.5 2535.0 1621.2 4156.2 AVERAG E
  • 18. The unit was restored on the 3rd week of September, 2006. By November, 2006 it developed bearing vibration trouble. It was virtually out of service in 2007 due to crack on the turbine blade and high vibration. 1.22 AFAM P. S. Afam GT1 was out of service since last quarter of 1993. It remained out of service by December, 2007. Afam GT2 - scrapped. Afam GT3 out of service since February 1990 on damaged exciter and generator bearing problem, still maintained its enoperatable state by December, 2007. Afam GT4 was unavailable due to rotor balancing and labyrinth seal problem since 1998. Afam GT5 was on outage due to excessive oil leakage from the generator between January and the third week of February. It ran for only a week and was then shut down due to smoke on the exciter. Tied in the first week of August, it rolled generation into the grid till 28th September, 2007. It was on bars for 9 days before it tripped as a result of system disturbance. Having generated the last week of September, the unit tripped again on turbine main lube oil low pressure. By 31st December, 2007, the unit was still out of service. Afam GT6 was unavailable throughout the year with the exception of the first five days of January, having developed high turbine inlet temperature. Afam GT7 was unavailable in the year on burnt generator breaker and control cable faults. Afam GT8 had been on outage since 3rd April, 1988 on damaged turbine and turbine blade failure. GT9’s major overhaul was suspended in the last quarter of 1995 and still on breakdown outage since. GT10 supposed to be on rehabilitation since 2002 was still unavailable by December, 31st 2007. GT11 was out of service in September 1997 due to the fatal fire outbreak at Afam P.S. though it was restored to service 2 weeks after, it sooned tripped on oil drain high temperature and still out by 31st December, 2007. Afam GT12 was shutdown in August 1998 due to compressor blade failure. It was still out of service at the expiration of 2007. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 13
  • 19. 2007 AVE. MONTHLY MW AVAILABILITY JANUARY-DECEMBER 2007 CHART 7(SEE TABLE2) 2500 2000 MONTHLY AVAILABILITY 1500 1000 500 0 J F M A M J J A S O N D MONTHS KAINJI JEBBA SHIRORO SAP.TOT AFAM EGBIN DELTA IJORA CALABAR AES OKPAI AJAOKU THMAL PHCN THMAL IPP HYDRO TOT GRAND TOT OMOKU POWER STATIONS AVAILABILITY FACTOR JANUARY-DECEMBER 2007, CHART 8(SEE TABLE 3) 1.20 AVAILABILITY FACTOR 1.00 0.80 0.60 0.40 0.20 0.00 ) O O O O RO M ST / ) T ) ) TA AS AS AS AS AS G R R SH G EA KU YD YD O LE SO G (G (G (G KU (G ST TO IR AI AO PE H H N AM S O TA SH U O KP E. N U M JI A EG SA AJ M EL BI R AF BB IN A. O O O LO EG ER D KA JE O G POWER STATIONS Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 14
  • 20. Afam GT13 had been on outage due to turbine failure since February 1997. By the end of 2007, the unit was still unavailable. Afam GT14 which had been on outage due to compressor blade failure since April 1992 was on outage by December, 2007. Afam GT15 had been out of service since 1995 and required major overhaul to come back on stream. Afam GT16 which had compressor blades failure in 1992 was still unavailable by 31st December, 2007. Afam GT17 was out of service on ignition failure from January to October 21, 2007. It came back on stream briefly and was later shutdown for reliability test. By November, when the reliability test was over, it only generated for 2 days following which it was shutdown due to bearing oil leakage. It was still on outage by December, 2007. GT18 was shutdown from January to 15th October to clear the accumulated condensates on the gas pipeline. It generated in the 2nd weekend, shutdown thereafter on low gas pressure. Returned to the grid in early November, the unit tripped a week after on low gas pressure. Attempts to restore it failed as condensate problems surfaced. By 31st December, 2007, the unit was out of service. GT19 was out of service on high air intake differential pressure. The unit was synchronized to the grid a week after. Between 14th and 23rd January, it went out of service on dirty air inlet filters. From 8th April to end of June, the unit was available. Out for a week on underfrequency, the unit was available thereafter till the expiration of 2007. GT20 generated into the grid in the first 14 days of January. It was then shutdown due to dirty air inlet filters till 16th March. On 25th March, it shutdown again due to air intake filter leakages. The unit was available then till the end of 2007 except the third week of June when it tripped on high inlet temperature. Afam average plant availability was 166.9 MW in January 2007. The first half annual peak of 232.6 MW was attained February. In the second half of the year, the peak average demand was 295.2 MW, recorded in December. The year’s average MW availability was 228.1MW. It was 147.8MW (189%) greater than 2006 figure of 80.30 MW. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 15
  • 21. 1.23 DELTA P.S. Delta GT1 & GT2 had been scrapped. Delta GT3, 4 & 5 were out of service due to non-availability of the 81MVA 11/132kV transformer since January 2006 and remained unavailable by the end of 2007. Delta GT6 was generally available in 2007. It only went out on a week outage on excitation fault. Delta GT7 was available from January to mid May when it was on a week outage. It ran thereafter till the 3rd week in July when it was on forced outage for a week. By the 2nd week of November, the unit developed compressor bleed valve trouble and was still unavailable by 31st December, 2007. Delta GT8 was in service from January to 17th April. It developed serious oil leakage from reduction gear for a week and run till the 2nd week of September when it shutdown due to faulty generator bleed valve position trouble. It thereafter generated in the 3rd and 4th week of October but tripped in early November. It was thereafter synchronized to the grid till the end of December, 2007. Delta GT9 was generally available through out the year except the outage to seal the oil leakage on its unit transformer between 7th and 18th February, 2007. Delta GT10 was available from January to 7th February. It then went on outage to seal the oil leakage on the unit transformer. Returned to the grid by 18th February, the unit ran till the 1st week in September when it tripped on excitation trouble. After a week outage the unit remained on the grid till 31st December, 2007. Delta GT11 was on the grid from January to 7th February when it was shutdown on planned outage to seal oil leakage on its unit transformer. Restored to the grid on 18th February, the generating unit was available till the end of 2007. Delta GT12 was available through out the year except the planned outage on the 3rd week of July, 2007. Delta GT13 was available in the year 2007 except the 3rd week in July when it was on planned outage and the last week of December when the unit was shutdown due to abnormal bearing problem. Delta GT14 was on the grid from January to the 3rd week of July when it was on planned outage. It then generated till mid October when it tripped on exhaust over temperature. By 31st December, 2007, the unit was still unavailable. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 16
  • 22. Delta GT15 was available from January to March 2007. It developed starting problem and remained out of service by 31st December, 2007. Delta GT16 was still undergoing rehabilitation in 2007. Delta GT17 was out of service from January to 31st July 2007. It ran for 13 days in August. Thereafter, it was shutdown due to fire in the turbine accessory. Delta GT18 was available throughout 2007 except the last 3 weeks of August when it was on outage due to high exhaust temperature. Delta GT19 had been on outage since April 1998 on combustion trouble. Rehabilitation was still in been awaited by 31st December, 2007. Delta GT20 generated into the grid from January to 19th February 2007, when it developed hydrogen gas leakage. By February 28 the unit was tied to the grid. It tripped again by 1st April on faulty crank motor. Synchronized back on 14th April, the unit generated till 18th May when it tripped on ignition problem. The unit was then available from mid June till 31st December, 2007. Delta monthly average availability was 474.5 MW in January 2007. That was the mid year peak generation. In the second half of the year, the peak demand was 381.7 MW recorded in October, 2007. The Station’s annual average availability was 338.8MW. It was 31.21% lower than 2006 value of 492.5 MW. 1.24. EGBIN P.S. Egbin ST1 was available from January to April 2007. It was shutdown from 1st to 17th May for condenser cleaning. The unit was then available till the last week of July when it tripped on control system failure. By the third week of September the unit was out for inspection. Restored to the grid by the 2nd week of November, the unit generated for a week. It was thence available till 31st December, 2007 except a week of outage to clear its control valve problem. Egbin ST2 was available throughout the year except a week outage each in April and June 2007. Egbin ST3 was on the grid from January to the tail end of January when it developed boiler problem. By 31st December, 2007 the unit was still unavailable Egbin ST4 generated from January to the first week in March, 2007. It then went on planned outage till 21st March. It was shutdown for condenser cleaning in the third week Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 17
  • 23. of June and went on planted outage in the last week of August. It was thereafter available till 31st December, 2007. Egbin ST5 was available from January to 20th March when it went on outage due to generator breaker fault. It remained on bars thence. Egbin ST6 which tripped on 13th March, 2006 on furnace distortion remained unavailable by 31st December, 2007. Egbin plant generation availability was 997.4 MW in January, 2007. That was the peak availability for the 1st half of the year (January to June). In the second half of the year, the peak plant generation availability of 814.0 MW was attained in September. Annual average generation availability was 735.5 MW. It fell short of 2006 value of 1005.5 MW by 26.80%. 1.25 IJORA P.S. Ijora GT4 was awaiting commissioning throughout the year 2007. GT5 which had been on breakdown outage due to exhaust plenum fault since the third week of March, 2006 was still unavailable by 31st December, 2007 1.26 CALABAR P.S. Calabar EE1 was unavailable since the 2nd week of March, 2002 on burnt bearing. By 31st December, 2007 the unit was still unavailable. Calabar EE2 has been out of service due to abnormal noise since 31st March, 2005. It was still unavailable by 31 December, 2007 GM2’s starting problem that commenced in June 2004, continued throughout 2007. 1.27 AES – INDEPENDENT POWER PRODUCERS (IPP) AES Barge 202 was tied to the grid from January to December 2007, safe a week outage in the last week of January and the 2nd week of April when it was shutdown due to the Nigeria Gas Company (NGC) pigging work. Barge 203 ran from January to 9th March. It then tripped on high bearing vibration. Tied back in the 1st week of April, it generated for only 3 days after which it was shutdown due to condensate problem. From early May to the 3rd week of July, it was unavailable due to bearing, it failure and lube oil leakage. The unit was synchronized to the grid from 4th week in July to 31st December, 2007. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 18
  • 24. Barge 204 was on the grid between January and 5th April when it was shutdown due to condensate problem. It was tied back on 12th April and ran till 22nd May when it tripped on high frequency. Between June and December 2007, the unit went on outage thrice viz: 1st to 8th September on maintenance outage; third week of September due to water leakage from cooling water pump and 26th October to the first week of November due to rotating pump problem. AES 205 barge went on outage six times in 2007. Between 22nd and 9th February it was shutdown to reposition its circuit. From 1st to 22nd March it was unavailable on diesel main starting problem. In second week of April, it was shutdown due to condensate problem. From the first week in September to 19th October, a major combustion inspection was carried out on the unit. By 31st December 2007, the unit was still available and synchronized to the grid. Barge 207 ran from January to 5th February. It was on planned outage thence till the tail end of February. On the 2nd week of April it had starting problem. Synchronized on 18th April, it ran till 8th May when it was shutdown 7 weeks for compressor washing. It later went on outage from 3rd July to the 2nd week of August on generator fault. The unit was however available thereafter till 31st December, 2007. Barge 208 generated in the first 3 weeks of January, tripped on turbine bearing high vibration and remained out of service till 10th May. It generated thence till 31st December except outage in June (15th – 13th); August (1st week maintenance) and November (1st week due to serious water leakage. Barge 209 was mostly available in 2007. It was shutdown only once in the third week of March due to condensate problem. Barge 210 was available from January to December, 2007 except a week outage in the 2nd week of April due to condensate problem. Barge 211 was on outage due to transformer fault. It ran till 2nd week in April when it was shutdown due to condensate problem. From then till 31st December, 2007, the unit produced energy into the grid. 1.28 OKPAI IPP Okpai ST1 was synchronized to the grid from January to 10th April when it went on outage due to steam leakages. Restored on 29th April, the unit was available till 31st December except the first week of June when it tripped on fault and the third week of December when it was shutdown for generator maintenance. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 19
  • 25. TABLE 3. SUMMARY OF GENERATION CAPABILITIES OF PHCN POWER STATIONS AS OPERATED IN THE YEAR 2007( JANUARY - DECEMBER ) AVAILABILIT AVERAGE INSTALLED POWER STATION Y FACTOR AVAILABILIT CAPACITY (MW) (MW) Y (MW) KAINJI HYDRO 0.69 524.14 760.00 JEBBA HYDRO 0.99 572.28 578.40 SHIRORO 0.87 524.80 600.00 EGBIN STEAM 0.56 735.53 1320.00 AJAOKUTA 0.90 80.94 90.00 A.E.S (GAS) 0.81 219.96 270.00 SAPELE ST 0.11 114.59 1020.00 OKPAI GAS/ 0.88 393.88 450.00 AFAM (GAS) 0.37 228.11 623.00 DELTA (GAS) 0.38 338.80 882.00 GEREGU (GAS) 0.60 250.42 414.00 OMOKU GT 0.86 85.67 100.00 OMOTOSHO 0.23 76.79 335.00 OLORUNSOGO 0.03 10.29 335.00 TOTAL 0.53 4156.19 7777.40 DEFINITIONS:- 1. AVAILABILITY FACTOR = AVERAGE MW. AVAILABILITY PI 2. PI = The sum of current site rating of commissioned units installed in the station for the year. 3. AVERAGE MW. AVAILABIL = This is a measure of average usable MW capacity of each station putting gas pressure constraints and other external factors into consideration. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 20
  • 26. POWER STATIONS AVERAGE MW AVAILABILITY JANUARY-DECEMBER 2007, CHART 9 (SEE TABLE 3) 800.00 700.00 AVERAGE MW AVAILABILITY (MW) 600.00 500.00 400.00 300.00 200.00 100.00 0.00 TA S) S) S) S/ RO S) O M ST O O RO T G R G SH EA A A A A A U YD YD O LE SO IG (G (G (G (G U K TO ST IR K O PE H H PA N M .S TA O SH U JA O RU IN FA A JI M .E EG SA K M EL B IN A O B A O A O LO B EG ER D A JE K O G POWER STATIONS POWER STATIONS INTALLED CAPACITIES JANUARY-DECEMBER 2007, CHART 10 (SEE TABLE3) 1400 1200 INSTALLED CAPACITIES(MW) 1000 800 600 400 200 0 O AF G KA JE SH EG AJ A. SA D O O O EL KP ER M LO E. M B AO AM IN PE IR BI O BA S O TA AI R EG JI O N TO KU LE KU (G U (G RO G H ST H (G N U SH AS TA AS YD AS YD ST SO G AS EA (G T O ) / ) R R G ) AS M O O O ) POWER STATIONS Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 21
  • 27. GT11 was available throughout the year except a five week outage between the 2nd week of May and 3rd week of June (20th) when the unit was shutdown for overhaul. GT12 was synchronized to the grid from January to 22nd March. It then went on inspection and restored by the end of April 2007. The unit pooled power to the grid till 31st December except the last week of September 2007. 1.29. AJAOKUTA P.S. Ajaokuta ST1 produced from January to 9th February when it was shutdown for routine maintenance. It was restored by 17th February but tripped again by 12th March as the H.P. side of the unit. The unit was then available for 10 weeks after which it tripped on axial shifts problem in the 2nd week of June. It ran in the next 13 weeks and then tripped due to System Disturbance. The unit generated into the grid in November and December 2007, except the last week of November when it was out due to low gas pressure. ST2 was available in the first 3 weeks of January. After a week outage the unit stayed on grid till the last week of May when it tripped on fault. In the next 13 weeks June to the 1st week in September, the unit generated into the grid following which it tripped and remained out of service for 10 days. It barely ran for a week when it developed hydrologic trouble. From October to 31st December, 2007, the unit was unavailable. 1.30 OMOKU P.S. Omoku GT1 was available throughout 2007 except 17th to 23rd January when the causes of its tripping could not be ascertained and the last week in May when it was out of service on reverse power problem. Omoku GT2 was available through out 2007. Omoku GT3 was available throughout 2007 with exception of the 2nd to 4th week of January when it tripped on fault. Omoku GT4 was unavailable from January to the 3rd week of March, It then generated till the 1st week of May when it was shutdown on planned outage. Restored back by 5th June, the unit was synchronized to the grid. It remained available until the last week of September when it was on annual maintenance. The unit was still out-of-service by 31st December, 2007. 1.31 OMOTOSHO P.S. Commissioning of Omotosho GT1 commenced on 23rd June, 2007. 1st July, the unit was shutdown for continuation of commissioning test. Tied back to the grid by the 3rd week of July, GT1 generated till 6th August when it developed starting problem for about Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 22
  • 28. a week. On 14th August it could not run due to low gas pressure that spanned 10 days. The unit was however available from 24th August to 31st December, 2007. Omotosho GT3 was commissioned in the first week of December. It tripped on D.C. ground fault but was restored by the 2nd week and remained available by 31st December, 2007. Omotosho GT6 commissioning and commenced in mid October. It generated till 21st when it tripped due to system disturbance, restored back by the last week of October, it generated thereafter till 31st December, 2007. Omotosho GT7 was commissioned tied to the grid on 2nd September 2007. It generated till 7th October when it tripped on fault. Tied back in the 2nd week of October, the unit was synchronized to the grid up till 31st December, 2007. Omotosho GT8 commenced generation by 15th August and was available till 31st December, 2007. 1.32 GEREGU P. S. GT1 was commissioned on 9th March 2007. It was shutdown by 18th March for checks. Restored on 21st March, the unit ran till 26th June when it was shutdown for gas restoration. Between 1st to 23rd July, the unit generated into the grid. Thereafter it was on outage due to faulty natural gas unloading valve. From then the unit was available except 10 days outage on mid September caused by low water pressure and an 11 – day maintenance outage in early December. The unit was however synchronously tied to grid by 31st December, 2007. GT1 started production on 5th April, 2007. Its was on a 4 day outage for gas pipe restoration on 26th June. From 1st July to August, the unit was tied to the grid. For almost a month of September the unit was on outage due to vent fan oil leakage. It generated on October and November but unavailable through out December on faulty cooling system. GT13 came on stream in early June. It was however shutdown in order to restore gas pipe line. Between 7th to 25th July, the unit developed faulty fan motor. From 25th July to 28th September it generated into the grid. It then went on a week outage to repair the generator transformer tap changer. The unit was on the grid throughout December, 2007. 1.33 OLORUNSOGO P.S. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 23
  • 29. Commissioning of the units commenced in December, 2007. GT1’s commissioning commenced on 7th. It ran for the rest of December, 2007. GT2’s commissioning began on 17th December, 2007. It was on the grid for the rest of December, 2007. GT3 was commissioned on 10th December, 2007. The unit was still generating by 31st December, 2007. GT5 was commissioned on 16th December. It generated for the remaining days of December, 2007. 1.40 GENERATION ORDERING AND LOAD DISPATCH An integrated grid was operated in 2007, pooling generation from Kainji, Jebba and Shiroro Hydro Power Station and Egbin, Delta, Afam, Sapele, AES, Okpai, Omotosho, Omoku and Olorunsogo thermal Stations. Inadequate gas supply from the Nigerian Gas Company (NGC) and incessant low gas pressure militated against full thermal capacity generation into the grid. Among the affected Stations were: Egbin and AES which although capable of an average generation of 955.0MW was frequently confined between 200 and 700 MW. There was a time that the combined stations could only pooled less than 100 MW into the grid. Likewise, Geregu, Omotosho and Olorunsogo output to the grid was often limited by gas availability to about 30% of available capacity. Since generation availability was grossly inadequate to meet the ever increasing load demand, load shedding continued through out the year in order to maintain power balance. 1.50 FREQUENCY CONTROL Due to generation shortage, the grid was operated outside the frequency control policy of 50Hz + 0.40% i.e. 49.80Hz to 50.20Hz, resulting in frequency excursions outside the operational limits. Most of the gas turbines on the grid were operated on temperature control mode. Hence they were often insensitive to vagaries of system frequency. The automatic voltage regulator (AVRs) and governor system of Kainji, Kaplan units (variable blades) were not functional. All the other machines in the system were considered base load, except Jebba units that regulate occasionally. Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 24
  • 30. ANNUAL ENERGY GENERATED (GWH) 1973-2007 CHART 11 07 23,187 06 23,300 05 24,077 04 24,132 03 22,612 02 21,544 01 17,637 00 15,227 99 16,291 98 16,253 97 15,416 96 15,971 95 15,793 94 14,557 93 14,617 YEAR 92 15,066 91 14,212 90 13,364 89 12,700 88 11,471 87 11,141 86 10,665 85 10,155 84 8,927 83 8,456 82 7,102 81 6,766 80 5,724 79 5,151 78 4,359 77 4,195 76 3,750 75 3,322 74 2,780 73 2,493 0 5000 10000 15000 20000 25000 30000 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 ENERGY(GWH) 24 27 33 37 41 43 51 57 67 71 84 89 10 10 11 11 12 13 14 15 14 14 15 15 15 16 16 15 17 21 22 24 24 23 23 ENERGY GENERATED (GWH) SIMULTANEOUS NATIONAL PEAK (MW) 1973-2007 CHART 12 07 3,600 06 3,682 05 3,774.1 04 3,427.5 03 3,479.3 02 3,223.4 01 2,934.49 00 2,499 99 2,458 98 2,448 97 2,457 96 2,470 95 2,452 94 2,446 93 YEAR 2,330 92 2,382 91 2,246 90 2,219 89 2,008 88 1,952 87 1,855 86 1,730 85 1,720 84 1,532 83 1,434 82 1,448 81 1,323 80 1,181 79 1,095 78 887 77 767 76 708 75 579 74 457 73 385 0 500 1000 1500 2000 2500 3000 3500 4000 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 PEAK 385 457 579 708 767 887 109 118 132 144 143 153 172 173 185 195 200 221 224 238 233 244 245 247 245 244 245 249 293 322 347 342 377 368 360 PEAK DEMAND (MW) Generation and Transmission Grid Operations-2007-National Control Centre, Osogbo 25