Ss training fidic moustafa ismail 2017 _ lec. 1
1. Project Management
Development
FIDIC Forms of Contracts
How to think?
July 2017
Riyadh-KSA
123 July 2017SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think?
Course no- 1011BTA
2. Dr. Eng. Moustafa Ismail Abu Dief
PhD. CFCC™, FICCP, MCIOB, PMP®, RMP®, ACIArb, CCP
TOT level 2, 2008
Contracts and Claims Manager - Certified Claims Consultant
www.ZBenaa-pm.com
https://www.facebook.com/groups/1541580426160256/
https://www.facebook.com/Moustafa-Ismail-150838095005187/
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 2
FIDIC Forms of Contracts
Training Course:
Saudi Council of Engineers
23 July 2017
3. international federation of national associations of independent consulting engineers
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How
to think?
3
FIDIC Forms of Contracts
Training Course:
23 July 2017
LECTURE ONE
وبركاته هللا ورحمة عليكن السالم
23-07-2017
4. .
• Introduction
• FIDIC Documents
• Risk
• Procurement
• Strategy
• First 100 days
• Responsibilities
• Nominated Sub-Con.
• Staff & labour
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 4
• Plant & Materials
• Commencement
• Delays
• Taking Over
• Measurement
• Guarantees
• Claims
• Short Form
• Disputes/ Resolution
23 July 2017
Contents
5. FIDIC:
AN INTRODUCTION
• Founded in 1913
• Expanded in 1945 to include 40 national
associations
• Published first Conditions of Contract in 1957
• In 2004 has 64 member associations
• Headquarters in Switzerland
• Web Site : www.fidic.org
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
523 July 2017
6. FIDIC FORMS of Contracts
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
6
1. Introduction To The FIDIC Contracts
FIDIC stands for the “Fédération Internationale
des Ingénieurs-Conseils” and is the French acronym for
the international federation of national associations of
independent consulting engineers. FIDIC was founded in
Belgium in 1913. The objectives the federation were :
“to promote … the professional interests of the
member associations and to disseminate information
of interest to members of its component national
associations.”
23 July 2017
8. FIDIC forms of Contracts
• In 1957 FIDIC published the 1st.
edition of its Conditions of Contract for Works of Civil
Engineering Construction, became to be known as the
“RED Book”.
First “red book” based on UK ICE conditions
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
823 July 2017
9. International forms of contract
• Federation International des Ingeneurs-Counseils
(FIDIC);
• Other notable standard forms have been
developed for use internationally by:
the Engineering Advancement Association of Japan
(ENAA);
Joint Contracts Tribunal (JCT) in the United Kingdom;
the European Development Fund (EDF);
Institution of Civil Engineers New Engineering Contract (NEC3).
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How
to think?
923 July 2017
10. FIDIC Documents
• Old “rainbow books” قزح قوسneeded revision
• Changes within International Projects &
Contracting
• Standardisation
• Clauses to meet current practice
• Update “Engineer” and consultant role
• Introduce “Disputes Adjudication Board”
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think? 1023 July 2017
11. FIDIC 1999 Documents
• Conditions of Contract for Construction (Red Book)
• Conditions of Contract for Plant & Design
Build (Yellow Book)
• Conditions of Contract for EPC Turnkey
Projects (Silver Book)
• Short Form of Contracts (Green Book)
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
1123 July 2017
12. SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
12
The Form of Contract for Dredging and
Reclamation Works (The Blue Book)
The MDB Harmonized Conditions of Contract for
Construction (The MDB Edition)
Client/Consultant Model Services Agreement
(„The White Book‟, 3rd ed, 1998)
FIDIC 1999 Documents- continued
23 July 2017
13. New Contract Features in FIDIC Contracts
• Simple Language
o 20 Clauses & 163 Sub Clauses/ 72 clauses in 1987
• Engineer instead of Employer’s Representative
Clause 1.1.2.4
• Employer's Claims Clause 2.5
• Contractor’s Claims Clause .20.1
• Value Engineering Clause 13.2
• QUALITY & PROCEDURES: Cl.4.9, 4.18, 6.7, 8.3, 13.2 & 13.3
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
1323 July 2017
14. Formats of FIDIC Documents
• Acknowledgements
• Foreword & Charts
• General Conditions
• DAB Conditions
• Directive and Guidance Notes
• Forms of Agreements
• Appendix to Tender
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think? 1423 July 2017
15. Conditions of Contract for Construction
Red. Book
• Works designed by Employer or Engineer
• Contractor Constructs in accordance
with designs provided
• May include some design elements
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
1523 July 2017
16. FIDIC Conditions of Contract (Y Book) for Plant
& Design Build
• Electrical & Mechanical Plant
• May include building and engineering
• Design & Execution of works
• Contractor designs and constructs in
accordance with Employer’s Requirements
• Engineer Administers
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think? 1623 July 2017
17. Features of Plant & Design Build Contract
• General Comments:
Contractor will economise
Employer will supervise
More risk for Employer Variations
Good for Lump Sum
Design Savings
Employer responsible for ER errors
Risk Shared
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
1723 July 2017
18. FIDIC Conditions of Contract for:
EPC/Turnkey Projects ( Silver Book)
• Process or Power Plant
• Infrastructure Projects
• High Degree of Certainty
• Contractor has total responsibility for Design
& Execution
• Administered by Employer- no Engineer
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think? 1823 July 2017
19. Features of EPC/Turnkey Form (Silver Book)
• General Comments
o Not suitable when:
• No time to tender
• Much underground works
• If Employer wishes to supervise
• If payments need to be administered
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
1923 July 2017
20. Featured Clauses in EPC Contracts
• Single point of responsibility – Contractor/all design,
engineering, procurement, construction, commissioning and testing
• If EPC Contractor is a JV, liability/responsibility is joint
• Fixed Contract Price – limited Contractor‟s RF changes
• Constrained Duration and definite date for completion. Any
delay will activate LD which is properly predefined based on
actual losses
• Extension of time, sub-clause 8.4 C granted where Contractor
is inculpable
23 July 2017
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
20
21. FIDIC Short Form of Contract Green Book
• Small capital value projects Up to 500 $
• Simple content
• Contractor constructs to Employer’s designs
• No use for “Particular Conditions”
• No identification of “Impartial” Engineer/ consultant
, it shows authorized person and Emp. representative
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
2123 July 2017
22. COMMUNICATIONS in FIDIC
• Cl.1.3:
o Approvals, Certificates, Consents,
Determinations, Notices, Requests
• Official In Writing
• Delivered
• No-unreasonably withheld or delayed
• Number of Copies
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How
to think?
2223 July 2017
23. Outlines- the Engineer
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I
How to think?
2323 July 2017
24. Q&A
SS FIDIC Training 1011 BTA - Dr. Moustafa
Ismail July 2017 LEC- I How to think?
24
Q1. FIDIC Conditions of Contract for Construction
1. Red. Book 2-White Book
Q.2 In the Red Book the Works is designed by Employer
or Engineer
1. TRUE 2-False
Q.3 FIDIC Red Book Employer's Claims Clause 2.5
1-TRUE 2-False
Q.4 Contractor‟s Claims Clause .20.1
1-TRUE 2-False
Q.5 FIDIC Conditions of Contract for Plant
& Design Build “Electrical & Mechanical Plant”
1- (Y Book) 2-False 23 July 2017
25. Q&A
SS FIDIC Training 1011 BTA - Dr. Moustafa
Ismail July 2017 LEC- I How to think?
25
Q1. FIDIC Conditions of Contract for Construction
1. Red. Book 2-White Book
Q.2 In the Red Book the Works is designed by Employer
or Engineer
1. TRUE 2-False
Q.3 FIDIC Red Book Employer's Claims Clause 2.5
1-TRUE 2-False
Q.4 Contractor’s Claims Clause .20.1
1-TRUE 2-False
Q.5 FIDIC Conditions of Contract for Plant
& Design Build “Electrical & Mechanical Plant”
1- (Y.Book) 2-False 23 July 2017
26. General provisions: 1.1 Definitions- 65w
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
2623 July 2017
1. Abu Dief, M. (2017) Applied Management for FIDIC Contracts, Part One:
Segregation of General Provisions , PM World Journal, Vol. VI, Issue VII – July
2017
Example: Engineer .. engineer
27. Interpretation
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 2723 July 2017
MR : MRS
Work Works
28. Communication
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 2823 July 2017
Receiving Emails ?
29. SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 29
Communication- continued
23 July 2017
Mutual agreement- confirm receipt-written communication, mail, receiving signature
Law and Language:
The applicable law and language of the parties‟
communication shall be identified in the contract
documents- appendix to tender- particular conditions.
30. Priority in contract documents
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How
to think?
3023 July 2017
31. Contract Preparation
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 3123 July 2017
The Contractor submits the Letter of Tender LOT
If accepted by The Employer
The Employer issues the Letter of Acceptance
If received and accepted by the Contractor with the date D
Then: A binding Contractual relationship exists
In 28 days from the date D the parties should sign a
Contract Agreement as per the form annexed to the
Particular conditions
LOA may Substitute the Contract Agreement--- missing LOA, then
Contract Agreement is mandatory
32. Establishing a contractual relationship
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 32
• Three possibilities to establish a contractual
relationship.
Issue letter of acceptance “ LOA”
Signing an agreement with or without “LOA”
Signing of a formal comprehensive „ Contract
‟ document which would include the Contract
Agreement.
23 July 2017
33. Assignment
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 33
„ Neither Party is permitted to assign or transfer the
whole or any part of the Contract or any benefit or
interest in or under the Contract without the
agreement of the other Party. ’ Exceptionally either
Party may, as security, assign its right to any
money due under the Contract to a bank or
financial institution.
23 July 2017
34. Care of project documents
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
34
• The Employer is required to provide to the Contractor
two copies of the Contract & drawings.
• The Contractor has to supply 6 copies of the Contractor‟ s
Documents to the Engineer/including submittal/ approval
• The Contractor should seek clarification from the
Engineer if a 6 copies is required at the submittal - for -
approval stage or only required once the documents are
approved.
23 July 2017
35. Delayed Drawings and Instructions
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to think? 35
• The Contractor is required to give notice to the
Engineer whenever „ the Works are likely to be
delayed or disrupted ‟ due to delay in
Drawings/instructions
• The Contractor is further required to provide
details of „ how, when and why ‟ the drawings
or other instructions are needed. This has a
direct relationship to the preparation of
programs (Sub - Clause 8.3 refers).
23 July 2017
36. Case Study (1)
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
3623 July 2017
37. Case Study (1) Analyzed by: Eng. …………………………….
SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How to
think?
3723 July 2017
In the shown part of Contract Agreement, as per FIDIC
general conditions requirements discuss:
The Project name and location is identified in order to:
……………………………………………………………….
The Contract parties names and addresses are necessary as
per FIDIC Red Book 1999 Clause/s:
……………………………………………………………………
The Contract Date shall affect the following:
1- Date of submission of performance security
2- Date of project completion
…………………………………………………………………
To identify the Contract Cause and place of work/ applicable Law
38. SS FIDIC Training 1011 BTA - Dr. Moustafa Ismail July 2017 LEC- I How
to think?
38
END OF LECTUTRE ONE
Thank you