On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for
Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it
would take between 2 and 3 years to complete the building. On December 31, 2019, the building
was deemed substantially completed. Following are accumulated contract costs incurred,
estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018,
and 2019.
At
12/31/17
At
12/31/18
At
12/31/19
Contract costs incurred to date $298,000 $1,194,000 $2,098,500
Estimated costs to complete the contract 1,192,000 796,000 –0–
Billings to Gumbel 300,000 1,100,000 1,820,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss
to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and
2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.)
2017
[Entry field with correct answer]
Costs to date (12/31/17)
Estimated Total Costs
Percent Complete
Revenue Recognized
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
$
[Entry field with correct answer]
[Entry field with correct answer]
Costs to date (12/31/17)
Revenue Recognized
Estimated Costs to Complete
Profit / (Loss) Recognized in 2017
Estimated Total Costs
Percent Complete
[Entry field with correct answer]
[Entry field with correct answer]
Revenue Recognized
Percent Complete
Profit / (Loss) Recognized in 2017
Costs to date (12/31/17)
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with correct answer]
[Entry field with correct answer]
Profit / (Loss) Recognized in 2017
Percent Complete
Costs to date (12/31/17)
Estimated Total Costs
Estimated Costs to Complete
Revenue Recognized
[Entry field with correct answer]
%
[Entry field with correct answer]
Estimated Total Costs
Percent Complete
Revenue Recognized
Estimated Costs to Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
$
[Entry field with correct answer]
[Entry field with correct answer]
Estimated Costs to Complete
Revenue Recognized
Percent Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
Estimated Total Costs
[Entry field with correct answer]
[Entry field with correct answer]
Estimated Total Costs
Costs Incurred
Percent Complete
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
Revenue Recognized
$
[Entry field with correct answer]
2018
[Entry field with correct answer]
Estimated Total Costs
Total Profit/Loss
Contract Price
Costs to date (12/31/18)
Estimated Costs to Complete
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2018
Profit/Loss Recognized in 2017
$
[Entry field with correct answer]
[Entry field with correct answer]
Gross Profit Recognized in 2017
Contract Price
Estimated Total Costs
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Total Profit/Loss
Costs to date (12/31/18)
Estimated Costs to Complete
[Entry field with correct an.
On July 1, 2017, Sheridan Construction Company Inc. contracted to bu.pdf
1. On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for
Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it
would take between 2 and 3 years to complete the building. On December 31, 2019, the building
was deemed substantially completed. Following are accumulated contract costs incurred,
estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018,
and 2019.
At
12/31/17
At
12/31/18
At
12/31/19
Contract costs incurred to date $298,000 $1,194,000 $2,098,500
Estimated costs to complete the contract 1,192,000 796,000 –0–
Billings to Gumbel 300,000 1,100,000 1,820,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss
to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and
2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.)
2017
[Entry field with correct answer]
Costs to date (12/31/17)
Estimated Total Costs
Percent Complete
Revenue Recognized
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
$
[Entry field with correct answer]
[Entry field with correct answer]
Costs to date (12/31/17)
Revenue Recognized
Estimated Costs to Complete
2. Profit / (Loss) Recognized in 2017
Estimated Total Costs
Percent Complete
[Entry field with correct answer]
[Entry field with correct answer]
Revenue Recognized
Percent Complete
Profit / (Loss) Recognized in 2017
Costs to date (12/31/17)
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with correct answer]
[Entry field with correct answer]
Profit / (Loss) Recognized in 2017
Percent Complete
Costs to date (12/31/17)
Estimated Total Costs
Estimated Costs to Complete
Revenue Recognized
[Entry field with correct answer]
%
[Entry field with correct answer]
Estimated Total Costs
Percent Complete
Revenue Recognized
Estimated Costs to Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
$
3. [Entry field with correct answer]
[Entry field with correct answer]
Estimated Costs to Complete
Revenue Recognized
Percent Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
Estimated Total Costs
[Entry field with correct answer]
[Entry field with correct answer]
Estimated Total Costs
Costs Incurred
Percent Complete
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
Revenue Recognized
$
[Entry field with correct answer]
2018
[Entry field with correct answer]
Estimated Total Costs
Total Profit/Loss
Contract Price
Costs to date (12/31/18)
Estimated Costs to Complete
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2018
Profit/Loss Recognized in 2017
$
[Entry field with correct answer]
[Entry field with correct answer]
4. Gross Profit Recognized in 2017
Contract Price
Estimated Total Costs
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Total Profit/Loss
Costs to date (12/31/18)
Estimated Costs to Complete
[Entry field with correct answer]
[Entry field with correct answer]
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Estimated Total Costs
Costs to date (12/31/18)
Gross Profit Recognized in 2017
Estimated Costs to Complete
Contract Price
Total Profit/Loss
[Entry field with correct answer]
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2018
Gross Profit Recognized in 2017
Profit/Loss Recognized in 2017
Costs to date (12/31/18)
Estimated Costs to Complete
Estimated Total Costs
Contract Price
Total Profit/Loss
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Contract Price
Total Profit/Loss
Costs to date (12/31/18)
5. Estimated Costs to Complete
Profit/Loss Recognized in 2017
Gross Profit Recognized in 2017
Estimated Total Costs
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Costs to date (12/31/18)
Profit / (Loss) Recognized in 2018
Contract Price
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
Profit/Loss Recognized in 2017
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Add
Less
:
[Entry field with incorrect answer]
Estimated Total Costs
Contract Price
Estimated Costs to Complete
Total Profit/Loss
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Gross Profit Recognized in 2017
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
6. Gross Profit Recognized in 2017
Estimated Total Costs
Total Profit/Loss
Contract Price
Estimated Costs to Complete
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
$
[Entry field with incorrect answer]
2019
[Entry field with incorrect answer]
Contract Price
Costs to date (12/31/19)
Gross Profit Recognized in 2018
Total Profit/Loss
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Gross Profit Recognized in 2018
Estimated Total Costs
Total Profit/Loss
Estimated Costs to Complete
Profit / (Loss) Recognized in 2019
Costs to date (12/31/19)
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
7. Contract Price
Profit/Loss Recognized in 2017
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Profit / (Loss) Recognized in 2019
Profit/Loss Recognized in 2017
Costs to date (12/31/19)
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
Gross Profit Recognized in 2018
Contract Price
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Costs to date (12/31/19)
Contract Price
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Total Profit/Loss
Gross Profit Recognized in 2018
Profit / (Loss) Recognized in 2019
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Contract Price
Total Profit/Loss
Profit/Loss Recognized in 2018
8. Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Gross Profit Recognized in 2018
Costs to date (12/31/19)
Profit/Loss Recognized in 2017
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Add
Less
:
[Entry field with incorrect answer]
Gross Profit Recognized in 2018
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Total Costs
Costs to date (12/31/19)
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Contract Price
Total Profit/Loss
Estimated Costs to Complete
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Costs to date (12/31/19)
Estimated Total Costs
Profit/Loss Recognized in 2018
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Contract Price
9. Total Profit/Loss
Gross Profit Recognized in 2017
Profit/Loss Recognized in 2017
Gross Profit Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Contract Price
Profit/Loss Recognized in 2017
Estimated Total Costs
Gross Profit Recognized in 2017
Gross Profit Recognized in 2018
Profit/Loss Recognized in 2018
Profit / (Loss) Recognized in 2019
Costs to date (12/31/19)
Estimated Costs to Complete
$
[Entry field with incorrect answer]
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be
recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019.
(Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)
2018
[Entry field with incorrect answer]
Estimated Total Costs
Estimated Costs to Complete
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
Contract Price
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
10. Estimated Costs to Complete
Estimated Total Costs
Contract Price
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Costs to Complete
Estimated Total Costs
Contract Price
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Total Costs
Contract Price
Costs to date (12/31/18)
Estimated Costs to Complete
Profit / (Loss) Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Costs to Complete
Costs to date (12/31/18)
Contract Price
Estimated Total Costs
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer]
2019
[Entry field with incorrect answer]
Costs Incurred
Contract Price
11. Profit / (Loss) Recognized in 2018
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2019
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2018
Profit / (Loss) Recognized in 2019
Contract Price
Costs Incurred
Total Profit / (Loss) on Contract
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2019
Profit / (Loss) Recognized in 2018
Costs Incurred
Contract Price
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Less
Add
:
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2019
Contract Price
Costs Incurred
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
12. Costs Incurred
Contract Price
Profit / (Loss) Recognized in 2019
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer now contains modified data]
Solution
(a) Percentage-of-Completion Method 2017 Costs up to
12/31/17........................................................... $ 298,000 Estimated costs for
completetion......................................... 1,192,000 Estimated total
costs.................................................... $1,4,90,000 Percentage completed
($298,000/$1,490,000)..................... 20% Revenue to be recognized
($1,880,000*20%)....................... $ 376000 Costs
incurred...................................................................... ($298000) Profit to be
recognized in 2017............................................ $ 78000 2018 Costs to date
(12/31/18)....................................................... $1,1,94,000 Estimated costs to
complete................................................. 796,000 Estimated total
costs.................................................... $1990000 Contract
price...................................................................... (1,880,000) Total
loss............................................................................. $ 110,000 Total
loss............................................................................. $ 110,000 Plus gross profit
recognized in 2017.................................... 78,000 Loss recognized in
2018....................................................... $ 188,000
2019 Costs to date
(12/31/19).............................................. $2,098,500 Estimated costs to
complete........................................ 0
2,098,500
Contract price............................................................. 1,880,000 Total
loss.................................................................... $ (218,500) Total
loss.................................................................... $ (218,500) Less: Loss
recognized in 2018.................................... $188000 Gross profit recognized in
2017.................................. (78,000) (110,000) Loss recognized in
2019.............................................. $ (108,500) (b)
Completed-Contract Method 2017—No revenue or profit is reognized 2018
13. Costs to date (12/31/18)............................................... $1,194,000 Estimated
costs to complete......................................... 796,000 Estimated total
costs............................................ $1990000 Contract
price............................................................... 1,880,000 Loss recognized in
2018............................................... $ (1100,000) 2019 Total costs
incurred till 12/31/19.................................. $2,098,500 Total revenue
recognized.............................................. 1,880000 Total loss on
contract........................................... (218500) Less: loss recognized in
2018........................................ (110,000) Loss recognized in
2019................................................ $ (108500)