SlideShare a Scribd company logo
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for
Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it
would take between 2 and 3 years to complete the building. On December 31, 2019, the building
was deemed substantially completed. Following are accumulated contract costs incurred,
estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018,
and 2019.
At
12/31/17
At
12/31/18
At
12/31/19
Contract costs incurred to date $298,000 $1,194,000 $2,098,500
Estimated costs to complete the contract 1,192,000 796,000 –0–
Billings to Gumbel 300,000 1,100,000 1,820,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss
to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and
2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.)
2017
[Entry field with correct answer]
Costs to date (12/31/17)
Estimated Total Costs
Percent Complete
Revenue Recognized
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
$
[Entry field with correct answer]
[Entry field with correct answer]
Costs to date (12/31/17)
Revenue Recognized
Estimated Costs to Complete
Profit / (Loss) Recognized in 2017
Estimated Total Costs
Percent Complete
[Entry field with correct answer]
[Entry field with correct answer]
Revenue Recognized
Percent Complete
Profit / (Loss) Recognized in 2017
Costs to date (12/31/17)
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with correct answer]
[Entry field with correct answer]
Profit / (Loss) Recognized in 2017
Percent Complete
Costs to date (12/31/17)
Estimated Total Costs
Estimated Costs to Complete
Revenue Recognized
[Entry field with correct answer]
%
[Entry field with correct answer]
Estimated Total Costs
Percent Complete
Revenue Recognized
Estimated Costs to Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
$
[Entry field with correct answer]
[Entry field with correct answer]
Estimated Costs to Complete
Revenue Recognized
Percent Complete
Costs Incurred
Profit / (Loss) Recognized in 2017
Estimated Total Costs
[Entry field with correct answer]
[Entry field with correct answer]
Estimated Total Costs
Costs Incurred
Percent Complete
Profit / (Loss) Recognized in 2017
Estimated Costs to Complete
Revenue Recognized
$
[Entry field with correct answer]
2018
[Entry field with correct answer]
Estimated Total Costs
Total Profit/Loss
Contract Price
Costs to date (12/31/18)
Estimated Costs to Complete
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2018
Profit/Loss Recognized in 2017
$
[Entry field with correct answer]
[Entry field with correct answer]
Gross Profit Recognized in 2017
Contract Price
Estimated Total Costs
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Total Profit/Loss
Costs to date (12/31/18)
Estimated Costs to Complete
[Entry field with correct answer]
[Entry field with correct answer]
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Estimated Total Costs
Costs to date (12/31/18)
Gross Profit Recognized in 2017
Estimated Costs to Complete
Contract Price
Total Profit/Loss
[Entry field with correct answer]
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2018
Gross Profit Recognized in 2017
Profit/Loss Recognized in 2017
Costs to date (12/31/18)
Estimated Costs to Complete
Estimated Total Costs
Contract Price
Total Profit/Loss
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Contract Price
Total Profit/Loss
Costs to date (12/31/18)
Estimated Costs to Complete
Profit/Loss Recognized in 2017
Gross Profit Recognized in 2017
Estimated Total Costs
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Costs to date (12/31/18)
Profit / (Loss) Recognized in 2018
Contract Price
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
Profit/Loss Recognized in 2017
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Add
Less
:
[Entry field with incorrect answer]
Estimated Total Costs
Contract Price
Estimated Costs to Complete
Total Profit/Loss
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Gross Profit Recognized in 2017
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Gross Profit Recognized in 2017
Estimated Total Costs
Total Profit/Loss
Contract Price
Estimated Costs to Complete
Profit/Loss Recognized in 2017
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
$
[Entry field with incorrect answer]
2019
[Entry field with incorrect answer]
Contract Price
Costs to date (12/31/19)
Gross Profit Recognized in 2018
Total Profit/Loss
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Gross Profit Recognized in 2018
Estimated Total Costs
Total Profit/Loss
Estimated Costs to Complete
Profit / (Loss) Recognized in 2019
Costs to date (12/31/19)
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Contract Price
Profit/Loss Recognized in 2017
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Profit / (Loss) Recognized in 2019
Profit/Loss Recognized in 2017
Costs to date (12/31/19)
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
Gross Profit Recognized in 2018
Contract Price
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Costs to date (12/31/19)
Contract Price
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Total Profit/Loss
Gross Profit Recognized in 2018
Profit / (Loss) Recognized in 2019
Gross Profit Recognized in 2017
Estimated Costs to Complete
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Contract Price
Total Profit/Loss
Profit/Loss Recognized in 2018
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Gross Profit Recognized in 2018
Costs to date (12/31/19)
Profit/Loss Recognized in 2017
Estimated Total Costs
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Add
Less
:
[Entry field with incorrect answer]
Gross Profit Recognized in 2018
Gross Profit Recognized in 2017
Profit / (Loss) Recognized in 2019
Estimated Total Costs
Costs to date (12/31/19)
Profit/Loss Recognized in 2017
Profit/Loss Recognized in 2018
Contract Price
Total Profit/Loss
Estimated Costs to Complete
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Costs to date (12/31/19)
Estimated Total Costs
Profit/Loss Recognized in 2018
Profit / (Loss) Recognized in 2019
Estimated Costs to Complete
Contract Price
Total Profit/Loss
Gross Profit Recognized in 2017
Profit/Loss Recognized in 2017
Gross Profit Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit/Loss
Contract Price
Profit/Loss Recognized in 2017
Estimated Total Costs
Gross Profit Recognized in 2017
Gross Profit Recognized in 2018
Profit/Loss Recognized in 2018
Profit / (Loss) Recognized in 2019
Costs to date (12/31/19)
Estimated Costs to Complete
$
[Entry field with incorrect answer]
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be
recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019.
(Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)
2018
[Entry field with incorrect answer]
Estimated Total Costs
Estimated Costs to Complete
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
Contract Price
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Costs to Complete
Estimated Total Costs
Contract Price
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Costs to Complete
Estimated Total Costs
Contract Price
Profit / (Loss) Recognized in 2018
Costs to date (12/31/18)
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Total Costs
Contract Price
Costs to date (12/31/18)
Estimated Costs to Complete
Profit / (Loss) Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Estimated Costs to Complete
Costs to date (12/31/18)
Contract Price
Estimated Total Costs
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer]
2019
[Entry field with incorrect answer]
Costs Incurred
Contract Price
Profit / (Loss) Recognized in 2018
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2019
$
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2018
Profit / (Loss) Recognized in 2019
Contract Price
Costs Incurred
Total Profit / (Loss) on Contract
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2019
Profit / (Loss) Recognized in 2018
Costs Incurred
Contract Price
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Less
Add
:
[Entry field with incorrect answer]
Profit / (Loss) Recognized in 2019
Contract Price
Costs Incurred
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2018
[Entry field with incorrect answer]
[Entry field with incorrect answer]
Costs Incurred
Contract Price
Profit / (Loss) Recognized in 2019
Total Profit / (Loss) on Contract
Profit / (Loss) Recognized in 2018
$
[Entry field with incorrect answer now contains modified data]
Solution
(a) Percentage-of-Completion Method 2017 Costs up to
12/31/17........................................................... $ 298,000 Estimated costs for
completetion......................................... 1,192,000 Estimated total
costs.................................................... $1,4,90,000 Percentage completed
($298,000/$1,490,000)..................... 20% Revenue to be recognized
($1,880,000*20%)....................... $ 376000 Costs
incurred...................................................................... ($298000) Profit to be
recognized in 2017............................................ $ 78000 2018 Costs to date
(12/31/18)....................................................... $1,1,94,000 Estimated costs to
complete................................................. 796,000 Estimated total
costs.................................................... $1990000 Contract
price...................................................................... (1,880,000) Total
loss............................................................................. $ 110,000 Total
loss............................................................................. $ 110,000 Plus gross profit
recognized in 2017.................................... 78,000 Loss recognized in
2018....................................................... $ 188,000
2019 Costs to date
(12/31/19).............................................. $2,098,500 Estimated costs to
complete........................................ 0
2,098,500
Contract price............................................................. 1,880,000 Total
loss.................................................................... $ (218,500) Total
loss.................................................................... $ (218,500) Less: Loss
recognized in 2018.................................... $188000 Gross profit recognized in
2017.................................. (78,000) (110,000) Loss recognized in
2019.............................................. $ (108,500) (b)
Completed-Contract Method 2017—No revenue or profit is reognized 2018
Costs to date (12/31/18)............................................... $1,194,000 Estimated
costs to complete......................................... 796,000 Estimated total
costs............................................ $1990000 Contract
price............................................................... 1,880,000 Loss recognized in
2018............................................... $ (1100,000) 2019 Total costs
incurred till 12/31/19.................................. $2,098,500 Total revenue
recognized.............................................. 1,880000 Total loss on
contract........................................... (218500) Less: loss recognized in
2018........................................ (110,000) Loss recognized in
2019................................................ $ (108500)

More Related Content

More from mohammedfootwear

5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
mohammedfootwear
 
C programming. Answer question only in C code In the eighth part, yo.pdf
C programming. Answer question only in C code In the eighth part, yo.pdfC programming. Answer question only in C code In the eighth part, yo.pdf
C programming. Answer question only in C code In the eighth part, yo.pdf
mohammedfootwear
 
Biology Lab questions1. Why can a very small amount of bacteria b.pdf
Biology Lab questions1. Why can a very small amount of bacteria b.pdfBiology Lab questions1. Why can a very small amount of bacteria b.pdf
Biology Lab questions1. Why can a very small amount of bacteria b.pdf
mohammedfootwear
 
You will choose a country, other than the USA or Turkey, that you wo.pdf
You will choose a country, other than the USA or Turkey, that you wo.pdfYou will choose a country, other than the USA or Turkey, that you wo.pdf
You will choose a country, other than the USA or Turkey, that you wo.pdf
mohammedfootwear
 
Why does the RNA polymerase complex in eukaryotes contain a histone .pdf
Why does the RNA polymerase complex in eukaryotes contain a histone .pdfWhy does the RNA polymerase complex in eukaryotes contain a histone .pdf
Why does the RNA polymerase complex in eukaryotes contain a histone .pdf
mohammedfootwear
 
what Linux command allows you to scan the disk for partition changes.pdf
what Linux command allows you to scan the disk for partition changes.pdfwhat Linux command allows you to scan the disk for partition changes.pdf
what Linux command allows you to scan the disk for partition changes.pdf
mohammedfootwear
 
What is the correct answer Chrome File Edit View History Bookmarks.pdf
What is the correct answer Chrome File Edit View History Bookmarks.pdfWhat is the correct answer Chrome File Edit View History Bookmarks.pdf
What is the correct answer Chrome File Edit View History Bookmarks.pdf
mohammedfootwear
 
What is fault tolerance, and what network aspects must be monitored .pdf
What is fault tolerance, and what network aspects must be monitored .pdfWhat is fault tolerance, and what network aspects must be monitored .pdf
What is fault tolerance, and what network aspects must be monitored .pdf
mohammedfootwear
 
Using SQL Developer ONLY!Your assignment is to create an auditing .pdf
Using SQL Developer ONLY!Your assignment is to create an auditing .pdfUsing SQL Developer ONLY!Your assignment is to create an auditing .pdf
Using SQL Developer ONLY!Your assignment is to create an auditing .pdf
mohammedfootwear
 
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdfUse the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
mohammedfootwear
 
To what degree, if any, has America’s ascendancy on the world stage .pdf
To what degree, if any, has America’s ascendancy on the world stage .pdfTo what degree, if any, has America’s ascendancy on the world stage .pdf
To what degree, if any, has America’s ascendancy on the world stage .pdf
mohammedfootwear
 
This for English class.I need help for writing 4 to 5 paragraphs a.pdf
This for English class.I need help for writing 4 to 5 paragraphs a.pdfThis for English class.I need help for writing 4 to 5 paragraphs a.pdf
This for English class.I need help for writing 4 to 5 paragraphs a.pdf
mohammedfootwear
 
The debt ratio is the relationship between O A. total assets and cur.pdf
The debt ratio is the relationship between O A. total assets and cur.pdfThe debt ratio is the relationship between O A. total assets and cur.pdf
The debt ratio is the relationship between O A. total assets and cur.pdf
mohammedfootwear
 
The atmosphere in a Trident nuclear submarine is generally calm and .pdf
The atmosphere in a Trident nuclear submarine is generally calm and .pdfThe atmosphere in a Trident nuclear submarine is generally calm and .pdf
The atmosphere in a Trident nuclear submarine is generally calm and .pdf
mohammedfootwear
 
Question A woman has a particular disease and all of her children (.pdf
Question A woman has a particular disease and all of her children (.pdfQuestion A woman has a particular disease and all of her children (.pdf
Question A woman has a particular disease and all of her children (.pdf
mohammedfootwear
 
Question 50 (1 point) occurs when savers money makes its way into the.pdf
Question 50 (1 point) occurs when savers money makes its way into the.pdfQuestion 50 (1 point) occurs when savers money makes its way into the.pdf
Question 50 (1 point) occurs when savers money makes its way into the.pdf
mohammedfootwear
 
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdfName the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
mohammedfootwear
 
Please .pdf
Please .pdfPlease .pdf
Please .pdf
mohammedfootwear
 
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdfnumber 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
mohammedfootwear
 
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdfPLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
mohammedfootwear
 

More from mohammedfootwear (20)

5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
5. value 10.00 polnts On May 1, Soriano Co. reported the following ac.pdf
 
C programming. Answer question only in C code In the eighth part, yo.pdf
C programming. Answer question only in C code In the eighth part, yo.pdfC programming. Answer question only in C code In the eighth part, yo.pdf
C programming. Answer question only in C code In the eighth part, yo.pdf
 
Biology Lab questions1. Why can a very small amount of bacteria b.pdf
Biology Lab questions1. Why can a very small amount of bacteria b.pdfBiology Lab questions1. Why can a very small amount of bacteria b.pdf
Biology Lab questions1. Why can a very small amount of bacteria b.pdf
 
You will choose a country, other than the USA or Turkey, that you wo.pdf
You will choose a country, other than the USA or Turkey, that you wo.pdfYou will choose a country, other than the USA or Turkey, that you wo.pdf
You will choose a country, other than the USA or Turkey, that you wo.pdf
 
Why does the RNA polymerase complex in eukaryotes contain a histone .pdf
Why does the RNA polymerase complex in eukaryotes contain a histone .pdfWhy does the RNA polymerase complex in eukaryotes contain a histone .pdf
Why does the RNA polymerase complex in eukaryotes contain a histone .pdf
 
what Linux command allows you to scan the disk for partition changes.pdf
what Linux command allows you to scan the disk for partition changes.pdfwhat Linux command allows you to scan the disk for partition changes.pdf
what Linux command allows you to scan the disk for partition changes.pdf
 
What is the correct answer Chrome File Edit View History Bookmarks.pdf
What is the correct answer Chrome File Edit View History Bookmarks.pdfWhat is the correct answer Chrome File Edit View History Bookmarks.pdf
What is the correct answer Chrome File Edit View History Bookmarks.pdf
 
What is fault tolerance, and what network aspects must be monitored .pdf
What is fault tolerance, and what network aspects must be monitored .pdfWhat is fault tolerance, and what network aspects must be monitored .pdf
What is fault tolerance, and what network aspects must be monitored .pdf
 
Using SQL Developer ONLY!Your assignment is to create an auditing .pdf
Using SQL Developer ONLY!Your assignment is to create an auditing .pdfUsing SQL Developer ONLY!Your assignment is to create an auditing .pdf
Using SQL Developer ONLY!Your assignment is to create an auditing .pdf
 
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdfUse the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
Use the definition of big- Theta to prove that 5x^4 + 2x^3 - 1 is The.pdf
 
To what degree, if any, has America’s ascendancy on the world stage .pdf
To what degree, if any, has America’s ascendancy on the world stage .pdfTo what degree, if any, has America’s ascendancy on the world stage .pdf
To what degree, if any, has America’s ascendancy on the world stage .pdf
 
This for English class.I need help for writing 4 to 5 paragraphs a.pdf
This for English class.I need help for writing 4 to 5 paragraphs a.pdfThis for English class.I need help for writing 4 to 5 paragraphs a.pdf
This for English class.I need help for writing 4 to 5 paragraphs a.pdf
 
The debt ratio is the relationship between O A. total assets and cur.pdf
The debt ratio is the relationship between O A. total assets and cur.pdfThe debt ratio is the relationship between O A. total assets and cur.pdf
The debt ratio is the relationship between O A. total assets and cur.pdf
 
The atmosphere in a Trident nuclear submarine is generally calm and .pdf
The atmosphere in a Trident nuclear submarine is generally calm and .pdfThe atmosphere in a Trident nuclear submarine is generally calm and .pdf
The atmosphere in a Trident nuclear submarine is generally calm and .pdf
 
Question A woman has a particular disease and all of her children (.pdf
Question A woman has a particular disease and all of her children (.pdfQuestion A woman has a particular disease and all of her children (.pdf
Question A woman has a particular disease and all of her children (.pdf
 
Question 50 (1 point) occurs when savers money makes its way into the.pdf
Question 50 (1 point) occurs when savers money makes its way into the.pdfQuestion 50 (1 point) occurs when savers money makes its way into the.pdf
Question 50 (1 point) occurs when savers money makes its way into the.pdf
 
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdfName the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
Name the Three Kings of the Chicago-Memphis Electric Blues in ch.pdf
 
Please .pdf
Please .pdfPlease .pdf
Please .pdf
 
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdfnumber 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
number 4 1.4 Ordered Pairs The elements of be able to speak about.pdf
 
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdfPLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
PLEASE HELP ME !!IT IS Due Tonight ;(!i have to submit it before.pdf
 

Recently uploaded

PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
สมใจ จันสุกสี
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
Celine George
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
Wahiba Chair Training & Consulting
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Diana Rendina
 

Recently uploaded (20)

PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
 

On July 1, 2017, Sheridan Construction Company Inc. contracted to bu.pdf

  • 1. On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19 Contract costs incurred to date $298,000 $1,194,000 $2,098,500 Estimated costs to complete the contract 1,192,000 796,000 –0– Billings to Gumbel 300,000 1,100,000 1,820,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.) 2017 [Entry field with correct answer] Costs to date (12/31/17) Estimated Total Costs Percent Complete Revenue Recognized Profit / (Loss) Recognized in 2017 Estimated Costs to Complete $ [Entry field with correct answer] [Entry field with correct answer] Costs to date (12/31/17) Revenue Recognized Estimated Costs to Complete
  • 2. Profit / (Loss) Recognized in 2017 Estimated Total Costs Percent Complete [Entry field with correct answer] [Entry field with correct answer] Revenue Recognized Percent Complete Profit / (Loss) Recognized in 2017 Costs to date (12/31/17) Estimated Costs to Complete Estimated Total Costs $ [Entry field with correct answer] [Entry field with correct answer] Profit / (Loss) Recognized in 2017 Percent Complete Costs to date (12/31/17) Estimated Total Costs Estimated Costs to Complete Revenue Recognized [Entry field with correct answer] % [Entry field with correct answer] Estimated Total Costs Percent Complete Revenue Recognized Estimated Costs to Complete Costs Incurred Profit / (Loss) Recognized in 2017 $
  • 3. [Entry field with correct answer] [Entry field with correct answer] Estimated Costs to Complete Revenue Recognized Percent Complete Costs Incurred Profit / (Loss) Recognized in 2017 Estimated Total Costs [Entry field with correct answer] [Entry field with correct answer] Estimated Total Costs Costs Incurred Percent Complete Profit / (Loss) Recognized in 2017 Estimated Costs to Complete Revenue Recognized $ [Entry field with correct answer] 2018 [Entry field with correct answer] Estimated Total Costs Total Profit/Loss Contract Price Costs to date (12/31/18) Estimated Costs to Complete Gross Profit Recognized in 2017 Profit / (Loss) Recognized in 2018 Profit/Loss Recognized in 2017 $ [Entry field with correct answer] [Entry field with correct answer]
  • 4. Gross Profit Recognized in 2017 Contract Price Estimated Total Costs Profit/Loss Recognized in 2017 Profit / (Loss) Recognized in 2018 Total Profit/Loss Costs to date (12/31/18) Estimated Costs to Complete [Entry field with correct answer] [Entry field with correct answer] Profit/Loss Recognized in 2017 Profit / (Loss) Recognized in 2018 Estimated Total Costs Costs to date (12/31/18) Gross Profit Recognized in 2017 Estimated Costs to Complete Contract Price Total Profit/Loss [Entry field with correct answer] [Entry field with incorrect answer] Profit / (Loss) Recognized in 2018 Gross Profit Recognized in 2017 Profit/Loss Recognized in 2017 Costs to date (12/31/18) Estimated Costs to Complete Estimated Total Costs Contract Price Total Profit/Loss [Entry field with incorrect answer] [Entry field with incorrect answer] Contract Price Total Profit/Loss Costs to date (12/31/18)
  • 5. Estimated Costs to Complete Profit/Loss Recognized in 2017 Gross Profit Recognized in 2017 Estimated Total Costs Profit / (Loss) Recognized in 2018 $ [Entry field with incorrect answer] [Entry field with incorrect answer] Total Profit/Loss Costs to date (12/31/18) Profit / (Loss) Recognized in 2018 Contract Price Gross Profit Recognized in 2017 Estimated Costs to Complete Estimated Total Costs Profit/Loss Recognized in 2017 $ [Entry field with incorrect answer] [Entry field with incorrect answer] Add Less : [Entry field with incorrect answer] Estimated Total Costs Contract Price Estimated Costs to Complete Total Profit/Loss Profit/Loss Recognized in 2017 Profit / (Loss) Recognized in 2018 Gross Profit Recognized in 2017 Costs to date (12/31/18) [Entry field with incorrect answer] [Entry field with incorrect answer]
  • 6. Gross Profit Recognized in 2017 Estimated Total Costs Total Profit/Loss Contract Price Estimated Costs to Complete Profit/Loss Recognized in 2017 Profit / (Loss) Recognized in 2018 Costs to date (12/31/18) $ [Entry field with incorrect answer] 2019 [Entry field with incorrect answer] Contract Price Costs to date (12/31/19) Gross Profit Recognized in 2018 Total Profit/Loss Profit/Loss Recognized in 2017 Profit/Loss Recognized in 2018 Gross Profit Recognized in 2017 Profit / (Loss) Recognized in 2019 Estimated Costs to Complete Estimated Total Costs $ [Entry field with incorrect answer] [Entry field with incorrect answer] Gross Profit Recognized in 2018 Estimated Total Costs Total Profit/Loss Estimated Costs to Complete Profit / (Loss) Recognized in 2019 Costs to date (12/31/19) Profit/Loss Recognized in 2018 Gross Profit Recognized in 2017
  • 7. Contract Price Profit/Loss Recognized in 2017 [Entry field with incorrect answer] [Entry field with incorrect answer] [Entry field with incorrect answer] Total Profit/Loss Profit / (Loss) Recognized in 2019 Profit/Loss Recognized in 2017 Costs to date (12/31/19) Profit/Loss Recognized in 2018 Gross Profit Recognized in 2017 Estimated Costs to Complete Estimated Total Costs Gross Profit Recognized in 2018 Contract Price [Entry field with incorrect answer] [Entry field with incorrect answer] Costs to date (12/31/19) Contract Price Profit/Loss Recognized in 2017 Profit/Loss Recognized in 2018 Total Profit/Loss Gross Profit Recognized in 2018 Profit / (Loss) Recognized in 2019 Gross Profit Recognized in 2017 Estimated Costs to Complete Estimated Total Costs $ [Entry field with incorrect answer] [Entry field with incorrect answer] Contract Price Total Profit/Loss Profit/Loss Recognized in 2018
  • 8. Gross Profit Recognized in 2017 Profit / (Loss) Recognized in 2019 Estimated Costs to Complete Gross Profit Recognized in 2018 Costs to date (12/31/19) Profit/Loss Recognized in 2017 Estimated Total Costs $ [Entry field with incorrect answer] [Entry field with incorrect answer] Add Less : [Entry field with incorrect answer] Gross Profit Recognized in 2018 Gross Profit Recognized in 2017 Profit / (Loss) Recognized in 2019 Estimated Total Costs Costs to date (12/31/19) Profit/Loss Recognized in 2017 Profit/Loss Recognized in 2018 Contract Price Total Profit/Loss Estimated Costs to Complete $ [Entry field with incorrect answer] [Entry field with incorrect answer] Costs to date (12/31/19) Estimated Total Costs Profit/Loss Recognized in 2018 Profit / (Loss) Recognized in 2019 Estimated Costs to Complete Contract Price
  • 9. Total Profit/Loss Gross Profit Recognized in 2017 Profit/Loss Recognized in 2017 Gross Profit Recognized in 2018 [Entry field with incorrect answer] [Entry field with incorrect answer] [Entry field with incorrect answer] Total Profit/Loss Contract Price Profit/Loss Recognized in 2017 Estimated Total Costs Gross Profit Recognized in 2017 Gross Profit Recognized in 2018 Profit/Loss Recognized in 2018 Profit / (Loss) Recognized in 2019 Costs to date (12/31/19) Estimated Costs to Complete $ [Entry field with incorrect answer] (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.) 2018 [Entry field with incorrect answer] Estimated Total Costs Estimated Costs to Complete Profit / (Loss) Recognized in 2018 Costs to date (12/31/18) Contract Price $ [Entry field with incorrect answer] [Entry field with incorrect answer]
  • 10. Estimated Costs to Complete Estimated Total Costs Contract Price Profit / (Loss) Recognized in 2018 Costs to date (12/31/18) [Entry field with incorrect answer] [Entry field with incorrect answer] Estimated Costs to Complete Estimated Total Costs Contract Price Profit / (Loss) Recognized in 2018 Costs to date (12/31/18) [Entry field with incorrect answer] [Entry field with incorrect answer] Estimated Total Costs Contract Price Costs to date (12/31/18) Estimated Costs to Complete Profit / (Loss) Recognized in 2018 [Entry field with incorrect answer] [Entry field with incorrect answer] Estimated Costs to Complete Costs to date (12/31/18) Contract Price Estimated Total Costs Profit / (Loss) Recognized in 2018 $ [Entry field with incorrect answer] 2019 [Entry field with incorrect answer] Costs Incurred Contract Price
  • 11. Profit / (Loss) Recognized in 2018 Total Profit / (Loss) on Contract Profit / (Loss) Recognized in 2019 $ [Entry field with incorrect answer] [Entry field with incorrect answer] Profit / (Loss) Recognized in 2018 Profit / (Loss) Recognized in 2019 Contract Price Costs Incurred Total Profit / (Loss) on Contract [Entry field with incorrect answer] [Entry field with incorrect answer] Total Profit / (Loss) on Contract Profit / (Loss) Recognized in 2019 Profit / (Loss) Recognized in 2018 Costs Incurred Contract Price [Entry field with incorrect answer] [Entry field with incorrect answer] Less Add : [Entry field with incorrect answer] Profit / (Loss) Recognized in 2019 Contract Price Costs Incurred Total Profit / (Loss) on Contract Profit / (Loss) Recognized in 2018 [Entry field with incorrect answer] [Entry field with incorrect answer]
  • 12. Costs Incurred Contract Price Profit / (Loss) Recognized in 2019 Total Profit / (Loss) on Contract Profit / (Loss) Recognized in 2018 $ [Entry field with incorrect answer now contains modified data] Solution (a) Percentage-of-Completion Method 2017 Costs up to 12/31/17........................................................... $ 298,000 Estimated costs for completetion......................................... 1,192,000 Estimated total costs.................................................... $1,4,90,000 Percentage completed ($298,000/$1,490,000)..................... 20% Revenue to be recognized ($1,880,000*20%)....................... $ 376000 Costs incurred...................................................................... ($298000) Profit to be recognized in 2017............................................ $ 78000 2018 Costs to date (12/31/18)....................................................... $1,1,94,000 Estimated costs to complete................................................. 796,000 Estimated total costs.................................................... $1990000 Contract price...................................................................... (1,880,000) Total loss............................................................................. $ 110,000 Total loss............................................................................. $ 110,000 Plus gross profit recognized in 2017.................................... 78,000 Loss recognized in 2018....................................................... $ 188,000 2019 Costs to date (12/31/19).............................................. $2,098,500 Estimated costs to complete........................................ 0 2,098,500 Contract price............................................................. 1,880,000 Total loss.................................................................... $ (218,500) Total loss.................................................................... $ (218,500) Less: Loss recognized in 2018.................................... $188000 Gross profit recognized in 2017.................................. (78,000) (110,000) Loss recognized in 2019.............................................. $ (108,500) (b) Completed-Contract Method 2017—No revenue or profit is reognized 2018
  • 13. Costs to date (12/31/18)............................................... $1,194,000 Estimated costs to complete......................................... 796,000 Estimated total costs............................................ $1990000 Contract price............................................................... 1,880,000 Loss recognized in 2018............................................... $ (1100,000) 2019 Total costs incurred till 12/31/19.................................. $2,098,500 Total revenue recognized.............................................. 1,880000 Total loss on contract........................................... (218500) Less: loss recognized in 2018........................................ (110,000) Loss recognized in 2019................................................ $ (108500)