CIPS CH Meetup
AGILITY IN PROCUREMENT -
JUST TALK OR REALITY?!
The Air France - KLM, Cargo Truck
case.
Frédéric Jacques - Air France
Sophie Durand - Goood!
January 2021
2
PASSENGERS MAINTENANCE CARGO
Air France KLM Group : 6 brands / 3 activities
2 000
APPLICATIONS
Mostly developed
internaly
The Story
Mirko Kleiner
Latest Early Adopters
In Cooperation
Frédéric
JACQUES
Lionel
MASSIERA
Mirko
KLEINER
2 major challenges for Air France KLM :
- Delivering within a short timeframe a
new system to improve the efficiency
and productivity of its door-to-door
cargo services.
- Remodelling the vendor sourcing policy
for IT teams : sourcing complete teams
rather than individuals.
How to outsource a strategic
product development ?
4
5
I have a major business
goal at stake. If we
bring in a new team
now, is this goal
endangered ?
I have to ensure that
the new product will
integrate smoothly
into the Cargo
Information System
I want to be sure that all
contractual aspects are
well understood, and
that they are fair to both
parties.
My managing team is
overwhelmed by
external resource
management. This has
to stop !
I have a very smooth
and efficient
communication with the
current team. I fear it
won’t be the same with
the new team !
I need to add new skills
to my IT teams. I also
need new people to
inspire a stronger
innovation culture.
Hackthon
-Same location
-2 hard days for
developpers
-2 days of proposal details
and improvments with
sales representatives
LAP LAUNCH
21
Jan
Alignment
Workshops
25
Jan
Vendors info
webinar
31
Jan
Evaluation
Workshop
25/26
Feb
Partner Choice
26
Feb
Start Working
4
Mar
8 Weeks (lead time)
Days with vendor
Working Days
Looking for True North
‟
REX Cargo
Instead of eliminating the less promising
offers, we ended up improving each
proposal and choosing the best one.
Eric Chaumette – Managed Delivery Centers Program
Management
Lean Agile Procurement is an innovative, outstanding
partnership accelerator to identify and select your
right team with the right people having the best
fitting competences and team spirit.
It took less than two months getting our complete IT
team !
Something new is
Dominique Guillet - Business Analyst
8
And then ?
1 year Birthday !
- Team started 2 months earlier
than the initial estimation
- IT Application has been
delivered in due date as
mentionned in L.A.P.
- IT CARGO was about 1 year
ahead other AF KLM Teams in
moving to the new sourcing
model adoption
- Business and IT grew together.
- Partnership proven during covid
crisis
- 2nd L.A.P. processed
successfully for on site
partnership.
9
Thank you.

AirFrance KLM - How to Outsource a Critical Project with Lean-Agile Procurement

  • 1.
    CIPS CH Meetup AGILITYIN PROCUREMENT - JUST TALK OR REALITY?! The Air France - KLM, Cargo Truck case. Frédéric Jacques - Air France Sophie Durand - Goood! January 2021
  • 2.
    2 PASSENGERS MAINTENANCE CARGO AirFrance KLM Group : 6 brands / 3 activities 2 000 APPLICATIONS Mostly developed internaly
  • 3.
    The Story Mirko Kleiner LatestEarly Adopters In Cooperation Frédéric JACQUES Lionel MASSIERA Mirko KLEINER
  • 4.
    2 major challengesfor Air France KLM : - Delivering within a short timeframe a new system to improve the efficiency and productivity of its door-to-door cargo services. - Remodelling the vendor sourcing policy for IT teams : sourcing complete teams rather than individuals. How to outsource a strategic product development ? 4
  • 5.
    5 I have amajor business goal at stake. If we bring in a new team now, is this goal endangered ? I have to ensure that the new product will integrate smoothly into the Cargo Information System I want to be sure that all contractual aspects are well understood, and that they are fair to both parties. My managing team is overwhelmed by external resource management. This has to stop ! I have a very smooth and efficient communication with the current team. I fear it won’t be the same with the new team ! I need to add new skills to my IT teams. I also need new people to inspire a stronger innovation culture.
  • 6.
    Hackthon -Same location -2 harddays for developpers -2 days of proposal details and improvments with sales representatives LAP LAUNCH 21 Jan Alignment Workshops 25 Jan Vendors info webinar 31 Jan Evaluation Workshop 25/26 Feb Partner Choice 26 Feb Start Working 4 Mar 8 Weeks (lead time) Days with vendor Working Days Looking for True North
  • 7.
    ‟ REX Cargo Instead ofeliminating the less promising offers, we ended up improving each proposal and choosing the best one. Eric Chaumette – Managed Delivery Centers Program Management Lean Agile Procurement is an innovative, outstanding partnership accelerator to identify and select your right team with the right people having the best fitting competences and team spirit. It took less than two months getting our complete IT team ! Something new is Dominique Guillet - Business Analyst
  • 8.
    8 And then ? 1year Birthday ! - Team started 2 months earlier than the initial estimation - IT Application has been delivered in due date as mentionned in L.A.P. - IT CARGO was about 1 year ahead other AF KLM Teams in moving to the new sourcing model adoption - Business and IT grew together. - Partnership proven during covid crisis - 2nd L.A.P. processed successfully for on site partnership.
  • 9.