The situation @ CKW on 1st of April 2018
The CKW Group is a Swiss energy company with 200’000
customers, 1700 employees an annual revenue of $850
million. It is still in the early stages of transitioning to
business agility.
• 1.1.2018 - 31.3.2018: The board approved the project
«SOLER» that should introduce a new collaboration and
communication software suite for their 1700 employees
• 31.04.2018 - 30.06.2018: A solution and supplier
should be found
• 01.07.2018 - 30.09.2018: In this time space a project
should happen
THE CHALLENGE