SlideShare a Scribd company logo
1 of 14
OPEN CIRCUIT & SHORT CIRCUIT 
TEST ON TRANSFORMER 
PREPAIRED BY: 
MANAVAR MILAN
INTRODUCTION 
• Necessity of testing 
• Open circuit test 
• Short circuit test 
• Advantages 
• Application
NECESSITY OF TESTING 
• In transformer and other equipment have 
input and output. Hence how to we find the 
performance of transformer and other 
equipment…..? 
• We have a solution even we will find the loss 
of transformer so we can easily find the all 
parameters of transformer like, we can find 
iron loss, cu loss, impedance, no load current, 
short circuit current and efficiency.
OPEN CIRCUIT TEST
HOW TO MEASURE O.C. TEST 
1. To connect Wattmeter in primary side. 
2. To connect Ammeter in series of phase. 
3. To connect Voltmeter in parallel of primary 
side. 
4. We will open the Secondary side. 
5. We will give the supply primary side for the 
measurement of iron losses.
• The purpose of this test is to find the no-load loss 
or core loss. 
• A wattmeter, voltmeter and an ammeter are 
connected in low voltage side. 
• Secondary side of transformer we will keep open. 
• We give the normal voltage applied to the 
primary, normal flux will be set up in the core, 
hence normal iron losses will occur which are 
recorded by the wattmeter.
• As the primary no-load current is measured 
by ammeter and its value is small, Cu-loss is 
negligibly small in primary and nil in 
secondary (it being open). 
• Hence, the wattmeter reading represents 
practically the CORE LOSS under no-load 
condition.
• Sometimes a high resistance voltmeter is 
connected across the secondary. The reading 
of the voltmeter gives the induced e.m.f. in 
the secondary winding.
SHORT CIRCUIT TEST
HOW TO MEASURE S.C. TEST 
1. To connect the wattmeter primary side 
2. To connect the Ammeter in series of primary 
side 
3. To connect the Voltmeter in parallel of 
primary side 
4. Short the secondary side using thick 
conductor 
5. Now give the small voltage supply for the 
measurement of Cu-losses.
• A wattmeter, voltmeter and an ammeter are 
connected in high voltage side. 
• The low voltage side of transformer is short 
circuited. 
• The applied voltage is a small percentage of the 
normal voltage. 
• Hence the core losses are very small with the 
result of the wattmeter reading represent the 
full-load CU-LOSS or loss for the whole 
transformer .
ADVANTAGES 
• No require for extra load 
• This test are very economical and convenient, 
because they furnish the required information 
without actually loading the transformer.
APPLICATION 
• By using open circuit test we can measure the 
loss of no-load losses means that iron losses. 
• By using short circuit test we can measure the 
loss of full-load losses means that Cu-losses. 
• We can find the efficiency by using of iron 
losses and cu-losses.
THANK YOU

More Related Content

What's hot

transformer slide prsentation
transformer slide prsentation transformer slide prsentation
transformer slide prsentation abu jubayer
 
Starting method of induction motors
Starting method of induction motorsStarting method of induction motors
Starting method of induction motorsGurkirat Singh
 
Presentation on bipolar junction transistor
Presentation on bipolar junction transistorPresentation on bipolar junction transistor
Presentation on bipolar junction transistorKawsar Ahmed
 
Three phase transformer
Three phase transformer Three phase transformer
Three phase transformer Muhammadhamad24
 
Construction & E.M.F. eqn. of transformer
Construction & E.M.F. eqn. of transformerConstruction & E.M.F. eqn. of transformer
Construction & E.M.F. eqn. of transformerJay Baria
 
Three phase Induction Motor (Construction and working Principle)
Three phase Induction Motor (Construction and working Principle)Three phase Induction Motor (Construction and working Principle)
Three phase Induction Motor (Construction and working Principle)Sharmitha Dhanabalan
 
Current Transformer and Potential Transformer
Current Transformer and Potential TransformerCurrent Transformer and Potential Transformer
Current Transformer and Potential TransformerRidwanul Hoque
 
Electrical transformer working and construction
Electrical transformer working and constructionElectrical transformer working and construction
Electrical transformer working and constructionSourabh sharma
 
Dc motors and its types
Dc motors and its typesDc motors and its types
Dc motors and its typesSumeet Patel
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Moving iron (MI) instruments
Moving iron (MI) instrumentsMoving iron (MI) instruments
Moving iron (MI) instrumentsChandan Singh
 
Power Electronics Chopper (dc – dc converter)
Power Electronics   Chopper (dc – dc converter)Power Electronics   Chopper (dc – dc converter)
Power Electronics Chopper (dc – dc converter)Burdwan University
 

What's hot (20)

TRIAC
TRIACTRIAC
TRIAC
 
transformer slide prsentation
transformer slide prsentation transformer slide prsentation
transformer slide prsentation
 
Starting method of induction motors
Starting method of induction motorsStarting method of induction motors
Starting method of induction motors
 
Presentation on bipolar junction transistor
Presentation on bipolar junction transistorPresentation on bipolar junction transistor
Presentation on bipolar junction transistor
 
Three phase transformer
Three phase transformer Three phase transformer
Three phase transformer
 
Construction & E.M.F. eqn. of transformer
Construction & E.M.F. eqn. of transformerConstruction & E.M.F. eqn. of transformer
Construction & E.M.F. eqn. of transformer
 
Three phase Induction Motor (Construction and working Principle)
Three phase Induction Motor (Construction and working Principle)Three phase Induction Motor (Construction and working Principle)
Three phase Induction Motor (Construction and working Principle)
 
Current Transformer and Potential Transformer
Current Transformer and Potential TransformerCurrent Transformer and Potential Transformer
Current Transformer and Potential Transformer
 
Dc motor starters
Dc motor startersDc motor starters
Dc motor starters
 
Transformer basics
Transformer   basicsTransformer   basics
Transformer basics
 
Electrical transformer working and construction
Electrical transformer working and constructionElectrical transformer working and construction
Electrical transformer working and construction
 
Dc motors and its types
Dc motors and its typesDc motors and its types
Dc motors and its types
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
dc Generator Ppt
dc Generator Pptdc Generator Ppt
dc Generator Ppt
 
Unit5:- D.C Machines
Unit5:- D.C MachinesUnit5:- D.C Machines
Unit5:- D.C Machines
 
Dc machines (Generator & Motor)
Dc machines (Generator & Motor)Dc machines (Generator & Motor)
Dc machines (Generator & Motor)
 
Moving iron (MI) instruments
Moving iron (MI) instrumentsMoving iron (MI) instruments
Moving iron (MI) instruments
 
Power Electronics Chopper (dc – dc converter)
Power Electronics   Chopper (dc – dc converter)Power Electronics   Chopper (dc – dc converter)
Power Electronics Chopper (dc – dc converter)
 
Single phase im-lecture_10_1
Single phase im-lecture_10_1Single phase im-lecture_10_1
Single phase im-lecture_10_1
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 

Viewers also liked

EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6ruhiyah
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)ruhiyah
 
EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4 ruhiyah
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORSAJAL A J
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)firozamin
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behinBehin anben
 

Viewers also liked (8)

Lecture 8 bjt_1
Lecture 8 bjt_1Lecture 8 bjt_1
Lecture 8 bjt_1
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)
 
EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORS
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behin
 

Similar to open circuit and short circuit test on transformer

O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...Abhishek Choksi
 
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...Prasant Kumar
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of TransformersGirin Chutia
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connectionssanewton
 
Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on TransformersSoham Gajjar
 
Special transformers
Special transformersSpecial transformers
Special transformersPreet_patel
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier pptvikas kumar
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...sanewton
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfsrevathiap
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE Lalit Kumar
 
IET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxIET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxDavy40
 

Similar to open circuit and short circuit test on transformer (20)

Akshay kumar
Akshay kumarAkshay kumar
Akshay kumar
 
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
 
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of Transformers
 
Notes
NotesNotes
Notes
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connections
 
Usage of meters
 Usage of meters  Usage of meters
Usage of meters
 
Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on Transformers
 
Special transformers
Special transformersSpecial transformers
Special transformers
 
multimeter.pptx
multimeter.pptxmultimeter.pptx
multimeter.pptx
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Transformers
TransformersTransformers
Transformers
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdf
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
IET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxIET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptx
 
Usage of meters - Notes
Usage of meters - NotesUsage of meters - Notes
Usage of meters - Notes
 

Recently uploaded

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 

Recently uploaded (20)

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 

open circuit and short circuit test on transformer

  • 1. OPEN CIRCUIT & SHORT CIRCUIT TEST ON TRANSFORMER PREPAIRED BY: MANAVAR MILAN
  • 2. INTRODUCTION • Necessity of testing • Open circuit test • Short circuit test • Advantages • Application
  • 3. NECESSITY OF TESTING • In transformer and other equipment have input and output. Hence how to we find the performance of transformer and other equipment…..? • We have a solution even we will find the loss of transformer so we can easily find the all parameters of transformer like, we can find iron loss, cu loss, impedance, no load current, short circuit current and efficiency.
  • 5. HOW TO MEASURE O.C. TEST 1. To connect Wattmeter in primary side. 2. To connect Ammeter in series of phase. 3. To connect Voltmeter in parallel of primary side. 4. We will open the Secondary side. 5. We will give the supply primary side for the measurement of iron losses.
  • 6. • The purpose of this test is to find the no-load loss or core loss. • A wattmeter, voltmeter and an ammeter are connected in low voltage side. • Secondary side of transformer we will keep open. • We give the normal voltage applied to the primary, normal flux will be set up in the core, hence normal iron losses will occur which are recorded by the wattmeter.
  • 7. • As the primary no-load current is measured by ammeter and its value is small, Cu-loss is negligibly small in primary and nil in secondary (it being open). • Hence, the wattmeter reading represents practically the CORE LOSS under no-load condition.
  • 8. • Sometimes a high resistance voltmeter is connected across the secondary. The reading of the voltmeter gives the induced e.m.f. in the secondary winding.
  • 10. HOW TO MEASURE S.C. TEST 1. To connect the wattmeter primary side 2. To connect the Ammeter in series of primary side 3. To connect the Voltmeter in parallel of primary side 4. Short the secondary side using thick conductor 5. Now give the small voltage supply for the measurement of Cu-losses.
  • 11. • A wattmeter, voltmeter and an ammeter are connected in high voltage side. • The low voltage side of transformer is short circuited. • The applied voltage is a small percentage of the normal voltage. • Hence the core losses are very small with the result of the wattmeter reading represent the full-load CU-LOSS or loss for the whole transformer .
  • 12. ADVANTAGES • No require for extra load • This test are very economical and convenient, because they furnish the required information without actually loading the transformer.
  • 13. APPLICATION • By using open circuit test we can measure the loss of no-load losses means that iron losses. • By using short circuit test we can measure the loss of full-load losses means that Cu-losses. • We can find the efficiency by using of iron losses and cu-losses.