The document discusses time management techniques for projects. It defines key time management processes like activity definition, duration estimation, and schedule development. It describes developing a schedule by outlining tasks, estimating durations, sequencing tasks, and using critical path methods. The document provides examples of time management tools like Gantt charts, network diagrams, and an output schedule with tasks, durations, dependencies, and resources. It discusses schedule control activities like tracking progress against the baseline, measuring variances, and identifying corrective actions.
24. Schedule Control
• Determine the current status of the project
• Influence the factors that cause changes
• Identify schedule changes
• Evaluate change requests
• Manage change requests
– Plan changes
– Execute changes
www.projektor.ee/pm/#time
26. Baseline
Time baseline is a fixed schedule
which is used to measure the
performance of the project
The value or condition against
which all future measurements will
be compared
www.projektor.ee/pm/#time
27. Schedule Progress Data
• Actual start dates
• Actual finish dates
• Remaining duration for unfinished activities
• Calculating:
– Percent complete
– Schedule variance (SV)
– Schedule performance index (SPI = EV/PV)
www.projektor.ee/pm/#time
29. Slack
The amount of time that a task in
a project schedule can be delayed
without causing a delay in other
tasks or in project deadline
www.projektor.ee/pm/#time