1. Production Schedule- 'On My Way'
Day one- 10th
June 2016
Scene: Running through the woods
Crew required at location: Camera operator, director, actors, editor, costume
Call Time: All cast should be ready latest 9:45 am
Actors required: Danny, Jammi,
Set up start time: 9:00 am, set up
Set up finish time: 9:30 am
Contingency Plan:
An issue for the first day of filming would be if the actors were unable to turn up for
filming, dew to things such as illness. Filming would then get delayed if they were ill,
we will make sure that there are a few days leeway before filming so we can cope
with these issues. Another issue is the fact that we only have one chance for our final
cut, therefore Saturday the 11th will be the day if there are any touchups.
Shots:
Close up
Wide shot
Mid shot
Wide shot
Wide shot
Mid shot
Wide shot
Mid shot
Close up
Wide shot
Two Shot
Mid Shot
Zoom Out
Two Shot
Wide shot
Close up
Pan Shot
Wide shot
Three shot
Day Two- 20th June 2016
Scene: Green screen shots
Crew required at location: Camera operator, director, actors, editor, costume
Call Time: All cast should be ready latest 1:25 pm
Actors required: Danny, Jammi,
Set up start time: 10:00 am
Set up finish time: 1:10 am
Shots:
2. Wide shot
Mid Shot
Wide shot
Pan shot
Close up
Contingency Plan:
On this day like the last we are at risk of there being potential rainfall. But we will
take precautions in that we will postpone filming for a couple of days and make time
to edit what we have so far, while we still wait to edit the rest of the video.