MILL SETTING
DEFINITIONS :
Mean effective diameter of Top Roller D
= (Outside diameter of roller - Depth of grooving)
Work Opening : Actual opening between any two points on the
surface of the two rollers in their common
axial plane when the mills are in operation.
Mill Setting opening : Actual opening between PCD to PCD of concerned
opening rollers, when mills are at rest and empty.
DATA REQUIRED FOR MILL SETTING
C = Crush rate desired in tons (Metric)/hr.
f = fibre % cane
D = Mean effective diameter of Top Roller (mm)
L = Length of the roller (mm)
n = Speed of rotation (rpm) {To be determined based on
No. of rollers in mill tandem, crush rate, preparatory
index, specific fibre loading, power availability at setting
speed etc.}
PROCEDURE FOR CALCULATION OF MILL SETTING
V = Mill Roller surface speed
 x D x n
V = ------------- m/min.
1000
Calculate fibre rate 'F' as per formula given below:
F = C x f x 0.166 Kg / min.
Calculate the discharge work opening as
per formula given below:
F x 63429.6
Discharge work opening = ---------------------- mm.
S x V x L
Where ‘S’ denotes the Fibre Index to be read from Table – 1.
Actual Discharge Work Opening = (Discharge work opening – Roller
Rise) mm.
The 'Roller Rise' considered for the mills shall be taken as per Table 2.
Mills 12 Roller Tandem 15 Roller Tandem
2nd of `B’ Tandem 38 40
3rd of `B’ Tandem 45 46
4th of `I’ Tandem 52 52
TABLE – 1
Values of Fibre Index ‘S’
Mill No. 12 Roller Tandem 15 Roller Tandem
Roller Trash Roller Trash
2nd of `B’
Tandem
7 8 7 8
3rd of `B’ Tandem 6 7 6 7
4th of `I’ Tandem 5 6 6 6
TABLE – 2
ROLLER RISE
Calculate the Feed work opening as per formula given below:
Feed work opening = Discharge work opening X (Ratio of feed
to discharge opening) mm.
The Ratio of Feed to Discharge opening for the mills shall be taken as per
Table 3.
Actual Feed Work Opening = (Feed work opening – Roller Rise) mm.
Mills 12 Roller Tandem 15 Roller Tandem
2nd of `B’Tandem 2.00 2.05
3rd of `B’Tandem 2.15 2.10
4th of `I’Tandem 2.20 2.15
TABLE – 3
Ratio of Feed to Discharge Opening presumed for calculations
Calculate the Trash plate work opening as per formula given
below:
Trash Plate work opening = Feed work opening X (Ratio of trash
plate to
feed opening ) mm.
The Ratio of Trash Plate to Feed opening for the mills shall be taken as
per
Table 4.
Actual Trash Plate Work Opening = (Trash Plate work opening – Roller
Rise)mm.
Mill No. 12 Roller Tandem 15 Roller Tandem
2nd of `B’Tandem 1.70 1.75
3rd of `B’ Tandem 1.80 1.80
4th of `I’Tandem 1.80 1.85
TABLE – 4
Ratios of trash plate to feed opening presumed for calculations
SPECIMEN CALCULATIONS

 DATA

 Crushing Rate (c) : 250 Tons (Metric) of Cane per hour (TCH)

 Fibre % Cane (f) : 13%

 Roller Length (L) : 78 1/8 inches

 Mill Size (D x L) : 39 inches O.D. x 78 1/8 inches

 Speed selected (n): 5.5 r.p.m.

 Now calculate the factor 'F' for the above conditions
  x D x n 3.1416 x 915 x 5.5
 V = --------------- m/min. = ------------------------
 1000 1000
 = 15.81 m / min.
Calculate factor 'F' as per formula given below:

 F = C x f x 0.3733 lb / min.

 = 250 x 13 x 0.166
 = 539.5 Kg / min.
Calculation of Discharge work opening
 F x 63429.6
 Discharge work opening = -----------------mm.
 S x V xL
 For value of ‘S’ see table - 1
 539.5 x 63429.6
 = ------------------------
40 x 15.81 x 1980

 = 27.3 mm

Calculation of Feed work opening
 Feed work opening = Discharge work opening X
 (Ratio of feed to discharge
Opening)
 For value of ‘Ratio’ see TABLE-3

 = 27.32 x 2.05

 = 56 mm
Calculation of Trash plate work opening
 Trash Plate work opening= Feed work opening X
(Ratio of trash plate
to Feed Opening)
 For value of ‘Ratio’ see TABLE-3

 = 56 x 1.75

 = 98 mm.
Mill No. Feed Side Opening
(mm)
Discharge Side Opening
(mm)
Trash Plate
Opening
(mm)
2nd of `B’
Tandem
56 27.3 98
3rd of `B’ Tandem 50 23.8 89.8
4th of `I’ Tandem 45 21 83.7
The discharge, feed and trash plate openings for all the four mills are
tabulated below.
Mill No. Feed Setting =
Actual opening- roller
rise
Discharge Opening =
Actual opening- roller
rise
Trash Plate Setting =
Actual opening- roller
rise
2nd of
`B’
Tandem
56 – 7 = 49 27.3 – 7 = 20.3 98 – 8 = 90
3rd of `B’
Tandem
50 – 6 = 44 23.8 – 6 = 17.8 89.8 – 7 = 82.8
4th of `I’
Tandem
45 – 6 = 39 21 – 6 = 15 83.7 – 6 = 77.7
The ‘Mill Settings’ for all four mills can be calculated as given
below:
Mill Settings in mm
The mill settings calculated should be rounded off for practical adjustment
purpose.

More Related Content

What's hot

What's hot (20)

Ball & tube mill
Ball & tube millBall & tube mill
Ball & tube mill
 
Hydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operationHydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operation
 
Chapter 3 centrifugal comp
Chapter 3 centrifugal compChapter 3 centrifugal comp
Chapter 3 centrifugal comp
 
Bag filter operation pradeep kumar
Bag filter operation pradeep kumarBag filter operation pradeep kumar
Bag filter operation pradeep kumar
 
Scoop coupling
Scoop couplingScoop coupling
Scoop coupling
 
Formulas kiln
Formulas kilnFormulas kiln
Formulas kiln
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
Centrifugal pumps
Centrifugal pumpsCentrifugal pumps
Centrifugal pumps
 
Compressor
CompressorCompressor
Compressor
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Loesche Mill for Solid Fuels
Loesche Mill for Solid FuelsLoesche Mill for Solid Fuels
Loesche Mill for Solid Fuels
 
Alignment of-kiln
Alignment of-kilnAlignment of-kiln
Alignment of-kiln
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
Steam traps and their types
Steam traps and their typesSteam traps and their types
Steam traps and their types
 
HYDRAULIC TRUCK TIPPLER
HYDRAULIC TRUCK TIPPLERHYDRAULIC TRUCK TIPPLER
HYDRAULIC TRUCK TIPPLER
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
 
Principle of operation bowl mill
Principle of operation bowl millPrinciple of operation bowl mill
Principle of operation bowl mill
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)
 

Similar to Mill setting for Sugar Mills

construction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfconstruction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfexample43
 
Design of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 ProcedureDesign of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 Procedures Kumaravel
 
pressure drop calculation in sieve plate distillation column
pressure drop calculation in sieve plate distillation columnpressure drop calculation in sieve plate distillation column
pressure drop calculation in sieve plate distillation columnAli Shaan Ghumman
 
78607049-Ventilacion-para-un-taller-de-soldadura.pdf
78607049-Ventilacion-para-un-taller-de-soldadura.pdf78607049-Ventilacion-para-un-taller-de-soldadura.pdf
78607049-Ventilacion-para-un-taller-de-soldadura.pdfFarid Herrera
 
Textile calculations - Vignesh Dhanabalan
Textile calculations - Vignesh DhanabalanTextile calculations - Vignesh Dhanabalan
Textile calculations - Vignesh DhanabalanVignesh Dhanabalan
 
Development of Machine for Opening and Cleaning of Cotton Fibre in Laboratories
Development of Machine for Opening and Cleaning of Cotton Fibre in LaboratoriesDevelopment of Machine for Opening and Cleaning of Cotton Fibre in Laboratories
Development of Machine for Opening and Cleaning of Cotton Fibre in LaboratoriesIRJET Journal
 
IRJET- Design of Bell-Mouth Spillway at Barvi Dam
IRJET- Design of Bell-Mouth Spillway at Barvi DamIRJET- Design of Bell-Mouth Spillway at Barvi Dam
IRJET- Design of Bell-Mouth Spillway at Barvi DamIRJET Journal
 
IRJET- Theoretical Analysis of Rocker Arm
IRJET- Theoretical Analysis of Rocker ArmIRJET- Theoretical Analysis of Rocker Arm
IRJET- Theoretical Analysis of Rocker ArmIRJET Journal
 
"Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme""Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme"IRJET Journal
 
Yarn calculations By Samrat Dewan
Yarn calculations By Samrat DewanYarn calculations By Samrat Dewan
Yarn calculations By Samrat DewanSamrat Dewan
 
HYDRAULIC SYSTEM DESIGN from hydraulics .pptx
HYDRAULIC SYSTEM DESIGN from hydraulics .pptxHYDRAULIC SYSTEM DESIGN from hydraulics .pptx
HYDRAULIC SYSTEM DESIGN from hydraulics .pptxsbpatalescoe
 
Vertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectVertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectPoorna Hewapathirana
 

Similar to Mill setting for Sugar Mills (20)

Vb
VbVb
Vb
 
construction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfconstruction equpment Chapter 2.pdf
construction equpment Chapter 2.pdf
 
Design of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 ProcedureDesign of Machine Elements - Unit 5 Procedure
Design of Machine Elements - Unit 5 Procedure
 
pressure drop calculation in sieve plate distillation column
pressure drop calculation in sieve plate distillation columnpressure drop calculation in sieve plate distillation column
pressure drop calculation in sieve plate distillation column
 
Textile calculations
Textile calculationsTextile calculations
Textile calculations
 
78607049-Ventilacion-para-un-taller-de-soldadura.pdf
78607049-Ventilacion-para-un-taller-de-soldadura.pdf78607049-Ventilacion-para-un-taller-de-soldadura.pdf
78607049-Ventilacion-para-un-taller-de-soldadura.pdf
 
Textile calculations - Vignesh Dhanabalan
Textile calculations - Vignesh DhanabalanTextile calculations - Vignesh Dhanabalan
Textile calculations - Vignesh Dhanabalan
 
Development of Machine for Opening and Cleaning of Cotton Fibre in Laboratories
Development of Machine for Opening and Cleaning of Cotton Fibre in LaboratoriesDevelopment of Machine for Opening and Cleaning of Cotton Fibre in Laboratories
Development of Machine for Opening and Cleaning of Cotton Fibre in Laboratories
 
IRJET- Design of Bell-Mouth Spillway at Barvi Dam
IRJET- Design of Bell-Mouth Spillway at Barvi DamIRJET- Design of Bell-Mouth Spillway at Barvi Dam
IRJET- Design of Bell-Mouth Spillway at Barvi Dam
 
IRJET- Theoretical Analysis of Rocker Arm
IRJET- Theoretical Analysis of Rocker ArmIRJET- Theoretical Analysis of Rocker Arm
IRJET- Theoretical Analysis of Rocker Arm
 
Unit 3.2 Design of Clutches
Unit 3.2 Design of ClutchesUnit 3.2 Design of Clutches
Unit 3.2 Design of Clutches
 
"Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme""Design Criteria of Lift Irrigation Scheme"
"Design Criteria of Lift Irrigation Scheme"
 
Yarn calculations By Samrat Dewan
Yarn calculations By Samrat DewanYarn calculations By Samrat Dewan
Yarn calculations By Samrat Dewan
 
HYDRAULIC SYSTEM DESIGN from hydraulics .pptx
HYDRAULIC SYSTEM DESIGN from hydraulics .pptxHYDRAULIC SYSTEM DESIGN from hydraulics .pptx
HYDRAULIC SYSTEM DESIGN from hydraulics .pptx
 
K0342060066
K0342060066K0342060066
K0342060066
 
Wells & Pumps Project Report
Wells & Pumps Project ReportWells & Pumps Project Report
Wells & Pumps Project Report
 
B012460814
B012460814B012460814
B012460814
 
O44097379
O44097379O44097379
O44097379
 
Vertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectVertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design Project
 
Blow room
Blow room Blow room
Blow room
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Mill setting for Sugar Mills

  • 1. J E G A D E E S H . M E N G I N E E R I N D I A N C A N E P O W E R L I M I T E D MILL SETTING
  • 2. DEFINITIONS : Mean effective diameter of Top Roller D = (Outside diameter of roller - Depth of grooving) Work Opening : Actual opening between any two points on the surface of the two rollers in their common axial plane when the mills are in operation. Mill Setting opening : Actual opening between PCD to PCD of concerned opening rollers, when mills are at rest and empty.
  • 3. DATA REQUIRED FOR MILL SETTING C = Crush rate desired in tons (Metric)/hr. f = fibre % cane D = Mean effective diameter of Top Roller (mm) L = Length of the roller (mm) n = Speed of rotation (rpm) {To be determined based on No. of rollers in mill tandem, crush rate, preparatory index, specific fibre loading, power availability at setting speed etc.}
  • 4. PROCEDURE FOR CALCULATION OF MILL SETTING V = Mill Roller surface speed  x D x n V = ------------- m/min. 1000 Calculate fibre rate 'F' as per formula given below: F = C x f x 0.166 Kg / min.
  • 5. Calculate the discharge work opening as per formula given below: F x 63429.6 Discharge work opening = ---------------------- mm. S x V x L Where ‘S’ denotes the Fibre Index to be read from Table – 1. Actual Discharge Work Opening = (Discharge work opening – Roller Rise) mm. The 'Roller Rise' considered for the mills shall be taken as per Table 2.
  • 6. Mills 12 Roller Tandem 15 Roller Tandem 2nd of `B’ Tandem 38 40 3rd of `B’ Tandem 45 46 4th of `I’ Tandem 52 52 TABLE – 1 Values of Fibre Index ‘S’ Mill No. 12 Roller Tandem 15 Roller Tandem Roller Trash Roller Trash 2nd of `B’ Tandem 7 8 7 8 3rd of `B’ Tandem 6 7 6 7 4th of `I’ Tandem 5 6 6 6 TABLE – 2 ROLLER RISE
  • 7. Calculate the Feed work opening as per formula given below: Feed work opening = Discharge work opening X (Ratio of feed to discharge opening) mm. The Ratio of Feed to Discharge opening for the mills shall be taken as per Table 3. Actual Feed Work Opening = (Feed work opening – Roller Rise) mm. Mills 12 Roller Tandem 15 Roller Tandem 2nd of `B’Tandem 2.00 2.05 3rd of `B’Tandem 2.15 2.10 4th of `I’Tandem 2.20 2.15 TABLE – 3 Ratio of Feed to Discharge Opening presumed for calculations
  • 8. Calculate the Trash plate work opening as per formula given below: Trash Plate work opening = Feed work opening X (Ratio of trash plate to feed opening ) mm. The Ratio of Trash Plate to Feed opening for the mills shall be taken as per Table 4. Actual Trash Plate Work Opening = (Trash Plate work opening – Roller Rise)mm.
  • 9. Mill No. 12 Roller Tandem 15 Roller Tandem 2nd of `B’Tandem 1.70 1.75 3rd of `B’ Tandem 1.80 1.80 4th of `I’Tandem 1.80 1.85 TABLE – 4 Ratios of trash plate to feed opening presumed for calculations
  • 10. SPECIMEN CALCULATIONS   DATA   Crushing Rate (c) : 250 Tons (Metric) of Cane per hour (TCH)   Fibre % Cane (f) : 13%   Roller Length (L) : 78 1/8 inches   Mill Size (D x L) : 39 inches O.D. x 78 1/8 inches   Speed selected (n): 5.5 r.p.m.   Now calculate the factor 'F' for the above conditions   x D x n 3.1416 x 915 x 5.5  V = --------------- m/min. = ------------------------  1000 1000  = 15.81 m / min.
  • 11. Calculate factor 'F' as per formula given below:   F = C x f x 0.3733 lb / min.   = 250 x 13 x 0.166  = 539.5 Kg / min.
  • 12. Calculation of Discharge work opening  F x 63429.6  Discharge work opening = -----------------mm.  S x V xL  For value of ‘S’ see table - 1  539.5 x 63429.6  = ------------------------ 40 x 15.81 x 1980   = 27.3 mm 
  • 13. Calculation of Feed work opening  Feed work opening = Discharge work opening X  (Ratio of feed to discharge Opening)  For value of ‘Ratio’ see TABLE-3   = 27.32 x 2.05   = 56 mm
  • 14. Calculation of Trash plate work opening  Trash Plate work opening= Feed work opening X (Ratio of trash plate to Feed Opening)  For value of ‘Ratio’ see TABLE-3   = 56 x 1.75   = 98 mm.
  • 15. Mill No. Feed Side Opening (mm) Discharge Side Opening (mm) Trash Plate Opening (mm) 2nd of `B’ Tandem 56 27.3 98 3rd of `B’ Tandem 50 23.8 89.8 4th of `I’ Tandem 45 21 83.7 The discharge, feed and trash plate openings for all the four mills are tabulated below.
  • 16. Mill No. Feed Setting = Actual opening- roller rise Discharge Opening = Actual opening- roller rise Trash Plate Setting = Actual opening- roller rise 2nd of `B’ Tandem 56 – 7 = 49 27.3 – 7 = 20.3 98 – 8 = 90 3rd of `B’ Tandem 50 – 6 = 44 23.8 – 6 = 17.8 89.8 – 7 = 82.8 4th of `I’ Tandem 45 – 6 = 39 21 – 6 = 15 83.7 – 6 = 77.7 The ‘Mill Settings’ for all four mills can be calculated as given below: Mill Settings in mm The mill settings calculated should be rounded off for practical adjustment purpose.