Hydraulic control ROLCOX
of the rolls
1
Fixed Roller
Movable Roller
Left Right
Hydraulic oil tank
Pump HT 1 M 01
Next
HT 1 V 3/4 Prop. valve right
HT 1 V 1/2 Prop. valve left
HT 1 V 09 Emergency valve
HT 1 V 10
Pressure decrease valve left
( one way valve )
HT 1 V 11
Pressure decrease valve right
( one way valve )
HT 1 V 08 Retraction cylinder valve
HT 1 M 01 Hydraulic pump
HT 1 V 07 Bypass valve right
HT 1 V 06 Bypass valve left
Left Right
Retraction cylinder
Fixed Roller
Retraction cylinder
Hydraulic oil tank
Movable Roller
Press cylinder
V 09
V 08
Pump HT 1 M 01
V 07V 06
V 10 V 11
2
Next
Next
Next
Next
Next
Next
Next
Next
Next
V 1/2 V 3/4
+ Bearing dist. = 0 mm
RP - Frame
Gap sensor Limit switch
Press cylinder
Fixed Bearing
3
Roller dist. = 10 mm fix
Gap = 10 mm
Movable Bearing
Next
Retraction cylinder
NextNextNextNext
measured by
Distance block
This is the point where the bearing distance is 0.
For the gap measuring this point is 4 m Amp.
The bearing blocks are fixed in a way that the
rollers can never touch each other physically
Fixed Roller
Movable Roller
Left Right
Distance pieces
Movble
Roller
Fixed Roller
Left Right
Distance between the bearings used as lower
limit for the pressure control.
If distance is less pressure control will be
deactivated.
Roller distance 10mm = Gap 10 mm
Roller distance 10 mm
+ Bearing dist. 15 mm
= Gap 25 mm
Gap = 10 mm
Set points 4
0 mm ( Bearing distance )L 0mm
GAP > L min Pressure control ON
normal operation
L min 15 mm ( Bearing distance )
Next
Movable Roller
Next
Next
Next
GAP < L min Pressure control OFF
Next
Gap = 25 mm
L min
Movable
Roller
Fixed
RollerLeft Right
Gap = 35 mm
Movable
Fixed
RollerLeft Right
Gap = 45 mm
L2
Parameter set in the PLC. Set only once.
Range from 5.0 to 30.0 mm
Actual set point 25 mm
( Set point for material feeding )
Roller distance 10 mm
Set points
L min
+ L2 + 10 Bearing dist. 35 mm
5
Next
= Gap 35 mm
+ L2 Bearing dist. 25 mm
Next
L2
+ 10 mm
Until this value the rollers are pushed back
during start up the main motors.
= Gap 45 mm
Roller distance 10 mm
Next
Next
Movable
Roller
Fixed
RollerLeft Right
Gap = 65 mm maximum
Roller distance 10 mm
+ Bearing dist. > 55 mm
= Gap > 65 mm
Limit switch
Maximum distance allowed
between the bearings. ( 65 mm Gap )
Determined by a mechanical switch.
Over 65 mm gap the roller press will
stop with max. gap alarm.
Set points
6
Normal operation
Movable
Roller
Next
Next
Ok.
L2
L min
+ 10 mm
Movable
Roller
Movable
Roller
Movble
Roller
V 09
V 08
Hydraulic oil tank
Pump HT 1 M 01
Press cylinder
After reaching of L2 + 10 mm, the main drives will be
started one by one.
7
Start RP group
At every start the emergency valve is energized
to close the hydraulic circuit.
The movable roller will be moved
by the retraction cylinders to L2 + 10 mm = 45 mm
To release the oil of the main cylinders the bypass valves
and the pressure decrease valves are energized (opened).
This will occur with standing rollers.
Next
V 06V 06 V 07V 07
Next
NextNext
Next
V 09
Movable
Roller
Left
Fixed
Roller Right
Gap = 45 mm
Next
Next
L min
L2
+ 10 mm
V 11
V 3/4
V 10
V 1/2
V 10
V 06V 06 V 07V 07
V 3/4V 1/2
V 07V 07V 07V 07V 06V 06V 06V 06
V 11
Valve closed
Valve open
Next
V 08
Start RP group
Retraction cylinders are drawn back by springs.
After L2 will be reached in pre bin the shut off Gate will be opened
to release material flow to the rollers.
8
Next
L2 Gap = 35 mm
In case if during moving back the movable roller an oil pressure
is measured of more than 40 bar ( normal < 40 bar ), the start will
be interrupted by an alarm signal.
Fault has to be acknowledged at the roller press after checking.
Possible causes:
Material between the rollers.
Disturbance in the hydraulic circuit.
Roller can not move free.
After bearing distance is on both sides L2 the roller press group will
be released and feeding of the pre bin can be started.
Next
Next
Movble
Roller
V 09
Hydraulic oil tank
Pump HT 1 M 01
Press cylinder
V 06V 06 V 07V 07V 09
Movable
Roller
Left
Fixed
Roller Right
Gap = 45 mm
V 10
V 3/4V 1/2
V 07V 07V 07V 07V 06V 06V 06V 06
V 11
After this the movable roller will be pushed back to
L2 by the main cylinders from 45 mm to 35 mm.
This happens with running rollers.
V 08
Next
V 06V 06 V 07V 07
V 11V 10
V 1/2 V 3/4V 1/2 V 3/4
Gap = 35 mm
Pump stops and valves will be closed.
V 3/4V 1/2 V 3/4V 1/2
V 09
V 08
V 07V 06
Press cylinder
Left RightFixed Roller
The proportional valves will increase pressure to the
main cylinders up until the set point.
Hydraulic pump start.
9
Hydraulic oil tank
Pump HT 1 M 01
Next
Start Pressure control
After the start program is ready the pressure
control will start automatically.
After opening of the shut off gate there will get
material between the rollers.
Next
Movable Roller
Next
V 11V 10
Pressure control
By the intake behaviour of the running rollers
combined with the pressure of the column ( gap )
of material on the rollers the material flow will
tend to press the rollers apart.
Hydraulic oil tank
V 3/4V 1/2
V 08
Pump HT 1 M 01
V 09 V 07V 06
Left Right
Press cylinder
Movable Roller
Fixed Roller
When the hydraulic reaches the
value set point-tolerance
the proportional valves will be closed
and the pump will stop.
10
Pres.Set point
At this value the material counter pressure
and the cylinder pressure will be on balance.
- 10 bar
+ 10 bar
V 1/2 V 3/4
Next
Next
V 11V 10
Accumulator
Gas ( N2 ) Pressure = 90 bar100 bar
135 bar
125 bar
115 bar
Set point 125 bar
Hydraulic oil tank
V 3/4V 1/2
V 08
Pump HT 1 M 01
V 09 V 07V 06
Left Right
Fixed Roller
Press cylinder
Movable Roller
90
bar
Start up
< 90 bar
Pressure control
Pressure variations with in tolerance will be
compensated by the N2 accumulators.
11
V 1/2 V 3/4
100
bar Next
125 bar
Next
V 11V 10
Note: This can happen at both sides at the same time but also
on one of both sides, depending of pressure measurement on
this side.
V 3/4V 1/2
V 10
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
Fixed Roller
Left Right
12
They will remain open until the set point
operation pressure + tolerance is reached.
After this the valves will be closed.
Pressure control
When the hydraulic exceeds the pressure (value)
set point + tolerance the proportional valves will open and the
pressure decrease valves will be opened (energized).
135 bar
125 bar
115 bar
4 m Amp
Characteristics of proportional valves.
100
%
100
%
12 m Amp
0 %
Proportion valve
pressure
increase
20 m Amp
Proportion valve
pressure
decrease
Set point
30 %
30 %
8 m Amp
V 3/4
Next
Press cylinder
Movable Roller
Next
Next
V 11V 11V 10
Pressure control
When the hydraulic gets beneath the pressure (value)
set point โ€“ tolerance the proportional valves will be
opened and the pump will start.
V 3/4V 1/2
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
V 10 V 11
Fixed Roller
Left Right
Press cylinder
Movable Roller
13
This will remain so until set point operation pressure โ€“ tolerance
has been reached.
After this the valves will close again and pump will stopped.
In this example on one side.
135 bar
125 bar
115 bar
Characteristics proportional valves.
100
%
100
%
12 m Amp
0 %
4 m Amp
Proportion valve
pressure
increase
20 m Amp
Proportion valve
pressure
decrease
80 %
80 %
18,4 m Amp
V 3/4
Next
Next
Next
V 11
V 10
A certain deviation is due to non homogenate mixture
of raw materials (coarse, fine, wet, dry).
Gap (l) Gap (r)=
V 3/4V 1/2
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
V 10
Left Right
Fixed Roller
Gap (r)
Gap (l)
Gap(l) Gap(r) =- Gap(diff)
Gap(diff) > Gap(diff)toll.
Correction will be done first on the side with the bigger
gap by pressure increasing.
Correction is permitted until operation pressure + 5 bar.
14
If this value is exceeded the skewing will be corrected.
Gap correction
A deviation in gap width between left and right
in permitted until a preset value.
This will remain so until gap - difference - tolerance
has been reached. Set point 4 mm.
After this the valves will close again and pump will stop.
Presscilinder
Movble
RollerPresscilinder
Movble
RollerPress cylinder
Movable Roller
V 1/2
Next
Next
Next
V 11V 10
V 3/4V 1/2
V 10
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
Movble
Roller
Gap (r)
Right
Fixed Roller
Left
Gap (l)
If skewing is after this correction still not within
tolerance limits, at the side with the smallest gap,
pressure will be released.
15
Gap correction
This will remain so until gap - difference - tolerance
has been reached. Set point 4 mm.
After this the valves will close again.
PresscilinderPress cylinder
Movable Roller
V 3/4
Next
Next
V 11V 11V 10
V 1/2 V 3/4
After this correction pressure control will be reactivated.
If pressure difference between left and right exceeds a
preset maximum ( 30 bar ) an alarm will be generated
and pressure will be released at both sides.
Gap (diff) < Gap (diff)toll. ( 4 mm )
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
V 1/2 V 3/4
Left Right
Fixed Roller
L(r)L(l)
Presscilinder
Movble
Roller
16
Gap correction
and Pressure Control
Press cylinder
Movable Roller
Next
Next
V 11V 11V 10V 10
Next
Current control
By means of to much adjusting of operation pressure or
due to changing material properties
the electrical load of the main drives can become to high.
If this load exceeds a preset maximum the pressure will
be reduced.
V 08
Hydraulic oil tank
Pump HT 1 M 01
V 09 V 07V 06
Left Right
Fixed Roller
17
After this the pressure control will be reactivated.
V 1/2V 1/2 V 3/4V 3/4
This will last until the movable roller reaches
L2 + 10 mm = 45 mm gap
or until the drives get below operation load.
Press cylinder
Movable Roller
Next
V 11V 11V 10V 10
Next
V 10
V 11
RP Group stop
The Pressure decrease valves will open,
the proportional valves will open,
and the emergency valve will open.
Hydraulic oil tank
Pump HT 1 M 01
Left Right
Fix Roller
18
Press cylinder
Movble
Roller
Fixed Roller
Movable Roller
V 08
V 09 V 07V 06
V 1/2V 1/2 V 3/4
V 09
The rollers will due to material pressure move apart
until L2 is reached on both sides or after time limit.
Roller press will stop after 30 sec.
At a stop of the roller press (desired or undesired)
the RP - slide gate will close and
stopped the material feed to the RP.
Next
The Pressure decrease valves will close,
the proportional valves will close,
and the emergency valve will open.
Next
Next
V 11
V 3/4
V 10V 10
Roller press
Dosing Gate
min. Pos.
open
Open
the
Dosing
Gate
Dosing
Gate in
Movable
Roller
Fixed
Roller
19
close
RP - Bin
Slide Gate.
opened
max. Pos.
Dosing
Gate
Last
20

More Related Content

What's hot

Vertical Roller Mill Gearbox Reduction Ratio Calculations
Vertical Roller Mill Gearbox Reduction Ratio CalculationsVertical Roller Mill Gearbox Reduction Ratio Calculations
Vertical Roller Mill Gearbox Reduction Ratio CalculationsSyed Fahad Ahmed
ย 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing processNITIN ASNANI
ย 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operationDin Sokreach
ย 
304372123-4-Kiln-Supports.pdf
304372123-4-Kiln-Supports.pdf304372123-4-Kiln-Supports.pdf
304372123-4-Kiln-Supports.pdfSuad45
ย 
Kiln training
Kiln trainingKiln training
Kiln trainingmkpq pasha
ย 
Best cement-handbook-final-pdf
Best cement-handbook-final-pdfBest cement-handbook-final-pdf
Best cement-handbook-final-pdfmkpq pasha
ย 
Kiln Condition Report (Line1)(March 2015)
Kiln Condition Report (Line1)(March 2015)Kiln Condition Report (Line1)(March 2015)
Kiln Condition Report (Line1)(March 2015)Mohamed Gomaa
ย 
Exemplary report-rotary-kiln-alignment
Exemplary report-rotary-kiln-alignmentExemplary report-rotary-kiln-alignment
Exemplary report-rotary-kiln-alignmentmkpq pasha
ย 
Cement mill notebook
Cement mill notebookCement mill notebook
Cement mill notebookNael Shabana
ย 
Mechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kilnMechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kilnmkpq pasha
ย 
cement-plant-operation-handbook
cement-plant-operation-handbookcement-plant-operation-handbook
cement-plant-operation-handbookVijay Kumar
ย 
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdfRAM PRAKASH PATEL
ย 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Karan Walia
ย 
Bag filter operation pradeep kumar
Bag filter operation  pradeep kumarBag filter operation  pradeep kumar
Bag filter operation pradeep kumarpradeepdeepi
ย 
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptxPROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptxSirajALsharif
ย 
Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2cesar hernandez
ย 

What's hot (20)

Vertical Roller Mill Gearbox Reduction Ratio Calculations
Vertical Roller Mill Gearbox Reduction Ratio CalculationsVertical Roller Mill Gearbox Reduction Ratio Calculations
Vertical Roller Mill Gearbox Reduction Ratio Calculations
ย 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing process
ย 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operation
ย 
304372123-4-Kiln-Supports.pdf
304372123-4-Kiln-Supports.pdf304372123-4-Kiln-Supports.pdf
304372123-4-Kiln-Supports.pdf
ย 
Kiln Migration.pptx
Kiln Migration.pptxKiln Migration.pptx
Kiln Migration.pptx
ย 
Kiln training
Kiln trainingKiln training
Kiln training
ย 
Best cement-handbook-final-pdf
Best cement-handbook-final-pdfBest cement-handbook-final-pdf
Best cement-handbook-final-pdf
ย 
Kiln Condition Report (Line1)(March 2015)
Kiln Condition Report (Line1)(March 2015)Kiln Condition Report (Line1)(March 2015)
Kiln Condition Report (Line1)(March 2015)
ย 
Exemplary report-rotary-kiln-alignment
Exemplary report-rotary-kiln-alignmentExemplary report-rotary-kiln-alignment
Exemplary report-rotary-kiln-alignment
ย 
Ball Mill Optimization
Ball Mill OptimizationBall Mill Optimization
Ball Mill Optimization
ย 
Cement mill notebook
Cement mill notebookCement mill notebook
Cement mill notebook
ย 
Mechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kilnMechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kiln
ย 
Mill setting for Sugar Mills
Mill setting for Sugar MillsMill setting for Sugar Mills
Mill setting for Sugar Mills
ย 
cement-plant-operation-handbook
cement-plant-operation-handbookcement-plant-operation-handbook
cement-plant-operation-handbook
ย 
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf
๐•๐‘๐Œ ๐“๐ซ๐จ๐ฎ๐›๐ฅ๐ž๐ฌ๐ก๐จ๐จ๐ญ๐ข๐ง๐  ๐๐จ๐ญ๐ž๐ฌ.(LOESCHE).pdf
ย 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
ย 
Kiln axis
Kiln axisKiln axis
Kiln axis
ย 
Bag filter operation pradeep kumar
Bag filter operation  pradeep kumarBag filter operation  pradeep kumar
Bag filter operation pradeep kumar
ย 
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptxPROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
ย 
Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2
ย 

Similar to Hydraulic control of the ROLCOX rolls

Kiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfKiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfHamedMostafa10
ย 
EH Oil System.pptx
EH Oil System.pptxEH Oil System.pptx
EH Oil System.pptxssuserb3fedf1
ย 
Renr8305 renr8305 02-sis
Renr8305 renr8305 02-sisRenr8305 renr8305 02-sis
Renr8305 renr8305 02-sisafrodita123
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...ujdfjjsjekfkkem
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...fujsjfskekmm
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...fikskefjsekfsem
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...fjskekxcddmmme
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...fjjskeqwekfksmemm
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...dujjsjfkksekm
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...fjjskmdmem
ย 
017 pressure regulation and control valves
017 pressure regulation and control valves017 pressure regulation and control valves
017 pressure regulation and control valvesRob Holt
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2615002 to 2616002
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2615002 to 2616002Jcb 3 cx t2  t3 backhoe loader service repair manual from 2615002 to 2616002
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2615002 to 2616002fikskekdmdm
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000fiskkdmmd
ย 
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdfJCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdfifkksem9didok
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2674101 to 2675100
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2674101 to 2675100Jcb 3 cx t2  t3 backhoe loader service repair manual from 2674101 to 2675100
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2674101 to 2675100fikskekdmdm
ย 
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdfJCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdff8soekmdmdm
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000fikkskemdmd
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000fiskkdmmd
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000fikkskemdmd
ย 

Similar to Hydraulic control of the ROLCOX rolls (20)

Kiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfKiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdf
ย 
EH Oil System.pptx
EH Oil System.pptxEH Oil System.pptx
EH Oil System.pptx
ย 
Renr8305 renr8305 02-sis
Renr8305 renr8305 02-sisRenr8305 renr8305 02-sis
Renr8305 renr8305 02-sis
ย 
960649.pdf
960649.pdf960649.pdf
960649.pdf
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
Jcb tm320 tier 4i telescopic wheeled loader service repair manual (from 20908...
ย 
017 pressure regulation and control valves
017 pressure regulation and control valves017 pressure regulation and control valves
017 pressure regulation and control valves
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2615002 to 2616002
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2615002 to 2616002Jcb 3 cx t2  t3 backhoe loader service repair manual from 2615002 to 2616002
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2615002 to 2616002
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
ย 
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdfJCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2674101 to 2675100
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2674101 to 2675100Jcb 3 cx t2  t3 backhoe loader service repair manual from 2674101 to 2675100
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2674101 to 2675100
ย 
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdfJCB 3CX T2  T3 Backhoe Loader Service Repair Manual Instant Download.pdf
JCB 3CX T2 T3 Backhoe Loader Service Repair Manual Instant Download.pdf
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000Jcb 3 cx t2  t3 backhoe loader service repair manual from 2419861 to 2420000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 2419861 to 2420000
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
ย 
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000Jcb 3 cx t2  t3 backhoe loader service repair manual from 1918307 to 1920000
Jcb 3 cx t2 t3 backhoe loader service repair manual from 1918307 to 1920000
ย 

Recently uploaded

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
ย 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
ย 
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ Abridged
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ AbridgedLean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ Abridged
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ AbridgedKaiNexus
ย 
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCRsoniya singh
ย 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
ย 
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...lizamodels9
ย 
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCRsoniya singh
ย 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
ย 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
ย 
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...lizamodels9
ย 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
ย 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...lizamodels9
ย 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
ย 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxgeorgebrinton95
ย 
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756dollysharma2066
ย 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
ย 
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,noida100girls
ย 
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...lizamodels9
ย 

Recently uploaded (20)

Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
ย 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
ย 
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ Abridged
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ AbridgedLean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ Abridged
Lean: From Theory to Practice โ€” One Cityโ€™s (and Libraryโ€™s) Lean Storyโ€ฆ Abridged
ย 
Enjoy โžฅ8448380779โ–ป Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy โžฅ8448380779โ–ป Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy โžฅ8448380779โ–ป Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy โžฅ8448380779โ–ป Call Girls In Sector 18 Noida Escorts Delhi NCR
ย 
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Hauz Khas ๐Ÿ” Delhi NCR
ย 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
ย 
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad โžฅ9990211544 Independent Best Escorts In...
ย 
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR
(8264348440) ๐Ÿ” Call Girls In Mahipalpur ๐Ÿ” Delhi NCR
ย 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
ย 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
ย 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
ย 
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida โค๏ธ8860477959 Escorts 100% Genuine Servi...
ย 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
ย 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar โค๏ธ8860477959 Escorts...
ย 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
ย 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
ย 
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756
Call Girls In โ‡›โ‡›Chhatarpurโ‡šโ‡š. Brings Offer Delhi Contact Us 8377877756
ย 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
ย 
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL โœจ 9773824855 โœจ Escorts Service In Delhi Ncr,
ย 
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon โค๏ธ8860477959_Russian 100% Genuine Escorts I...
ย 

Hydraulic control of the ROLCOX rolls

  • 1. Hydraulic control ROLCOX of the rolls 1 Fixed Roller Movable Roller Left Right Hydraulic oil tank Pump HT 1 M 01 Next
  • 2. HT 1 V 3/4 Prop. valve right HT 1 V 1/2 Prop. valve left HT 1 V 09 Emergency valve HT 1 V 10 Pressure decrease valve left ( one way valve ) HT 1 V 11 Pressure decrease valve right ( one way valve ) HT 1 V 08 Retraction cylinder valve HT 1 M 01 Hydraulic pump HT 1 V 07 Bypass valve right HT 1 V 06 Bypass valve left Left Right Retraction cylinder Fixed Roller Retraction cylinder Hydraulic oil tank Movable Roller Press cylinder V 09 V 08 Pump HT 1 M 01 V 07V 06 V 10 V 11 2 Next Next Next Next Next Next Next Next Next V 1/2 V 3/4
  • 3. + Bearing dist. = 0 mm RP - Frame Gap sensor Limit switch Press cylinder Fixed Bearing 3 Roller dist. = 10 mm fix Gap = 10 mm Movable Bearing Next Retraction cylinder NextNextNextNext measured by Distance block
  • 4. This is the point where the bearing distance is 0. For the gap measuring this point is 4 m Amp. The bearing blocks are fixed in a way that the rollers can never touch each other physically Fixed Roller Movable Roller Left Right Distance pieces Movble Roller Fixed Roller Left Right Distance between the bearings used as lower limit for the pressure control. If distance is less pressure control will be deactivated. Roller distance 10mm = Gap 10 mm Roller distance 10 mm + Bearing dist. 15 mm = Gap 25 mm Gap = 10 mm Set points 4 0 mm ( Bearing distance )L 0mm GAP > L min Pressure control ON normal operation L min 15 mm ( Bearing distance ) Next Movable Roller Next Next Next GAP < L min Pressure control OFF Next Gap = 25 mm
  • 5. L min Movable Roller Fixed RollerLeft Right Gap = 35 mm Movable Fixed RollerLeft Right Gap = 45 mm L2 Parameter set in the PLC. Set only once. Range from 5.0 to 30.0 mm Actual set point 25 mm ( Set point for material feeding ) Roller distance 10 mm Set points L min + L2 + 10 Bearing dist. 35 mm 5 Next = Gap 35 mm + L2 Bearing dist. 25 mm Next L2 + 10 mm Until this value the rollers are pushed back during start up the main motors. = Gap 45 mm Roller distance 10 mm Next Next
  • 6. Movable Roller Fixed RollerLeft Right Gap = 65 mm maximum Roller distance 10 mm + Bearing dist. > 55 mm = Gap > 65 mm Limit switch Maximum distance allowed between the bearings. ( 65 mm Gap ) Determined by a mechanical switch. Over 65 mm gap the roller press will stop with max. gap alarm. Set points 6 Normal operation Movable Roller Next Next Ok. L2 L min + 10 mm Movable Roller Movable Roller
  • 7. Movble Roller V 09 V 08 Hydraulic oil tank Pump HT 1 M 01 Press cylinder After reaching of L2 + 10 mm, the main drives will be started one by one. 7 Start RP group At every start the emergency valve is energized to close the hydraulic circuit. The movable roller will be moved by the retraction cylinders to L2 + 10 mm = 45 mm To release the oil of the main cylinders the bypass valves and the pressure decrease valves are energized (opened). This will occur with standing rollers. Next V 06V 06 V 07V 07 Next NextNext Next V 09 Movable Roller Left Fixed Roller Right Gap = 45 mm Next Next L min L2 + 10 mm V 11 V 3/4 V 10 V 1/2 V 10 V 06V 06 V 07V 07 V 3/4V 1/2 V 07V 07V 07V 07V 06V 06V 06V 06 V 11 Valve closed Valve open
  • 8. Next V 08 Start RP group Retraction cylinders are drawn back by springs. After L2 will be reached in pre bin the shut off Gate will be opened to release material flow to the rollers. 8 Next L2 Gap = 35 mm In case if during moving back the movable roller an oil pressure is measured of more than 40 bar ( normal < 40 bar ), the start will be interrupted by an alarm signal. Fault has to be acknowledged at the roller press after checking. Possible causes: Material between the rollers. Disturbance in the hydraulic circuit. Roller can not move free. After bearing distance is on both sides L2 the roller press group will be released and feeding of the pre bin can be started. Next Next Movble Roller V 09 Hydraulic oil tank Pump HT 1 M 01 Press cylinder V 06V 06 V 07V 07V 09 Movable Roller Left Fixed Roller Right Gap = 45 mm V 10 V 3/4V 1/2 V 07V 07V 07V 07V 06V 06V 06V 06 V 11 After this the movable roller will be pushed back to L2 by the main cylinders from 45 mm to 35 mm. This happens with running rollers. V 08 Next V 06V 06 V 07V 07 V 11V 10 V 1/2 V 3/4V 1/2 V 3/4 Gap = 35 mm Pump stops and valves will be closed.
  • 9. V 3/4V 1/2 V 3/4V 1/2 V 09 V 08 V 07V 06 Press cylinder Left RightFixed Roller The proportional valves will increase pressure to the main cylinders up until the set point. Hydraulic pump start. 9 Hydraulic oil tank Pump HT 1 M 01 Next Start Pressure control After the start program is ready the pressure control will start automatically. After opening of the shut off gate there will get material between the rollers. Next Movable Roller Next V 11V 10
  • 10. Pressure control By the intake behaviour of the running rollers combined with the pressure of the column ( gap ) of material on the rollers the material flow will tend to press the rollers apart. Hydraulic oil tank V 3/4V 1/2 V 08 Pump HT 1 M 01 V 09 V 07V 06 Left Right Press cylinder Movable Roller Fixed Roller When the hydraulic reaches the value set point-tolerance the proportional valves will be closed and the pump will stop. 10 Pres.Set point At this value the material counter pressure and the cylinder pressure will be on balance. - 10 bar + 10 bar V 1/2 V 3/4 Next Next V 11V 10
  • 11. Accumulator Gas ( N2 ) Pressure = 90 bar100 bar 135 bar 125 bar 115 bar Set point 125 bar Hydraulic oil tank V 3/4V 1/2 V 08 Pump HT 1 M 01 V 09 V 07V 06 Left Right Fixed Roller Press cylinder Movable Roller 90 bar Start up < 90 bar Pressure control Pressure variations with in tolerance will be compensated by the N2 accumulators. 11 V 1/2 V 3/4 100 bar Next 125 bar Next V 11V 10
  • 12. Note: This can happen at both sides at the same time but also on one of both sides, depending of pressure measurement on this side. V 3/4V 1/2 V 10 V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 Fixed Roller Left Right 12 They will remain open until the set point operation pressure + tolerance is reached. After this the valves will be closed. Pressure control When the hydraulic exceeds the pressure (value) set point + tolerance the proportional valves will open and the pressure decrease valves will be opened (energized). 135 bar 125 bar 115 bar 4 m Amp Characteristics of proportional valves. 100 % 100 % 12 m Amp 0 % Proportion valve pressure increase 20 m Amp Proportion valve pressure decrease Set point 30 % 30 % 8 m Amp V 3/4 Next Press cylinder Movable Roller Next Next V 11V 11V 10
  • 13. Pressure control When the hydraulic gets beneath the pressure (value) set point โ€“ tolerance the proportional valves will be opened and the pump will start. V 3/4V 1/2 V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 V 10 V 11 Fixed Roller Left Right Press cylinder Movable Roller 13 This will remain so until set point operation pressure โ€“ tolerance has been reached. After this the valves will close again and pump will stopped. In this example on one side. 135 bar 125 bar 115 bar Characteristics proportional valves. 100 % 100 % 12 m Amp 0 % 4 m Amp Proportion valve pressure increase 20 m Amp Proportion valve pressure decrease 80 % 80 % 18,4 m Amp V 3/4 Next Next Next V 11 V 10
  • 14. A certain deviation is due to non homogenate mixture of raw materials (coarse, fine, wet, dry). Gap (l) Gap (r)= V 3/4V 1/2 V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 V 10 Left Right Fixed Roller Gap (r) Gap (l) Gap(l) Gap(r) =- Gap(diff) Gap(diff) > Gap(diff)toll. Correction will be done first on the side with the bigger gap by pressure increasing. Correction is permitted until operation pressure + 5 bar. 14 If this value is exceeded the skewing will be corrected. Gap correction A deviation in gap width between left and right in permitted until a preset value. This will remain so until gap - difference - tolerance has been reached. Set point 4 mm. After this the valves will close again and pump will stop. Presscilinder Movble RollerPresscilinder Movble RollerPress cylinder Movable Roller V 1/2 Next Next Next V 11V 10
  • 15. V 3/4V 1/2 V 10 V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 Movble Roller Gap (r) Right Fixed Roller Left Gap (l) If skewing is after this correction still not within tolerance limits, at the side with the smallest gap, pressure will be released. 15 Gap correction This will remain so until gap - difference - tolerance has been reached. Set point 4 mm. After this the valves will close again. PresscilinderPress cylinder Movable Roller V 3/4 Next Next V 11V 11V 10
  • 16. V 1/2 V 3/4 After this correction pressure control will be reactivated. If pressure difference between left and right exceeds a preset maximum ( 30 bar ) an alarm will be generated and pressure will be released at both sides. Gap (diff) < Gap (diff)toll. ( 4 mm ) V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 V 1/2 V 3/4 Left Right Fixed Roller L(r)L(l) Presscilinder Movble Roller 16 Gap correction and Pressure Control Press cylinder Movable Roller Next Next V 11V 11V 10V 10 Next
  • 17. Current control By means of to much adjusting of operation pressure or due to changing material properties the electrical load of the main drives can become to high. If this load exceeds a preset maximum the pressure will be reduced. V 08 Hydraulic oil tank Pump HT 1 M 01 V 09 V 07V 06 Left Right Fixed Roller 17 After this the pressure control will be reactivated. V 1/2V 1/2 V 3/4V 3/4 This will last until the movable roller reaches L2 + 10 mm = 45 mm gap or until the drives get below operation load. Press cylinder Movable Roller Next V 11V 11V 10V 10 Next
  • 18. V 10 V 11 RP Group stop The Pressure decrease valves will open, the proportional valves will open, and the emergency valve will open. Hydraulic oil tank Pump HT 1 M 01 Left Right Fix Roller 18 Press cylinder Movble Roller Fixed Roller Movable Roller V 08 V 09 V 07V 06 V 1/2V 1/2 V 3/4 V 09 The rollers will due to material pressure move apart until L2 is reached on both sides or after time limit. Roller press will stop after 30 sec. At a stop of the roller press (desired or undesired) the RP - slide gate will close and stopped the material feed to the RP. Next The Pressure decrease valves will close, the proportional valves will close, and the emergency valve will open. Next Next V 11 V 3/4 V 10V 10
  • 19. Roller press Dosing Gate min. Pos. open Open the Dosing Gate Dosing Gate in Movable Roller Fixed Roller 19 close RP - Bin Slide Gate. opened max. Pos. Dosing Gate Last
  • 20. 20