Outages are significant events in any plant. It is generally the only
event that can simultaneously increase revenue and decrease cost.
6. 908 770 4955
www.theoutageexpert.com
Outage, planning and execution
are significantly different than
normal plant operations and as
such need different mind sets,
methods and practices to be
successful. Outage Planning and
Execution is it’s own sweet
science
12. 908 770 4955
www.theoutageexpert.com
OWNERS AGENT
TOE will manage all of the
steps of the outage and
report back to PPMS about
the outage readiness of
each plant at each step
13. 908 770 4955
www.theoutageexpert.com
Fill in for Plant Management
•Plant Managers
•Operation Managers
•Maintenance
Managers
Outage Development
•Downtime analysis
•Heat rate analysis
•Generation analysis
•Potential component failure analysis
•Financial Projection
•Cash flows
Engineering
•Work scopes/ RFP’s
•Material specifications
•Code requirements
Planning
• Scheduling
• Spare parts
identification and
ordering
• Material
identification and
ordering
• Outage set up
• Contract selection
Project Management
• Critical path
• Outage Management
15. 908 770 4955
www.theoutageexpert.com
TOE will guarantee the
“Open and Close” as well as
“known work” of the outage
from a dollar and schedule
perspective
• Note: every outage has an
adjustment to money and
schedule after all the
discovery work is completed
which will need to be
mutually agreed upon
during the outage
TOE will guarantee the unit
comes up and stays up
• Note: the unit will not come
down once released from
the outage for anything
outage related for 18 month
post outage
TOE will guarantee
performance of the unit
• Note: we will need to
handle each unit’s
performance individually
TURNKEY OUTAGES
16.
17. Frontera Fall 2014
•We helped the plant develop plan and
schedule two days into the outage the
Maintenance Manager quit and we
assumed control of the entire outage
•The outage came in on time and the
units performance was the best in
history
Fibrominn Spring 2015
•We helped the plant develop plan and
schedule two days into the outage the
Maintenance Manager quit and we
assumed control of the entire outage
•The outage came in on time and the
units performance was the best in
history
Parkchester burners Winter
2014
•We were able to get the burners to
comply with new RACT Emissions
standards while still burning #6 oil by
burner modifications. By being able to
do this the facility was able to comply
while avoiding spending anywhere
between 1 and 10 million dollars extra
Detroit Turbine outage Winter
2013
•Unit produces 13% more Megawatts on
the same steam flow a net result of
approx. $1.5 million in a plant that has
an EBITA of $10 million
Detroit controls upgrade
Winter 2013
•With the new controls in place we were
able to test different operating
modalities and identified a different
valve line up that yielded a 1% to 2%
increase in Megawatt increase that nets
the plant approx. $400,000 against an
EBITA of $10,000,000
Detroit Black plant Fall 2012
•Planned and executed a black plant in 3
months. Executed 184 distinct tasks in
just 132 hours
Berkshire Fall Outage 2012
•Lowed Heat rate significantly unit
availability went from 30% to 90%
Detroit Boiler 12 outage
Summer 2012
•Saved $300,000 on a budgeted
$3,200,000 one week early
Berkshire Spring Outage 2012
•Saved $880,000 on a budgeted
$2,000,000 3 days early
Detroit Boiler 13 outage Fall
2011
•Saved $500,000 on a budgeted
$3,700,000 two weeks early