2. Dr. Haitham El Sharnouby
Bill Of Quantities Item
No.
Item Description Unit Qty.
Unit
Price
Total Price
C000 Reinforced Concrete Works
C010
Supply and Pouring Reinforced
Concrete for Columns m3 80 3501.44 280115.34
C020
Supply and Pouring Reinforced
Concrete for Combined Slabs &
Beams m3 20 3768.03 75360.55
D000 Brick Works
D010
Supply and Erect Masonry for
Internal Partitions m2 150 78.95 11842.85
D020
Supply and Erect Masonry for
External Walls m3 50 668.50 33424.87
E000 Ceramic Works
E010
Supply and Erect Ceramic for
Floors m2 20 161.45 3228.93
E020
Supply and Erect Ceramic for
Walls m2 60 169.01 10140.75
F000 Plastering Works
F010
Supply and Apply Internal Plaster
Works m2 390 47.58 18556.11
Grand Total of BOQ 432669.4
3. Dr. Haitham El Sharnouby
Bill Of Quantities Item
No.
Item Description Unit Qty.
Unit
Price
Total Price
C000 Reinforced Concrete Works
C010
Supply and Pouring Reinforced
Concrete for Columns m3 80 3501.44 280115.34
C020
Supply and Pouring Reinforced
Concrete for Combined Slabs &
Beams m3 20 3768.03 75360.55
D000 Brick Works
D010
Supply and Erect Masonry for
Internal Partitions m2 150 78.95 11842.85
D020
Supply and Erect Masonry for
External Walls m3 50 668.50 33424.87
E000 Ceramic Works
E010
Supply and Erect Ceramic for
Floors m2 20 161.45 3228.93
E020
Supply and Erect Ceramic for
Walls m2 60 169.01 10140.75
F000 Plastering Works
F010
Supply and Apply Internal Plaster
Works m2 390 47.58 18556.11
Grand Total of BOQ 432669.4
4. Dr. Haitham El Sharnouby
Price Breakdown
Item
No.
Item Description Unit Qty. D. Cost Total D. C.
Mark
Up Pct.
Unit
Price
Total Price
C000 Reinforced Concrete Works
C010
Supply and Pouring Reinforced
Concrete for Columns m3 80 2812.40 224992.24 1.25 3501.44 280115.34
C020
Supply and Pouring Reinforced
Concrete for Combined Slabs &
Beams m3 20 3026.53 60530.56 1.25 3768.03 75360.55
D000 Brick Works
D010
Supply and Erect Masonry for
Internal Partitions m2 150 63.42 9512.33 1.25 78.95 11842.85
D020
Supply and Erect Masonry for
External Walls m3 50 536.95 26847.28 1.25 668.50 33424.87
E000 Ceramic Works
E010
Supply and Erect Ceramic for
Floors m2 20 129.68 2593.52 1.25 161.45 3228.93
E020
Supply and Erect Ceramic for
Walls m2 60 135.75 8145.18 1.25 169.01 10140.75
F000 Plastering Works
F010
Supply and Apply Internal Plaster
Works m2 390 38.22 14904.50 1.25 47.58 18556.11
Grand Total of BOQ 347526 432669.4
5. Dr. Haitham El Sharnouby
Res. Dictionary
ID Description Unit Price Notes
M Gravel m3 80
M Sand m3 40
M Cement ton 1420
M Water m3 1
M Rein. Steel ton 14000
M Brick 1000 600
M Floor Ceramic Tiles m2 90
M Wall Ceramic Tiles m2 80
M White Mortar Filling / m2 m2 3
M Lime m3 35
L R. C. Pouring Crew day 1200
L Steel Fixer day 180
L Steel Fixer Ass. day 120
L Steel O. Labor day 90
L Formwork Carpentry day 180
L Formwork Carpentry Ass. day 120
L Brick Laying Lab. day 180
L Brick Laying Ass. day 120
L Brick Laying O. Lab. day 90
L Ceramic Fixer day 180
L Ceramic F. Ass. day 120
L Plasterer day 180
L Plasterer Helper day 120
Q Mixer & Vibrator m3 25
Q Fuel & Electric m3 15
Q Small Tools / m3 RC m3 7
Q Formwork Timber m3 80
Q Scaffolding / m2 m2 1
Q Scaffolding / m3 m3 6
Q Small Tools / m2 Brick m2 1
Q Small Tools / m3 Brick m3 5
Q Ceramic Fixing Equipment m2 5
Q Plastering Equipment m2 2
6. Dr. Haitham El Sharnouby
Direct Cost Estimate كل3مساعد ومعهم حدادبن
أيام تسعة يحتاجون وعامل
ليثبتوا10وهذا حديد طن
قسمة حاصل10كمية على
م في الحديد3
كل4مساعدي وثالثة نجارينن
عمل أيام عشرة يحتاجون
لصب نجارة ليثبتوا40متر
خرسانة مكعب
C010
Supply and Pouring Reinforced
Concrete for Columns
m3 80 Res.
Category
Resource Description Amount Price Rate Losses
Pct. /
Multi.
Direct
Cost
C010 M Gravel 0.800 80 1 1.12 1 71.68
C010 M Sand 0.400 40 1 1.12 1 17.92
C010 M Cement 0.400 1420 1 1.07 1 607.76
C010 M Water 0.150 1 1 1.12 1 0.17
C010 M Rein. Steel 0.105 14000 1 1.1 1 1617.00
Direct Cost of Material 2314.53
C010 L R. C. Pouring Crew 1 1200 40 1 1 30.00
C010 L Steel Fixer 3 180 95.2381 1 9 51.03
C010 L Steel Fixer Ass. 1 120 95.2381 1 9 11.34
C010 L Steel O. Labor 1 90 95.2381 1 9 8.51
C010 (El Bakkary p. 243) L Formwork Carpentry 4 180 40 1 10 180.00
C010 (El Bakkary p. 243) L Formwork Carpentry Ass. 3 120 40 1 10 90.00
Direct Cost of Labor 370.88
C010 Q Mixer & Vibrator 1 25 1 1 1 25.00
C010 Q Fuel & Electric 1 15 1 1 1 15.00
C010 Q Small Tools / m3 RC 1 7 1 1 1 7.00
C010 Q Formwork Timber 1 80 1 1 1 80.00
Direct Cost of Equipment 127.00
Total Direct Cost for Each Item Unit 2812.40