#20. C. W.#42. Tec Rep.For. Technos
- 1. TEC INDUSTRY PROGRESS REPORT FOR ORESUNDSVERKET PROJECT Friday.October.19. 2007 / C.W. # 42
TECHNOS P.O. 151947-23942-11.May.2007 Rotec I.O. 27064-25.May.2007
CONTRACT TIME START TIME STOP TIME 1400 TWIN CTCS
FLOW-SHEET FOR A TWIN 1400 C.T.C.S.
No
25 May 2007 30.September.07 %
ROTEC
COMPLETE CONDENSER TUBE CLEANING SYSTEM No of Days =
1 SOFT -WORK PREPARATION: 14 cw # 22 cw # 23 100
FABRICATION PLANNING 100
WELDING BOOK TECHNOS CONFIRMATION cw # 25 100 Friday,06.22.07
QUALITY CONTROL PLAN 100
3.1.B CERTIFICATES FOR SHELLS RAW-MATERIAL cw # 22 cw # 26 100 Friday,06.29.07
3.1.B CERTIFICATES FOR FLANGES RAW-MATERIAL cw # 22 cw # 26 100 Friday,06.29.07
Rubber linning data sheet from Anticorosiv cw # 25 100 Friday,06.22.07
Painting specification from Technos to Rotec 100
ND1400 ND1400
2 HARD -WORK PERFORMANCE: 60 20.06.2007 28.08.2007
TWIN N.D. 1400MM BALL-STRAINERS(SHELLS IN CARBON-STEEL) % %
I SHELLS FABRICATION: 20.06.2007 28.08.2007 100 100
SHELL CUTTING-OFF TO SIZE cw # 25 cw # 27 100 100
SHELLS PREPARATION: ROLLING cw # 27 100 100
SHELLS LONGITUDINAL TACK-WELD 100 100
SHELLS LONGITUDINAL CONTINUOUS-WELD 100 100
SHELLS CALIBRATION 100 100
SHELLS N.D.T. BY 10% X-RAY EXAMINATION 100 100 Acc. to the last Report
FLANGES FABRICATION : 100 100
FLANGE-SEGMENTS CUTTING-OFF cw # 25 cw # 27 100 100
FLANGE-SEGMENTS-MACHINING 100 100
FLANGE-SEGMENTS-WELDING 100 100
FLANGES-FLATTENING + STRESS RELEAVING 100 100
FLANGES N.D.T. BY U. S. -EXAMINATION 100 100 Acc. to the last Report
3 SHELLS + FLANGES: TACK + COMPLETE-WELDING,STRESS RELEAVING 100 100
FLANGES TACK-WELDED ON SHELLS 100 100
FLANGES COMPLETELY WELDED ON SHELLS 100 100
OVERALL STRESS RELEAVING 100 100
4 C.N.C. -1 -FOR FLANGES + SHELLS: 100 100
C.N.C. -1 -FOR FLANGE HOLES : MARKING, INDEXING, DRILLING, 100 100
-FOR SHELL -HOLLES : MARKING, DRILLING , BORING 100 100
5 MACHINING EXTERNALS + INTERNALS 100 100
WELDING EXTERNALS + INTERNALS 100 100
6 C.N.C. -2 - FOR BOSSES -REAMING cw # 30 cw # 31 100 100
WELDS CORRECTIONS + .Q.C. BY D.P.-N.D.T 100 100
TECHNOS' S. S. FREE ISSUED ITEMS AT 30 DAYS AFTER P. O. MGS-S.S. F.I.I. June 21 2007 cw # 27 100 100 Departure from France
7 HYDROTEST 100 100 Mo.9/10/2007
INTERNAL BLASTING 100 100
8 RUBBER-LINNING + RUBBER-TEST IN ANTICOROSIV 3mm 100 100 Rubber Test
EXTERNAL BLASTING 100 100 Fri.9/28/2007.cw39
9 OUTSIDE PAINTING 100 100 Primer-coat only
TECHNOS' FREE ISSUED ITEMS AT 45 DAYS BEFORE F. INSP. Grids + Vortex June 30 2007 cw # 32 100 100 Departure from France
10 ASSEMBLING INTERNALS + EXTERNALS: S.S.GRIDS+VORTEX, S.S.PIPES 100 100 C.W. # 41
II RECIRCULATION UNIT FABRICATION:
BASE-PLATE CUTTING-OFF: STEEL-SHEET + PROFILES 100
LIFTING-LUGS MACHINING + WELDING 100
BASE-PLATE BLASTING 100
BASE-PLATE PAINTING Rotec request for 100 Technos accept for black-colour
III BALL-COLLECTOR FABRICATION: 100
BALL-COLLECTOR CUTTING-OFF N.D.250 mm 100
BALL-COLLECTOR MACHINING 100
BALL-COLLECTOR TACK, COMPLETE WELDING 100
BALL-COLLECTOR X-RAY N.D.T.EXAM 100
BALL-COLLECTOR HYDROTEST INTERNAL BLASTING 100 Mo.9/10/2007
BALL-COLLECTOR INTERNAL RUBBER LINNING 3mm 100 Rubber Test
BALL-COLLECTOR EXTERNAL PAINTING 100 Fri.9/28/2007.cw39
BALL-COLLECTOR ASSEMBLING 100
RECIRCULATION UNIT ASSEMBLING WITH BALL-COLLECTOR + F. I. I. 100 C.W. # 41
IV BALL-DISTRIBUTOR FABRICATION: 100
BALL-DISTRIBUTOR CUTTING-OFF, MACHINING, WELDING 100
BALL-DISTRIBUTOR HYDROSTATIC TEST, BLASTING ( 1-4"+ 2-3" ) 100 Mo.9/10/2007
BALL-DISTRIBUTOR INTERNAL RUBBER-LINNING 3mm 100 Rubber Test
BALL-DISTRIBUTOR EXTERNAL BLASTING, PAINTING 100 Fri.9/28/2007.cw39
V BALL-INJECTORS PREPARATION: 100
BALL-INJECTORS : WELDING S.S. FLANGES ON S.S. TUBES 100
GENERAL ASSEMBLING FOR F. R. T. 100
FACTORY RUNNING TEST - HOLD POINT IN Q. C. P. Alain Monseur October.15.2007 October.19.2007 Client Inspection Th10/18/2007.cw42
FINAL WORKSHOP INSPECTION -END OF MANUFACTURING REPORT 100
PACKING, MARKING, LABELLING 50
EX-WORKS -DELIVERY -PLANNED DATE 0 Tuesday,Oct.23.2007,c.w.#43
F. CA. DELIVERY 0
TEC ASSISTANCE IN ROTEC :