UET Peshawar Campus III Bannu4/17/2020 1
UET Peshawar Campus III Bannu4/17/2020 2
Final Year Project
Design of Sewerage System For Bannu Campus
UET Peshawar Campus III Bannu4/17/2020 3
Group Members
Irfanullah 0770
Shoukat Ullah 0763
M.Fawad Khan 0732
Supervised By:
Dr. Afed Ullah Khan
Department of Civil Engineering UET Peshawar BANNU Campus
UET Peshawar Campus III Bannu4/17/2020 4
Contents
• Introduction
• Design requirement
• Calculation of sanitary sewage
• Calculation of storm runoff
• Design of combined sewer
• Calculation of dia of sewer
UET Peshawar Campus III Bannu4/17/2020 5
Introduction
UET Peshawar Campus III Bannu4/17/2020 6
Sanitary Sewage
The sewage which originates of dwellings, industrial facilities, commercials
and institutions.
source-shutterstock.com
UET Peshawar Campus III Bannu4/17/2020 7
Storm Runoff
Storm sewage or storm water is the flow derived from rainfall events and introduced into
sewers intended for its conveyance.
Source -researchgate.net
UET Peshawar Campus III Bannu4/17/2020 8
Partial Combined Sewer
The sewer are designed as sanitary sewer but sufficient excess capacity
are provided to carry a part of storm discharge also. In this type
domestic sewage and storm water of buildings are carried out in one
set.
Source- WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 9
Design Requirements
UET Peshawar Campus III Bannu4/17/2020 10
Papulation forecast
Description Population
Present 700
Future 800
Total 1500
UET Peshawar Campus III Bannu4/17/2020 11
Peak Factor
Ratio of the maximum flow to the average flow, denoted as PF, is
observed to be dependent on contributory population.
s
UET Peshawar Campus III Bannu4/17/2020 12
Average Sewage Flow(m3 /day) Peak Factor
≤ 2500 4.0
2500 – 5000 3.4
5000 – 10000 3.1
10000 – 25000 2.7
25000 – 50000 2.5
50000 – 100000 2.3
100000 – 250000 2.15
250000 – 500000 2.08
> 500000 2.0
Peak Factor
Source-WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 13
Minimum Sewer Size
225 mm is taken as the minimum sewer size. The reason being that, the
choking does not take place even with the bigger size particles, which
are usually thrown into the sewers through manholes.
Source-WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 14
Minimum Cover Of Sewer
1 m is taken as the minimum cover over the sewers to avoid damage
from live loads coming on the sewer.
Minimum cover
Source- WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 15
Direction of Sewer Line
In choosing the alignment of a sewerage system, the following factors
shall also be considered,
•Sewer should flow, as for as possible the Natural Slope.
•The objectives to serve all existing and future land development.
•Site constraints.
•Proximity of trees and other vegetation.
•The hydraulic performance.
•Social and economic impact.
UET Peshawar Campus III Bannu4/17/2020 16
Slope Of Sewer Line
Sewer dia (mm) Minimum
slope(percent)
Maximum
slope(percent)
150 1.0 33.0
200 0.40 22.0
250 0.28 15.0
300 0.22 11.0
375 0.15 8.3
400 0.14 7.8
450 0.12 6.5
525 0.10 5.1
600 0.08 4.2
Source-Sewerage manual with Eurocodes
UET Peshawar Campus III Bannu4/17/2020 17
Trenching
• The width of the trench shall be ample to allow the pipe to be laid
and jointed properly and to allow the backfill to be placed and
compacted as needed. The trench sides shall be kept as nearly
vertical as possible. When wider trenches are dug, appropriate
bedding class and pipe strength shall be used.
• Ledge rock, boulders, and large stones shall be removed to provide a
minimum clearance of 100 mm below and on each side of all pipe
and joints.
UET Peshawar Campus III Bannu4/17/2020 18
Invert Level
The lowest inside level at any cross-section of a sewer pipe is known as
Invert Level at that Cross-section.
Invert Level = NGSL/Road Level – Depth of Sewer – Thickness of
Sewer – Dia. of Sewer.
Source-WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 19
The proper maintenance and operation of the sewerage system is
essential if the systems are to achieve their designed objectives.
Maintenance Objectives
•To monitor the capacity of the system and to restore the flow capacity.
•To monitor and maintain the structural integrity of the system.
•To prevent excessive infiltration and inflow.
Maintenance Of Sewerage Systems
UET Peshawar Campus III Bannu4/17/2020 20
Manhole
Source- WASA Lahore
Manhole is made or precast manhole is installed for
• Cleaning and
• inspection
At place where change occur
• In sewer direction
• Diameter and
• Slope.
UET Peshawar Campus III Bannu4/17/2020 21
Manhole
Manhole inside Dia
(mm)
45° Deflection
Max size of pipe (mm)
90° Deflection
Max size of pipe (mm)
1220 610 460
1525 915 690
1830 1070 760
UET Peshawar Campus III Bannu4/17/2020 22
Spacing Of Manhole
Sewer size Spacing not more than
225mm to 380mm 100 m
460mm to 760mm 120 m
Greater than 760mm 150 m
Spacing
Source- WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 23
Calculations
UET Peshawar Campus III Bannu4/17/2020 24
Calculation Of Sanitary Sewage
UET Peshawar Campus III Bannu4/17/2020 25
Calculation Of Storm Runoff
UET Peshawar Campus III Bannu4/17/2020 26
Total Sewage Flow
Total sewage = storm runoff + sanitary sewage
Total sewage = 1824 + 1824 = 3648 m3/day
UET Peshawar Campus III Bannu4/17/2020 27
Calculation of Dia Of Sewer
UET Peshawar Campus III Bannu4/17/2020 28
Slope Of Sewer Line
UET Peshawar Campus III Bannu4/17/2020 29
References
• Sewerage manual with Eurocodes “Drainage Service Department” Govt
of Hong Kong Special Administrative Region
• “Water Supply and Sewerage” by E.W Steel and Terenge J. Mcghee
• WASA Lahore
UET Peshawar Campus III Bannu4/17/2020 30

More Related Content

What's hot

Estimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemsEstimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemssidrarashiddar
 
Sewer appurtenances [recovered]
Sewer appurtenances [recovered]Sewer appurtenances [recovered]
Sewer appurtenances [recovered]Rajdip Bhdaraka
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeRajdip Bhdaraka
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationVijay Kumar
 
04 pipeline-channel hydraulics
04 pipeline-channel hydraulics04 pipeline-channel hydraulics
04 pipeline-channel hydraulicsAkepati S. Reddy
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.pptPRACHI DESSAI
 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysisAna Debbarma
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn designManoj Mota
 
Wasa guidelines for design of water and wastewater systems
Wasa   guidelines for design of water and wastewater systemsWasa   guidelines for design of water and wastewater systems
Wasa guidelines for design of water and wastewater systemsJeffrey James
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demandGARRE RAVI KUMAR
 
Cve471 lecture notes 4 spillways
Cve471 lecture notes 4   spillwaysCve471 lecture notes 4   spillways
Cve471 lecture notes 4 spillwayssaibabu48
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage systemManoj Mota
 
Simulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanetSimulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanetRiki Rahmadhan KS
 
Design of sewage treatment plant
Design of sewage treatment plantDesign of sewage treatment plant
Design of sewage treatment plantGARRE RAVI KUMAR
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxPRACHI DESSAI
 
Design water supply scheme
Design water supply schemeDesign water supply scheme
Design water supply schemeAby Mundackal
 

What's hot (20)

Estimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemsEstimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systems
 
Sewer appurtenances [recovered]
Sewer appurtenances [recovered]Sewer appurtenances [recovered]
Sewer appurtenances [recovered]
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
L 51 appurtennances (Valves)
L 51 appurtennances (Valves)L 51 appurtennances (Valves)
L 51 appurtennances (Valves)
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
Tutorial epanet
Tutorial epanetTutorial epanet
Tutorial epanet
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimation
 
04 pipeline-channel hydraulics
04 pipeline-channel hydraulics04 pipeline-channel hydraulics
04 pipeline-channel hydraulics
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.ppt
 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysis
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn design
 
Wasa guidelines for design of water and wastewater systems
Wasa   guidelines for design of water and wastewater systemsWasa   guidelines for design of water and wastewater systems
Wasa guidelines for design of water and wastewater systems
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demand
 
Cve471 lecture notes 4 spillways
Cve471 lecture notes 4   spillwaysCve471 lecture notes 4   spillways
Cve471 lecture notes 4 spillways
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage system
 
Simulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanetSimulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanet
 
Design of sewage treatment plant
Design of sewage treatment plantDesign of sewage treatment plant
Design of sewage treatment plant
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptx
 
Design water supply scheme
Design water supply schemeDesign water supply scheme
Design water supply scheme
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 

Similar to Design of sewerage system

Design of sewerage system part 2
Design of sewerage system part 2Design of sewerage system part 2
Design of sewerage system part 2fawad khan
 
IVRCL REPORT Atishay TYagi (UPES)
IVRCL REPORT Atishay TYagi (UPES)IVRCL REPORT Atishay TYagi (UPES)
IVRCL REPORT Atishay TYagi (UPES)ATISHAY TYAGI
 
Sewage, Sewer system, and elevations Module
Sewage, Sewer system, and elevations ModuleSewage, Sewer system, and elevations Module
Sewage, Sewer system, and elevations ModuleBahzad5
 
Multi-flow drainage system
Multi-flow drainage systemMulti-flow drainage system
Multi-flow drainage systemIrshad Ansari
 
IRJET- Assessment of Environmental Impacts during Operational Phase of a T...
IRJET- 	  Assessment of Environmental Impacts during Operational Phase of a T...IRJET- 	  Assessment of Environmental Impacts during Operational Phase of a T...
IRJET- Assessment of Environmental Impacts during Operational Phase of a T...IRJET Journal
 
Design of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyDesign of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyIRJET Journal
 
IRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET Journal
 
Sediment control at the source for a bulk water supply scheme in mysore, india
Sediment control at the source for a bulk water supply scheme in mysore, indiaSediment control at the source for a bulk water supply scheme in mysore, india
Sediment control at the source for a bulk water supply scheme in mysore, indiaIAEME Publication
 
IRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET Journal
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMAbhinay Saraswat
 
IRJET- Study of Conventional Drainage System
IRJET- Study of Conventional Drainage SystemIRJET- Study of Conventional Drainage System
IRJET- Study of Conventional Drainage SystemIRJET Journal
 
Efficient Use of Rain Water by Altering Channel System
Efficient Use of Rain Water by Altering Channel SystemEfficient Use of Rain Water by Altering Channel System
Efficient Use of Rain Water by Altering Channel Systemtheijes
 
A04320105
A04320105A04320105
A04320105theijes
 
Bulletin 829_1
Bulletin 829_1Bulletin 829_1
Bulletin 829_1Kun Liu
 
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...IRJET Journal
 
Multi-flow drainage System
Multi-flow drainage SystemMulti-flow drainage System
Multi-flow drainage SystemIrshad Ansari
 
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation System
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation SystemIRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation System
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation SystemIRJET Journal
 
Chapter 9 gravity flow water supply system
Chapter 9 gravity flow water supply systemChapter 9 gravity flow water supply system
Chapter 9 gravity flow water supply systemGokul Saud
 

Similar to Design of sewerage system (20)

Design of sewerage system part 2
Design of sewerage system part 2Design of sewerage system part 2
Design of sewerage system part 2
 
IVRCL REPORT Atishay TYagi (UPES)
IVRCL REPORT Atishay TYagi (UPES)IVRCL REPORT Atishay TYagi (UPES)
IVRCL REPORT Atishay TYagi (UPES)
 
Sewage, Sewer system, and elevations Module
Sewage, Sewer system, and elevations ModuleSewage, Sewer system, and elevations Module
Sewage, Sewer system, and elevations Module
 
Multi-flow drainage system
Multi-flow drainage systemMulti-flow drainage system
Multi-flow drainage system
 
IRJET- Assessment of Environmental Impacts during Operational Phase of a T...
IRJET- 	  Assessment of Environmental Impacts during Operational Phase of a T...IRJET- 	  Assessment of Environmental Impacts during Operational Phase of a T...
IRJET- Assessment of Environmental Impacts during Operational Phase of a T...
 
Design of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyDesign of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case Study
 
IRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla Junction
 
Sediment control at the source for a bulk water supply scheme in mysore, india
Sediment control at the source for a bulk water supply scheme in mysore, indiaSediment control at the source for a bulk water supply scheme in mysore, india
Sediment control at the source for a bulk water supply scheme in mysore, india
 
IRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment PlantIRJET- Hydraulic and Structural Design of Water Treatment Plant
IRJET- Hydraulic and Structural Design of Water Treatment Plant
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEM
 
IRJET- Study of Conventional Drainage System
IRJET- Study of Conventional Drainage SystemIRJET- Study of Conventional Drainage System
IRJET- Study of Conventional Drainage System
 
A04320105
A04320105A04320105
A04320105
 
Efficient Use of Rain Water by Altering Channel System
Efficient Use of Rain Water by Altering Channel SystemEfficient Use of Rain Water by Altering Channel System
Efficient Use of Rain Water by Altering Channel System
 
A04320105
A04320105A04320105
A04320105
 
Bulletin 829_1
Bulletin 829_1Bulletin 829_1
Bulletin 829_1
 
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...
IRJET- A Study of Application of Qanat System using Modern Techniques for Oas...
 
Multi-flow drainage System
Multi-flow drainage SystemMulti-flow drainage System
Multi-flow drainage System
 
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation System
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation SystemIRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation System
IRJET - Study for Pipe Distribution Network (PDN) in Aruna Dam Irrigation System
 
Chapter 9 gravity flow water supply system
Chapter 9 gravity flow water supply systemChapter 9 gravity flow water supply system
Chapter 9 gravity flow water supply system
 
Grassed water ways
Grassed water waysGrassed water ways
Grassed water ways
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

Design of sewerage system

  • 1. UET Peshawar Campus III Bannu4/17/2020 1
  • 2. UET Peshawar Campus III Bannu4/17/2020 2 Final Year Project Design of Sewerage System For Bannu Campus
  • 3. UET Peshawar Campus III Bannu4/17/2020 3 Group Members Irfanullah 0770 Shoukat Ullah 0763 M.Fawad Khan 0732 Supervised By: Dr. Afed Ullah Khan Department of Civil Engineering UET Peshawar BANNU Campus
  • 4. UET Peshawar Campus III Bannu4/17/2020 4 Contents • Introduction • Design requirement • Calculation of sanitary sewage • Calculation of storm runoff • Design of combined sewer • Calculation of dia of sewer
  • 5. UET Peshawar Campus III Bannu4/17/2020 5 Introduction
  • 6. UET Peshawar Campus III Bannu4/17/2020 6 Sanitary Sewage The sewage which originates of dwellings, industrial facilities, commercials and institutions. source-shutterstock.com
  • 7. UET Peshawar Campus III Bannu4/17/2020 7 Storm Runoff Storm sewage or storm water is the flow derived from rainfall events and introduced into sewers intended for its conveyance. Source -researchgate.net
  • 8. UET Peshawar Campus III Bannu4/17/2020 8 Partial Combined Sewer The sewer are designed as sanitary sewer but sufficient excess capacity are provided to carry a part of storm discharge also. In this type domestic sewage and storm water of buildings are carried out in one set. Source- WASA Lahore
  • 9. UET Peshawar Campus III Bannu4/17/2020 9 Design Requirements
  • 10. UET Peshawar Campus III Bannu4/17/2020 10 Papulation forecast Description Population Present 700 Future 800 Total 1500
  • 11. UET Peshawar Campus III Bannu4/17/2020 11 Peak Factor Ratio of the maximum flow to the average flow, denoted as PF, is observed to be dependent on contributory population.
  • 12. s UET Peshawar Campus III Bannu4/17/2020 12 Average Sewage Flow(m3 /day) Peak Factor ≤ 2500 4.0 2500 – 5000 3.4 5000 – 10000 3.1 10000 – 25000 2.7 25000 – 50000 2.5 50000 – 100000 2.3 100000 – 250000 2.15 250000 – 500000 2.08 > 500000 2.0 Peak Factor Source-WASA Lahore
  • 13. UET Peshawar Campus III Bannu4/17/2020 13 Minimum Sewer Size 225 mm is taken as the minimum sewer size. The reason being that, the choking does not take place even with the bigger size particles, which are usually thrown into the sewers through manholes. Source-WASA Lahore
  • 14. UET Peshawar Campus III Bannu4/17/2020 14 Minimum Cover Of Sewer 1 m is taken as the minimum cover over the sewers to avoid damage from live loads coming on the sewer. Minimum cover Source- WASA Lahore
  • 15. UET Peshawar Campus III Bannu4/17/2020 15 Direction of Sewer Line In choosing the alignment of a sewerage system, the following factors shall also be considered, •Sewer should flow, as for as possible the Natural Slope. •The objectives to serve all existing and future land development. •Site constraints. •Proximity of trees and other vegetation. •The hydraulic performance. •Social and economic impact.
  • 16. UET Peshawar Campus III Bannu4/17/2020 16 Slope Of Sewer Line Sewer dia (mm) Minimum slope(percent) Maximum slope(percent) 150 1.0 33.0 200 0.40 22.0 250 0.28 15.0 300 0.22 11.0 375 0.15 8.3 400 0.14 7.8 450 0.12 6.5 525 0.10 5.1 600 0.08 4.2 Source-Sewerage manual with Eurocodes
  • 17. UET Peshawar Campus III Bannu4/17/2020 17 Trenching • The width of the trench shall be ample to allow the pipe to be laid and jointed properly and to allow the backfill to be placed and compacted as needed. The trench sides shall be kept as nearly vertical as possible. When wider trenches are dug, appropriate bedding class and pipe strength shall be used. • Ledge rock, boulders, and large stones shall be removed to provide a minimum clearance of 100 mm below and on each side of all pipe and joints.
  • 18. UET Peshawar Campus III Bannu4/17/2020 18 Invert Level The lowest inside level at any cross-section of a sewer pipe is known as Invert Level at that Cross-section. Invert Level = NGSL/Road Level – Depth of Sewer – Thickness of Sewer – Dia. of Sewer. Source-WASA Lahore
  • 19. UET Peshawar Campus III Bannu4/17/2020 19 The proper maintenance and operation of the sewerage system is essential if the systems are to achieve their designed objectives. Maintenance Objectives •To monitor the capacity of the system and to restore the flow capacity. •To monitor and maintain the structural integrity of the system. •To prevent excessive infiltration and inflow. Maintenance Of Sewerage Systems
  • 20. UET Peshawar Campus III Bannu4/17/2020 20 Manhole Source- WASA Lahore Manhole is made or precast manhole is installed for • Cleaning and • inspection At place where change occur • In sewer direction • Diameter and • Slope.
  • 21. UET Peshawar Campus III Bannu4/17/2020 21 Manhole Manhole inside Dia (mm) 45° Deflection Max size of pipe (mm) 90° Deflection Max size of pipe (mm) 1220 610 460 1525 915 690 1830 1070 760
  • 22. UET Peshawar Campus III Bannu4/17/2020 22 Spacing Of Manhole Sewer size Spacing not more than 225mm to 380mm 100 m 460mm to 760mm 120 m Greater than 760mm 150 m Spacing Source- WASA Lahore
  • 23. UET Peshawar Campus III Bannu4/17/2020 23 Calculations
  • 24. UET Peshawar Campus III Bannu4/17/2020 24 Calculation Of Sanitary Sewage
  • 25. UET Peshawar Campus III Bannu4/17/2020 25 Calculation Of Storm Runoff
  • 26. UET Peshawar Campus III Bannu4/17/2020 26 Total Sewage Flow Total sewage = storm runoff + sanitary sewage Total sewage = 1824 + 1824 = 3648 m3/day
  • 27. UET Peshawar Campus III Bannu4/17/2020 27 Calculation of Dia Of Sewer
  • 28. UET Peshawar Campus III Bannu4/17/2020 28 Slope Of Sewer Line
  • 29. UET Peshawar Campus III Bannu4/17/2020 29 References • Sewerage manual with Eurocodes “Drainage Service Department” Govt of Hong Kong Special Administrative Region • “Water Supply and Sewerage” by E.W Steel and Terenge J. Mcghee • WASA Lahore
  • 30. UET Peshawar Campus III Bannu4/17/2020 30