It is indicated that one of the areas that participants found difficult in international projects was the use of unfamiliar
contract forms. CNC Vietnam is proud to briefly introduces the comparison between typical rainbow suits (Red Book,
Yellow Book, and Silver Book) which are reputed as the leading contracts in international engineering and construction
projects for both practitioners, (Employers, Contractor), and professional (Lawyers, legal executive, contract executive
etc.) to have a further acknowledgment, and experience.
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
REGULATION AND WORKS Recommended for building
and engineering works
designed by the Employer
or his representative, the
Engineer.
Under the usual
arrangements for this type
of contract, the Contractor
constructs the works in
accordance with a design
provided by the Employer.
However, the works may
include some elements of
Contractor designed civil,
mechanical, electrical
Recommended for the
provision of electrical
and/or mechanical plant
and for the design and
execution of building or
engineering works.
Under the usual
arrangements for this type
of contract, the Contractor
designs and provides, in
accordance with the
Employer’s requirements,
plant and/or other works;
which may include any
combination of civil,
Suitable for the provision
on a turnkey basis of a
process or power plant, of
a factory or similar facility,
or of an infrastructure
projector other type of
development, where
 A higher degree of
certainty of final price and
time is required, and
 The Contractor takes total
responsibility for the
design and execution of
the project, with little
involvement of the
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
2
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
and/or construction works. mechanical, electrical
and/or construction works.
Employer.
Under the usual
arrangements for turnkey
projects, the Contractor
carries out all the
Engineering, Procurement
and Construction (EPC):
providing a fully equipped
facility, ready for operation
(at the “turn of the key”).
CONTRACT ADMINISTRATION The Contract is
administered by the
Engineer (appointed by the
Employer) who shall
determine any claim for
extension of time and
additional payment, certify
payments and issue taking
over and performance
certificates.
The Contract is
administered by the
Engineer (appointed by the
Employer) who shall
determine any claim for
extension of time and
additional payment, certify
payments and issue taking
over and performance
certificates.
There is Not Engineer. The
Contract is administered
directly by the Employer or
its representative who
endeavours to reach
agreement with the
Contractor on each claim.
The Introductory Note to
the Silver Book emphasises
that if the Contractor is to
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
3
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
achieve the certainly of time
and price stipulated, then
the involvement of the
Employer must be limited to
a minimum during
construction.
RISKS ALLOCATION Risks are allocated on a
fair and equitable basis
taking account of such
matters as insurability, and
each party's ability to
foresee, and mitigate the
effect of, the circumstances
relevant to each risk.
There are a number of
key risks that the Employer
retains, for example:
1. Errors in the Setting Out
data (Sub-Clause 4.7);
Risks are allocated on a
fair and equitable basis
taking account of such
matters as insurability, and
each party's ability to
foresee, and mitigate the
effect of, the circumstances
relevant to each risk.
There are a number of
key risks that the Employer
retains, for example:
1. Errors in the Setting Out
data (Sub-Clause 4.7);
A majority of risks is
allocated to the
Contractor under the
Contract, including any
errors in:
1. Errors in the Setting Out
data (Sub-Clause 4.7);
2. Site data (Sub-Clause
4.10);
3. Unforeseeable
difficulties or costs (Sub-
Clause 4.12)
The Contractor is expected
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
4
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
2. Site data (Sub-Clause
4.10);
3. "Unforeseeable" Site risks
(Sub-Clause 4.12)
As a result, the tender time
can be relatively short.
2. Site data (Sub-Clause
4.10);
3. "Unforeseeable" Site risks
(Sub-Clause 4.12)
As a result, the tender time
can be relatively short.
to:
 Price these risks; and/or
 Carryout extensive due
diligence to mitigate
risks.
A longer period for
preparation of a tender is
therefore usually required,
in particular to inspect the
Site and examine data
hydrological and
subsurface data and also
to scrutinise the Employer's
Requirements.
DESIGN
-
ERRORS IN THE EMPLOYER’S
REQUIREMENTS
The Contractor shall design
(to the extent specified in
the Contract), execute
and complete the Works in
accordance with the
The Contractor shall carry
out, and be responsible
for, the design of the Works.
Design shall be prepared
by qualified designers who
The Contractor shall be
deemed to have
scrutinised, prior to the Base
Date, the Employer's
Requirements (including
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
5
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Contract and with the
Engineer’s instructions, and
shall remedy any defects in
the Works.
Except to the extent
specified in the Contract,
the Contractor
 Shall be responsible for
all Contractor’s
Documents, Temporary
Works, and such design
of each item of Plant
and Materials as is
required for the item to
be in accordance with
the Contract, and
 Shall not otherwise be
responsible for the
design or specification of
are engineers who comply
with the criteria (if any)
stated in the Employer's
Requirements.
Unless otherwise stated in
the Contract, the
Contractor shall submit to
the Engineer for consent
the name and particulars
of each proposed designer
and design Subcontractor.
The Contractor warrants
that he, his designers and
design Subcontractors have
the experience and
capability necessary for
the design.
The Contractor undertakes
that the designers shall be
available to attend
design criteria and
calculations, if any). The
Contractor shall be
responsible for the design
of the Works and for the
accuracy of such
Employer's Requirements
(including design criteria
and calculations), except
as stated below.
The Employer shall not be
responsible for any error,
inaccuracy or omission of
any kind in the Employer's
Requirements as originally
included in the Contract
and shall not be deemed
to have given any
representation of accuracy
or completeness of any
data or information, except
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
6
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
the Permanent Works.
The Contractor shall,
whenever required by the
Engineer, submit details of
the arrangements and
methods, which the
Contractor proposes to
adopt for the execution of
the Works. No significant
alteration to these
arrangements and methods
shall be made without this
having previously been
notified to the Engineer. If
the Contract specifies that
the Contractor shall design
any part of the Permanent
Works, then unless otherwise
stated in the Particular
Conditions:
discussions with the
Engineer at all reasonable
times, until the expiry date
of the relevant Defects
Notification Period.
Upon receiving notice
under Sub-Clause8.1
[Commencement of Works],
the Contractor shall
scrutinise the Employer's
Requirements (including
design criteria and
calculations) and the items
of reference mentioned in
Sub Clause 4.7 [Setting Out].
Within the period stated in
the Appendix to Tender,
calculated from the
Commencement Date, the
Contractor shall give
as stated below. Any data
or information received by
the Contractor, from the
Employer or otherwise, shall
not relieve the Contractor
from his responsibility for
the design and execution of
the Works.
However, the Employer
shall be responsible for the
correctness of the following
portions of the Employer's
Requirements and of the
following data and
information provided by (or
on behalf of) the Employer:
 Portions, data and
information which are
stated in the Contract
as being immutable or
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
7
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
 The Contractor shall
submit to the Engineer
the Contractor’s
Documents for this part
in accordance with the
procedures specified in
the Contract;
 These Contractor’s
Documents shall be in
accordance with the
Specification and
Drawings, shall be written
in the language for
communications defined
in 1.4 [Law and
Language],and shall
include additional
information required by
the Engineer to add to
the Drawings for co-
ordination of each Party’s
notice to the Engineer of
any error, fault or other
defect found in the
Employer's Requirements or
these items of reference.
After receiving this notice,
the Engineer shall
determine whether Clause
13 [Variations and
Adjustments]shall be
applied, if so, give notice to
the Contractor accordingly.
If and to the extent that
(taking account of cost
and time) an experienced
contractor exercising due
care would have
discovered the error, fault
or other defect when
examining the Site and the
the responsibility of the
Employer,
 Definitions of intended
purposes of the Works or
any parts thereof,
 Criteria for the testing
and performance of the
completed Works, and
 Portions, data and
information which
cannot.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
8
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
designs.
 The Contractor shall be
responsible for this part
and it shall, when the
Works are completed,
be fit for such purposes
for which the part is
intended as are specified
in the Contract; and
 Prior to the
commencement of the
Tests on Completion, the
Contractor shall submit
to the Engineer the “as-
built” documents and
operation and
maintenance manuals in
accordance with the
Specification and in
sufficient detail for the
Employer's Requirements
before submitting the
Tender, the Time for
Completion shall not be
extended and the
Contract Price shall not be
adjusted.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
9
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Employer to operate,
maintain, dismantle,
reassemble, adjust and
repair this part of the
Works. Such part shall
not be considered to
be completed for the
purposes of taking over
under Sub-Clause 10.1
[Taking Over of the
Works and Sections] until
these documents and
manuals have been
submitted to the
Engineer.
CONTRACT PRICE Unless otherwise stated in
the Particular Conditions:
 The Contract Price shall
be agreed or
determined under Sub-
Unless otherwise stated in
the Particular Conditions:
 The Contract Price shall
be the lump sum
accepted contract
Unless otherwise stated in
the Particular Conditions:
 Payment for the Works
shall be made on the
basis of the lump sum
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
10
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Clause 12.3 and be
subject to adjustments in
accordance with the
Contract.
 The Contractor shall pay
all taxes, duties and
fees required to be paid
by him under the
Contract, and the
Contract Price shall not
be adjusted for any of
these costs except as
stated in Sub-Clause 13.7
[Adjustments for Changes
in Legislation];
 Any quantities which may
be set out in the Bill of
Quantities or other
Schedule are estimated
quantities and are not to
amount and be subject
to adjustments in
accordance with the
Contract;
 The Contractor shall pay
all taxes, duties and
fees required to be
paid by him under the
Contract, and the
Contract Price shallot be
adjusted for any of these
costs, except as stated in
Sub-Clause 13.7
[Adjustments for
Changes in Legislation]
 Any quantities which
may be set out in a
Schedule are estimated
quantities and are not
to be taken as the
Contract Price, subject
to adjustments in
accordance with the
Contract;
 The Contractor shall pay
all taxes, duties and
fees required to be
paid by him under the
Contract, and the
Contract Price shall not
be adjusted for any of
these costs, except as
stated in Sub Clause
13.7.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
11
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
be taken as the actual
and correct quantities:
1. of the Works which
the Contractor is
required to execute,
or
2. For the purposes of
Clause [Measurement
and Evaluation ];
 The Contractor shall
submit to the Engineer,
within 28 days after the
Commencement Date,
a proposed breakdown
of each lump sum price in
the Schedules. The
Engineer may take
account of the
breakdown when
preparing Payment
actual and correct
quantities of the Works
which the Contractor is
required to execute;
 Any quantities or price
data, which may be set
out in a Schedule, shall
be used for the purposes
stated in the Schedule
and may be
inapplicable for other
purposes. However, if
any part of the Works is
to be paid according to
quantity supplied or
work done, the
provisions for
measurement and
evaluation shall be as
stated in the Particular
Conditions. The Contract
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
12
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Certificates, but shall
not be bound by it.
 Notwithstanding the
provisions of
subparagraph (b),
Contractor’s Equipment,
including essential spare
parts therefore, imported
by the Contractor for
the sole purpose of
executing the Contract
shall be exempt from the
payment of import
duties and taxes upon
importation.
Price shall be
determined accordingly,
subject to adjustments
in accordance with the
Contract.
PAYMENT The Employer shall make an
advance payment, as an
interest-free loan for
mobilisation, when the
Contractor submits a
The Employer shall make an
advance payment, as an
interest-free loan for
mobilisation, when the
Contractor submits a
The Employer shall make an
advance payment, as an
interest-free loan for
mobilization and design,
when the Contractor
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
13
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
guarantee. Unless and until
the Employer receives this
guarantee, or if the total
advance payment is not
stated in the Contract
Data (or Appendix to
Tender), this Sub Clause shall
not apply.
The Engineer shall issue an
Interim Payment Certificate
for the first instalment after:
 Receiving a Statement
and
 after the Employer
Receives:
1. The Performance
Security
2. a guarantee in
amounts and
guarantee. Unless and until
the Employer receives this
guarantee, or if the total
advance payment is not
stated in the Contract
Data (or Appendix to
Tender), this Sub Clause shall
not apply.
The Engineer shall issue an
Interim Payment Certificate
for the first instalment after:
 Receiving a Statement
and
 after the Employer
Receives:
1. The Performance
Security
2. a guarantee in
amounts and
submits a guarantee.
Employer shall pay the first
instalment after receiving
1. A Statement;
2. The Performance
Security
The Contractor shall submit
a Statement in six copies
to the Employer after the
end of the period of
payment stated in the
Contract (if not stated,
after the end of each
month), in a form
approved by the Employer,
showing in detail the
amounts to which the
Contractor considers
himself to be entitled,
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
14
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
currencies equal to
the advance
payment
The Contractor shall submit
a Statement in six copies to
the Engineer after the end
of each month, in a form
approved by the Engineer,
showing in detail the
amounts to which the
Contractor considers
himself to be entitled,
together with supporting
documents which shall
include the report on the
progress during this month.
If the Contract includes a
schedule of payments
specifying the instalments in
which the Contract Price
currencies equal to
the advance
payment
The Contractor shall submit
a Statement in six copies to
the Engineer after the end
of each month, in a form
approved by the Engineer,
showing in detail the
amounts to which the
Contractor considers
himself to be entitled,
together with supporting
documents which shall
include the report on the
progress during this month.
If the Contract includes a
schedule of payments
specifying the instalments in
which the Contract Price
together with supporting
documents.
If the Contract includes a
Schedule of Payments
specifying the instalments
in which the Contract
Price will be paid, then
unless otherwise stated in
this Schedule.
If the Contract includes a
Schedule of Payments
specifying the instalments in
which the Contract Price
will be paid, then unless
otherwise stated in this
Schedule:
 The instalments quoted
in the Schedule of
Payments shall be the
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
15
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
will be paid, then unless
otherwise stated in this
schedule:
 The instalments quoted in
this schedule of
payments shall be the
estimated contract
values.
 If these instalments are
not defined by
reference to the actual
progress achieved in
executing the Works,
and if actual progress is
found to be less than
that on which the
Schedule of Payments
was based, then the
Engineer may proceed
to agree or determine
will be paid, then unless
otherwise stated in this
schedule:
 The instalments quoted in
this schedule of
payments shall be the
estimated contract
values.
 If these instalments are
not defined by
reference to the actual
progress achieved in
executing the Works,
and if actual progress is
found to be less than
that on which the
Schedule of Payments
was based, then the
Engineer may proceed
toagree or determine
estimated contract
 If these instalments are not
defined by reference to
the actual progress
achieved in executing the
Works, and if actual
progress is found to be
less than that on which
the Schedule of Payments
was based, then the
Employer may proceed to
agree or determine revised
instalments, which shall take
account of the extent to
which progress is less than
that on which the
instalments were previously
based.
If the Contract does not
include a Schedule of
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
16
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
revised instalments,
which shall take account
of the extent to which
progress is less than that
on which the
instalments were
previously based.
If the Contract does not
include a schedule of
payments, the Contractor
shall submit non-binding
estimates of the payments,
which he expects to
become due during each
quarterly period.
The first estimate shall be
submitted within 42 days
after the Commencement
Date.
Revised estimates shall be
revised instalments,
which shall take account
of the extent to which
progress is less than that
on which the
instalments were
previously based.
If the Contract does not
include a schedule of
payments, the Contractor
shall submit non-binding
estimates of the payments,
which he expects to
become due during each
quarterly period.
The first estimate shall be
submitted within 42 days
after the Commencement
Date.
Revised estimates shall be
Payments, the Contractor
shall submit non-binding
estimates of the payments,
which he expects to
become due during each
quarterly period.
The first estimate shall be
submitted within 42 days
after the Commencement
Date.
Revised estimates shall be
submitted at quarterly
intervals, until the Taking
Over Certificate has been
issued for the Works.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
17
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
submitted at quarterly
intervals, until the Taking
Over Certificate has been
issued for the Works.
submitted at quarterly
intervals, until the Taking
Over Certificate has been
issued for the Works.
EXTENSION OF TIME
ASSOCIATED COSTS
Various rights for the
Contractor to claim
Extension of Time OR
Associated Cost under the
Contract for errors:
 In the Setting Out data
(Sub-Clause 4.7)
 In the Site data (Sub-
Clause 4.10)
 Unforeseen Site risks (Sub-
Clause 4.12)
 Others.
Various rights for the
Contractor to claim
Extension of Time OR
Associated Cost under the
Contract for errors:
 In the Setting Out data
(Sub-Clause 4.7)
 In the Site data (Sub-
Clause 4.10)
 Unforeseen Site risks (Sub-
Clause 4.12)
 Others.
The Contractor shall be
entitled to an EOT if (and to
the extent that)completion
for the purposes of Taking
Over of the Works and
Sections is or will be delayed
by any of the following
causes:
 A Variation (unless an
adjustment to the Time
for Completion has
been agreed under
Variation Procedure;
 A cause of delay giving
an entitlement to
extension of time under
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
18
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
a Sub-Clause of these
Conditions;
 Any delay, impediment
or prevention caused
by (or attributable
to)the Employer, the
Employer’s Personnel, or
the Employer’s other
contractors on the Site.
TESTS ON COMPLETION The Contractor shall carry
out the Tests on
Completion.
The Contractor shall give
to the Engineer not less than
21 days’ notice of the date
after which the Contractor
will be ready to carry out
each of the Tests on
Completion.
The Contractor shall carry
out the Tests on
Completion.
The Contractor shall give
to the Engineer not less than
21 days’ notice of the date
after which the Contractor
will be ready to carry out
each of the Tests on
Completion.
The Contractor shall carry
out the Tests on
Completion.
The Contractor shall give
to the Engineer not less than
21 days’ notice of the date
after which the Contractor
will be ready to carry out
each of the Tests on
Completion.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
19
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Unless otherwise agreed,
Tests on Completion shall
be carried out within 14 days
after this date, on such
day or days as the
Engineer shall instruct.
In considering the results
of the Tests on Completion,
the Engineer shall make
allowances for the effect
of any use of the Works
by the Employer on the
performance or other
characteristics of the
Works. As soon as the Works,
or a Section, have passed
any Tests on Completion,
the Contractor shall submit
a certified report of the
results of these Tests to the
Unless otherwise agreed,
Tests on Completion shall
be carried out within 14 days
after this date, on such
day or days as the
Engineer shall instruct.
Unless otherwise stated in
the Particular Conditions,
the Tests on Completion
shall be carried out in the
following sequence:
a. PRE-COMMISSIONING
TESTS
which shall include the
appropriate inspections
and ("dry" or "cold")
functional tests to
demonstrate that each
item of Plant can safely
Unless otherwise agreed,
Tests on Completion shall
be carried out within 14 days
after this date, on such
day or days as the
Engineer shall instruct.
Unless otherwise stated in
the Particular Conditions,
the Tests on Completion
shall be carried out in the
following sequence:
a. PRE-COMMISSIONING
TESTS
which shall include the
appropriate inspections
and ("dry" or "cold")
functional tests to
demonstrate that each
item of Plant can safely
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
20
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Engineer.
If the Tests on Completion
are being unduly delayed
by the Contractor, the
Engineer may by notice
require the Contractor to
carry out the Tests within 21
days after receiving the
notice. The Contractor
shall carry out the Tests on
such day or days within
that period as the
Contractor may fix and of
which he shall give notice
to the Engineer.
If the Contractor fails to
carry out the Tests on
Completion within the
period of 21 days, the
Employer’s Personnel may
undertake the next stage,
b. COMMISSIONING TESTS
which shall include the
specified operational tests
to demonstrate that the
Works or Section can be
operated safely and as
specified, under all available
operating conditions; and
c. TRIAL OPERATION
which shall demonstrate
that the Works or Section
perform reliably and in
accordance with the
Contract.
During trial operation,
when the Works are
operating under stable
conditions, the Contractor
undertake the next stage,
b. COMMISSIONING TESTS
which shall include the
specified operational tests
to demonstrate that the
Works or Section can be
operated safely and as
specified, under all available
operating conditions; and
c. TRIAL OPERATION
which shall demonstrate
that the Works or Section
perform reliably and in
accordance with the
Contract.
During trial operation,
when the Works are
operating under stable
conditions, the Contractor
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
21
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
proceed with the Tests at
the risk and cost of the
Contractor. The Tests on
Completion shall then be
deemed to have been
carried out in the presence
of the Contractor and the
results of the Tests shall be
accepted as accurate.
Failure to pass tests
If the Works, or a Section, fail
to pass the Test son
Completion repeated
under Sub- Clause 9.3
[Retesting], the Engineer
shall be entitled to:
 Order further repetition of
Tests on Completion
under Sub-Clause 9.3;
shall give notice to the
Engineer that the Works
are ready for any other
Tests on Completion,
including performance tests
to demonstrate whether the
Works conform with criteria
specified in the Employer's
Requirements and with the
Schedule of Guarantees.
Trial operation shall not
constitute a taking-over
under Clause 10 [Employer’s
Taking Over].
Unless otherwise stated in
the Particular Conditions,
any product produced by
the Works during trial
operation shall be the
property of the Employer.
shall give notice to the
Engineer that the Works
are ready for any other
Tests on Completion,
including performance tests
to demonstrate whether the
Works conform with criteria
specified in the Employer's
Requirements and with the
Schedule of Guarantees.
Trial operation shall not
constitute a taking-over
under Clause 10 [Employer’s
Taking Over].
Unless otherwise stated in
the Particular Conditions,
any product produced by
the Works during trial
operation shall be the
property of the Employer.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
22
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
 If the failure deprives the
Employer of substantially
the whole benefit of the
Works or Section, reject
the Works or Section(as
the case may be), in
which event the
Employer shall have the
same remedies as are
provided in
subparagraph (c) of
Sub Clause 11.4 [Failure
to Remedy Defects]; or
 Issue a Taking-Over
Certificate, if the
Employer so requests.
But in this case, the
Contractor shall proceed in
accordance with all other
obligations under the
In considering the results
of the Tests on Completion,
the Engineer shall make
allowances for the effect
of any use of the Works
by the Employer on the
performance or other
characteristics of the Works.
As soon as the Works, or a
Section, have passed each
of the Tests on Completion
described in sub-paragraph
(a), (b) or (c), the
Contractor shall submit a
certified report of the results
of these Tests to the
Engineer.
If the Tests on Completion
are being unduly delayed
by the Contractor, the
Engineer may by notice
In considering the results
of the Tests on Completion,
the Engineer shall make
allowances for the effect
of any use of the Works
by the Employer on the
performance or other
characteristics of the Works.
As soon as the Works, or a
Section, have passed each
of the Tests on Completion
described in sub-paragraph
(a), (b) or (c), the
Contractor shall submit a
certified report of the results
of these Tests to the
Engineer.
If the Tests on Completion
are being unduly delayed
by the Contractor, the
Engineer may by notice
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
23
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Contract, and the Contract
Price shall be reduced by
such amount as shall be
appropriate to cover the
reduced value to the
Employer as a result of this
failure. Unless the relevant
reduction for this failure is
stated (or its method of
calculation is defined) in
the Contract, the Employer
may require the reduction to
be
 Agreed by both Parties
(in full satisfaction of this
failure only) and paid
before this Taking-Over
Certificate is issued;
 Determined and paid
under Sub-Clause 2.5
require the Contractor to
carry out the Tests within 21
days after receiving the
notice.
The Contractor shall carry
out the Tests on such day or
days within that period as
the Contractor may fix
and of which he shall give
notice to the Engineer.
If the Contractor fails to
carry out the Tests on
Completion within the
period of 21 days, the
Employer's Personnel may
proceed with the Tests at
the risk and cost of the
Contractor. The Tests on
Completion shall then be
deemed to have been
require the Contractor to
carry out the Tests within 21
days after receiving the
notice.
The Contractor shall carry
out the Tests on such day or
days within that period as
the Contractor may fix
and of which he shall give
notice to the Engineer.
If the Contractor fails to
carry out the Tests on
Completion within the
period of 21 days, the
Employer's Personnel may
proceed with the Tests at
the risk and cost of the
Contractor. The Tests on
Completion shall then be
deemed to have been
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
24
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
[Employer’s Claims] and
Sub Clause 3.5
[Determinations]
carried out in the
presence of the Contractor
and the results of the Tests
shall be accepted as
accurate.
Failure to pass tests
If the Works, or a Section, fail
to pass the Tests on
Completion repeated under
Sub-Clause 9.3 [Retesting],
the Engineer shall be
entitled to:
 Order further repetition of
Tests on Completion
under Sub-Clause 9.3;
 If the failure deprives the
Employer of substantially
the whole benefit of the
Works or Section, reject
carried out in the
presence of the Contractor
and the results of the Tests
shall be accepted as
accurate.
Failure to pass tests
If the Works, or a Section, fail
to pass the Tests on
Completion repeated under
Sub-Clause 9.3 [Retesting],
the Engineer shall be
entitled to:
 Order further repetition of
Tests on Completion
under Sub-Clause 9.3;
 If the failure deprives the
Employer of substantially
the whole benefit of the
Works or Section, reject
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
25
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
the Works or Section(as
the case may be), in
which event the
Employer shall have the
same remedies as are
provided in
subparagraph (c) of
Sub-Clause 11.4[Failure to
Remedy Defects];
 Issue a Taking-Over
Certificate.
But in this case, the
Contractor shall then
proceed in accordance
with all other obligations
under the Contract, and the
Contract Price shall be
reduced by such amount
as shall be appropriate to
cover the reduced value
the Works or Section(as
the case may be), in
which event the
Employer shall have the
same remedies as are
provided in
subparagraph (c) of
Sub-Clause 11.4[Failure to
Remedy Defects];
 Issue a Taking-Over
Certificate.
But in this case, the
Contractor shall then
proceed in accordance
with all other obligations
under the Contract, and the
Contract Price shall be
reduced by such amount
as shall be appropriate to
cover the reduced value
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
26
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
to the Employer as a result
of this failure. Unless the
relevant reduction for this
failure is stated (or its
method of calculation is
defined) in the Contract:
the Employer may require
the reduction to be
 Agreed by both Parties
(in full satisfaction of this
failure only) and paid
before this Taking-Over
Certificate is issued;
 Determined and paid
under Sub-Clause 2.5
[Employer’s Claims] and
Sub Clause 3.5
[Determinations].
to the Employer as a result
of this failure. Unless the
relevant reduction for this
failure is stated (or its
method of calculation is
defined) in the Contract:
the Employer may require
the reduction to be
 Agreed by both Parties
(in full satisfaction of this
failure only) and paid
before this Taking-Over
Certificate is issued;
 Determined and paid
under Sub-Clause 2.5
[Employer’s Claims] and
Sub Clause 3.5
[Determinations].
TAKING-OVER Except as stated in Sub-
Clause 9.4 [Failure to Pass
Except as stated in Sub-
Clause 9.4 [Failure to Pass
Except as stated in Sub-
Clause 9.4 [Failure to Pass
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
27
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Tests on Completion],the
Works shall be taken over
by the Employer when
 The Works have been
completed in
accordance with the
Contract, including the
matters described in
Sub Clause 8.2 [Time for
Completion] and except
as allowed in
subparagraph (a) below,
and
 A Taking-Over Certificate
for the Works has been
issued, or is deemed to
have been issued in
accordance with this
Sub-Clause.
The Contractor may apply
Tests on Completion],the
Works shall be taken over
by the Employer when
 The Works have been
completed in
accordance with the
Contract, including the
matters described in
Sub Clause 8.2 [Time for
Completion] and except
as allowed in
subparagraph (a) below,
and
 A Taking-Over Certificate
for the Works has been
issued, or is deemed to
have been issued in
accordance with this
Sub-Clause.
The Contractor may apply
Tests on Completion],the
Works shall be taken over
by the Employer when
 The Works have been
completed in
accordance with the
Contract, including the
matters described in
Sub Clause 8.2 [Time for
Completion] and except
as allowed in
subparagraph (a) below,
and
 A Taking-Over Certificate
for the Works has been
issued, or is deemed to
have been issued in
accordance with this
Sub-Clause.
The Contractor may apply
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
28
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
by notice to the Engineer
for a Taking-Over
Certificate not earlier than
14 days before the Works will,
in the Contractor’s opinion,
be complete and ready for
taking over. If the Works
are divided into Sections,
the Contractor may similarly
apply for a Taking Over
Certificate for each
Section.
The Engineer shall, within
28 days after receiving the
Contractor’s application:
 Issue the Taking-Over
Certificate to the
Contractor, stating the
date on which the
Works or Section were
by notice to the Engineer
for a Taking-Over
Certificate not earlier than
14 days before the Works will,
in the Contractor’s opinion,
be complete and ready for
taking over. If the Works
are divided into Sections,
the Contractor may similarly
apply for a Taking Over
Certificate for each
Section.
The Engineer shall, within
28 days after receiving the
Contractor’s application:
 Issue the Taking-Over
Certificate to the
Contractor, stating the
date on which the
Works or Section were
by notice to the Engineer
for a Taking-Over
Certificate not earlier than
14 days before the Works will,
in the Contractor’s opinion,
be complete and ready for
taking over. If the Works
are divided into Sections,
the Contractor may similarly
apply for a Taking Over
Certificate for each
Section.
The Engineer shall, within
28 days after receiving the
Contractor’s application:
 Issue the Taking-Over
Certificate to the
Contractor, stating the
date on which the
Works or Section were
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
29
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
completed in
accordance with the
Contract, except for any
minor outstanding work
and defects which will
not substantially affect
the use of the Works or
Section for their intended
purpose (either until or
whilst this work is
completed and these
defects are remedied)
 Reject the application,
giving reasons and
specifying the work
required to be done by
the Contractor to enable
the Taking-Over
Certificate to be issued.
The Contractor shall then
complete this work
completed in
accordance with the
Contract, except for any
minor outstanding work
and defects which will
not substantially affect
the use of the Works or
Section for their intended
purpose (either until or
whilst this work is
completed and these
defects are remedied)
 Reject the application,
giving reasons and
specifying the work
required to be done by
the Contractor to enable
the Taking-Over
Certificate to be issued.
The Contractor shall then
complete this work
completed in
accordance with the
Contract, except for any
minor outstanding work
and defects which will
not substantially affect
the use of the Works or
Section for their intended
purpose (either until or
whilst this work is
completed and these
defects are remedied)
 Reject the application,
giving reasons and
specifying the work
required to be done by
the Contractor to enable
the Taking-Over
Certificate to be issued.
The Contractor shall then
complete this work
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
30
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
before issuing a further
notice under this Sub
Clause.
If the Engineer fails either
to issue the Taking-Over
Certificate or to reject the
Contractor’s application
within the period of 28
days, and if the Works or
Section(as the case may
be) are substantially in
accordance with the
Contract, the Taking-Over
Certificate shall be
deemed to have been
issued on the last day of
that period.
The Engineer may, at the
sole discretion of the
Employer, issue a Taking-
before issuing a further
notice under this Sub
Clause.
If the Engineer fails either
to issue the Taking-Over
Certificate or to reject the
Contractor’s application
within the period of 28
days, and if the Works or
Section(as the case may
be) are substantially in
accordance with the
Contract, the Taking-Over
Certificate shall be
deemed to have been
issued on the last day of
that period.
The Engineer may, at the
sole discretion of the
Employer, issue a Taking-
before issuing a further
notice under this Sub
Clause.
If the Engineer fails either
to issue the Taking-Over
Certificate or to reject the
Contractor’s application
within the period of 28
days, and if the Works or
Section(as the case may
be) are substantially in
accordance with the
Contract, the Taking-Over
Certificate shall be
deemed to have been
issued on the last day of
that period.
Parts of the Works (other
than Sections) shall not be
taken over or used by the
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
31
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
Over Certificate for any
part of the Permanent
Works.
The Employer shall not use
any part of the Works(other
than as a temporary
measure which is either
specified in the Contract or
agreed by both Parties)
unless and until the
Engineer has issued a
Taking-Over Certificate for
this part. However, if the
Employer does use any part
of the Works before the
Taking Over Certificate is
issued:
 The part which is used
shall be deemed to
have been taken over as
Over Certificate for any
part of the Permanent
Works.
The Employer shall not use
any part of the Works(other
than as a temporary
measure which is either
specified in the Contract or
agreed by both Parties)
unless and until the
Engineer has issued a
Taking-Over Certificate for
this part. However, if the
Employer does use any part
of the Works before the
Taking Over Certificate is
issued:
 The part which is used
shall be deemed to
have been taken over as
Employer, except as may
be stated in the Contract
or as may be agreed by
both Parties.
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
32
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
from the date on which it
is used,
 The Contractor shall
cease to be liable for
the care of such part
as from this date, when
responsibility shall pass
to the Employer, and
 If requested by the
Contractor, the Engineer
shall issue a Taking-Over
Certificate for this part.
After the Engineer has issued
a Taking-Over Certificate
for a part of the Works,
the Contractor shall be
given the earliest
opportunity to take such
steps as may be necessary
to carry out any
from the date on which it
is used,
 The Contractor shall
cease to be liable for
the care of such part
as from this date, when
responsibility shall pass
to the Employer, and
 If requested by the
Contractor, the Engineer
shall issue a Taking-Over
Certificate for this part.
After the Engineer has issued
a Taking-Over Certificate
for a part of the Works,
the Contractor shall be
given the earliest
opportunity to take such
steps as may be necessary
to carry out any
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
33
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
outstanding Tests on
Completion.
The Contractor shall carry
out these Tests on
Completion as soon as
practicable before the
expiry date of the relevant
Defects Notification Period.
If the Contractor incurs Cost
as a result of the Employer
taking over and/or using a
part of the Works, other than
such use as is specified in
the Contract or agreed by
the Contractor, the
Contractor shall
 Give notice to the
Engineer;
 Be entitled to 20.1
outstanding Tests on
Completion.
The Contractor shall carry
out these Tests on
Completion as soon as
practicable before the
expiry date of the relevant
Defects Notification Period.
If the Contractor incurs Cost
as a result of the Employer
taking over and/or using a
part of the Works, other than
such use as is specified in
the Contract or agreed by
the Contractor, the
Contractor shall
 Give notice to the
Engineer;
 Be entitled to 20.1
CNC Vietnam Consultant Co., Ltd
[A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St.,
Dist. 1, Ho Chi Minh, Vietnam
[T] 08 6288 5128 | [F] 08 6288 5138
[W] www.consultantcnc.com | [E] contact@consultantcnc.com
34
ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)
[Contractor’s Claims] to
payment of any such
Cost plus profit, which
shall be included in the
Contract Price. After this
notice, the Engineer
(3.5) to agree or
determine this Cost and
profit.
[Contractor’s Claims] to
payment of any such
Cost plus profit, which
shall be included in the
Contract Price. After this
notice, the Engineer
(3.5) to agree or
determine this Cost and
profit.
Important Notes:
1) This information has been prepared by CNC as a general guide only and does not constitute advice on any
specific matter. We recommend that you seek professional advice before taking action. No liability can be
accepted by us for any action taken or not taken as a result of this information.
2) The materials on this Web site may not reflect the most current legal developments, verdicts or settlements and
should not be considered an indication of future results.

More Related Content

What's hot

time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfsajidkhan82714
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 

What's hot (20)

Contract Management
Contract ManagementContract Management
Contract Management
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 

Similar to Fidic comparison red book yellow book_silver book_en_newsletters

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementdrmujahidkhan85
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen AntovAssen Antov
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptxAditya Mane
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBESahl Buhary
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfHamsathFarludeen
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Appendix K Model Letters For Use By The Engineer
Appendix K Model Letters For Use By The EngineerAppendix K Model Letters For Use By The Engineer
Appendix K Model Letters For Use By The EngineerSean Flores
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2shensin1015
 

Similar to Fidic comparison red book yellow book_silver book_en_newsletters (20)

Ak contract management
Ak contract managementAk contract management
Ak contract management
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
 
Cl report final
Cl report finalCl report final
Cl report final
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Appendix K Model Letters For Use By The Engineer
Appendix K Model Letters For Use By The EngineerAppendix K Model Letters For Use By The Engineer
Appendix K Model Letters For Use By The Engineer
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Working drawing and detailing
Working drawing and detailingWorking drawing and detailing
Working drawing and detailing
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 

Recently uploaded

2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914Delhi Call girls
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGIPanoram CGI
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...ApartmentWala1
 
Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfpritika141199
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTurbo Tenant
 
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)Delhi Call girls
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdfManishSaxena95
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentAntalya Development
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhiasmaqueen5
 
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhidelhimodel235
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhidelhimodel235
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needsaidasheikh47
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhidelhimodel235
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhidelhimodel235
 

Recently uploaded (20)

2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
 
Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdf
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
 
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
 
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdfMagarpatta Nova Elegance Mundhwa Pune  E-Brochure.pdf
Magarpatta Nova Elegance Mundhwa Pune E-Brochure.pdf
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
 
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
 
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 137 Noida (Call Girls) Delhi
 
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
Call Girls in shastri nagar Delhi 8264348440 ✅ call girls ❤️
 
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 2 Delhi (Call Girls) Delhi
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
 

Fidic comparison red book yellow book_silver book_en_newsletters

  • 1. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 1 It is indicated that one of the areas that participants found difficult in international projects was the use of unfamiliar contract forms. CNC Vietnam is proud to briefly introduces the comparison between typical rainbow suits (Red Book, Yellow Book, and Silver Book) which are reputed as the leading contracts in international engineering and construction projects for both practitioners, (Employers, Contractor), and professional (Lawyers, legal executive, contract executive etc.) to have a further acknowledgment, and experience. ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) REGULATION AND WORKS Recommended for building and engineering works designed by the Employer or his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However, the works may include some elements of Contractor designed civil, mechanical, electrical Recommended for the provision of electrical and/or mechanical plant and for the design and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employer’s requirements, plant and/or other works; which may include any combination of civil, Suitable for the provision on a turnkey basis of a process or power plant, of a factory or similar facility, or of an infrastructure projector other type of development, where  A higher degree of certainty of final price and time is required, and  The Contractor takes total responsibility for the design and execution of the project, with little involvement of the
  • 2. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 2 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) and/or construction works. mechanical, electrical and/or construction works. Employer. Under the usual arrangements for turnkey projects, the Contractor carries out all the Engineering, Procurement and Construction (EPC): providing a fully equipped facility, ready for operation (at the “turn of the key”). CONTRACT ADMINISTRATION The Contract is administered by the Engineer (appointed by the Employer) who shall determine any claim for extension of time and additional payment, certify payments and issue taking over and performance certificates. The Contract is administered by the Engineer (appointed by the Employer) who shall determine any claim for extension of time and additional payment, certify payments and issue taking over and performance certificates. There is Not Engineer. The Contract is administered directly by the Employer or its representative who endeavours to reach agreement with the Contractor on each claim. The Introductory Note to the Silver Book emphasises that if the Contractor is to
  • 3. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 3 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) achieve the certainly of time and price stipulated, then the involvement of the Employer must be limited to a minimum during construction. RISKS ALLOCATION Risks are allocated on a fair and equitable basis taking account of such matters as insurability, and each party's ability to foresee, and mitigate the effect of, the circumstances relevant to each risk. There are a number of key risks that the Employer retains, for example: 1. Errors in the Setting Out data (Sub-Clause 4.7); Risks are allocated on a fair and equitable basis taking account of such matters as insurability, and each party's ability to foresee, and mitigate the effect of, the circumstances relevant to each risk. There are a number of key risks that the Employer retains, for example: 1. Errors in the Setting Out data (Sub-Clause 4.7); A majority of risks is allocated to the Contractor under the Contract, including any errors in: 1. Errors in the Setting Out data (Sub-Clause 4.7); 2. Site data (Sub-Clause 4.10); 3. Unforeseeable difficulties or costs (Sub- Clause 4.12) The Contractor is expected
  • 4. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 4 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) 2. Site data (Sub-Clause 4.10); 3. "Unforeseeable" Site risks (Sub-Clause 4.12) As a result, the tender time can be relatively short. 2. Site data (Sub-Clause 4.10); 3. "Unforeseeable" Site risks (Sub-Clause 4.12) As a result, the tender time can be relatively short. to:  Price these risks; and/or  Carryout extensive due diligence to mitigate risks. A longer period for preparation of a tender is therefore usually required, in particular to inspect the Site and examine data hydrological and subsurface data and also to scrutinise the Employer's Requirements. DESIGN - ERRORS IN THE EMPLOYER’S REQUIREMENTS The Contractor shall design (to the extent specified in the Contract), execute and complete the Works in accordance with the The Contractor shall carry out, and be responsible for, the design of the Works. Design shall be prepared by qualified designers who The Contractor shall be deemed to have scrutinised, prior to the Base Date, the Employer's Requirements (including
  • 5. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 5 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Contract and with the Engineer’s instructions, and shall remedy any defects in the Works. Except to the extent specified in the Contract, the Contractor  Shall be responsible for all Contractor’s Documents, Temporary Works, and such design of each item of Plant and Materials as is required for the item to be in accordance with the Contract, and  Shall not otherwise be responsible for the design or specification of are engineers who comply with the criteria (if any) stated in the Employer's Requirements. Unless otherwise stated in the Contract, the Contractor shall submit to the Engineer for consent the name and particulars of each proposed designer and design Subcontractor. The Contractor warrants that he, his designers and design Subcontractors have the experience and capability necessary for the design. The Contractor undertakes that the designers shall be available to attend design criteria and calculations, if any). The Contractor shall be responsible for the design of the Works and for the accuracy of such Employer's Requirements (including design criteria and calculations), except as stated below. The Employer shall not be responsible for any error, inaccuracy or omission of any kind in the Employer's Requirements as originally included in the Contract and shall not be deemed to have given any representation of accuracy or completeness of any data or information, except
  • 6. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 6 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) the Permanent Works. The Contractor shall, whenever required by the Engineer, submit details of the arrangements and methods, which the Contractor proposes to adopt for the execution of the Works. No significant alteration to these arrangements and methods shall be made without this having previously been notified to the Engineer. If the Contract specifies that the Contractor shall design any part of the Permanent Works, then unless otherwise stated in the Particular Conditions: discussions with the Engineer at all reasonable times, until the expiry date of the relevant Defects Notification Period. Upon receiving notice under Sub-Clause8.1 [Commencement of Works], the Contractor shall scrutinise the Employer's Requirements (including design criteria and calculations) and the items of reference mentioned in Sub Clause 4.7 [Setting Out]. Within the period stated in the Appendix to Tender, calculated from the Commencement Date, the Contractor shall give as stated below. Any data or information received by the Contractor, from the Employer or otherwise, shall not relieve the Contractor from his responsibility for the design and execution of the Works. However, the Employer shall be responsible for the correctness of the following portions of the Employer's Requirements and of the following data and information provided by (or on behalf of) the Employer:  Portions, data and information which are stated in the Contract as being immutable or
  • 7. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 7 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)  The Contractor shall submit to the Engineer the Contractor’s Documents for this part in accordance with the procedures specified in the Contract;  These Contractor’s Documents shall be in accordance with the Specification and Drawings, shall be written in the language for communications defined in 1.4 [Law and Language],and shall include additional information required by the Engineer to add to the Drawings for co- ordination of each Party’s notice to the Engineer of any error, fault or other defect found in the Employer's Requirements or these items of reference. After receiving this notice, the Engineer shall determine whether Clause 13 [Variations and Adjustments]shall be applied, if so, give notice to the Contractor accordingly. If and to the extent that (taking account of cost and time) an experienced contractor exercising due care would have discovered the error, fault or other defect when examining the Site and the the responsibility of the Employer,  Definitions of intended purposes of the Works or any parts thereof,  Criteria for the testing and performance of the completed Works, and  Portions, data and information which cannot.
  • 8. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 8 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) designs.  The Contractor shall be responsible for this part and it shall, when the Works are completed, be fit for such purposes for which the part is intended as are specified in the Contract; and  Prior to the commencement of the Tests on Completion, the Contractor shall submit to the Engineer the “as- built” documents and operation and maintenance manuals in accordance with the Specification and in sufficient detail for the Employer's Requirements before submitting the Tender, the Time for Completion shall not be extended and the Contract Price shall not be adjusted.
  • 9. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 9 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Employer to operate, maintain, dismantle, reassemble, adjust and repair this part of the Works. Such part shall not be considered to be completed for the purposes of taking over under Sub-Clause 10.1 [Taking Over of the Works and Sections] until these documents and manuals have been submitted to the Engineer. CONTRACT PRICE Unless otherwise stated in the Particular Conditions:  The Contract Price shall be agreed or determined under Sub- Unless otherwise stated in the Particular Conditions:  The Contract Price shall be the lump sum accepted contract Unless otherwise stated in the Particular Conditions:  Payment for the Works shall be made on the basis of the lump sum
  • 10. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 10 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Clause 12.3 and be subject to adjustments in accordance with the Contract.  The Contractor shall pay all taxes, duties and fees required to be paid by him under the Contract, and the Contract Price shall not be adjusted for any of these costs except as stated in Sub-Clause 13.7 [Adjustments for Changes in Legislation];  Any quantities which may be set out in the Bill of Quantities or other Schedule are estimated quantities and are not to amount and be subject to adjustments in accordance with the Contract;  The Contractor shall pay all taxes, duties and fees required to be paid by him under the Contract, and the Contract Price shallot be adjusted for any of these costs, except as stated in Sub-Clause 13.7 [Adjustments for Changes in Legislation]  Any quantities which may be set out in a Schedule are estimated quantities and are not to be taken as the Contract Price, subject to adjustments in accordance with the Contract;  The Contractor shall pay all taxes, duties and fees required to be paid by him under the Contract, and the Contract Price shall not be adjusted for any of these costs, except as stated in Sub Clause 13.7.
  • 11. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 11 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) be taken as the actual and correct quantities: 1. of the Works which the Contractor is required to execute, or 2. For the purposes of Clause [Measurement and Evaluation ];  The Contractor shall submit to the Engineer, within 28 days after the Commencement Date, a proposed breakdown of each lump sum price in the Schedules. The Engineer may take account of the breakdown when preparing Payment actual and correct quantities of the Works which the Contractor is required to execute;  Any quantities or price data, which may be set out in a Schedule, shall be used for the purposes stated in the Schedule and may be inapplicable for other purposes. However, if any part of the Works is to be paid according to quantity supplied or work done, the provisions for measurement and evaluation shall be as stated in the Particular Conditions. The Contract
  • 12. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 12 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Certificates, but shall not be bound by it.  Notwithstanding the provisions of subparagraph (b), Contractor’s Equipment, including essential spare parts therefore, imported by the Contractor for the sole purpose of executing the Contract shall be exempt from the payment of import duties and taxes upon importation. Price shall be determined accordingly, subject to adjustments in accordance with the Contract. PAYMENT The Employer shall make an advance payment, as an interest-free loan for mobilisation, when the Contractor submits a The Employer shall make an advance payment, as an interest-free loan for mobilisation, when the Contractor submits a The Employer shall make an advance payment, as an interest-free loan for mobilization and design, when the Contractor
  • 13. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 13 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) guarantee. Unless and until the Employer receives this guarantee, or if the total advance payment is not stated in the Contract Data (or Appendix to Tender), this Sub Clause shall not apply. The Engineer shall issue an Interim Payment Certificate for the first instalment after:  Receiving a Statement and  after the Employer Receives: 1. The Performance Security 2. a guarantee in amounts and guarantee. Unless and until the Employer receives this guarantee, or if the total advance payment is not stated in the Contract Data (or Appendix to Tender), this Sub Clause shall not apply. The Engineer shall issue an Interim Payment Certificate for the first instalment after:  Receiving a Statement and  after the Employer Receives: 1. The Performance Security 2. a guarantee in amounts and submits a guarantee. Employer shall pay the first instalment after receiving 1. A Statement; 2. The Performance Security The Contractor shall submit a Statement in six copies to the Employer after the end of the period of payment stated in the Contract (if not stated, after the end of each month), in a form approved by the Employer, showing in detail the amounts to which the Contractor considers himself to be entitled,
  • 14. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 14 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) currencies equal to the advance payment The Contractor shall submit a Statement in six copies to the Engineer after the end of each month, in a form approved by the Engineer, showing in detail the amounts to which the Contractor considers himself to be entitled, together with supporting documents which shall include the report on the progress during this month. If the Contract includes a schedule of payments specifying the instalments in which the Contract Price currencies equal to the advance payment The Contractor shall submit a Statement in six copies to the Engineer after the end of each month, in a form approved by the Engineer, showing in detail the amounts to which the Contractor considers himself to be entitled, together with supporting documents which shall include the report on the progress during this month. If the Contract includes a schedule of payments specifying the instalments in which the Contract Price together with supporting documents. If the Contract includes a Schedule of Payments specifying the instalments in which the Contract Price will be paid, then unless otherwise stated in this Schedule. If the Contract includes a Schedule of Payments specifying the instalments in which the Contract Price will be paid, then unless otherwise stated in this Schedule:  The instalments quoted in the Schedule of Payments shall be the
  • 15. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 15 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) will be paid, then unless otherwise stated in this schedule:  The instalments quoted in this schedule of payments shall be the estimated contract values.  If these instalments are not defined by reference to the actual progress achieved in executing the Works, and if actual progress is found to be less than that on which the Schedule of Payments was based, then the Engineer may proceed to agree or determine will be paid, then unless otherwise stated in this schedule:  The instalments quoted in this schedule of payments shall be the estimated contract values.  If these instalments are not defined by reference to the actual progress achieved in executing the Works, and if actual progress is found to be less than that on which the Schedule of Payments was based, then the Engineer may proceed toagree or determine estimated contract  If these instalments are not defined by reference to the actual progress achieved in executing the Works, and if actual progress is found to be less than that on which the Schedule of Payments was based, then the Employer may proceed to agree or determine revised instalments, which shall take account of the extent to which progress is less than that on which the instalments were previously based. If the Contract does not include a Schedule of
  • 16. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 16 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) revised instalments, which shall take account of the extent to which progress is less than that on which the instalments were previously based. If the Contract does not include a schedule of payments, the Contractor shall submit non-binding estimates of the payments, which he expects to become due during each quarterly period. The first estimate shall be submitted within 42 days after the Commencement Date. Revised estimates shall be revised instalments, which shall take account of the extent to which progress is less than that on which the instalments were previously based. If the Contract does not include a schedule of payments, the Contractor shall submit non-binding estimates of the payments, which he expects to become due during each quarterly period. The first estimate shall be submitted within 42 days after the Commencement Date. Revised estimates shall be Payments, the Contractor shall submit non-binding estimates of the payments, which he expects to become due during each quarterly period. The first estimate shall be submitted within 42 days after the Commencement Date. Revised estimates shall be submitted at quarterly intervals, until the Taking Over Certificate has been issued for the Works.
  • 17. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 17 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) submitted at quarterly intervals, until the Taking Over Certificate has been issued for the Works. submitted at quarterly intervals, until the Taking Over Certificate has been issued for the Works. EXTENSION OF TIME ASSOCIATED COSTS Various rights for the Contractor to claim Extension of Time OR Associated Cost under the Contract for errors:  In the Setting Out data (Sub-Clause 4.7)  In the Site data (Sub- Clause 4.10)  Unforeseen Site risks (Sub- Clause 4.12)  Others. Various rights for the Contractor to claim Extension of Time OR Associated Cost under the Contract for errors:  In the Setting Out data (Sub-Clause 4.7)  In the Site data (Sub- Clause 4.10)  Unforeseen Site risks (Sub- Clause 4.12)  Others. The Contractor shall be entitled to an EOT if (and to the extent that)completion for the purposes of Taking Over of the Works and Sections is or will be delayed by any of the following causes:  A Variation (unless an adjustment to the Time for Completion has been agreed under Variation Procedure;  A cause of delay giving an entitlement to extension of time under
  • 18. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 18 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) a Sub-Clause of these Conditions;  Any delay, impediment or prevention caused by (or attributable to)the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site. TESTS ON COMPLETION The Contractor shall carry out the Tests on Completion. The Contractor shall give to the Engineer not less than 21 days’ notice of the date after which the Contractor will be ready to carry out each of the Tests on Completion. The Contractor shall carry out the Tests on Completion. The Contractor shall give to the Engineer not less than 21 days’ notice of the date after which the Contractor will be ready to carry out each of the Tests on Completion. The Contractor shall carry out the Tests on Completion. The Contractor shall give to the Engineer not less than 21 days’ notice of the date after which the Contractor will be ready to carry out each of the Tests on Completion.
  • 19. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 19 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Unless otherwise agreed, Tests on Completion shall be carried out within 14 days after this date, on such day or days as the Engineer shall instruct. In considering the results of the Tests on Completion, the Engineer shall make allowances for the effect of any use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the Works, or a Section, have passed any Tests on Completion, the Contractor shall submit a certified report of the results of these Tests to the Unless otherwise agreed, Tests on Completion shall be carried out within 14 days after this date, on such day or days as the Engineer shall instruct. Unless otherwise stated in the Particular Conditions, the Tests on Completion shall be carried out in the following sequence: a. PRE-COMMISSIONING TESTS which shall include the appropriate inspections and ("dry" or "cold") functional tests to demonstrate that each item of Plant can safely Unless otherwise agreed, Tests on Completion shall be carried out within 14 days after this date, on such day or days as the Engineer shall instruct. Unless otherwise stated in the Particular Conditions, the Tests on Completion shall be carried out in the following sequence: a. PRE-COMMISSIONING TESTS which shall include the appropriate inspections and ("dry" or "cold") functional tests to demonstrate that each item of Plant can safely
  • 20. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 20 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Engineer. If the Tests on Completion are being unduly delayed by the Contractor, the Engineer may by notice require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Engineer. If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer’s Personnel may undertake the next stage, b. COMMISSIONING TESTS which shall include the specified operational tests to demonstrate that the Works or Section can be operated safely and as specified, under all available operating conditions; and c. TRIAL OPERATION which shall demonstrate that the Works or Section perform reliably and in accordance with the Contract. During trial operation, when the Works are operating under stable conditions, the Contractor undertake the next stage, b. COMMISSIONING TESTS which shall include the specified operational tests to demonstrate that the Works or Section can be operated safely and as specified, under all available operating conditions; and c. TRIAL OPERATION which shall demonstrate that the Works or Section perform reliably and in accordance with the Contract. During trial operation, when the Works are operating under stable conditions, the Contractor
  • 21. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 21 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) proceed with the Tests at the risk and cost of the Contractor. The Tests on Completion shall then be deemed to have been carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate. Failure to pass tests If the Works, or a Section, fail to pass the Test son Completion repeated under Sub- Clause 9.3 [Retesting], the Engineer shall be entitled to:  Order further repetition of Tests on Completion under Sub-Clause 9.3; shall give notice to the Engineer that the Works are ready for any other Tests on Completion, including performance tests to demonstrate whether the Works conform with criteria specified in the Employer's Requirements and with the Schedule of Guarantees. Trial operation shall not constitute a taking-over under Clause 10 [Employer’s Taking Over]. Unless otherwise stated in the Particular Conditions, any product produced by the Works during trial operation shall be the property of the Employer. shall give notice to the Engineer that the Works are ready for any other Tests on Completion, including performance tests to demonstrate whether the Works conform with criteria specified in the Employer's Requirements and with the Schedule of Guarantees. Trial operation shall not constitute a taking-over under Clause 10 [Employer’s Taking Over]. Unless otherwise stated in the Particular Conditions, any product produced by the Works during trial operation shall be the property of the Employer.
  • 22. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 22 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999)  If the failure deprives the Employer of substantially the whole benefit of the Works or Section, reject the Works or Section(as the case may be), in which event the Employer shall have the same remedies as are provided in subparagraph (c) of Sub Clause 11.4 [Failure to Remedy Defects]; or  Issue a Taking-Over Certificate, if the Employer so requests. But in this case, the Contractor shall proceed in accordance with all other obligations under the In considering the results of the Tests on Completion, the Engineer shall make allowances for the effect of any use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the Works, or a Section, have passed each of the Tests on Completion described in sub-paragraph (a), (b) or (c), the Contractor shall submit a certified report of the results of these Tests to the Engineer. If the Tests on Completion are being unduly delayed by the Contractor, the Engineer may by notice In considering the results of the Tests on Completion, the Engineer shall make allowances for the effect of any use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the Works, or a Section, have passed each of the Tests on Completion described in sub-paragraph (a), (b) or (c), the Contractor shall submit a certified report of the results of these Tests to the Engineer. If the Tests on Completion are being unduly delayed by the Contractor, the Engineer may by notice
  • 23. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 23 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Contract, and the Contract Price shall be reduced by such amount as shall be appropriate to cover the reduced value to the Employer as a result of this failure. Unless the relevant reduction for this failure is stated (or its method of calculation is defined) in the Contract, the Employer may require the reduction to be  Agreed by both Parties (in full satisfaction of this failure only) and paid before this Taking-Over Certificate is issued;  Determined and paid under Sub-Clause 2.5 require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Engineer. If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer's Personnel may proceed with the Tests at the risk and cost of the Contractor. The Tests on Completion shall then be deemed to have been require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Engineer. If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer's Personnel may proceed with the Tests at the risk and cost of the Contractor. The Tests on Completion shall then be deemed to have been
  • 24. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 24 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) [Employer’s Claims] and Sub Clause 3.5 [Determinations] carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate. Failure to pass tests If the Works, or a Section, fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting], the Engineer shall be entitled to:  Order further repetition of Tests on Completion under Sub-Clause 9.3;  If the failure deprives the Employer of substantially the whole benefit of the Works or Section, reject carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate. Failure to pass tests If the Works, or a Section, fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting], the Engineer shall be entitled to:  Order further repetition of Tests on Completion under Sub-Clause 9.3;  If the failure deprives the Employer of substantially the whole benefit of the Works or Section, reject
  • 25. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 25 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) the Works or Section(as the case may be), in which event the Employer shall have the same remedies as are provided in subparagraph (c) of Sub-Clause 11.4[Failure to Remedy Defects];  Issue a Taking-Over Certificate. But in this case, the Contractor shall then proceed in accordance with all other obligations under the Contract, and the Contract Price shall be reduced by such amount as shall be appropriate to cover the reduced value the Works or Section(as the case may be), in which event the Employer shall have the same remedies as are provided in subparagraph (c) of Sub-Clause 11.4[Failure to Remedy Defects];  Issue a Taking-Over Certificate. But in this case, the Contractor shall then proceed in accordance with all other obligations under the Contract, and the Contract Price shall be reduced by such amount as shall be appropriate to cover the reduced value
  • 26. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 26 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) to the Employer as a result of this failure. Unless the relevant reduction for this failure is stated (or its method of calculation is defined) in the Contract: the Employer may require the reduction to be  Agreed by both Parties (in full satisfaction of this failure only) and paid before this Taking-Over Certificate is issued;  Determined and paid under Sub-Clause 2.5 [Employer’s Claims] and Sub Clause 3.5 [Determinations]. to the Employer as a result of this failure. Unless the relevant reduction for this failure is stated (or its method of calculation is defined) in the Contract: the Employer may require the reduction to be  Agreed by both Parties (in full satisfaction of this failure only) and paid before this Taking-Over Certificate is issued;  Determined and paid under Sub-Clause 2.5 [Employer’s Claims] and Sub Clause 3.5 [Determinations]. TAKING-OVER Except as stated in Sub- Clause 9.4 [Failure to Pass Except as stated in Sub- Clause 9.4 [Failure to Pass Except as stated in Sub- Clause 9.4 [Failure to Pass
  • 27. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 27 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Tests on Completion],the Works shall be taken over by the Employer when  The Works have been completed in accordance with the Contract, including the matters described in Sub Clause 8.2 [Time for Completion] and except as allowed in subparagraph (a) below, and  A Taking-Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub-Clause. The Contractor may apply Tests on Completion],the Works shall be taken over by the Employer when  The Works have been completed in accordance with the Contract, including the matters described in Sub Clause 8.2 [Time for Completion] and except as allowed in subparagraph (a) below, and  A Taking-Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub-Clause. The Contractor may apply Tests on Completion],the Works shall be taken over by the Employer when  The Works have been completed in accordance with the Contract, including the matters described in Sub Clause 8.2 [Time for Completion] and except as allowed in subparagraph (a) below, and  A Taking-Over Certificate for the Works has been issued, or is deemed to have been issued in accordance with this Sub-Clause. The Contractor may apply
  • 28. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 28 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) by notice to the Engineer for a Taking-Over Certificate not earlier than 14 days before the Works will, in the Contractor’s opinion, be complete and ready for taking over. If the Works are divided into Sections, the Contractor may similarly apply for a Taking Over Certificate for each Section. The Engineer shall, within 28 days after receiving the Contractor’s application:  Issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or Section were by notice to the Engineer for a Taking-Over Certificate not earlier than 14 days before the Works will, in the Contractor’s opinion, be complete and ready for taking over. If the Works are divided into Sections, the Contractor may similarly apply for a Taking Over Certificate for each Section. The Engineer shall, within 28 days after receiving the Contractor’s application:  Issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or Section were by notice to the Engineer for a Taking-Over Certificate not earlier than 14 days before the Works will, in the Contractor’s opinion, be complete and ready for taking over. If the Works are divided into Sections, the Contractor may similarly apply for a Taking Over Certificate for each Section. The Engineer shall, within 28 days after receiving the Contractor’s application:  Issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or Section were
  • 29. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 29 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) completed in accordance with the Contract, except for any minor outstanding work and defects which will not substantially affect the use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied)  Reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work completed in accordance with the Contract, except for any minor outstanding work and defects which will not substantially affect the use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied)  Reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work completed in accordance with the Contract, except for any minor outstanding work and defects which will not substantially affect the use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied)  Reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work
  • 30. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 30 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) before issuing a further notice under this Sub Clause. If the Engineer fails either to issue the Taking-Over Certificate or to reject the Contractor’s application within the period of 28 days, and if the Works or Section(as the case may be) are substantially in accordance with the Contract, the Taking-Over Certificate shall be deemed to have been issued on the last day of that period. The Engineer may, at the sole discretion of the Employer, issue a Taking- before issuing a further notice under this Sub Clause. If the Engineer fails either to issue the Taking-Over Certificate or to reject the Contractor’s application within the period of 28 days, and if the Works or Section(as the case may be) are substantially in accordance with the Contract, the Taking-Over Certificate shall be deemed to have been issued on the last day of that period. The Engineer may, at the sole discretion of the Employer, issue a Taking- before issuing a further notice under this Sub Clause. If the Engineer fails either to issue the Taking-Over Certificate or to reject the Contractor’s application within the period of 28 days, and if the Works or Section(as the case may be) are substantially in accordance with the Contract, the Taking-Over Certificate shall be deemed to have been issued on the last day of that period. Parts of the Works (other than Sections) shall not be taken over or used by the
  • 31. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 31 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) Over Certificate for any part of the Permanent Works. The Employer shall not use any part of the Works(other than as a temporary measure which is either specified in the Contract or agreed by both Parties) unless and until the Engineer has issued a Taking-Over Certificate for this part. However, if the Employer does use any part of the Works before the Taking Over Certificate is issued:  The part which is used shall be deemed to have been taken over as Over Certificate for any part of the Permanent Works. The Employer shall not use any part of the Works(other than as a temporary measure which is either specified in the Contract or agreed by both Parties) unless and until the Engineer has issued a Taking-Over Certificate for this part. However, if the Employer does use any part of the Works before the Taking Over Certificate is issued:  The part which is used shall be deemed to have been taken over as Employer, except as may be stated in the Contract or as may be agreed by both Parties.
  • 32. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 32 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) from the date on which it is used,  The Contractor shall cease to be liable for the care of such part as from this date, when responsibility shall pass to the Employer, and  If requested by the Contractor, the Engineer shall issue a Taking-Over Certificate for this part. After the Engineer has issued a Taking-Over Certificate for a part of the Works, the Contractor shall be given the earliest opportunity to take such steps as may be necessary to carry out any from the date on which it is used,  The Contractor shall cease to be liable for the care of such part as from this date, when responsibility shall pass to the Employer, and  If requested by the Contractor, the Engineer shall issue a Taking-Over Certificate for this part. After the Engineer has issued a Taking-Over Certificate for a part of the Works, the Contractor shall be given the earliest opportunity to take such steps as may be necessary to carry out any
  • 33. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 33 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) outstanding Tests on Completion. The Contractor shall carry out these Tests on Completion as soon as practicable before the expiry date of the relevant Defects Notification Period. If the Contractor incurs Cost as a result of the Employer taking over and/or using a part of the Works, other than such use as is specified in the Contract or agreed by the Contractor, the Contractor shall  Give notice to the Engineer;  Be entitled to 20.1 outstanding Tests on Completion. The Contractor shall carry out these Tests on Completion as soon as practicable before the expiry date of the relevant Defects Notification Period. If the Contractor incurs Cost as a result of the Employer taking over and/or using a part of the Works, other than such use as is specified in the Contract or agreed by the Contractor, the Contractor shall  Give notice to the Engineer;  Be entitled to 20.1
  • 34. CNC Vietnam Consultant Co., Ltd [A] Level 8, Vietnam Business Center Bldg., 57-59 Ho Tung Mau St., Dist. 1, Ho Chi Minh, Vietnam [T] 08 6288 5128 | [F] 08 6288 5138 [W] www.consultantcnc.com | [E] contact@consultantcnc.com 34 ISSUE RED BOOK (1999) YELLOW BOOK (1999) SILVER BOOK (1999) [Contractor’s Claims] to payment of any such Cost plus profit, which shall be included in the Contract Price. After this notice, the Engineer (3.5) to agree or determine this Cost and profit. [Contractor’s Claims] to payment of any such Cost plus profit, which shall be included in the Contract Price. After this notice, the Engineer (3.5) to agree or determine this Cost and profit. Important Notes: 1) This information has been prepared by CNC as a general guide only and does not constitute advice on any specific matter. We recommend that you seek professional advice before taking action. No liability can be accepted by us for any action taken or not taken as a result of this information. 2) The materials on this Web site may not reflect the most current legal developments, verdicts or settlements and should not be considered an indication of future results.