SlideShare a Scribd company logo
1 of 30
PROJECT MANAGEMENT
 CPM & PERT TECHNIQUES
FLOW OF PRESENTATION




 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project Management



Project
• A project is an interrelated set of activities that has a definite
   starting and ending point and that results in a unique product
   or service.

Project management
• Project management is a scientific way of planning, implementing,
   monitoring & controlling the various aspects of a project such as time,
   money, materials, manpower & other resources.
Network Planning Methods



    Methods used for network planning are:
       CPM
       PERT

    Managing a project with network planning methods involves four steps:

1.   Describing the Project.
2.   Diagramming the Network.
3.   Estimating time of completion.
4.   Monitoring Project Progress.
Network Diagram



Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram




1.   Before an activity can begin, its preceding
     activities must be completed.
2.   Arrows indicate logical precedence.
3.   Flow of the diagram is from left to right.
4.   Arrows should not intersect.
5.   Dangling should be avoided.
APPRAOCHES FOR
                                   NETWORK DIAGRAM



ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
  to represent events.
• It is Event Oriented.
                     3



         1     2                    6     7     8




                         4   5
DUMMY ACTIVITY

    AOA approach requires the addition of a                Dummy
    Activity to clarify the precedence relationships     between
    the two activities. It is a zero time activity and
    consumes no resources.

Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
   nodes
                                 1             3



                                           2
2) When two or more activities share the same
   precedence activity but not all the precedence are
   shared.

                 1       3       5

                                           7

                 2       4           6
ACTIVITY ON NODE(AON):


Uses nodes to represent activities and arcs indicate
precedence relationships between       them.
It is Activity Oriented.
ESTIMATING TIME
                                                      OF
                                                  COMPLETION

Planning the schedule of the project

Time estimates include:
1)   Total time for completion.
2)    ES- Earliest start time: the earliest time at which the activity
     can start given that its precedent activities must be completed first.

3)   EF-Earliest finish time: equals to the earliest start time for the activity
     plus the time required to complete the activity.

4)   LF- Latest finish time: the latest time in which the activity can be
     completed without delaying the project.

5)   LS- Latest start time: equal to the latest finish time minus the time
     required to complete the activity.
6)   FORWARD PASS:
     The early start and early finish times are calculated by
     moving forward through the network and considering the
     predecessor activities Considers maximum

7)   BACKWARD PASS:
     The latest start and finish times are calculated by moving backward through the
     network.
     Considers minimum

8)   SLACK TIME:
     Slack time for an activity is the difference between its earliest and latest start
     time or between the earliest and latest finish time.
     Critical path is the path of activities having zero Slack time.
A Simple Project




Activity    Immediate      Expected
           Predecessor       Time
   A            -              5
   B            -             6
   C           A              4
   D          A, B            2
Precedence Diagram
ES      Earliest Starting (time)
EF      Earliest Finishing
LS      Latest Starting
LF      Latest Finishing
Slack   Difference Time
CRITICAL PATH
                                         METHODS(CPM)

HISTORY :
  It was developed by J.E.KELLY of REMINGTON-RAND
  and M.R.WALKER of DU PONT and the emphasis was
  on the trade-off between the cost of project and its overall
  completion time. The first test was made in 1958,when CPM
  was applied to the construction of a new chemical plant.

DEFINITION:
  Critical path is the sequence of activities between a project’s
  start and finish that takes the longest time to complete.
STEPS IN DETERMINING
                                      CRITICAL PATH


• Specify the individual activities.

• Determine the sequence of the activities.

• Draw the network diagram.

• Estimate the activity completion time.

• Identify the critical path.

• Update the CPM diagram.
Activit Preceden Normal time   Normal
y       ce       (week)        Cost (Rs)


A         -            3       300
B         A            3       30
C         A            7       420
D         A            9       720
E         D            5       250
F       B,C,E          6       320
G         F            4       400
H         F           13       780
I         G           10       1000
Total                          4220
4           7




1   2       5   6




        3
                    8
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
             4             7




  1      2             6
                 5


             3
                           8
TIME ESTIMATES


o Optimistic time (to) – It is the shortest time     in which the
   activity can be completed.
o Most likely time (tm) – It is the probable time
   required to perform the activity.
o Pessimistic time (tp) – It is the longest estimated time
   required to perform an activity.
o Expected time
  te = to + 4tm + tp
                6
STEPS IN PERT

1.   Identify the specific activities.

2.   Determine proper sequence of the activities.

3.   Construct the network diagram.

4.   Estimate the time required for each activity.

5.   Determine the critical path.

6.   Update the PERT chart.
Activity   Descrip Preced    Optimis Most      Pessimi Expecte
           tion    ence      tic time Likely   stic    d time
                                      time     time

A          Initial      -      12       16       26      17
           design
B          Survey      A        6        9       18      10
           market
C          Build       A        8       10       18      11
           prototype
D          Test        C        2        3       4       3
           prototype
E          Redesign    B,D      3        4       11      5
           ing
F          Market      E        6        8       10      8
           testing
G          Set up      F       15       20       25      20
           productio
           n
1   2       4      5      6       7




        3


                 A-B-E-F-G = 60
        A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT


• Expected project completion time.

• Probability of completion before a specified date.

• The critical path activities that directly impact the completion
  time.

• The activities that have slack time and that can lend resources
  to critical path activities.

• Activity start and end dates.
LIMITATIONS

• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
  activities.
• Updating of the project is time consuming and requires high
  costs.
• Emphasis is laid only on time factors and cost factors are
  neglected.
Difference between
                                            CPM & PERT

               CPM                                  PERT
• CPM works with fixed               • PERT works with probabilistic
deterministic time                   time
• CPM is useful for repetitive and   • PERT is useful for non repetitive
non complex projects with a          and complex projects with
certain degree of time estimates.    uncertain time estimates.

• CPM includes time-cost trade off. • PERT is restricted to time
                                     variable.

• CPM- for construction projects.    • PERT- used for R&D programs.
Thank You…

More Related Content

What's hot

PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPMRajendrakumar Kadi
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 

What's hot (20)

PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPM
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
project management information system
project management information systemproject management information system
project management information system
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 

Viewers also liked

Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi AnalysisAnkita Bharti
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniquesCjkayes CjKayes
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pertdjoufack
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GMohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit AnalysisSaurabh Sood
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhiQuery
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics IndustrySunil Singh
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and LogisticseTailing India
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and chinaKaushik Raja
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesKabir Uddin
 

Viewers also liked (20)

Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi Analysis
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Om edit
Om editOm edit
Om edit
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit Analysis
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni Channel
 
E logistics
E logisticsE logistics
E logistics
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics Industry
 
E logistics
E logisticsE logistics
E logistics
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and Logistics
 
Snapdeal vs amazon
Snapdeal vs amazonSnapdeal vs amazon
Snapdeal vs amazon
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and china
 
E-Logisitics PPT
E-Logisitics PPTE-Logisitics PPT
E-Logisitics PPT
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite Images
 

Similar to Pert & cpm project management

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.pptalbert937613
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 

Similar to Pert & cpm project management (20)

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Project management
Project managementProject management
Project management
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 

Recently uploaded

joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...NadhimTaha
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubaijaehdlyzca
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Availablepr788182
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxDitasDelaCruz
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowranineha57744
 

Recently uploaded (20)

joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 

Pert & cpm project management

  • 1. PROJECT MANAGEMENT CPM & PERT TECHNIQUES
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress.
  • 5. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 6. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 7. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 3 1 2 6 7 8 4 5
  • 8. DUMMY ACTIVITY AOA approach requires the addition of a Dummy Activity to clarify the precedence relationships between the two activities. It is a zero time activity and consumes no resources. Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 9. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 3 5 7 2 4 6
  • 10. ACTIVITY ON NODE(AON): Uses nodes to represent activities and arcs indicate precedence relationships between them. It is Activity Oriented.
  • 11. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 12. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 13. A Simple Project Activity Immediate Expected Predecessor Time A - 5 B - 6 C A 4 D A, B 2
  • 15. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 16.
  • 17. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 18. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 19. Activit Preceden Normal time Normal y ce (week) Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 20. 4 7 1 2 5 6 3 8
  • 21. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 22. Critical path – A-D-F-G-I = 32 4 7 1 2 6 5 3 8
  • 23. TIME ESTIMATES o Optimistic time (to) – It is the shortest time in which the activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 24. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 25. Activity Descrip Preced Optimis Most Pessimi Expecte tion ence tic time Likely stic d time time time A Initial - 12 16 26 17 design B Survey A 6 9 18 10 market C Build A 8 10 18 11 prototype D Test C 2 3 4 3 prototype E Redesign B,D 3 4 11 5 ing F Market E 6 8 10 8 testing G Set up F 15 20 25 20 productio n
  • 26. 1 2 4 5 6 7 3 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH)
  • 27. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 28. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.
  • 29. Difference between CPM & PERT CPM PERT • CPM works with fixed • PERT works with probabilistic deterministic time time • CPM is useful for repetitive and • PERT is useful for non repetitive non complex projects with a and complex projects with certain degree of time estimates. uncertain time estimates. • CPM includes time-cost trade off. • PERT is restricted to time variable. • CPM- for construction projects. • PERT- used for R&D programs.