SlideShare a Scribd company logo
1 of 35
Medical IS Vendor Medical IS Vendor Medical IS Vendor
Medical IS Vendor –––– Project Project Project Project
CharterCharterCharterCharter
Project Name: Health System ImplementationProject Name:
Health System ImplementationProject Name: Health System
ImplementationProject Name: Health System Implementation
PJM 6140 Troubled Health System Project Case Study
Background
Healthcare Unlimited, LLC a leading health services company,
embarked on a new product development
project. Healthcare Unlimited needs to expand its clinical data
warehouse (CDW) to ingest third-party
data feeds from medical IS vendor and onsite clinic data to
incorporate this information to downstream
employer group analytics and reporting processes. This
expansion will also be used to develop new
activity reports to message value on these products.
The nature of the company’s business is that it operates in an
extremely competitive environment that
necessitates fast delivery to market so as to prevent competitor
companies from gaining dominant
market share with similar competitive products. Therefore, the
key success factors of the project were
time to market and quality. Cost of delivery was not a major
concern.
Scope
The scope of the project was to create a modular software
package to handle medical IS vendor data to
ensure appropriate preventative care is being tracked for
members, including the systems changes, the
vendor medical IS database tables, and medical IS vendor
reporting. The project was divided into
modules consisting of: medical IS DB tables, promote tables,
and medical IS vendor reporting. A project
manager was appointed, but has since left due to personal
reasons.
Time Scales
The launch date was set as December 1, 2015. The product had
to be ready for launch on this date, as all
the marketing material would reflect this date and the launch
had to precede the launch of similar
products from competitors. The project kickoff was May 5,
2015. The tasks that had been completed
prior to May 5, 2015 were the business case compilation and
approval and the project team
establishment.
Technology
The systems development was to be done using the MS Visual
Studio programming language and SQL
environment, which was new to the development team. The
developers were sent on MS Visual Studio
programming training two weeks prior to the project start. The
developers were used to working in a
Java programming environment and had not worked with any
MS-oriented languages before. The new
medical IS vendor reports will integrate into the existing
system located behind the intranet. These new
reports, unlike the existing reports, will utilize both SQL Server
and Teradata. SQL Server will control the
security access and parameter selection for the reports. The
application will then send the selected
parameters to Teradata in order to populate the body of the
report.
Infrastructure
Database Servers
• MS SQL Server 2008 R2
• Teradata 14
Reporting Servers
• The system will use an SSRS deployment server.
Development Tools
• MS Visual Studio 2008 Shell
• SQL Server Business Intelligence Development Studio
• SQL Server Management Studio
Business Requirements
The current application will display the medical IS vendor
reports. The system generates SQL Server
Reporting Services (SSRS) reports based on user-selected
parameters. Users can choose to view reports
in three formats: Excel 97-2003 (XLS), Portable Document
Format (PDF), or Comma Separated Value
(CSV).
The exported data within Excel or CSV files will contain “user-
friendly” headers and not
database column headers.
Scripts will execute on a weekly basis to import the following
vendor sources into the target system:
• Chip Rewards
• Spire
Scripts will execute on a monthly basis to import the following
vendor sources into the target system:
MDLive.
Case Study Summary of Events
Business Case Development
The product development department developed the business
case for the proposed new product,
including projected cost/benefit analysis based on previous
similar products and current market share.
The business case was reviewed by executive management and
approved.
Requirements Definition
The product development department developed the
requirements specification for the new product.
These requirements were specified based on the understanding
level of the project team, which had
many years of experience in the company and an extremely
good understanding of the systems. Some
of the finer details of the requirements, such as the reporting
requirements and the final policy
document wording, were not defined at this initial stage. The
outstanding requirements would be
agreed upon during the project, once the users had decided
exactly what they wanted in this regard.
Project Team Appointment
Peter was appointed as the overall project manager. Peter had
been with the company for 15 years and
been involved in numerous projects for new product
developments in the past. He knows the existing
systems intimately and had good working relationships with all
the various departments involved in
product development and launch. The project team appointed
consisted of people from various
departments, all of whom had been involved in previous product
development projects. Their
knowledge of the systems and applications is extensive. After
delivery of Module Two, Peter left due to
personal reasons.
Project Kick-off
The product development executive, the sponsor of the project,
chaired the project kick-off meeting,
held on May 5, 2015. She emphasized the importance of the
project to the company, as it would ensure
good returns by getting the new product to market before its
competitors. She stressed that the delivery
date must not be compromised in any way, as this would open
the doors for competitive products and
the opportunity would be missed. The project manager and the
team were asked to get busy
immediately with their planning, and a follow-up meeting was
set for August 5, 2015 to review the
project plans.
Project Plan Development
The project manager had been involved in many similar projects
in the past, and thus knew exactly what
the project entailed. For this reason the plans were based on
previous historical information of past
projects. The project plans included only the systems-related
work. The interfacing to other areas, such
as the legal department, marketing, and operations, would be
handled by the project manager at the
specific time required for their input. Project plans were drawn
up using a scheduling tool. The phases
and tasks were detailed, but resources were not allocated to the
tasks. Task dependencies were not put
into the plan.
Project Plan Management
Management of the project plan consisted of updating tasks with
their percentage complete on a
weekly basis. Record of actual hours spent on specific tasks was
deemed not necessary. Each resource
gave an estimate of the percentage complete for each task,
which was used to update the plan.
Resource availability was handled in an informal manner
whereby each resource gave feedback on a
weekly basis regarding his or her workload on the project and
other non-project work responsibilities,
such as systems maintenance.
Progress Reporting
Progress reports were produced every two weeks. These
consisted of a progress summary, deliverables
attained, percent complete, risks, issues, and cost information.
(See the most recent Medical IS Progress
Report below.) Minutes were kept for some meetings. (See the
most recent Meeting Minutes below.)
Progress for Period May 5, 2015 – August 5, 2015
Initial progress was good, with all team members working well
together. Programming started almost
immediately, since the team knew the systems so well that they
were able to make some of the
required changes immediately. Some issues were identified with
the user requirements, since not
enough detail was in the requirements document. These issues
were resolved between the
programmers and the users. Some of the programmers
experienced problems when they discovered
they were working on the wrong version of the user
requirements. This was resolved when the users
printed out the current version of the requirements for all the
team members to make sure they were
all working on the current version.
Progress was not as fast as desired, due mainly to users
changing their minds about the requirements.
The programmers were very accommodating with such changes
and tried their utmost to keep the users
satisfied. Unfortunately, the number of changes and additional
requirements requested by the users
caused the work to fall behind schedule. When some of the
programmers complained to the project
manager, he said that it was essential that users received what
they wanted, so their changes must be
accommodated, even if it meant having to work extra hours to
catch up.
The programming was also delayed from time to time due to
technical problems experienced with the
new development environment. The company did not have
anyone experienced in the new
development software, thus had to rely on vendor support,
which was a bit lacking due to their
commitments at other companies.
Progress for Period August 5, 2015 – October 5, 2015 (two
months before live date)
The sponsor became concerned with the project progress, since
she felt there was a risk of not meeting
the required delivery date. The programmers were working long
hours to try catch up on the project
work, as well as doing their required maintenance and problem
fixing of the live systems. The legal
department said that they may not be able to provide the policy
document wording in time for the live
date, due to other priorities. They said they may have been able
to if they had known about it sooner.
The user department said they may have a problem getting the
test packs ready for user testing, as
some staff were going on leave over the Thanksgiving period.
Initial testing revealed that the performance of some of the
modules was very slow. This was resolved to
some extent when it was found that some of the programmers
had used inefficient coding, as they were
new to the programming language being used. There were also a
number of bugs reported, one of
which causes the product to crash at least once a week. There
are numerous change requests submitted
by users for enhancements to the product.
Peter, the project manager, has left, and the project team is in
complete disarray, and there seem to be
issues between the architect and database administrators on just
how the database supports the vendor
reports. As of now the two areas are not working together to
develop solutions for the issues. There also
seems to be a loss of a defined testing strategy, which has
cropped concerns with development and user
acceptance. There is no existing method of capturing reported
issues, or how to handle changes.
Management is unhappy about the project and there is no
established communications method to
inform them about the project status. The project is over budget
by 20%. The vendor is asking for pre-
payment in order to deliver the third and final module for the
final payment of $75,000, which was 75%
of the total vendor cost. The module has not been tested yet.
There is no communications plan, no risk
plan, no systems implementation plan (to define how system
implementation testing is handled), and no
total cost of ownership (TCO) fee schedule. There is a conflict
within the project team (e.g., team
members have conflicting roles, or experience time pressure as
a result of working in two positions
within the organization simultaneously).
Medical IS Progress Report
Client VP Operations Project Number W1005
Project Medical IS Vendor Type of Project Development
Project Manager Peter Johnson Reporting Period Start:
End:
1 Progress Summary
Programming work is almost complete and testing has begun.
Unfortunately, it is going to take longer than planned to
complete the programming
due to changes requested by the users and errors made by the
programmers using the new programming language. We are
hoping that this time
will be caught up by working overtime and reducing the testing
time planned.
2 Major Activities Completed before Reporting Period
Commenced
2.1 Business case approved
2.2 User requirements document completed
2.3 Programming underway
2.4 Unit testing underway
2.5 Test pack compilation started
3 Major Activities during Reporting Period
3.1 Programming continuing
3.2 Unit testing underway
3.3 Test packs complete
3.4 Implementation plan started
3.5 Changes made per user requests to date
4
Deliverables and Milestones
No Description Baseline End
Date
Forecast or
Actual End Date
%
Complete
4.1 Initial project plan
4.2 Approved project charter
4.3 Program code
4.4 System testing
4.5 User acceptance testing
4.6 Go live
4.7 Post implementation audit
4.8 Project acceptance sign-off
5
Risks
Contingency Plan/Actions
Impact
(1-10)
Probability
(1-10)
Score
(I * P)
Actionee
Status
5.1 Delivery date may be
missed due to changes in
user requirements
Work overtime to catch up 8 5 40 PJ Open
5.2 Project team members
may take leave over the
Thanksgiving holidays
Plan leave into project
schedule
7 5 35 PJ Open
5.3 Other departments may
not have resources to do
the policy docs and
testing when required
Agree tasks with other
departments
8 6 48 PJ Open
6
Issues
Impact
(1-10)
Actionee
Due Date/
Status
Action
6.1 Changes to requirements requested by the users are
causing delays in project delivery
9 PJ Agree final requirements
with the users
6.2 Currently behind schedule with some tasks, but should be
able to catch up without affecting the scheduled delivery
date
9 PJ Work overtime
6.3 Get final policy document wording from legal
department
8 PJ Agree date with Legal Dept.
6.4 Make sure Testers are available for required testing dates 8
PJ Agree resources and dates for
testing with user departments
7 List of Scope Change Requests
No Date Description Client
Approval
Impact
7.1 No official change requests to date
8 Major Activities for Next Period
8.1 Complete programming
8.2 Complete and get approval for project charter
8.3 Start system testing
8.4 Start planning for user acceptance test (compile test plan)
8.5 Fix errors and omissions identified during testing
8.6 Compile and agree implementation plan
8 Budget Tracking
Task/Phase Planned Cost
(Baseline)
Actual Cost to
Date
Remaining
Cost
Estimate at
Completion
Percent
Variance
Medical IS Vendor 441,650 230,892 210,758 529,980 20%
Meeting Minutes
MEETING DATE: May 15, 2015
PROJECT: Medical IS Vendor
SUBJECT: Weekly Progress
ATTENDEES: James Weary (JW), Peter Johnson (PJ), Tim
Drew (TD), project team members
APOLOGIES: Wanda Jackson (Sponsor)
Outstanding from Previous Meeting’s Minutes
Item
Minute
Actionee
Status / Due Date
1. PJ to discuss user requirements changes impact with sponsor
PJ PJ could not get
meeting with sponsor
Meeting Minutes
Item
Minute
Actionee
Status / Due Date
1. Testing plan to be drawn up and testers allocated by the user
department PJ
2. Leave schedule to be drawn up for all project staff to assess
project schedule impact PJ
3. Legal department to give expected completion date for new
policy document wording PJ
4. Machine needs to be booked and set up for training of testers
and running of the user
acceptance test
JW
5. Testers to be identified by user departments and allocated for
testing period required TD
6. Current problems with system performance of the Java code
to be escalated to vendor for
urgent resolution
PJ
Scope Change Requests
Item
Change request description
Actionee
Due Date
Status
1. No official scope change requests to date
Next meeting: 06/01/2015 (3pm. – 4pm) - Meeting Room 2.3
The Case of the Troubled Health System Implementation
at Healthcare Unlimited, LLC
The Confidential Memo
Along with you welcoming papers, you received the following
confidential memo from the PROJECT
SPONSOR:
From: Project Sponsor, Healthcare Unlimited, LLC
To: IT Project Manager (you)
Date: September 4, 2015
Welcome to Healthcare Unlimited, LLC and congratulations on
accepting the project manager
position for the Medical IS project. It is my sincere hope that
your tenure with Healthcare
Unlimited, LLC will be both productive and rewarding. In this
letter you will find a list of several
critical barriers you need to consider and address as you take
charge of this troubled project.
1) Both your Architect and the Database Administrator
representative on your team
are very competent employees. Unfortunately, during the past
two months they
have created a difficult environment on the team that spurred
higher level of
conflict.
2) Senior management is quite unhappy with the dynamics of
the team and its
inability to address the internal conflict. The rest of the
organization has already
expressed concerns over the lack of motivation and tangible
results with the
team. As a result, you must take this into account if you choose
to restructure the
team.
3) The strategic plan for our company highlights the importance
of quality and time-
to-market of all our services. The board of directors is anxious
to see results with
the Medical IS project since it will have a large impact the
strategic direction of
the company.
My door is always open and I look forward to a productive
relationship.
Regards,
Your PROJECT SPONSOR
After reading the memo, you contact the PROJECT SPONSOR’s
administrative assistant to request your
first meeting with her as the new project manager of the
Medical IS project.
Meeting the PROJECT SPONSOR
During your meeting with the PROJECT SPONSOR you realize
that her job security hinges on your success
with the project.
You also find out that your team is not fully dedicated to the
project, but team members still spend half
of their time working on other duties in their departments.
Moreover, each one reports to a separate
manager in addition to you. The PROJECT SPONSOR notes:
“The first project manager never considered negotiating with
the various managers to acquire
additional team members from the legal, marketing, and
operations departments to be assigned
full time. He also didn’t consider the early warning signs that
the team conflict was escalating as
a result of their other duties. Projects do not start as ‘red’ and if
they do, they are doomed from
the start. I have to admit, I expected a lot more from him, but
instead felt mislead. At this point,
the board of directors is really unhappy with the lack of
progress on the project. We all need
someone who can take charge, motivate the crew, make any
changes necessary to set this
project on the correct path and ensure its success. I know this
will be a difficult task, but I am
confident in your ability to resolve the conflict on the team.
I also have to be honest with you. The previous project
manager complained about not having
control over the decision-making process in the team, because
of the conflict between the
Architect and the Database Administrators’ representative. In
fact, he mentioned that their
competitive and stubborn attitudes about who should actually
make decisions on the project
were ‘out of control.’ As a result, the morale of the team is low.
There is no sense of belonging.
I will support any changes you decide to make, but I want you
to be cautious and think several
moves ahead as to how each of your decisions will impact your
team and our organization. Also,
keep in mind, if you need to train any of your staff, I will
approve the training budget. You just
need to act soon.”
You ask about the skills of your team members. Your PROJECT
SPONSOR informs you that:
1) The Architect has the most technical expertise among the rest
of the team and has
been on several prior system integration projects. He was on the
original Medical IS
project team;
2) The Database Administrators’ representative has well
established political
connections in the organization, but lacks credibility among the
rest of the team
members. He has background in project management, but this is
his first technology
project at our company and he is the most recent addition to the
team;
3) The Operations representative has great initiative and
ambition to be on the project,
but her availability is very limited. She is well respected in the
organization for her
ability to round-the-troops behind a common vision. She was on
the original team
that procured Medical IS system contract and knows the most
common issues that
can occur with modifications to such systems. Her current direct
supervisor is flexible
when it comes down to ‘loaning’ her full time to the project, but
he needs to be
informed;
4) Your Marketing representative has great problem-solving
skills and an excellent
attention to detail. She was on several prior system integration
projects with our
company. She has previously worked in the Legal team for 3
years before moving to
the Marketing team.
You ask what immediate changes would you like your
PROJECT SPONSOR to see. She reflects:
“One of the most important things is to make sure that before
the project starts, you have a
good plan since a project that is off track costs more to recover
than later. At the present time,
the company is not capable if designating any more resources.
The way I see this, the number
one challenge is the team. You won’t be able to start this
project in isolation. The team is the
key! Yet, since the morale is low that by itself can kill the
project.”
You thank her and promise to provide her with status as soon as
you meet with your team and make a
decision. Next, you schedule a meeting with your team.
Meeting the Team
At your first team meeting, the Database Administrators’
representative show up late. Before you even
start the meeting, the Architect comments how important it is
for all to show up on time.
Database Administrators’ Representative:
“From the start, I know this is going to be a team-roast meeting
for me. Before you even start, I
have to say one thing, how do you expect me to make it on time
when yesterday I was handed
ten new requests and had four back-to-back meetings since 8AM
this morning? I can’t clone
myself and you know we are understaffed. This isn’t my first
team meeting and I understand the
importance of being here on time. Perhaps, you can speak with
my Manager next time and ask
him to take away some of these requests.”
Architect:
“We all have other responsibilities, but if we are not here on
time, we can’t finish on time and
then we are late for our other tasks. You were aware that the
meeting starts at 10AM. You knew
about it since yesterday. Also, this is not the first time you are
late-”
The Marketing Representative cuts the Architect short:
“I think we should hear what our new project manager has to
say. So perhaps you two can table
this discussion for later.”
The Database Administrators’ Representative:
“I am getting really tired of this. I can’t stand each time either
of you two (the Architect and the
Database Administrator’s Representatives) come into my office
and tell me what I should or
shouldn’t do. We already had this discussion once and I don’t
want to repeat myself. When I
have a priority request, all else is set aside. I don’t think this is
going to change, considering how
important some of these requests are for the future of the
company.”
The Marketing Representative:
“I have to say that without many of the software initiatives, the
company will have a hard time
retaining qualified staff to assist with the work on the requests.
The same is true for the
architecture design and for functional units such as Marketing
and Legal. Now, the Medical IS
project is not less important than your requests. In fact, it is
strategically aligned with our fiscal
year’s growth projections and if it fails, none of us will be
around to have this discussion again.
Architect turns to the Database Administrators’ Representative:
“The Design department is in the middle of system design for an
application to assist them with
the software roll-out process. I have been involved with it from
the start and can tell you that no
other member of that team is as problematic and as self-
centered as you. In fact, when the
schedule began to slip on that project, all team members
hunkered down and worked extra hard
to meet the established deadlines. We all pitched in and acted as
one unit. No other task was
more important than the project-”
Database Administrators’ Representative interrupts the
Architect:
“Wait a minute! You are misleading the rest of us again. ‘We’
on that project was you, the
Architect, and a member of the Documentations department plus
the complexity of that system
was so low that it hardly mattered to the company. It certainly
is nowhere near the caliber of this
project. Besides, if you knew anything about project
management, you’d know that the intent is
to break down the work into smaller packages and estimate it
properly. Your project manager
had no experience with this and he underestimated the work. As
a result, you all had to work
crazy hours to meet the deadline. I can’t stand incompetence
when it comes to project
management.”
At this point the Database Administrators’ Representative turns
to you and smirks.

More Related Content

Similar to Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx

RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docxRUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docxsusanschei
 
GSTi India Overview
GSTi India OverviewGSTi India Overview
GSTi India OverviewGSTi India
 
Great Eastern Duties
Great Eastern DutiesGreat Eastern Duties
Great Eastern DutiesBernard Quah
 
Lakshmi_Resume
Lakshmi_ResumeLakshmi_Resume
Lakshmi_ResumeVK Lakshmi
 
Ashutosh_Sharma_7 Yrs_Manual Testing
Ashutosh_Sharma_7 Yrs_Manual TestingAshutosh_Sharma_7 Yrs_Manual Testing
Ashutosh_Sharma_7 Yrs_Manual TestingAshutosh Sharma
 
Bhagesh_Resume_23042016
Bhagesh_Resume_23042016Bhagesh_Resume_23042016
Bhagesh_Resume_23042016bhagesh Nayak
 
Anitha_Resume_BigData
Anitha_Resume_BigDataAnitha_Resume_BigData
Anitha_Resume_BigDataAnitha Bade
 
SOFTWARE PROJECT MANAGEMENT TOOL PPT
SOFTWARE PROJECT MANAGEMENT TOOL PPTSOFTWARE PROJECT MANAGEMENT TOOL PPT
SOFTWARE PROJECT MANAGEMENT TOOL PPTSai Charan
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday DeploymentZaranTech LLC
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPlunkettz
 
COMP6214 Project 2.docx
COMP6214 Project 2.docxCOMP6214 Project 2.docx
COMP6214 Project 2.docxwrite31
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMProduct School
 
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docxUnit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docxwillcoxjanay
 
Sonu balasubramanian agile_qtp_selenium
Sonu balasubramanian  agile_qtp_seleniumSonu balasubramanian  agile_qtp_selenium
Sonu balasubramanian agile_qtp_seleniumSonu Balasubramanian
 

Similar to Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx (20)

Resume
ResumeResume
Resume
 
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docxRUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT                   .docx
RUNNING HEAD ERP SYSTEM IMPLIMENTATION PROJECT .docx
 
GSTi India Overview
GSTi India OverviewGSTi India Overview
GSTi India Overview
 
Great Eastern Duties
Great Eastern DutiesGreat Eastern Duties
Great Eastern Duties
 
Lakshmi_Resume
Lakshmi_ResumeLakshmi_Resume
Lakshmi_Resume
 
Ashutosh_Sharma_7 Yrs_Manual Testing
Ashutosh_Sharma_7 Yrs_Manual TestingAshutosh_Sharma_7 Yrs_Manual Testing
Ashutosh_Sharma_7 Yrs_Manual Testing
 
Bhagesh_Resume_23042016
Bhagesh_Resume_23042016Bhagesh_Resume_23042016
Bhagesh_Resume_23042016
 
Anitha_Resume_BigData
Anitha_Resume_BigDataAnitha_Resume_BigData
Anitha_Resume_BigData
 
VASUDEO RANE
VASUDEO RANEVASUDEO RANE
VASUDEO RANE
 
SOFTWARE PROJECT MANAGEMENT TOOL PPT
SOFTWARE PROJECT MANAGEMENT TOOL PPTSOFTWARE PROJECT MANAGEMENT TOOL PPT
SOFTWARE PROJECT MANAGEMENT TOOL PPT
 
6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment6 Steps to Confirm Successful Workday Deployment
6 Steps to Confirm Successful Workday Deployment
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
 
COMP6214 Project 2.docx
COMP6214 Project 2.docxCOMP6214 Project 2.docx
COMP6214 Project 2.docx
 
Swetha Nelluru
Swetha NelluruSwetha Nelluru
Swetha Nelluru
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
 
Sonali-resume
Sonali-resumeSonali-resume
Sonali-resume
 
myresume
myresumemyresume
myresume
 
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docxUnit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
 
Sonu balasubramanian agile_qtp_selenium
Sonu balasubramanian  agile_qtp_seleniumSonu balasubramanian  agile_qtp_selenium
Sonu balasubramanian agile_qtp_selenium
 

More from buffydtesurina

Create three classes for the words An abstract class called Word, a.docx
Create three classes for the words An abstract class called Word, a.docxCreate three classes for the words An abstract class called Word, a.docx
Create three classes for the words An abstract class called Word, a.docxbuffydtesurina
 
Create an imaginary person you want to write to in your journal. Alt.docx
Create an imaginary person you want to write to in your journal. Alt.docxCreate an imaginary person you want to write to in your journal. Alt.docx
Create an imaginary person you want to write to in your journal. Alt.docxbuffydtesurina
 
Create an environmental public health emergency plan for you as an i.docx
Create an environmental public health emergency plan for you as an i.docxCreate an environmental public health emergency plan for you as an i.docx
Create an environmental public health emergency plan for you as an i.docxbuffydtesurina
 
Create an elevator speech (a 30-second speech) that illustrates why .docx
Create an elevator speech (a 30-second speech) that illustrates why .docxCreate an elevator speech (a 30-second speech) that illustrates why .docx
Create an elevator speech (a 30-second speech) that illustrates why .docxbuffydtesurina
 
Create an Access database with the data given in Problem Exercise .docx
Create an Access database with the data given in Problem Exercise .docxCreate an Access database with the data given in Problem Exercise .docx
Create an Access database with the data given in Problem Exercise .docxbuffydtesurina
 
create avatar with adobe illustratorUsing the Basic Shapes and t.docx
create avatar with adobe illustratorUsing the Basic Shapes and t.docxcreate avatar with adobe illustratorUsing the Basic Shapes and t.docx
create avatar with adobe illustratorUsing the Basic Shapes and t.docxbuffydtesurina
 
Create an argument about the supernatural facets of the natural worl.docx
Create an argument about the supernatural facets of the natural worl.docxCreate an argument about the supernatural facets of the natural worl.docx
Create an argument about the supernatural facets of the natural worl.docxbuffydtesurina
 
Create a SIOP lesson plan that integrates students reading levels.docx
Create a SIOP lesson plan that integrates students reading levels.docxCreate a SIOP lesson plan that integrates students reading levels.docx
Create a SIOP lesson plan that integrates students reading levels.docxbuffydtesurina
 
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docx
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docxCreate an 8- to 10-slide Microsoft® PowerPoint® presentati.docx
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docxbuffydtesurina
 
Create a Problem Statement for a study that explore Compensation I.docx
Create a Problem Statement for a study that explore Compensation I.docxCreate a Problem Statement for a study that explore Compensation I.docx
Create a Problem Statement for a study that explore Compensation I.docxbuffydtesurina
 
Create a scenario that demonstrates a poor exchange of informa.docx
Create a scenario that demonstrates a poor exchange of informa.docxCreate a scenario that demonstrates a poor exchange of informa.docx
Create a scenario that demonstrates a poor exchange of informa.docxbuffydtesurina
 
Create a mobile application using Android™ Studio that saves d.docx
Create a mobile application using Android™ Studio that saves d.docxCreate a mobile application using Android™ Studio that saves d.docx
Create a mobile application using Android™ Studio that saves d.docxbuffydtesurina
 
Create a power point presentation on the subject of Banruptcy. Descr.docx
Create a power point presentation on the subject of Banruptcy. Descr.docxCreate a power point presentation on the subject of Banruptcy. Descr.docx
Create a power point presentation on the subject of Banruptcy. Descr.docxbuffydtesurina
 
Create a Microsoft PowerPoint presentation explaining the various ty.docx
Create a Microsoft PowerPoint presentation explaining the various ty.docxCreate a Microsoft PowerPoint presentation explaining the various ty.docx
Create a Microsoft PowerPoint presentation explaining the various ty.docxbuffydtesurina
 
Create a PowerPoint® presentation of 9 to 12 slides that you w.docx
Create a PowerPoint® presentation of 9 to 12 slides that you w.docxCreate a PowerPoint® presentation of 9 to 12 slides that you w.docx
Create a PowerPoint® presentation of 9 to 12 slides that you w.docxbuffydtesurina
 
Create a PowerPoint presentation to analyzes the objectives of perso.docx
Create a PowerPoint presentation to analyzes the objectives of perso.docxCreate a PowerPoint presentation to analyzes the objectives of perso.docx
Create a PowerPoint presentation to analyzes the objectives of perso.docxbuffydtesurina
 
Create a PowerPoint presentation with 12 to 15 slides that addresses.docx
Create a PowerPoint presentation with 12 to 15 slides that addresses.docxCreate a PowerPoint presentation with 12 to 15 slides that addresses.docx
Create a PowerPoint presentation with 12 to 15 slides that addresses.docxbuffydtesurina
 
Create a PowerPoint presentation that is seven slides in length, inc.docx
Create a PowerPoint presentation that is seven slides in length, inc.docxCreate a PowerPoint presentation that is seven slides in length, inc.docx
Create a PowerPoint presentation that is seven slides in length, inc.docxbuffydtesurina
 
Create a power point presentationAttached is the assignment fo.docx
Create a power point presentationAttached is the assignment fo.docxCreate a power point presentationAttached is the assignment fo.docx
Create a power point presentationAttached is the assignment fo.docxbuffydtesurina
 
Create a Policy Memo that explain and assess the advantages and chal.docx
Create a Policy Memo that explain and assess the advantages and chal.docxCreate a Policy Memo that explain and assess the advantages and chal.docx
Create a Policy Memo that explain and assess the advantages and chal.docxbuffydtesurina
 

More from buffydtesurina (20)

Create three classes for the words An abstract class called Word, a.docx
Create three classes for the words An abstract class called Word, a.docxCreate three classes for the words An abstract class called Word, a.docx
Create three classes for the words An abstract class called Word, a.docx
 
Create an imaginary person you want to write to in your journal. Alt.docx
Create an imaginary person you want to write to in your journal. Alt.docxCreate an imaginary person you want to write to in your journal. Alt.docx
Create an imaginary person you want to write to in your journal. Alt.docx
 
Create an environmental public health emergency plan for you as an i.docx
Create an environmental public health emergency plan for you as an i.docxCreate an environmental public health emergency plan for you as an i.docx
Create an environmental public health emergency plan for you as an i.docx
 
Create an elevator speech (a 30-second speech) that illustrates why .docx
Create an elevator speech (a 30-second speech) that illustrates why .docxCreate an elevator speech (a 30-second speech) that illustrates why .docx
Create an elevator speech (a 30-second speech) that illustrates why .docx
 
Create an Access database with the data given in Problem Exercise .docx
Create an Access database with the data given in Problem Exercise .docxCreate an Access database with the data given in Problem Exercise .docx
Create an Access database with the data given in Problem Exercise .docx
 
create avatar with adobe illustratorUsing the Basic Shapes and t.docx
create avatar with adobe illustratorUsing the Basic Shapes and t.docxcreate avatar with adobe illustratorUsing the Basic Shapes and t.docx
create avatar with adobe illustratorUsing the Basic Shapes and t.docx
 
Create an argument about the supernatural facets of the natural worl.docx
Create an argument about the supernatural facets of the natural worl.docxCreate an argument about the supernatural facets of the natural worl.docx
Create an argument about the supernatural facets of the natural worl.docx
 
Create a SIOP lesson plan that integrates students reading levels.docx
Create a SIOP lesson plan that integrates students reading levels.docxCreate a SIOP lesson plan that integrates students reading levels.docx
Create a SIOP lesson plan that integrates students reading levels.docx
 
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docx
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docxCreate an 8- to 10-slide Microsoft® PowerPoint® presentati.docx
Create an 8- to 10-slide Microsoft® PowerPoint® presentati.docx
 
Create a Problem Statement for a study that explore Compensation I.docx
Create a Problem Statement for a study that explore Compensation I.docxCreate a Problem Statement for a study that explore Compensation I.docx
Create a Problem Statement for a study that explore Compensation I.docx
 
Create a scenario that demonstrates a poor exchange of informa.docx
Create a scenario that demonstrates a poor exchange of informa.docxCreate a scenario that demonstrates a poor exchange of informa.docx
Create a scenario that demonstrates a poor exchange of informa.docx
 
Create a mobile application using Android™ Studio that saves d.docx
Create a mobile application using Android™ Studio that saves d.docxCreate a mobile application using Android™ Studio that saves d.docx
Create a mobile application using Android™ Studio that saves d.docx
 
Create a power point presentation on the subject of Banruptcy. Descr.docx
Create a power point presentation on the subject of Banruptcy. Descr.docxCreate a power point presentation on the subject of Banruptcy. Descr.docx
Create a power point presentation on the subject of Banruptcy. Descr.docx
 
Create a Microsoft PowerPoint presentation explaining the various ty.docx
Create a Microsoft PowerPoint presentation explaining the various ty.docxCreate a Microsoft PowerPoint presentation explaining the various ty.docx
Create a Microsoft PowerPoint presentation explaining the various ty.docx
 
Create a PowerPoint® presentation of 9 to 12 slides that you w.docx
Create a PowerPoint® presentation of 9 to 12 slides that you w.docxCreate a PowerPoint® presentation of 9 to 12 slides that you w.docx
Create a PowerPoint® presentation of 9 to 12 slides that you w.docx
 
Create a PowerPoint presentation to analyzes the objectives of perso.docx
Create a PowerPoint presentation to analyzes the objectives of perso.docxCreate a PowerPoint presentation to analyzes the objectives of perso.docx
Create a PowerPoint presentation to analyzes the objectives of perso.docx
 
Create a PowerPoint presentation with 12 to 15 slides that addresses.docx
Create a PowerPoint presentation with 12 to 15 slides that addresses.docxCreate a PowerPoint presentation with 12 to 15 slides that addresses.docx
Create a PowerPoint presentation with 12 to 15 slides that addresses.docx
 
Create a PowerPoint presentation that is seven slides in length, inc.docx
Create a PowerPoint presentation that is seven slides in length, inc.docxCreate a PowerPoint presentation that is seven slides in length, inc.docx
Create a PowerPoint presentation that is seven slides in length, inc.docx
 
Create a power point presentationAttached is the assignment fo.docx
Create a power point presentationAttached is the assignment fo.docxCreate a power point presentationAttached is the assignment fo.docx
Create a power point presentationAttached is the assignment fo.docx
 
Create a Policy Memo that explain and assess the advantages and chal.docx
Create a Policy Memo that explain and assess the advantages and chal.docxCreate a Policy Memo that explain and assess the advantages and chal.docx
Create a Policy Memo that explain and assess the advantages and chal.docx
 

Recently uploaded

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 

Recently uploaded (20)

INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 

Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical .docx

  • 1. Medical IS Vendor Medical IS Vendor Medical IS Vendor Medical IS Vendor –––– Project Project Project Project CharterCharterCharterCharter Project Name: Health System ImplementationProject Name: Health System ImplementationProject Name: Health System ImplementationProject Name: Health System Implementation
  • 2. PJM 6140 Troubled Health System Project Case Study Background Healthcare Unlimited, LLC a leading health services company, embarked on a new product development project. Healthcare Unlimited needs to expand its clinical data warehouse (CDW) to ingest third-party data feeds from medical IS vendor and onsite clinic data to incorporate this information to downstream employer group analytics and reporting processes. This expansion will also be used to develop new activity reports to message value on these products. The nature of the company’s business is that it operates in an extremely competitive environment that necessitates fast delivery to market so as to prevent competitor companies from gaining dominant market share with similar competitive products. Therefore, the key success factors of the project were time to market and quality. Cost of delivery was not a major concern.
  • 3. Scope The scope of the project was to create a modular software package to handle medical IS vendor data to ensure appropriate preventative care is being tracked for members, including the systems changes, the vendor medical IS database tables, and medical IS vendor reporting. The project was divided into modules consisting of: medical IS DB tables, promote tables, and medical IS vendor reporting. A project manager was appointed, but has since left due to personal reasons. Time Scales The launch date was set as December 1, 2015. The product had to be ready for launch on this date, as all the marketing material would reflect this date and the launch had to precede the launch of similar products from competitors. The project kickoff was May 5, 2015. The tasks that had been completed prior to May 5, 2015 were the business case compilation and approval and the project team establishment.
  • 4. Technology The systems development was to be done using the MS Visual Studio programming language and SQL environment, which was new to the development team. The developers were sent on MS Visual Studio programming training two weeks prior to the project start. The developers were used to working in a Java programming environment and had not worked with any MS-oriented languages before. The new medical IS vendor reports will integrate into the existing system located behind the intranet. These new reports, unlike the existing reports, will utilize both SQL Server and Teradata. SQL Server will control the security access and parameter selection for the reports. The application will then send the selected parameters to Teradata in order to populate the body of the report. Infrastructure Database Servers • MS SQL Server 2008 R2 • Teradata 14
  • 5. Reporting Servers • The system will use an SSRS deployment server. Development Tools • MS Visual Studio 2008 Shell • SQL Server Business Intelligence Development Studio • SQL Server Management Studio Business Requirements The current application will display the medical IS vendor reports. The system generates SQL Server Reporting Services (SSRS) reports based on user-selected parameters. Users can choose to view reports in three formats: Excel 97-2003 (XLS), Portable Document Format (PDF), or Comma Separated Value (CSV). The exported data within Excel or CSV files will contain “user- friendly” headers and not database column headers.
  • 6. Scripts will execute on a weekly basis to import the following vendor sources into the target system: • Chip Rewards • Spire Scripts will execute on a monthly basis to import the following vendor sources into the target system: MDLive. Case Study Summary of Events Business Case Development The product development department developed the business case for the proposed new product, including projected cost/benefit analysis based on previous similar products and current market share. The business case was reviewed by executive management and approved. Requirements Definition
  • 7. The product development department developed the requirements specification for the new product. These requirements were specified based on the understanding level of the project team, which had many years of experience in the company and an extremely good understanding of the systems. Some of the finer details of the requirements, such as the reporting requirements and the final policy document wording, were not defined at this initial stage. The outstanding requirements would be agreed upon during the project, once the users had decided exactly what they wanted in this regard. Project Team Appointment Peter was appointed as the overall project manager. Peter had been with the company for 15 years and been involved in numerous projects for new product developments in the past. He knows the existing systems intimately and had good working relationships with all the various departments involved in product development and launch. The project team appointed consisted of people from various departments, all of whom had been involved in previous product development projects. Their
  • 8. knowledge of the systems and applications is extensive. After delivery of Module Two, Peter left due to personal reasons. Project Kick-off The product development executive, the sponsor of the project, chaired the project kick-off meeting, held on May 5, 2015. She emphasized the importance of the project to the company, as it would ensure good returns by getting the new product to market before its competitors. She stressed that the delivery date must not be compromised in any way, as this would open the doors for competitive products and the opportunity would be missed. The project manager and the team were asked to get busy immediately with their planning, and a follow-up meeting was set for August 5, 2015 to review the project plans. Project Plan Development The project manager had been involved in many similar projects in the past, and thus knew exactly what the project entailed. For this reason the plans were based on
  • 9. previous historical information of past projects. The project plans included only the systems-related work. The interfacing to other areas, such as the legal department, marketing, and operations, would be handled by the project manager at the specific time required for their input. Project plans were drawn up using a scheduling tool. The phases and tasks were detailed, but resources were not allocated to the tasks. Task dependencies were not put into the plan. Project Plan Management Management of the project plan consisted of updating tasks with their percentage complete on a weekly basis. Record of actual hours spent on specific tasks was deemed not necessary. Each resource gave an estimate of the percentage complete for each task, which was used to update the plan. Resource availability was handled in an informal manner whereby each resource gave feedback on a weekly basis regarding his or her workload on the project and other non-project work responsibilities,
  • 10. such as systems maintenance. Progress Reporting Progress reports were produced every two weeks. These consisted of a progress summary, deliverables attained, percent complete, risks, issues, and cost information. (See the most recent Medical IS Progress Report below.) Minutes were kept for some meetings. (See the most recent Meeting Minutes below.) Progress for Period May 5, 2015 – August 5, 2015 Initial progress was good, with all team members working well together. Programming started almost immediately, since the team knew the systems so well that they were able to make some of the required changes immediately. Some issues were identified with the user requirements, since not enough detail was in the requirements document. These issues were resolved between the programmers and the users. Some of the programmers experienced problems when they discovered they were working on the wrong version of the user requirements. This was resolved when the users
  • 11. printed out the current version of the requirements for all the team members to make sure they were all working on the current version. Progress was not as fast as desired, due mainly to users changing their minds about the requirements. The programmers were very accommodating with such changes and tried their utmost to keep the users satisfied. Unfortunately, the number of changes and additional requirements requested by the users caused the work to fall behind schedule. When some of the programmers complained to the project manager, he said that it was essential that users received what they wanted, so their changes must be accommodated, even if it meant having to work extra hours to catch up. The programming was also delayed from time to time due to technical problems experienced with the new development environment. The company did not have anyone experienced in the new development software, thus had to rely on vendor support, which was a bit lacking due to their commitments at other companies.
  • 12. Progress for Period August 5, 2015 – October 5, 2015 (two months before live date) The sponsor became concerned with the project progress, since she felt there was a risk of not meeting the required delivery date. The programmers were working long hours to try catch up on the project work, as well as doing their required maintenance and problem fixing of the live systems. The legal department said that they may not be able to provide the policy document wording in time for the live date, due to other priorities. They said they may have been able to if they had known about it sooner. The user department said they may have a problem getting the test packs ready for user testing, as some staff were going on leave over the Thanksgiving period. Initial testing revealed that the performance of some of the modules was very slow. This was resolved to some extent when it was found that some of the programmers had used inefficient coding, as they were new to the programming language being used. There were also a number of bugs reported, one of which causes the product to crash at least once a week. There are numerous change requests submitted
  • 13. by users for enhancements to the product. Peter, the project manager, has left, and the project team is in complete disarray, and there seem to be issues between the architect and database administrators on just how the database supports the vendor reports. As of now the two areas are not working together to develop solutions for the issues. There also seems to be a loss of a defined testing strategy, which has cropped concerns with development and user acceptance. There is no existing method of capturing reported issues, or how to handle changes. Management is unhappy about the project and there is no established communications method to inform them about the project status. The project is over budget by 20%. The vendor is asking for pre- payment in order to deliver the third and final module for the final payment of $75,000, which was 75% of the total vendor cost. The module has not been tested yet. There is no communications plan, no risk plan, no systems implementation plan (to define how system
  • 14. implementation testing is handled), and no total cost of ownership (TCO) fee schedule. There is a conflict within the project team (e.g., team members have conflicting roles, or experience time pressure as a result of working in two positions within the organization simultaneously). Medical IS Progress Report Client VP Operations Project Number W1005 Project Medical IS Vendor Type of Project Development Project Manager Peter Johnson Reporting Period Start: End: 1 Progress Summary Programming work is almost complete and testing has begun. Unfortunately, it is going to take longer than planned to complete the programming due to changes requested by the users and errors made by the programmers using the new programming language. We are
  • 15. hoping that this time will be caught up by working overtime and reducing the testing time planned. 2 Major Activities Completed before Reporting Period Commenced 2.1 Business case approved 2.2 User requirements document completed 2.3 Programming underway 2.4 Unit testing underway 2.5 Test pack compilation started 3 Major Activities during Reporting Period 3.1 Programming continuing 3.2 Unit testing underway 3.3 Test packs complete 3.4 Implementation plan started 3.5 Changes made per user requests to date 4
  • 16. Deliverables and Milestones No Description Baseline End Date Forecast or Actual End Date % Complete 4.1 Initial project plan 4.2 Approved project charter 4.3 Program code 4.4 System testing 4.5 User acceptance testing 4.6 Go live 4.7 Post implementation audit 4.8 Project acceptance sign-off 5 Risks
  • 17. Contingency Plan/Actions Impact (1-10) Probability (1-10) Score (I * P) Actionee Status 5.1 Delivery date may be missed due to changes in user requirements Work overtime to catch up 8 5 40 PJ Open 5.2 Project team members may take leave over the Thanksgiving holidays
  • 18. Plan leave into project schedule 7 5 35 PJ Open 5.3 Other departments may not have resources to do the policy docs and testing when required Agree tasks with other departments 8 6 48 PJ Open 6 Issues Impact (1-10)
  • 19. Actionee Due Date/ Status Action 6.1 Changes to requirements requested by the users are causing delays in project delivery 9 PJ Agree final requirements with the users 6.2 Currently behind schedule with some tasks, but should be able to catch up without affecting the scheduled delivery date 9 PJ Work overtime 6.3 Get final policy document wording from legal department 8 PJ Agree date with Legal Dept. 6.4 Make sure Testers are available for required testing dates 8 PJ Agree resources and dates for
  • 20. testing with user departments 7 List of Scope Change Requests No Date Description Client Approval Impact 7.1 No official change requests to date 8 Major Activities for Next Period 8.1 Complete programming 8.2 Complete and get approval for project charter 8.3 Start system testing 8.4 Start planning for user acceptance test (compile test plan) 8.5 Fix errors and omissions identified during testing 8.6 Compile and agree implementation plan 8 Budget Tracking Task/Phase Planned Cost (Baseline) Actual Cost to
  • 21. Date Remaining Cost Estimate at Completion Percent Variance Medical IS Vendor 441,650 230,892 210,758 529,980 20% Meeting Minutes MEETING DATE: May 15, 2015 PROJECT: Medical IS Vendor SUBJECT: Weekly Progress ATTENDEES: James Weary (JW), Peter Johnson (PJ), Tim Drew (TD), project team members APOLOGIES: Wanda Jackson (Sponsor)
  • 22. Outstanding from Previous Meeting’s Minutes Item Minute Actionee Status / Due Date 1. PJ to discuss user requirements changes impact with sponsor PJ PJ could not get meeting with sponsor Meeting Minutes Item Minute Actionee Status / Due Date
  • 23. 1. Testing plan to be drawn up and testers allocated by the user department PJ 2. Leave schedule to be drawn up for all project staff to assess project schedule impact PJ 3. Legal department to give expected completion date for new policy document wording PJ 4. Machine needs to be booked and set up for training of testers and running of the user acceptance test JW 5. Testers to be identified by user departments and allocated for testing period required TD 6. Current problems with system performance of the Java code to be escalated to vendor for urgent resolution PJ Scope Change Requests Item Change request description
  • 24. Actionee Due Date Status 1. No official scope change requests to date Next meeting: 06/01/2015 (3pm. – 4pm) - Meeting Room 2.3 The Case of the Troubled Health System Implementation at Healthcare Unlimited, LLC The Confidential Memo Along with you welcoming papers, you received the following confidential memo from the PROJECT SPONSOR: From: Project Sponsor, Healthcare Unlimited, LLC To: IT Project Manager (you) Date: September 4, 2015
  • 25. Welcome to Healthcare Unlimited, LLC and congratulations on accepting the project manager position for the Medical IS project. It is my sincere hope that your tenure with Healthcare Unlimited, LLC will be both productive and rewarding. In this letter you will find a list of several critical barriers you need to consider and address as you take charge of this troubled project. 1) Both your Architect and the Database Administrator representative on your team are very competent employees. Unfortunately, during the past two months they have created a difficult environment on the team that spurred higher level of conflict. 2) Senior management is quite unhappy with the dynamics of the team and its inability to address the internal conflict. The rest of the organization has already expressed concerns over the lack of motivation and tangible results with the team. As a result, you must take this into account if you choose to restructure the
  • 26. team. 3) The strategic plan for our company highlights the importance of quality and time- to-market of all our services. The board of directors is anxious to see results with the Medical IS project since it will have a large impact the strategic direction of the company. My door is always open and I look forward to a productive relationship. Regards, Your PROJECT SPONSOR After reading the memo, you contact the PROJECT SPONSOR’s administrative assistant to request your first meeting with her as the new project manager of the Medical IS project. Meeting the PROJECT SPONSOR During your meeting with the PROJECT SPONSOR you realize
  • 27. that her job security hinges on your success with the project. You also find out that your team is not fully dedicated to the project, but team members still spend half of their time working on other duties in their departments. Moreover, each one reports to a separate manager in addition to you. The PROJECT SPONSOR notes: “The first project manager never considered negotiating with the various managers to acquire additional team members from the legal, marketing, and operations departments to be assigned full time. He also didn’t consider the early warning signs that the team conflict was escalating as a result of their other duties. Projects do not start as ‘red’ and if they do, they are doomed from the start. I have to admit, I expected a lot more from him, but instead felt mislead. At this point, the board of directors is really unhappy with the lack of progress on the project. We all need someone who can take charge, motivate the crew, make any changes necessary to set this project on the correct path and ensure its success. I know this will be a difficult task, but I am
  • 28. confident in your ability to resolve the conflict on the team. I also have to be honest with you. The previous project manager complained about not having control over the decision-making process in the team, because of the conflict between the Architect and the Database Administrators’ representative. In fact, he mentioned that their competitive and stubborn attitudes about who should actually make decisions on the project were ‘out of control.’ As a result, the morale of the team is low. There is no sense of belonging. I will support any changes you decide to make, but I want you to be cautious and think several moves ahead as to how each of your decisions will impact your team and our organization. Also, keep in mind, if you need to train any of your staff, I will approve the training budget. You just need to act soon.” You ask about the skills of your team members. Your PROJECT SPONSOR informs you that: 1) The Architect has the most technical expertise among the rest of the team and has
  • 29. been on several prior system integration projects. He was on the original Medical IS project team; 2) The Database Administrators’ representative has well established political connections in the organization, but lacks credibility among the rest of the team members. He has background in project management, but this is his first technology project at our company and he is the most recent addition to the team; 3) The Operations representative has great initiative and ambition to be on the project, but her availability is very limited. She is well respected in the organization for her ability to round-the-troops behind a common vision. She was on the original team that procured Medical IS system contract and knows the most common issues that can occur with modifications to such systems. Her current direct supervisor is flexible when it comes down to ‘loaning’ her full time to the project, but
  • 30. he needs to be informed; 4) Your Marketing representative has great problem-solving skills and an excellent attention to detail. She was on several prior system integration projects with our company. She has previously worked in the Legal team for 3 years before moving to the Marketing team. You ask what immediate changes would you like your PROJECT SPONSOR to see. She reflects: “One of the most important things is to make sure that before the project starts, you have a good plan since a project that is off track costs more to recover than later. At the present time, the company is not capable if designating any more resources. The way I see this, the number one challenge is the team. You won’t be able to start this project in isolation. The team is the key! Yet, since the morale is low that by itself can kill the project.” You thank her and promise to provide her with status as soon as
  • 31. you meet with your team and make a decision. Next, you schedule a meeting with your team. Meeting the Team At your first team meeting, the Database Administrators’ representative show up late. Before you even start the meeting, the Architect comments how important it is for all to show up on time. Database Administrators’ Representative: “From the start, I know this is going to be a team-roast meeting for me. Before you even start, I have to say one thing, how do you expect me to make it on time when yesterday I was handed ten new requests and had four back-to-back meetings since 8AM this morning? I can’t clone myself and you know we are understaffed. This isn’t my first team meeting and I understand the importance of being here on time. Perhaps, you can speak with my Manager next time and ask him to take away some of these requests.” Architect:
  • 32. “We all have other responsibilities, but if we are not here on time, we can’t finish on time and then we are late for our other tasks. You were aware that the meeting starts at 10AM. You knew about it since yesterday. Also, this is not the first time you are late-” The Marketing Representative cuts the Architect short: “I think we should hear what our new project manager has to say. So perhaps you two can table this discussion for later.” The Database Administrators’ Representative: “I am getting really tired of this. I can’t stand each time either of you two (the Architect and the Database Administrator’s Representatives) come into my office and tell me what I should or shouldn’t do. We already had this discussion once and I don’t want to repeat myself. When I have a priority request, all else is set aside. I don’t think this is going to change, considering how
  • 33. important some of these requests are for the future of the company.” The Marketing Representative: “I have to say that without many of the software initiatives, the company will have a hard time retaining qualified staff to assist with the work on the requests. The same is true for the architecture design and for functional units such as Marketing and Legal. Now, the Medical IS project is not less important than your requests. In fact, it is strategically aligned with our fiscal year’s growth projections and if it fails, none of us will be around to have this discussion again. Architect turns to the Database Administrators’ Representative: “The Design department is in the middle of system design for an application to assist them with the software roll-out process. I have been involved with it from the start and can tell you that no other member of that team is as problematic and as self- centered as you. In fact, when the schedule began to slip on that project, all team members hunkered down and worked extra hard
  • 34. to meet the established deadlines. We all pitched in and acted as one unit. No other task was more important than the project-” Database Administrators’ Representative interrupts the Architect: “Wait a minute! You are misleading the rest of us again. ‘We’ on that project was you, the Architect, and a member of the Documentations department plus the complexity of that system was so low that it hardly mattered to the company. It certainly is nowhere near the caliber of this project. Besides, if you knew anything about project management, you’d know that the intent is to break down the work into smaller packages and estimate it properly. Your project manager had no experience with this and he underestimated the work. As a result, you all had to work crazy hours to meet the deadline. I can’t stand incompetence when it comes to project management.” At this point the Database Administrators’ Representative turns
  • 35. to you and smirks.