5. We are going to tell about….
Information
Details
1
Project
Management
Gantt Chart
2
Pert
Calculation
3
Dependency
Between
tasks
4
Network
Diagram
&
Ultimate
result
5
6. Information Details
Operational
InformationNeeded for day to day operations
of the organization.
Strategic
InformationNeeded for long range planning
and directions. This is less
structured.
Tactical
InformationNeeded to take short range
decisions to improve profitability
and performance.
Statutory
InformationNeeded by law to sent to
government authorities.
Type of
Information
8. Tactical Information
Tactical
Information
Ensure the job
opportunities
Restrict the discipline
to students, faculties
and employees
Moderate all systems
Collect tuition fee from all
students in time
Spread reputation of
university
Admit brilliant students
9. Strategic Information
Tuition fee should be affordable
for students
Enhance the job fair
programs regular
Increase Research
programs. This will help to
improve the rank of the
university
10. Statutory Information
Income tax account
Provide to government all accounts information
which can give a clearance to university.
Because, university is a non-profitable
organization.
12. Pert Calculation
Activity
Time Estimate(In weeks) Expected
Time(E.T)
𝒐 + 𝟒𝒓 + 𝒑
𝟔
Optimisitic
O
Realistic
r
Pessimistic
p
Material Collection 1 3 5 3
Planning & Design 1 2 3 2
Database Design 2 4 6 4
Cloud System
Management
3 4 5 4
Web Design 3 5 7 5
Web Development 5 7 9 7
Security Ensuring 3 4 5 4
Data Entry 2 3 4 3
Testing 3 4 5 4
Installation 2 2 2 2
Training 2 3 4 3
13. Dependency Between tasks
Activity Preceding Activity Expected Time(Week)
(A)Material Collection - 3
(B)Planning & Design A 2
(C)Database Design B 4
(D)Cloud System Management C 4
(E)Web Design B 5
(F)Web Development B 7
(G)Security Ensuring B 4
(H)Data Entry G 3
(I)Testing D,E,F,H 4
(J)Installation I 2
(K)Training J 3
15. Sales Chart
Ultimate
Result
Applying Formula
We need to match the following
conditions for identifying critical path
1. Earliest start time = Latest start time
2. Earliest finish time = Latest finish time
Duration
Project time = 22 weeks.
Critical Path
0 1 2 3 4 6 7 8 has
following condition. So that, it is the
critical path for this project.
Critical & Non-critical
Activies The critical activities are A, B, C, D, I, J, K.
The non-critical activities are E, G, H