SlideShare a Scribd company logo
1 of 91
Download to read offline
1
INTEGRITY PROBLEMS OF CONCRETE PILES
ENGINEERSTALK
Mohammad Alhusein, PhD
Managing Partner
M: +971 552592001
E: malhusein@superarc.net
W: www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
www.superarc.net
WEBINAR OUTLINE
INTEGRITY PROBLEMS OF CONCRETE PILES
2
www.superarc.net
 Introduction
 Common Defective Construction for Bored Piles
 Boring Problems
 Improper drilled shaft stabilization method and procedure
 Inadequate or poor base cleaning method
 Reinforcement cage is not properly fabricated
 Poor Concreting Technique
 Pile Testing — Anomalies, Flaws and Defects
 PIT motivation and advantages
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
3
www.superarc.net
 Introduction
INTEGRITY PROBLEMS OF CONCRETE PILES
4
www.superarc.net
Ultimate Bearing Capacity - Static
Formula Method (Qu = Qp + Qs)
Embedded
Length
= D
Qu = Ultimate Bearing Capacity
Qs = fAs
f = Unit Frictional
Resistance
AS = Shaft Area
qP = Unit Bearing
Capacity
AP = Area of Point
QP = qPAP
INTEGRITY PROBLEMS OF CONCRETE PILES
5
www.superarc.net
Static Pile Capacity
INTEGRITY PROBLEMS OF CONCRETE PILES
6
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
7
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
8
www.superarc.net
 Common Defective Construction for Bored Piles
Boring Problems
Improper drilled shaft stabilization method and procedure
Inadequate or poor base cleaning method
Reinforcement cage is not properly fabricated
Poor Concreting Technique
INTEGRITY PROBLEMS OF CONCRETE PILES
9
www.superarc.net
 Soil collapse is common at the
transition between compacted
Soil Layers and the less
compacted Layers.
 During a vibration, it is hard to
protect the hole from mud.
Because of ground water and
the firm fine sand that lie below
it, high pressure is needed to
bore the piles, causing vibration
and soil collapse.
Boring Problems
INTEGRITY PROBLEMS OF CONCRETE PILES
10
www.superarc.net
Improper drilled shaft stabilization method and procedure
Shaft Friction: Load / Settlement Curves – After Burland- CIRIA PG3
INTEGRITY PROBLEMS OF CONCRETE PILES
11
www.superarc.net
CIRIA PG3
Results of element bottom cleaning (including measured
bottom sediment thickness using a Shaft Inspection
Device (SID) prior to reinforcing steel placement and
concreting.
The thickness of sediment shall be measured at four
locations around the perimeter and one at the center of
the pile using a Shaft Inspection Device (SID). The
maximum allowed thickness of debris shall be 50 mm
and the average shall not exceed 25 mm at the time of
concreting.
INTEGRITY PROBLEMS OF CONCRETE PILES
12
www.superarc.net
Bentonite to comply with ACI 336.1-01
“Specification for the Construction of Drilled Piers”
INTEGRITY PROBLEMS OF CONCRETE PILES
13
www.superarc.net
CIRIA PG3
INTEGRITY PROBLEMS OF CONCRETE PILES
14
www.superarc.net
Sieve Zone-I Zone-II Zone-III Zone-IV
10mm 100 100 100 100
4.75mm 90-100 90-100 90-100 95-100
2.36mm 60-95 75-100 85-100 95-100
1.18mm 30-70 55-90 75-100 90-100
600mic 15-34 35-59 60-79 80-100
300mic 5-20 8-30 12-40 15-50
150mic 0-10 0-10 0-10 0-15
FINE AGGREGATES (FA) (SAND)
FA can be natural sand or crushed sand (produced by crushing rock
pieces), most of which passes 4.75mm and is governed by IS: 383-1970
sieve. It shall satisfy any of the following grading requirements.
INTEGRITY PROBLEMS OF CONCRETE PILES
15
www.superarc.net
CIRIA PG3
INTEGRITY PROBLEMS OF CONCRETE PILES
16
www.superarc.net
CIRIA R144-2
CIRIA R144-2
INTEGRITY PROBLEMS OF CONCRETE PILES
17
www.superarc.net
CIRIA R144-2
INTEGRITY PROBLEMS OF CONCRETE PILES
18
www.superarc.net
CIRIA R144-2
CIRIA PG7
INTEGRITY PROBLEMS OF CONCRETE PILES
19
www.superarc.net
CIRIA PG7
INTEGRITY PROBLEMS OF CONCRETE PILES
20
www.superarc.net
CIRIA PG7
INTEGRITY PROBLEMS OF CONCRETE PILES
21
www.superarc.net
Alabama department of transportation specifications of drilled shaft construction
INTEGRITY PROBLEMS OF CONCRETE PILES
22
www.superarc.net
506.10 Testing Requirements For Drilled Shafts
Alabama department of transportation specifications of drilled shaft construction
INTEGRITY PROBLEMS OF CONCRETE PILES
23
www.superarc.net
Reinforcement cage is not properly fabricated
Poor Concreting Technique
Defects Arising from General Construction Problems:
(a) placing concrete by free fall without directing the stream away from reinforcing steel or the
sides of the excavation,
(b) excavating a borehole for a drilled shaft near a shaft that has just been concreted,
(c) placing concrete through water that has accumulated in the borehole,
(d) drilling the shaft out of position,
(e) developing mud waves in surface soil without protecting the newly concreted shaft,
placing lateral loads on the setting or green concrete at the shaft head, which causes
cracks.
INTEGRITY PROBLEMS OF CONCRETE PILES
24
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
25
www.superarc.net
Concrete Flow in Under Tremie Placement
A mixture with the desired workability
will not result in more than a few
inches of difference in height between
the top of the concrete surface near
the tremie and the concrete on the
outside of the reinforcement.
The Contractor shall maintain a continuous
record of the volume of concrete used and
the level of the concrete in the pipe. Any
deviations from the theoretical, or expected,
volume/level relationship shall be
immediately reported to the Engineer.
The volume of concrete : not less than 105% of the
nominal volume of the pile.
INTEGRITY PROBLEMS OF CONCRETE PILES
26
www.superarc.net
Exposure of Trapped Laitance Attributed to Inadequate Workability
INTEGRITY PROBLEMS OF CONCRETE PILES
27
www.superarc.net
Restriction of Lateral Flow by Reinforcing Cage
INTEGRITY PROBLEMS OF CONCRETE PILES
28
www.superarc.net
Effects of Loss of Workability During Concrete Placement
INTEGRITY PROBLEMS OF CONCRETE PILES
29
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
30
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
31
www.superarc.net
Major Defects in Concrete Drilled Shafts
1- Major Voids
Similar to cracks, voids can affect the consistency and quality of pile materials. Voids can affect the load bearing
capacity of concrete piles, as they reduce the effective cross-sectional dimension. pile integrity testing does not
provide any useful information about the portion of the pile that locates underneath the major voids or cracks.
2- Soil Inclusion
According to HON-FUNG CYRIL CHAN (1987 ) Inclusion of foreign material, soil lumps, slurry, etc. within the body of
the pile can negatively impact the integrity of piles and deep foundations. This could happen as a result of borehole
wall slide into the hole which can potentially create gaps over length of pile. Soil inclusion can impact the load
bearing capacity of the pile. Evaluating soil inclusion through acoustic waves can be quite challenging since the
acoustic impedance between the two regions of hardened concrete and soil might not be significant. Methods such
as pile integrity test (sonic-echo) can be used to evaluate the integrity issues.
3- Necking
Necking in concrete piles can happen during casting of pile shaft in soft clay. This rapid change of cross section (as a
results of necking) can be a source of integrity problem. Necking can affect the load bearing capacity of concrete
piles. According to Zhaoyin Zhou, “Poor performance and large water loss of mud causes water swelling of plastic
layer or form lax honeycomb thick mud cake; improper distance between neighboring pile constructions, the stresses
in the layers of soil has not been diffused, soft clay creeps in new holes, or the bit size wears excessively are the
main causes.”
INTEGRITY PROBLEMS OF CONCRETE PILES
32
www.superarc.net
4- Bulging
El-Wakil and Kassim cite that bulging is defined as a kind of pile shape imperfection; bulging increases the pile
cross-section in certain areas along the pile length. While bulging may increase the pile ultimate load capacity, it is
still considered as a pile defect and should be investigated. Pile integrity testing can effectively help identify
bulging and necking in concrete piles.
INTEGRITY PROBLEMS OF CONCRETE PILES
33
www.superarc.net
 Pile Testing — Anomalies, Flaws and Defects
 Pile integrity means strict adherence to the relevant drawings and specifications.
 This includes the pile geometry (e.g., length, diameter or width and verticality) as well as
continuity and material properties.
 Since the construction process of piles is practically blind, practitioners realized early on that pile
integrity should not be taken for granted.
 Starting in the early 1960s, the discipline of pile integrity testing has made giant steps in both testing
methods and their implementation worldwide.
 Presently, the prevalent methods are the low-strain impact method (ASTM D5882, Standard Test
Method for Low Strain Impact Integrity Testing of Deep Foundations) and the crosshole ultrasonic
method (ASTM D6760, Standard Test Method for Integrity Testing of Concrete Deep Foundations by
Ultrasonic Crosshole Testing).
INTEGRITY PROBLEMS OF CONCRETE PILES
34
www.superarc.net
Definitions-ASTM D6760 − 16
(Standard Test Method for Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing)
Anomaly: Any irregular feature in the results from the nondestructive testing (NDT). An anomaly may be due
to the testing instrument (e.g., noise), the means used (e.g., access tube debonding), the surrounding soil
(e.g., abrupt changes of soil friction) or the pile itself. It is the responsibility of the personnel and/or
agency performing the testing to gather and analyze all relevant data and to try to resolve every anomaly.
Flaw: Any deviation from the planned shape or composition of the pile, which does not necessarily detract
from the performance of the pile.
Defect: A flaw that, because of either size or location, may detract from the resistance, durability and/or
performance of the pile. The geotechnical engineer and the structural engineer are jointly responsible
for deciding whether a specific flaw constitutes a defect.
INTEGRITY PROBLEMS OF CONCRETE PILES
35
www.superarc.net
EXAMPLES: Joram M. Amir, Ph.D., C.E., D.GE, Piletest.com Ltd. DEEP FOUNDATIONS • MAY/JUNE 2019 • 93
I - Anomaly That Is Not a Flaw:
An anomaly that is not a flaw, also
known as a false positive, will be
illustrated using two cases: one from
crosshole ultrasonic testing of a
barrette and one from low-strain
impact testing on a pile.
INTEGRITY PROBLEMS OF CONCRETE PILES
36
www.superarc.net
 As shown on the graphic “Ultrasonic test results on a
barrette,” (Fig 2) the first arrival time (FAT) is shown in
red and the relative energy (RE) in shown in blue.
 Down to a depth of about 22 m (72 ft), both curves
appear rather regular (i.e., relatively straight lines) with
nearly constant values of FAT and RE.
 However, below this depth and down to about 29.3 m
(96 ft), the FAT gradually decreases from 330 μsec to
100 μsec, doubtlessly an anomaly.
 A quick questioning onsite revealed the reason;
the foundation element was reinforced only in the
upper 21 m (69 ft).
 Nevertheless, the engineer required that the access
tubes be extended all the way to the bottom of the
barrette.
INTEGRITY PROBLEMS OF CONCRETE PILES
37
www.superarc.net
 With no rebar cage to keep them aligned, the access
tubes dangled freely and likely moved toward each
other.
 This result had certainly nothing to do with the barrette
itself and, accordingly, was not declared a flaw.
INTEGRITY PROBLEMS OF CONCRETE PILES
38
www.superarc.net
 The following reflectogram was generated from low-
strain impact testing of a driven pile that was 27 m
(88.6 ft) long.
 From a review of the output (Fig 3), a major anomaly
appears at a depth of about 12.5 m (41 ft).
 However, after questioning the client about the pile, it
was discovered that this pile consisted of two
interlocked sections.
 What appeared as a discontinuity in the reflectogram
was actually just the joint between the two sections and
was therefore not declared a flaw.
INTEGRITY PROBLEMS OF CONCRETE PILES
39
www.superarc.net
II - Anomaly That Is a Flaw:
An anomaly that is a flaw includes “soft bottom” conditions, which
occur when the bottom of a drilled shaft constructed using a drilling
support fluid (i.e., slurry) is not cleaned properly.
The only existing method in which the soft bottom condition is
detected and appears as an anomaly is the crosshole ultrasonic
logging (CSL) method. With the CSL method, a soft bottom
condition manifests as a large increase in the FAT with a
corresponding decrease of the RE (Fig 4). Understandably, a soft
bottom condition anomaly, should be reported as a flaw.
INTEGRITY PROBLEMS OF CONCRETE PILES
40
www.superarc.net
III - Flaw That Is Not an Anomaly and
Not a Defect:
A flaw that is not an anomaly and not a
defect includes a minor soil pocket in the
pile which is, by definition, a flaw (Fig 5).
However, due to its small size, the flaw
may be undetectable even by today’s
most sensitive instruments and, therefore,
cannot produce an anomaly. Fortunately,
such a small flaw affects neither the
capacity nor the durability of the
foundation element; thus, the flaw is not a
defect.
INTEGRITY PROBLEMS OF CONCRETE PILES
41
www.superarc.net
IV - Anomaly That Is a Defect:
An example of when an anomaly is actually a
defect (i.e., true positive) is discussed hereafter.
From the results of CSL testing performed on a
drilled shaft, a major anomaly was discovered at a
depths between 1.8 m and 3 m (6 ft and 10 ft),
where the FAT increased from 190 μsec to
a maximum of about 330 μsec , an increase of
about 74%. The attenuation increased by 16 dB,
which was an 84% decrease in the energy (Fig 6).
Since this feature was quite shallow and the
groundwater level much deeper than the location
of the anomaly, it was decided to excavate around
the pile to expose the anomaly. Upon excavating
around the pile, visual observations confirmed the
test results and suspicions that this anomaly was
indeed a flaw. Due to its size and location, the
flaw was justly classified as a defect (Fig 7).
INTEGRITY PROBLEMS OF CONCRETE PILES
42
www.superarc.net
V – Defect That Is Not an Anomaly:
A defect that is not an anomaly (i.e., a
false negative) represents all the true
defects that go undetected, such as:
 Deviation from the vertical, which is
not detected unless tested using a
dedicated system.
 “Soft bottom” conditions that were
undetected by either the low strain
impact method or thermal imaging.
 Large bulges, which are undetectable
by CSL testing.
However, defects such as the ones
listed above could have been detected
by selecting a proper test method.
INTEGRITY PROBLEMS OF CONCRETE PILES
43
www.superarc.net
 PIT motivation and advantages
What is Pile Integrity ?
In general, Pile Integrity refers (ASTM D 5882) to certain characteristics of deep
foundations and piles such as:
 Physical Dimensions of Pile (Length or Cross-Section);
 Continuity of Pile (presence of Voids or Major Cracks); and
 Consistency of the Pile Material.
Certain pile construction practices can lead to defects in drilled shafts. These defects
can be major voids, poor quality concrete, geometric errors, and entrapped slurry or
ground water. These defects may negatively impact the load bearing capacity and load
distribution properties.
Piles and deep foundations transmit top structure loads to strong substrate through
friction and/or standing on bed rock. This load transmission is performed effectively when
there are no major integrity problems in concrete piles; Defects may result in partial
settlement to significant damage or collapse of the top structure.
INTEGRITY PROBLEMS OF CONCRETE PILES
44
www.superarc.net
Pile Construction Methods
Before we begin, let us briefly review the main three methods of pile construction:
•Dry Method: In this procedure, the borehole is excavated, and backfilled directly
with concrete.
•Casing Method: In this procedure, a temporary casing is used to support the
borehole, prevent caving, and prevent intrusion of groundwater before placement of
concrete.
•Direct Slurry Displacement: In this method, drilling fluid is used to stabilize the
borehole during excavation. The liquid is then displaced by placing concrete under
the fluid through tremie pipe.
INTEGRITY PROBLEMS OF CONCRETE PILES
45
www.superarc.net
Low Strain Integrity Methods
• PILE INTEGRITY TESTING (PIT)
• Measure Pile Top Motion, Reflections from Defects
• CROSS-HOLE SONIC LOGGING (CSL)
• Determines Concrete Quality Between Tubes in Shaft
• For larger augercast piles
• SINGLE-HOLE SONIC LOGGING (SSL)
• For smaller augercast piles
• PARALLEL SEISMIC (PS)
• Hit Pile, Measure Hydrophone in Parallel Tube
• Determines only Pile Length,
INTEGRITY PROBLEMS OF CONCRETE PILES
46
www.superarc.net
Pile Integrity Testing looks for defects
Small hammer
impact device
Accelerometer
measures response
(defect)
One person operation
Pile Integrity Test # ASTM D5882
INTEGRITY PROBLEMS OF CONCRETE PILES
47
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
48
www.superarc.net
Accelerometers
Non-instrumented hammer Instrumented hammer
INTEGRITY PROBLEMS OF CONCRETE PILES
49
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
50
www.superarc.net
PIT motivation and advantages
• prime function is to locate major defects
(to evaluate questionable shafts)
Important
• inexpensive, can test many piles
(good for quality assurance)
• no advance selection required
(good for forensic purposes)
INTEGRITY PROBLEMS OF CONCRETE PILES
51
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
52
www.superarc.net
Local Defect: small medium large
Local Bulge: small medium large
PIT - Basic Interpretations
INTEGRITY PROBLEMS OF CONCRETE PILES
53
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
54
www.superarc.net
Normal test (pile
top “free”)
Good Pile
Bad Pile
800 mm drilled shafts
L = 25 m (L/D = 31)
INTEGRITY PROBLEMS OF CONCRETE PILES
55
www.superarc.net
800 mm drilled shafts
L = 25 m (L/D = 31)
magnification = 40x
P98
Defective
P125
Good Shaft
Top Bottom
INTEGRITY PROBLEMS OF CONCRETE PILES
56
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
57
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
58
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
59
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
60
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
61
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
62
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
63
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
64
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
65
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
66
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
67
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
68
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
69
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
70
www.superarc.net
Classifications
(4 categories proposed by GRL)
• A - Good Pile
Clear toe response, no obvious defect; sound shaft
• B - Bad Pile
Clear identification of serious defect; no toe signal
– needs contingency tests or corrective measures
• C - Possible Defect
– re-test, other tests, reduce capacity or replace
• D - Inconclusive data
(poor pile top quality,
or no reflections due to strong soil)
– fix pile top & re-test; might give info for upper pile shaft
which is reason to accept pile.
INTEGRITY PROBLEMS OF CONCRETE PILES
71
www.superarc.net
• Compare with other observations
• Re-test with PIT (trim pile top to solid concrete)
• Excavate if near top
• Request pile core
• Request a PDA test or a static test
• Replace pile (or repair)
• Other?
• Have a plan what to do if find a defect
What to do if find a “problem” ?
INTEGRITY PROBLEMS OF CONCRETE PILES
72
www.superarc.net
– Averaging several blows (reduce random noise)
– Magnification versus time (compensate for losses)
– High pass filtering (or pivoting)
(eliminate low frequencies; keeps data near zero)
– Wavelet filters (or low pass);
(eliminate high frequencies)
– Rayleigh wave correction (experimental)
Conclusions
Important!
• Use similar processing for similar piles in similar soils.
Compare results to spot unusual piles.
• Data processing usually includes:
INTEGRITY PROBLEMS OF CONCRETE PILES
73
www.superarc.net
• Interpretation looks for:
– Good data (consistent & reasonable)
– Similarity or differences for different piles
– Rapidly changing features in data
– Toe signal (tension or compression)
– Shaft uniformity
– Indications of major defects (+/- cycle)
– Comparison with soil profile, installation records
• Integrity testing locates major defects. It is limited to
general interpretations rather than exact detail. Do not
use “heroic effort” to read more than data really tells.
Conclusions
INTEGRITY PROBLEMS OF CONCRETE PILES
74
www.superarc.net
Ultrasonic Crosshole Testing provides information about the homogeneity and integrity of concrete.
The method can be used for quality control of concrete piles. This method overcomes the limitation of
low strain impact integrity testing. vertical holes are created using tubes at the time of pile construction
(at least two). The tubes are filled with water. An acoustic wave emitter transducer is lowered to the
bottom of one tube; while another acoustic wave receiving transducer is placed at the bottom of second
tube. Both transducers are pulled upward at the same rate. The signals are analyzed and integrity
profile of the pile is developed. an ultrasonic profile. The test procedure is standardized as ASTM D6760
Applications: Cross Hole testing can be used to determine the location of defects, as well as identifying
the extent of the defects. The test can be done on larger diameter piles.
Limitations: Requires installation of tubes during pile construction. Data recording and analysis might
be expensive. Access to the tip of the wall is needed for most applications.
CROSS-HOLE SONIC LOGGING (CSL)
INTEGRITY PROBLEMS OF CONCRETE PILES
75
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
INTEGRITY PROBLEMS OF CONCRETE PILES
76
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
INTEGRITY PROBLEMS OF CONCRETE PILES
77
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
First Arrival Time for
Analysis of CSL Test
Results
In this procedure, the arrival
time of the first peak in the
ultrasonic pulse wave train
is (First Arrival Time, FAT),
and the overall amplitude of
the early part of pulse is
measured. A practical
challenge in the FAT
method is distinguishing
between peaks in the wave
train, and the noise in the
construction site. This is
often performed through
filtering out the noise by
assigning a threshold value.
INTEGRITY PROBLEMS OF CONCRETE PILES
78
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
INTEGRITY PROBLEMS OF CONCRETE PILES
79
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
Capabilities of Ultrasonic Corsshole Test
 Crosshole Sonic Test is a great test for identifying Anomalies in concrete shafts such as soil
inclusion, poor quality concrete (low density, low modulus), and major voids.
 In general, the transit time of ultrasonic pulse between every two access tubes is measured using a
high precision data acquisition system.
 The resolution of the scan along elevation can be controlled by the rate of the withdrawal of the
transducers in the tube (normally performed form the bottom to top).
 The resolution of the scan at each elevation depends on a number of parameters, such as the
selected frequency (pulse wavelength), the number and horizontal spacing of access tubes.
 A modern CSL is equipped with transducers that can operate between 25 to 50 kHz, allowing
detection of defects as small as 2.5” to 4” (in each horizon). It is recommended to keep the spacing
of the probes to about 12’ (3.6 m).
INTEGRITY PROBLEMS OF CONCRETE PILES
80
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
Key Advantages of Crosshole Sonic Logging
 The interpretation of the test results in CSL test is relatively easy (compared to other tests, such as the low
strain pile integrity test).
 In theory, there is no limitations with regards to shaft length or diameter. The test results are not affected by skin
friction, variation in soil stiffness, or damping characteristics.
 The test can be further enhanced by implementing a diagonal positioning of the probes (in which the elevation
of transmitting transducer has an offset with the receiving transducer).
 This would enable engineers in creating 2D and 3D maps of defects inside shaft.
INTEGRITY PROBLEMS OF CONCRETE PILES
81
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
Disadvantages and Practical Limitations
 The main disadvantage of the test relates to the fact that most access tubes are installed inside the steel
reinforcement cage.
 This would limit the amount of information that can be obtained from concrete area that lies beyond the steel
cage (which happens to be the most problematic area in most cases).
 CSL test does not provide information about small horizontal defects.
 Another practical consideration is the installation of tubes. As the shaft dimeter increases, the minimum
number of access tubes is also increased.
 This will increase the number of paths that need CSL measurement (labor intensive and time consuming).
 The CSL test offers no indication of the concrete cover or cage alignment but simply that the integrity of the shaft
central core section.
INTEGRITY PROBLEMS OF CONCRETE PILES
82
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
Practical Considerations
Access Tubes | Steel Access Tubes or PVC Access Tubes?
 Proper selection of access tubes is critical in performing CSL test.
 Access tubes can either be steel, or PVC. However, experiences from North America have shown that the
PVC tubes are less reliable, and might result in unwanted challenges such as debonding from the
concrete. Plastic tends to lose its bond to concrete after a few weeks (following concrete placement).
 Since ultrasonic wave cannot pass through air, the debonding issue makes rendering the CSL test
ineffective.
What is the proper size of Access Tubes?
 Access tubes are typical 1 to 2 inches in diameter (25 mm – 50 mm). Access tubes are filled with water to
provide acoustic coupling, as a result, they should be water tight at the ends to prevent the penetration of
soil, groundwater and debris inside the tube.
INTEGRITY PROBLEMS OF CONCRETE PILES
83
www.superarc.net
CROSS-HOLE SONIC LOGGING (CSL)
INTEGRITY PROBLEMS OF CONCRETE PILES
84
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
85
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
86
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
87
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
88
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
89
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
90
www.superarc.net
INTEGRITY PROBLEMS OF CONCRETE PILES
91
www.superarc.net
Thank YOU
‫ﺟﺯﻳﻼ‬ ‫ﺷﻛﺭﺍ‬

More Related Content

What's hot

Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of SoilPirpasha Ujede
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Make Mannan
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test pptsayan sarkar
 
TERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYTERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYSANJEEV Wazir
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Make Mannan
 
Raft foundations
Raft foundationsRaft foundations
Raft foundationshatim ahmed
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Muhammad Irfan
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationArbaz Kazi
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanEr.Karan Chauhan
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma ABHISHEK SHARMA
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Make Mannan
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 

What's hot (20)

Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
05 chapter 6 mat foundations
05 chapter 6 mat foundations05 chapter 6 mat foundations
05 chapter 6 mat foundations
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of Soil
 
Pile integrity test
Pile integrity testPile integrity test
Pile integrity test
 
Plate load test
Plate load testPlate load test
Plate load test
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
 
Bearing capacity of soil final
Bearing capacity of soil  final Bearing capacity of soil  final
Bearing capacity of soil final
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
TERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYTERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORY
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
Geotechnical Engineering-II [Lec #4: Unconfined Compression Test]
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow Foundation
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan Chauhan
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 

Similar to Presentation1 integrity problems of concrete piles-emergency

State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
IRJET- The Rehabilitation Techniques for Irwin Bridge
IRJET-  	  The Rehabilitation Techniques for Irwin BridgeIRJET-  	  The Rehabilitation Techniques for Irwin Bridge
IRJET- The Rehabilitation Techniques for Irwin BridgeIRJET Journal
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"Remedy Geotechnics Ltd
 
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...IRJET Journal
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdfPradeepPokhrel5
 
IRJET- Study on Failure of Interlocking Pavements
IRJET-  	  Study on Failure of Interlocking PavementsIRJET-  	  Study on Failure of Interlocking Pavements
IRJET- Study on Failure of Interlocking PavementsIRJET Journal
 
Metal Mines Blasting
Metal Mines BlastingMetal Mines Blasting
Metal Mines Blastingpartha sharma
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsComparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsIRJET Journal
 
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdfNeohChengAik
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET Journal
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
"Post-installed screws for in-situ assessment of mortar strength" presented a...
"Post-installed screws for in-situ assessment of mortar strength" presented a..."Post-installed screws for in-situ assessment of mortar strength" presented a...
"Post-installed screws for in-situ assessment of mortar strength" presented a...TRUSS ITN
 
Final Presentation
Final PresentationFinal Presentation
Final PresentationMonique F M
 
culverts-channeline-international.pptx
culverts-channeline-international.pptxculverts-channeline-international.pptx
culverts-channeline-international.pptxraviyemmadi
 

Similar to Presentation1 integrity problems of concrete piles-emergency (20)

State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
IRJET- The Rehabilitation Techniques for Irwin Bridge
IRJET-  	  The Rehabilitation Techniques for Irwin BridgeIRJET-  	  The Rehabilitation Techniques for Irwin Bridge
IRJET- The Rehabilitation Techniques for Irwin Bridge
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
 
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...
Characterization of Self-compacting Concrete using Viscosity Modifying Admixt...
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 
IRJET- Study on Failure of Interlocking Pavements
IRJET-  	  Study on Failure of Interlocking PavementsIRJET-  	  Study on Failure of Interlocking Pavements
IRJET- Study on Failure of Interlocking Pavements
 
Metal Mines Blasting
Metal Mines BlastingMetal Mines Blasting
Metal Mines Blasting
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsComparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
 
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Rock support methods
Rock support methodsRock support methods
Rock support methods
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
"Post-installed screws for in-situ assessment of mortar strength" presented a...
"Post-installed screws for in-situ assessment of mortar strength" presented a..."Post-installed screws for in-situ assessment of mortar strength" presented a...
"Post-installed screws for in-situ assessment of mortar strength" presented a...
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
culverts-channeline-international.pptx
culverts-channeline-international.pptxculverts-channeline-international.pptx
culverts-channeline-international.pptx
 
07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
07 soil-grout threadbar
 

More from Super Arc Consultant

إختبار وتقييم المنشآت الخرسانية
إختبار وتقييم المنشآت الخرسانيةإختبار وتقييم المنشآت الخرسانية
إختبار وتقييم المنشآت الخرسانيةSuper Arc Consultant
 
Additional deterioration of concrete structures( repair and rehabilitation of...
Additional deterioration of concrete structures( repair and rehabilitation of...Additional deterioration of concrete structures( repair and rehabilitation of...
Additional deterioration of concrete structures( repair and rehabilitation of...Super Arc Consultant
 
Condition assessment of structures
Condition assessment of structuresCondition assessment of structures
Condition assessment of structuresSuper Arc Consultant
 
Understanding soil risks and hazards
Understanding soil risks and hazardsUnderstanding soil risks and hazards
Understanding soil risks and hazardsSuper Arc Consultant
 
A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesSuper Arc Consultant
 
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...Super Arc Consultant
 

More from Super Arc Consultant (8)

إختبار وتقييم المنشآت الخرسانية
إختبار وتقييم المنشآت الخرسانيةإختبار وتقييم المنشآت الخرسانية
إختبار وتقييم المنشآت الخرسانية
 
Additional deterioration of concrete structures( repair and rehabilitation of...
Additional deterioration of concrete structures( repair and rehabilitation of...Additional deterioration of concrete structures( repair and rehabilitation of...
Additional deterioration of concrete structures( repair and rehabilitation of...
 
Strength assessment techniques
Strength assessment techniquesStrength assessment techniques
Strength assessment techniques
 
Condition assessment of structures
Condition assessment of structuresCondition assessment of structures
Condition assessment of structures
 
Understanding soil risks and hazards
Understanding soil risks and hazardsUnderstanding soil risks and hazards
Understanding soil risks and hazards
 
A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniques
 
Soil improvement techniques
Soil improvement techniquesSoil improvement techniques
Soil improvement techniques
 
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...
Geosynthetics in civil engineering (multifunctional uses of geosynthetics in ...
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

Presentation1 integrity problems of concrete piles-emergency

  • 1. 1 INTEGRITY PROBLEMS OF CONCRETE PILES ENGINEERSTALK Mohammad Alhusein, PhD Managing Partner M: +971 552592001 E: malhusein@superarc.net W: www.superarc.net INTEGRITY PROBLEMS OF CONCRETE PILES www.superarc.net
  • 2. WEBINAR OUTLINE INTEGRITY PROBLEMS OF CONCRETE PILES 2 www.superarc.net  Introduction  Common Defective Construction for Bored Piles  Boring Problems  Improper drilled shaft stabilization method and procedure  Inadequate or poor base cleaning method  Reinforcement cage is not properly fabricated  Poor Concreting Technique  Pile Testing — Anomalies, Flaws and Defects  PIT motivation and advantages
  • 3. www.superarc.net INTEGRITY PROBLEMS OF CONCRETE PILES 3 www.superarc.net  Introduction
  • 4. INTEGRITY PROBLEMS OF CONCRETE PILES 4 www.superarc.net Ultimate Bearing Capacity - Static Formula Method (Qu = Qp + Qs) Embedded Length = D Qu = Ultimate Bearing Capacity Qs = fAs f = Unit Frictional Resistance AS = Shaft Area qP = Unit Bearing Capacity AP = Area of Point QP = qPAP
  • 5. INTEGRITY PROBLEMS OF CONCRETE PILES 5 www.superarc.net Static Pile Capacity
  • 6. INTEGRITY PROBLEMS OF CONCRETE PILES 6 www.superarc.net
  • 7. INTEGRITY PROBLEMS OF CONCRETE PILES 7 www.superarc.net
  • 8. INTEGRITY PROBLEMS OF CONCRETE PILES 8 www.superarc.net  Common Defective Construction for Bored Piles Boring Problems Improper drilled shaft stabilization method and procedure Inadequate or poor base cleaning method Reinforcement cage is not properly fabricated Poor Concreting Technique
  • 9. INTEGRITY PROBLEMS OF CONCRETE PILES 9 www.superarc.net  Soil collapse is common at the transition between compacted Soil Layers and the less compacted Layers.  During a vibration, it is hard to protect the hole from mud. Because of ground water and the firm fine sand that lie below it, high pressure is needed to bore the piles, causing vibration and soil collapse. Boring Problems
  • 10. INTEGRITY PROBLEMS OF CONCRETE PILES 10 www.superarc.net Improper drilled shaft stabilization method and procedure Shaft Friction: Load / Settlement Curves – After Burland- CIRIA PG3
  • 11. INTEGRITY PROBLEMS OF CONCRETE PILES 11 www.superarc.net CIRIA PG3 Results of element bottom cleaning (including measured bottom sediment thickness using a Shaft Inspection Device (SID) prior to reinforcing steel placement and concreting. The thickness of sediment shall be measured at four locations around the perimeter and one at the center of the pile using a Shaft Inspection Device (SID). The maximum allowed thickness of debris shall be 50 mm and the average shall not exceed 25 mm at the time of concreting.
  • 12. INTEGRITY PROBLEMS OF CONCRETE PILES 12 www.superarc.net Bentonite to comply with ACI 336.1-01 “Specification for the Construction of Drilled Piers”
  • 13. INTEGRITY PROBLEMS OF CONCRETE PILES 13 www.superarc.net CIRIA PG3
  • 14. INTEGRITY PROBLEMS OF CONCRETE PILES 14 www.superarc.net Sieve Zone-I Zone-II Zone-III Zone-IV 10mm 100 100 100 100 4.75mm 90-100 90-100 90-100 95-100 2.36mm 60-95 75-100 85-100 95-100 1.18mm 30-70 55-90 75-100 90-100 600mic 15-34 35-59 60-79 80-100 300mic 5-20 8-30 12-40 15-50 150mic 0-10 0-10 0-10 0-15 FINE AGGREGATES (FA) (SAND) FA can be natural sand or crushed sand (produced by crushing rock pieces), most of which passes 4.75mm and is governed by IS: 383-1970 sieve. It shall satisfy any of the following grading requirements.
  • 15. INTEGRITY PROBLEMS OF CONCRETE PILES 15 www.superarc.net CIRIA PG3
  • 16. INTEGRITY PROBLEMS OF CONCRETE PILES 16 www.superarc.net CIRIA R144-2 CIRIA R144-2
  • 17. INTEGRITY PROBLEMS OF CONCRETE PILES 17 www.superarc.net CIRIA R144-2
  • 18. INTEGRITY PROBLEMS OF CONCRETE PILES 18 www.superarc.net CIRIA R144-2 CIRIA PG7
  • 19. INTEGRITY PROBLEMS OF CONCRETE PILES 19 www.superarc.net CIRIA PG7
  • 20. INTEGRITY PROBLEMS OF CONCRETE PILES 20 www.superarc.net CIRIA PG7
  • 21. INTEGRITY PROBLEMS OF CONCRETE PILES 21 www.superarc.net Alabama department of transportation specifications of drilled shaft construction
  • 22. INTEGRITY PROBLEMS OF CONCRETE PILES 22 www.superarc.net 506.10 Testing Requirements For Drilled Shafts Alabama department of transportation specifications of drilled shaft construction
  • 23. INTEGRITY PROBLEMS OF CONCRETE PILES 23 www.superarc.net Reinforcement cage is not properly fabricated Poor Concreting Technique Defects Arising from General Construction Problems: (a) placing concrete by free fall without directing the stream away from reinforcing steel or the sides of the excavation, (b) excavating a borehole for a drilled shaft near a shaft that has just been concreted, (c) placing concrete through water that has accumulated in the borehole, (d) drilling the shaft out of position, (e) developing mud waves in surface soil without protecting the newly concreted shaft, placing lateral loads on the setting or green concrete at the shaft head, which causes cracks.
  • 24. INTEGRITY PROBLEMS OF CONCRETE PILES 24 www.superarc.net
  • 25. INTEGRITY PROBLEMS OF CONCRETE PILES 25 www.superarc.net Concrete Flow in Under Tremie Placement A mixture with the desired workability will not result in more than a few inches of difference in height between the top of the concrete surface near the tremie and the concrete on the outside of the reinforcement. The Contractor shall maintain a continuous record of the volume of concrete used and the level of the concrete in the pipe. Any deviations from the theoretical, or expected, volume/level relationship shall be immediately reported to the Engineer. The volume of concrete : not less than 105% of the nominal volume of the pile.
  • 26. INTEGRITY PROBLEMS OF CONCRETE PILES 26 www.superarc.net Exposure of Trapped Laitance Attributed to Inadequate Workability
  • 27. INTEGRITY PROBLEMS OF CONCRETE PILES 27 www.superarc.net Restriction of Lateral Flow by Reinforcing Cage
  • 28. INTEGRITY PROBLEMS OF CONCRETE PILES 28 www.superarc.net Effects of Loss of Workability During Concrete Placement
  • 29. INTEGRITY PROBLEMS OF CONCRETE PILES 29 www.superarc.net
  • 30. INTEGRITY PROBLEMS OF CONCRETE PILES 30 www.superarc.net
  • 31. INTEGRITY PROBLEMS OF CONCRETE PILES 31 www.superarc.net Major Defects in Concrete Drilled Shafts 1- Major Voids Similar to cracks, voids can affect the consistency and quality of pile materials. Voids can affect the load bearing capacity of concrete piles, as they reduce the effective cross-sectional dimension. pile integrity testing does not provide any useful information about the portion of the pile that locates underneath the major voids or cracks. 2- Soil Inclusion According to HON-FUNG CYRIL CHAN (1987 ) Inclusion of foreign material, soil lumps, slurry, etc. within the body of the pile can negatively impact the integrity of piles and deep foundations. This could happen as a result of borehole wall slide into the hole which can potentially create gaps over length of pile. Soil inclusion can impact the load bearing capacity of the pile. Evaluating soil inclusion through acoustic waves can be quite challenging since the acoustic impedance between the two regions of hardened concrete and soil might not be significant. Methods such as pile integrity test (sonic-echo) can be used to evaluate the integrity issues. 3- Necking Necking in concrete piles can happen during casting of pile shaft in soft clay. This rapid change of cross section (as a results of necking) can be a source of integrity problem. Necking can affect the load bearing capacity of concrete piles. According to Zhaoyin Zhou, “Poor performance and large water loss of mud causes water swelling of plastic layer or form lax honeycomb thick mud cake; improper distance between neighboring pile constructions, the stresses in the layers of soil has not been diffused, soft clay creeps in new holes, or the bit size wears excessively are the main causes.”
  • 32. INTEGRITY PROBLEMS OF CONCRETE PILES 32 www.superarc.net 4- Bulging El-Wakil and Kassim cite that bulging is defined as a kind of pile shape imperfection; bulging increases the pile cross-section in certain areas along the pile length. While bulging may increase the pile ultimate load capacity, it is still considered as a pile defect and should be investigated. Pile integrity testing can effectively help identify bulging and necking in concrete piles.
  • 33. INTEGRITY PROBLEMS OF CONCRETE PILES 33 www.superarc.net  Pile Testing — Anomalies, Flaws and Defects  Pile integrity means strict adherence to the relevant drawings and specifications.  This includes the pile geometry (e.g., length, diameter or width and verticality) as well as continuity and material properties.  Since the construction process of piles is practically blind, practitioners realized early on that pile integrity should not be taken for granted.  Starting in the early 1960s, the discipline of pile integrity testing has made giant steps in both testing methods and their implementation worldwide.  Presently, the prevalent methods are the low-strain impact method (ASTM D5882, Standard Test Method for Low Strain Impact Integrity Testing of Deep Foundations) and the crosshole ultrasonic method (ASTM D6760, Standard Test Method for Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing).
  • 34. INTEGRITY PROBLEMS OF CONCRETE PILES 34 www.superarc.net Definitions-ASTM D6760 − 16 (Standard Test Method for Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing) Anomaly: Any irregular feature in the results from the nondestructive testing (NDT). An anomaly may be due to the testing instrument (e.g., noise), the means used (e.g., access tube debonding), the surrounding soil (e.g., abrupt changes of soil friction) or the pile itself. It is the responsibility of the personnel and/or agency performing the testing to gather and analyze all relevant data and to try to resolve every anomaly. Flaw: Any deviation from the planned shape or composition of the pile, which does not necessarily detract from the performance of the pile. Defect: A flaw that, because of either size or location, may detract from the resistance, durability and/or performance of the pile. The geotechnical engineer and the structural engineer are jointly responsible for deciding whether a specific flaw constitutes a defect.
  • 35. INTEGRITY PROBLEMS OF CONCRETE PILES 35 www.superarc.net EXAMPLES: Joram M. Amir, Ph.D., C.E., D.GE, Piletest.com Ltd. DEEP FOUNDATIONS • MAY/JUNE 2019 • 93 I - Anomaly That Is Not a Flaw: An anomaly that is not a flaw, also known as a false positive, will be illustrated using two cases: one from crosshole ultrasonic testing of a barrette and one from low-strain impact testing on a pile.
  • 36. INTEGRITY PROBLEMS OF CONCRETE PILES 36 www.superarc.net  As shown on the graphic “Ultrasonic test results on a barrette,” (Fig 2) the first arrival time (FAT) is shown in red and the relative energy (RE) in shown in blue.  Down to a depth of about 22 m (72 ft), both curves appear rather regular (i.e., relatively straight lines) with nearly constant values of FAT and RE.  However, below this depth and down to about 29.3 m (96 ft), the FAT gradually decreases from 330 μsec to 100 μsec, doubtlessly an anomaly.  A quick questioning onsite revealed the reason; the foundation element was reinforced only in the upper 21 m (69 ft).  Nevertheless, the engineer required that the access tubes be extended all the way to the bottom of the barrette.
  • 37. INTEGRITY PROBLEMS OF CONCRETE PILES 37 www.superarc.net  With no rebar cage to keep them aligned, the access tubes dangled freely and likely moved toward each other.  This result had certainly nothing to do with the barrette itself and, accordingly, was not declared a flaw.
  • 38. INTEGRITY PROBLEMS OF CONCRETE PILES 38 www.superarc.net  The following reflectogram was generated from low- strain impact testing of a driven pile that was 27 m (88.6 ft) long.  From a review of the output (Fig 3), a major anomaly appears at a depth of about 12.5 m (41 ft).  However, after questioning the client about the pile, it was discovered that this pile consisted of two interlocked sections.  What appeared as a discontinuity in the reflectogram was actually just the joint between the two sections and was therefore not declared a flaw.
  • 39. INTEGRITY PROBLEMS OF CONCRETE PILES 39 www.superarc.net II - Anomaly That Is a Flaw: An anomaly that is a flaw includes “soft bottom” conditions, which occur when the bottom of a drilled shaft constructed using a drilling support fluid (i.e., slurry) is not cleaned properly. The only existing method in which the soft bottom condition is detected and appears as an anomaly is the crosshole ultrasonic logging (CSL) method. With the CSL method, a soft bottom condition manifests as a large increase in the FAT with a corresponding decrease of the RE (Fig 4). Understandably, a soft bottom condition anomaly, should be reported as a flaw.
  • 40. INTEGRITY PROBLEMS OF CONCRETE PILES 40 www.superarc.net III - Flaw That Is Not an Anomaly and Not a Defect: A flaw that is not an anomaly and not a defect includes a minor soil pocket in the pile which is, by definition, a flaw (Fig 5). However, due to its small size, the flaw may be undetectable even by today’s most sensitive instruments and, therefore, cannot produce an anomaly. Fortunately, such a small flaw affects neither the capacity nor the durability of the foundation element; thus, the flaw is not a defect.
  • 41. INTEGRITY PROBLEMS OF CONCRETE PILES 41 www.superarc.net IV - Anomaly That Is a Defect: An example of when an anomaly is actually a defect (i.e., true positive) is discussed hereafter. From the results of CSL testing performed on a drilled shaft, a major anomaly was discovered at a depths between 1.8 m and 3 m (6 ft and 10 ft), where the FAT increased from 190 μsec to a maximum of about 330 μsec , an increase of about 74%. The attenuation increased by 16 dB, which was an 84% decrease in the energy (Fig 6). Since this feature was quite shallow and the groundwater level much deeper than the location of the anomaly, it was decided to excavate around the pile to expose the anomaly. Upon excavating around the pile, visual observations confirmed the test results and suspicions that this anomaly was indeed a flaw. Due to its size and location, the flaw was justly classified as a defect (Fig 7).
  • 42. INTEGRITY PROBLEMS OF CONCRETE PILES 42 www.superarc.net V – Defect That Is Not an Anomaly: A defect that is not an anomaly (i.e., a false negative) represents all the true defects that go undetected, such as:  Deviation from the vertical, which is not detected unless tested using a dedicated system.  “Soft bottom” conditions that were undetected by either the low strain impact method or thermal imaging.  Large bulges, which are undetectable by CSL testing. However, defects such as the ones listed above could have been detected by selecting a proper test method.
  • 43. INTEGRITY PROBLEMS OF CONCRETE PILES 43 www.superarc.net  PIT motivation and advantages What is Pile Integrity ? In general, Pile Integrity refers (ASTM D 5882) to certain characteristics of deep foundations and piles such as:  Physical Dimensions of Pile (Length or Cross-Section);  Continuity of Pile (presence of Voids or Major Cracks); and  Consistency of the Pile Material. Certain pile construction practices can lead to defects in drilled shafts. These defects can be major voids, poor quality concrete, geometric errors, and entrapped slurry or ground water. These defects may negatively impact the load bearing capacity and load distribution properties. Piles and deep foundations transmit top structure loads to strong substrate through friction and/or standing on bed rock. This load transmission is performed effectively when there are no major integrity problems in concrete piles; Defects may result in partial settlement to significant damage or collapse of the top structure.
  • 44. INTEGRITY PROBLEMS OF CONCRETE PILES 44 www.superarc.net Pile Construction Methods Before we begin, let us briefly review the main three methods of pile construction: •Dry Method: In this procedure, the borehole is excavated, and backfilled directly with concrete. •Casing Method: In this procedure, a temporary casing is used to support the borehole, prevent caving, and prevent intrusion of groundwater before placement of concrete. •Direct Slurry Displacement: In this method, drilling fluid is used to stabilize the borehole during excavation. The liquid is then displaced by placing concrete under the fluid through tremie pipe.
  • 45. INTEGRITY PROBLEMS OF CONCRETE PILES 45 www.superarc.net Low Strain Integrity Methods • PILE INTEGRITY TESTING (PIT) • Measure Pile Top Motion, Reflections from Defects • CROSS-HOLE SONIC LOGGING (CSL) • Determines Concrete Quality Between Tubes in Shaft • For larger augercast piles • SINGLE-HOLE SONIC LOGGING (SSL) • For smaller augercast piles • PARALLEL SEISMIC (PS) • Hit Pile, Measure Hydrophone in Parallel Tube • Determines only Pile Length,
  • 46. INTEGRITY PROBLEMS OF CONCRETE PILES 46 www.superarc.net Pile Integrity Testing looks for defects Small hammer impact device Accelerometer measures response (defect) One person operation Pile Integrity Test # ASTM D5882
  • 47. INTEGRITY PROBLEMS OF CONCRETE PILES 47 www.superarc.net
  • 48. INTEGRITY PROBLEMS OF CONCRETE PILES 48 www.superarc.net Accelerometers Non-instrumented hammer Instrumented hammer
  • 49. INTEGRITY PROBLEMS OF CONCRETE PILES 49 www.superarc.net
  • 50. INTEGRITY PROBLEMS OF CONCRETE PILES 50 www.superarc.net PIT motivation and advantages • prime function is to locate major defects (to evaluate questionable shafts) Important • inexpensive, can test many piles (good for quality assurance) • no advance selection required (good for forensic purposes)
  • 51. INTEGRITY PROBLEMS OF CONCRETE PILES 51 www.superarc.net
  • 52. INTEGRITY PROBLEMS OF CONCRETE PILES 52 www.superarc.net Local Defect: small medium large Local Bulge: small medium large PIT - Basic Interpretations
  • 53. INTEGRITY PROBLEMS OF CONCRETE PILES 53 www.superarc.net
  • 54. INTEGRITY PROBLEMS OF CONCRETE PILES 54 www.superarc.net Normal test (pile top “free”) Good Pile Bad Pile 800 mm drilled shafts L = 25 m (L/D = 31)
  • 55. INTEGRITY PROBLEMS OF CONCRETE PILES 55 www.superarc.net 800 mm drilled shafts L = 25 m (L/D = 31) magnification = 40x P98 Defective P125 Good Shaft Top Bottom
  • 56. INTEGRITY PROBLEMS OF CONCRETE PILES 56 www.superarc.net
  • 57. INTEGRITY PROBLEMS OF CONCRETE PILES 57 www.superarc.net
  • 58. INTEGRITY PROBLEMS OF CONCRETE PILES 58 www.superarc.net
  • 59. INTEGRITY PROBLEMS OF CONCRETE PILES 59 www.superarc.net
  • 60. INTEGRITY PROBLEMS OF CONCRETE PILES 60 www.superarc.net
  • 61. INTEGRITY PROBLEMS OF CONCRETE PILES 61 www.superarc.net
  • 62. INTEGRITY PROBLEMS OF CONCRETE PILES 62 www.superarc.net
  • 63. INTEGRITY PROBLEMS OF CONCRETE PILES 63 www.superarc.net
  • 64. INTEGRITY PROBLEMS OF CONCRETE PILES 64 www.superarc.net
  • 65. INTEGRITY PROBLEMS OF CONCRETE PILES 65 www.superarc.net
  • 66. INTEGRITY PROBLEMS OF CONCRETE PILES 66 www.superarc.net
  • 67. INTEGRITY PROBLEMS OF CONCRETE PILES 67 www.superarc.net
  • 68. INTEGRITY PROBLEMS OF CONCRETE PILES 68 www.superarc.net
  • 69. INTEGRITY PROBLEMS OF CONCRETE PILES 69 www.superarc.net
  • 70. INTEGRITY PROBLEMS OF CONCRETE PILES 70 www.superarc.net Classifications (4 categories proposed by GRL) • A - Good Pile Clear toe response, no obvious defect; sound shaft • B - Bad Pile Clear identification of serious defect; no toe signal – needs contingency tests or corrective measures • C - Possible Defect – re-test, other tests, reduce capacity or replace • D - Inconclusive data (poor pile top quality, or no reflections due to strong soil) – fix pile top & re-test; might give info for upper pile shaft which is reason to accept pile.
  • 71. INTEGRITY PROBLEMS OF CONCRETE PILES 71 www.superarc.net • Compare with other observations • Re-test with PIT (trim pile top to solid concrete) • Excavate if near top • Request pile core • Request a PDA test or a static test • Replace pile (or repair) • Other? • Have a plan what to do if find a defect What to do if find a “problem” ?
  • 72. INTEGRITY PROBLEMS OF CONCRETE PILES 72 www.superarc.net – Averaging several blows (reduce random noise) – Magnification versus time (compensate for losses) – High pass filtering (or pivoting) (eliminate low frequencies; keeps data near zero) – Wavelet filters (or low pass); (eliminate high frequencies) – Rayleigh wave correction (experimental) Conclusions Important! • Use similar processing for similar piles in similar soils. Compare results to spot unusual piles. • Data processing usually includes:
  • 73. INTEGRITY PROBLEMS OF CONCRETE PILES 73 www.superarc.net • Interpretation looks for: – Good data (consistent & reasonable) – Similarity or differences for different piles – Rapidly changing features in data – Toe signal (tension or compression) – Shaft uniformity – Indications of major defects (+/- cycle) – Comparison with soil profile, installation records • Integrity testing locates major defects. It is limited to general interpretations rather than exact detail. Do not use “heroic effort” to read more than data really tells. Conclusions
  • 74. INTEGRITY PROBLEMS OF CONCRETE PILES 74 www.superarc.net Ultrasonic Crosshole Testing provides information about the homogeneity and integrity of concrete. The method can be used for quality control of concrete piles. This method overcomes the limitation of low strain impact integrity testing. vertical holes are created using tubes at the time of pile construction (at least two). The tubes are filled with water. An acoustic wave emitter transducer is lowered to the bottom of one tube; while another acoustic wave receiving transducer is placed at the bottom of second tube. Both transducers are pulled upward at the same rate. The signals are analyzed and integrity profile of the pile is developed. an ultrasonic profile. The test procedure is standardized as ASTM D6760 Applications: Cross Hole testing can be used to determine the location of defects, as well as identifying the extent of the defects. The test can be done on larger diameter piles. Limitations: Requires installation of tubes during pile construction. Data recording and analysis might be expensive. Access to the tip of the wall is needed for most applications. CROSS-HOLE SONIC LOGGING (CSL)
  • 75. INTEGRITY PROBLEMS OF CONCRETE PILES 75 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL)
  • 76. INTEGRITY PROBLEMS OF CONCRETE PILES 76 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL)
  • 77. INTEGRITY PROBLEMS OF CONCRETE PILES 77 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL) First Arrival Time for Analysis of CSL Test Results In this procedure, the arrival time of the first peak in the ultrasonic pulse wave train is (First Arrival Time, FAT), and the overall amplitude of the early part of pulse is measured. A practical challenge in the FAT method is distinguishing between peaks in the wave train, and the noise in the construction site. This is often performed through filtering out the noise by assigning a threshold value.
  • 78. INTEGRITY PROBLEMS OF CONCRETE PILES 78 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL)
  • 79. INTEGRITY PROBLEMS OF CONCRETE PILES 79 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL) Capabilities of Ultrasonic Corsshole Test  Crosshole Sonic Test is a great test for identifying Anomalies in concrete shafts such as soil inclusion, poor quality concrete (low density, low modulus), and major voids.  In general, the transit time of ultrasonic pulse between every two access tubes is measured using a high precision data acquisition system.  The resolution of the scan along elevation can be controlled by the rate of the withdrawal of the transducers in the tube (normally performed form the bottom to top).  The resolution of the scan at each elevation depends on a number of parameters, such as the selected frequency (pulse wavelength), the number and horizontal spacing of access tubes.  A modern CSL is equipped with transducers that can operate between 25 to 50 kHz, allowing detection of defects as small as 2.5” to 4” (in each horizon). It is recommended to keep the spacing of the probes to about 12’ (3.6 m).
  • 80. INTEGRITY PROBLEMS OF CONCRETE PILES 80 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL) Key Advantages of Crosshole Sonic Logging  The interpretation of the test results in CSL test is relatively easy (compared to other tests, such as the low strain pile integrity test).  In theory, there is no limitations with regards to shaft length or diameter. The test results are not affected by skin friction, variation in soil stiffness, or damping characteristics.  The test can be further enhanced by implementing a diagonal positioning of the probes (in which the elevation of transmitting transducer has an offset with the receiving transducer).  This would enable engineers in creating 2D and 3D maps of defects inside shaft.
  • 81. INTEGRITY PROBLEMS OF CONCRETE PILES 81 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL) Disadvantages and Practical Limitations  The main disadvantage of the test relates to the fact that most access tubes are installed inside the steel reinforcement cage.  This would limit the amount of information that can be obtained from concrete area that lies beyond the steel cage (which happens to be the most problematic area in most cases).  CSL test does not provide information about small horizontal defects.  Another practical consideration is the installation of tubes. As the shaft dimeter increases, the minimum number of access tubes is also increased.  This will increase the number of paths that need CSL measurement (labor intensive and time consuming).  The CSL test offers no indication of the concrete cover or cage alignment but simply that the integrity of the shaft central core section.
  • 82. INTEGRITY PROBLEMS OF CONCRETE PILES 82 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL) Practical Considerations Access Tubes | Steel Access Tubes or PVC Access Tubes?  Proper selection of access tubes is critical in performing CSL test.  Access tubes can either be steel, or PVC. However, experiences from North America have shown that the PVC tubes are less reliable, and might result in unwanted challenges such as debonding from the concrete. Plastic tends to lose its bond to concrete after a few weeks (following concrete placement).  Since ultrasonic wave cannot pass through air, the debonding issue makes rendering the CSL test ineffective. What is the proper size of Access Tubes?  Access tubes are typical 1 to 2 inches in diameter (25 mm – 50 mm). Access tubes are filled with water to provide acoustic coupling, as a result, they should be water tight at the ends to prevent the penetration of soil, groundwater and debris inside the tube.
  • 83. INTEGRITY PROBLEMS OF CONCRETE PILES 83 www.superarc.net CROSS-HOLE SONIC LOGGING (CSL)
  • 84. INTEGRITY PROBLEMS OF CONCRETE PILES 84 www.superarc.net
  • 85. INTEGRITY PROBLEMS OF CONCRETE PILES 85 www.superarc.net
  • 86. INTEGRITY PROBLEMS OF CONCRETE PILES 86 www.superarc.net
  • 87. INTEGRITY PROBLEMS OF CONCRETE PILES 87 www.superarc.net
  • 88. INTEGRITY PROBLEMS OF CONCRETE PILES 88 www.superarc.net
  • 89. INTEGRITY PROBLEMS OF CONCRETE PILES 89 www.superarc.net
  • 90. INTEGRITY PROBLEMS OF CONCRETE PILES 90 www.superarc.net
  • 91. INTEGRITY PROBLEMS OF CONCRETE PILES 91 www.superarc.net Thank YOU ‫ﺟﺯﻳﻼ‬ ‫ﺷﻛﺭﺍ‬