2. 2
www.superarc.net
Soil Improvement : why bother when I can do piles ?
The school just after completion…
School Play ground
Original
ground
:
clay
Reclaimed
fill
… and 5 years later !
• Exemple 1: the classic
mistake
Buidings only are taken care of
5. 5
www.superarc.net
Soil Improvement : why bother when I can do piles ? 2/2
LNG terminal, BONNY Island – NIGERIA
• Exemple 2: the classic design Piles everywhere, whatever the cost
Soil conditions Soil Improvement
Solution
Conventional Solution
Piles and deep
foundations
6. 6
www.superarc.net
Aims of soil improvement
Reduce post-construction
settlements (total and differential)
Increase the bearing capacity
and/or the stability
Mitigate the risk of liquefaction
Advantages
Eliminates the need for deep
foundations
Eliminates the need for soil
replacement
Offers a global treatment rather
than an isolated treatment
Well adapted to uniform loads (up
to G+5) over a large area
Saves time
Saves money !
7. 7
www.superarc.net
A comprehensive approach
A specific technical solution for each project, adpated to :
The structure and the loads
The type of soils (granular, cohesive)
The specifications
A complete solution bringing the advantages of soil improvement and
including:
Design
Construction / Execution of the designed treatment (single or multiple
technique)
Post-treatment quality control (PMT, CPT)
A guarantee to achieve the targets (planning and specifications)
Peace of mind for the general contractor / the client
13. 13
Dynamic Compaction – Concept
• Invention patented by Menard in 1969
• For soils with up to 30-35% fine content
• Versatile (soils, depth)
• Well adapted to large areas
17. 17
Dynamic Compaction – Key Features
For soils with up to 30-35% fine content
More fines The excess pore water pressure cannot
dissipate
Dynamic Replacement
Versatile
Economical and fast
Well adapted to large scale projects
No cement
No aggregate
Real-time adjustment of the applied energy to the actual
ground conditions
an effective and sustainable technique
19. 19
Dynamic Replacement – Concept
• Invention patented by Menard in 1975
• Derived from Dynamic Compaction
• For depths up to 5 – 6 metres
• Well adapted to large areas
20. 20
Dynamic Replacement – How does it work ?
Transition layer
Arching effect
Stress concentration into
the pillars
Existing ground relieved
from most of the load
Draining effect
Positive effect on the
consolidation of the existing
soil during the construction
Uniform Load
Transition Layer
21. 21
Dynamic Replacement – Key Features
• For soils where DC is not applicable sabkhas, etc.
• For depths up to 5 – 6 metres for deeper treatment:
• Pre-excavation
• High energy
• Other techniques (stone columns, CMC)
• Economical and fast
• Well adapted to large scale projects
• No cement
• No strict specification for incorporated material (recycled demolition
material OK)
• Real-time adjustment on site (DC / DR) if required
an effective and sustainable technique
22. 22
Dynamic Techniques – Can vibrations be an issue ?
Safe distance = 30m (or even 10m with a trench)
25. 25
PROPOSED SOLUTION – Testing, PMT principles
PMT No. 1
0
50
100
150
200
250
300
350
0 5 10 15 20 25
Pressure (bar)
Volume
(cc)
calibration
2 meter
Bearing Capacity is calculated from
the limit pressure
The modulus of deformation
is calculated from the
straight portion of the curve
• Reputable
• Reliable
• Simulates exactly the
loading conditions of a
footing/raft/tank
• The only test that goes to
failure good knowledge
of the FOS
• Measure both:
• The bearing capacity
• The modulus of deformation
• Best way to check design
specifications
28. 28
REFERENCES – Marafiq IWPP Phase 2, Jubail, 2007
Area: 56,500m2
Power block, fuel tanks, buildings, roads
100 to 200 kPa bearing capacity
25mm (footings) to 50mm (tanks)
settlement
Soil: 5.5m of very loose silty sands
29. 29
REFERENCES – Shuaiba IWPP III (2006)
Area: 150,000m2
Evaporators, water tanks,
support buildings
Tanks (Ø110m) : 200kPa /
75mm
Other: 150kPa / 25mm
Soil: 6 to 10m loose silty sands
30. 30
REFERENCES – ADCOP MOT – Fujairah, 2009
Area: 700,000m2
7 tanks – tank diameter = 110m
220 kPa (hydrotest)
Settlements:
Absolute: 100mm max
Differential 1: 50mm max between
any 2 points on the shell
Differential 2: 13mm per 10m max
on the shell
Soil
soft soil excavated and replaced by
quarry run
Final platform at +3 to +6 above
natural ground level
solution
Work from the FPL
Fast
No need of engineered fill
32. 32
Case study – King Abdullah University, Jeddah – 2007
Project challenges
Very fast track project,
Huge surface,
No knowledge of where the
buildings will be built,
Presence of Sabkha, large SI grid
Technical Specifications
Ensure bearing capacity for 150
tons footings @ 200 kPa
anywhere on site,
Minimize absolute settlement to
25 mm and differential
settlement to 1/500,
Ensure non liquefaction
Concept
Overall Soil Improvement
concept based on DC/DR
treatment
Benefits: high speed / Global
treatment
34. 34
KAUST – A typical example of DC/DR strategy
No, but
loose sand
Yes
Transition
layer > 2 m
Transition
layer < 2 m
Case A Case B1 Case B2 Case B3
DC DR
Sabkha
Subst. over
1 m + DR
HDR +
temporary
surcharge
Presence of Sabkha
No Deep Sabkha (ie sabkha till
max 5 m below WPL)
Deep Sabkha (ie sabkha till more
than 5 m below WPL)
Compressible layer
(from loose sand to Sabkha)
Working Platform
Engineered Fill
150 tons
TL
35. 35
KAUST – A successful challenge
As built quantities
Originally less than 1,500,000 m2 to be improved in 8
months including mobilization,
Major change:
Drastic increase due to additional areas
However no allowance in terms of planning
Finally nearly 2,600,000 m2 (increase of 80%)
improved within the original schedule (8 months)
40. 40
Vibro Compaction – Procedure
Possible deep
treatment (>20m)
Strict criteria on the
original ground grain
size distribution
Best suited for soil
with less than 12%
fines
Onshore or offshore
Variable grid of
application (specs,
soils, uniformity)
54. 54
Vibro-Replacement – Top Feed method
Main advantage: deep treatment possible
Limitations
Will not work in very sof soil (bulging)
Agregate size restriction make it a more costly solution than
DR
Top feed : integrity of the bottom part of the column can not
be guaranteed
55. 55
Vibro-Replacement – Bottom Feed method
Main advantages
deep treatment possible
Guarantee of a uniform column
Dry method
Limitations
Will not work in very sof soil (bulging)
Agregate size restricton make it a more costly
solution than DR
1 –penetration with air 2 –supply and compaction
of stones
3 –completed
columns
60. 60
CMC – Concept and procedure
A solution to the problem of bulging for stone columns
No surface spoil
Improved friction ratio between soil and inclusion
72. 72
Jet Grouting – Example : Quay Wall
Base solution: Combi-wall, 27m height (!) with tie-back anchors
Ground improvement Gravity wall
no more tie-backs
reduction of the pile diameter and thickness
max horizontal displacement = 150mm
83. Vacuum Consolidation: is a technique to speed up the
consolidation process needed to be employed to meet the
land development timings.
Vacuum consolidation method: The Menard Vacuum
Consolidation method is designed for preloading/surcharging
and consolidating very soft and soft saturated soils of low
permeability. The method consists of installing vertical and
horizontal vacuum transmission pipes under an airtight
membrane and sucking the air below the membrane thus
imposing a partial atmospheric pressure on the soil. This
loading process creates an accelerated isotropic consolidation in
the soil mass. The vacuum method can be combined with a
conventional surcharge placed on top of the membrane, in
order to achieve the required degree of consolidation under a
given design load and within the allowed time frame. 83
85. 85
Concepts : Principally, a vacuum consolidation system
consists of a system of drains vertically installed from ground
surface into the treated soil mass to prescribed depth, a
surface drainage system including a granular medium (sand
mat) and horizontal drains, and collector pipes leading to a
vacuum pump system for transmission of vacuum to the soil
as well as discharging water and air out of the treated soil
mass. The vacuum treated soil mass is isolated from surface
by an airtight membrane and if required laterally protected
from leakage by cut-off-walls. Table 1 presents three typical
vacuum consolidation systems utilizing different types of
vertical drains.
86. 86
Menard Vacuum – Concept
Failure Surface
Vertical
Stress
No Failure
Vertical
Stress
Classical Surcharge Menard Vacuum Method
The Menard vacuum proposal included the main concept to create
a ‘dam’ against potential slip failure under high fill surcharge of
the adjacent wick drain trial areas.
88. 88
Menard Vacuum – Application : Camau PP,
Viet Nam
• 15 to 17m of very soft
clay
• Specs: less than
100mm settlement
over 10 years
• 85,000m2 +70,000m2
• 24 months
89. 89
You have a problem of foundation… we
have solutions for:
Residential Development Plants Roads and Railways
Warehouses Tanks Ports and Airports