cRITICAL PATH.pdf
- 1. ID Task
Mode
Task Name Duration Start Finish Predecessors
1 Project Simulation 23 days Fri 8/6/21 Tue 9/7/21
2 A 6 days Fri 8/6/21 Fri 8/13/21
3 B 3 days Fri 8/6/21 Tue 8/10/21
4 C 3 days Mon 8/16/21Wed 8/18/212
5 D 5 days Mon 8/16/21Fri 8/20/21 2
6 E 1 day Mon 8/16/21Mon 8/16/212
7 F 4 days Thu 8/19/21 Tue 8/24/21 3,4
8 G 2 days Thu 8/19/21 Fri 8/20/21 3,4
9 H 6 days Wed 8/25/21Wed 9/1/21 6,7
10 I 5 days Wed 8/25/21Tue 8/31/21 6,7
11 J 3 days Thu 9/2/21 Mon 9/6/21 5,9
12 K 5 days Wed 9/1/21 Tue 9/7/21 8,10