SlideShare a Scribd company logo
1 of 24
Download to read offline
B-055, in: T.C. Fox and H.V. Rectanus (Chairs). Remediation of Chlorinated and Recalcitrant Compounds—2012.
Eighth International Conference on Remediation of Chlorinated and Recalcitrant Compounds (Monterey, CA; May 2012).
ISBN 978-0-9819730-5-0, ©2012 Battelle Memorial Institute, Columbus, OH, www.battelle.org/chlorcon.
Predicting the Operational Life of Zero-Valent Iron during
ISCR-Enhanced Bioremediation of TCE DNAPL
James Peale (jpeale@maulfoster.com) and Erik Bakkom
(Maul Foster & Alongi, Inc., Portland, Oregon, USA)
Jim Mueller, Josephine Molin, and Andrzej Przepiora
(Adventus Americas Inc., Freeport, IL, USA)
Background/Objectives. Groundwater at an active manufacturing facility on an 80-acre
site in Portland, Oregon, was impacted by TCE and its degradation products. Operations
at the facility began in 1980, and included the use of TCE from approximately 1980 to
1989. TCE and/or TCE-containing wastewater were released to the subsurface in the
early 1980s, roughly between 1980 and 1984. In 2006, concentrations of TCE and cis-
1,2-dichloroethene (DCE) in the primary release area ranged as high as 592,000 and
90,000 µg/L (respectively) at depths ranging from approximately 50 to 110 ft below
ground surface (bgs). Although not observed during drilling or groundwater sampling,
the presence of TCE DNAPL was inferred by concentrations approaching 50% of the
aqueous solubility limit.
Approach/Activities. Based upon bench and field pilot studies, ISCR-enhanced
bioremediation was selected for primary source area treatment and implemented in early
2009. Implementation consisted of an approximately 150 foot-long permeable reactive
barrier (PRB) consisting of EHC® and KB-1®, installed at depths ranging from approx-
imately 40 to 112 ft bgs using direct-push technology. Groundwater data were collected
from 23 performance monitoring wells located upgradient, within, and downgradient of
the PRB. Early data confirmed the success of the approach, with 99.99% TCE mass
removal less than a year following completion, with many wells below the USEPA MCL
(5 µg/L).
Results/Lessons Learned. While the performance data indicated successful remediation
of TCE DNAPL, residual concentrations of degradation products (primarily cis-1,2-DCE
and vinyl chloride) prompted questions regarding the long-term stability of the zero-
valent iron (ZVI) component of the EHC material. The primary mechanism resulting in
reduced effectiveness of ZVI is consumption of iron by processes such as corrosion,
reduction of chlorinated VOCs, reduction of nitrate, and reduction of sulfate. Pre-
injection groundwater concentration data were used to estimate the aggregate rate of ZVI
consumption based on the total amount of ZVI injected, with a predicted operational life
of the ZVI ranging from 14-60 years. Subsequent performance data (including iron,
dissolved oxygen, nitrate, sulfate, and CVOC) will be used to further evaluate the
predicted operational life. Modeling will be completed using publically available iron
corrosion/consumption calculations and geochemical models. These data and calculations
will be presented and compared to available data from other sites.
PREDICTING THE OPERATIONAL LIFE
OF ZERO-VALENT IRON DURING
ISCR-ENHANCED BIOREMEDIATION
OF TCE AND TCE DNAPL
James G.D. Peale, RG
Erik I. Bakkom, PE
(Maul Foster & Alongi Inc.)
Josephine Molin
Jim Mueller
Andrzej Przepiora
(FMC Environmental Solutions/Adventus)
May 2012
 Site Overview
 Technology Summary
 Problem Statement
 Analysis
 Results
 Summary
 Implications
TOPICS
 Former MGP waste site redeveloped for
manufacturing in 1970s
 80+ acres adjacent to Portland Harbor NPL site
 TCE or TCE+wastewater released from a recycling
system (1980-1985)
 Impacts from release discovered in 2002
 Source Zone
 Impacts from about 15-34 m bgs
 TCE up to 592,000 ug/L (DNAPL levels)
 No TCE DNAPL observed
 Cis-1,2-DCE up to 90,800 ug/L
 Very little VC (< 100 ug/L)
Site Overview
Site Overview
Technology Summary
 EHC
 Powdered blend of zero-valent iron (ZVI) and
hydrophilic organic carbon
 Creates strongly reducing conditions in groundwater
for in situ chemical reduction (ISCR)
 ISCR results in abiotic dechlorination and supports
anaerobic bacteria
 KB-1
 Anaerobic consortium of dechlorinating bacteria
 Includes dehalococcoides sp.
 Requires ORP < -75 mV
Technology Summary
 EHC+KB-1 Full-Scale Implementation
 46 m x 21 m x 3 m PRB – Source area only
 Injected from ~12 – 34 m bgs
 Supplemental upgradient areas
 200+ injection points
 ~269,400 kg EHC
 1,831 L KB-1
 Direct-push drilling
 23 Performance Monitoring Wells
 Group 1 – Upgradient or within injection zone
 Group 2 – Downgradient of injection zone
Technology Summary
Technology Summary
Technology Summary
 Insert TCE normalized plot?
 Subset of wells with pre-injection TCE > 11,000 ug/L
y = 0.1145e-0.011x
R² = 0.5859
y = 0.0352e-0.007x
R² = 0.4188
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
1.E+01
0 100 200 300 400 500 600 700 800 900
C/C0(ug/L)
Time Following Injection (d)
TCE DNAPL Predicted TCE DNAPL Not Predicted Predicted Wells Not Predicted Wells
Problem Statement
 Remedial action objective is 11,000 ug/L
 Threshold indicator for TCE DNAPL
 Achieved in less than 12 months
 Mean TCE 3 ug/L
 Declining cDCE
 Abiotic products confirm ZVI performance
 Dhc counts 107 – 108
 Question: how long can this continue?
 Will we see rebound?
Problem Statement
 How long can we rely on ZVI for residual
CVOCs?
 ZVI Consumers
 Corrosion by water
 Oxidation by CVOCs
 Oxidation by sulfate
 Wide range for longevity in experience
and literature
 15 years for granular ZVI
 7 years for micro-scale ZVI
 20-750 years (Henderson et al., 2007)
Problem Statement
y = -18.852x + 764496
R² = 0.9788
Predicts ZVI Exhaustion in 16 yrs
y = -1.5096x + 65608
R² = 0.4784
Predict ZVI Exhaustion in 201 yrs
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
12/18/2008 7/6/2009 1/22/2010 8/10/2010 2/26/2011 9/14/2011 4/1/2012
DissolvedFe(Kg)
Date
Rate 1 Rate 2 Linear Trend Linear Trend
Analysis
 Literature rates applied using t0 data
 10 – 20 yrs
 Bulk mass estimates (time-dependent)
 3D kriging of total mass of Fe over time
 10 – 200 yrs based on regression
 Geochemical modeling – PHREEQC
 Step 1: Inverse to simulate measured
chemistry assuming batch system
 Step 2: 1-D transport model to model flowing
system
Analysis - Geochemistry
 Data from well WS-32-76
 Geochemical trends
 Highest concentrations of iron (dissolved and
total)
 TOC and CaCO3 indicative of carbon
fermentation from the emplaced EHC
 “Worst case” – highest EHC consumption
indicated or inferred
Analysis - Geochemistry
Data from well WS-32-76
Analysis – Input Parameters
 Input parameters used in geochemical and
transport model
Background conditions (∑Fe=1.3E-3 M,
∑C=1.1E-2 M, and ∑S=4.3E-3 M); Fe(OH)2(a),
amakinite [Fe(OH)2], pyrite (FeS2] and
siderite [FeCO3] were assumed as
equilibrium mineral phases.
Analysis - Geochemistry
5 months after EHC injections
(∑Fe=6.5E-2 M, ∑C=7.2E-2 M, and
∑S=4.3E-3 M). Methane generation
was suppressed for equilibrium
calculations.
Analysis - Model
 Good fits for model
Results
 Difference between Fe(t) and Fe(d) indicates
precipitation
 Siderite (supersaturation); Fe-sulfides?
 Observed Fe controlled by:
 DNAPL/CVOC reduction
 Methanogenesis, sulfate reduction
 Requires carbon fermentation
 “Early” ZVI corrosion rate ~ 19 mmol/kgZVI/day
 Higher than expected; worst-case data set
 Predicts consumption of ZVI in injection + 10 years
 Useful?
Results – Rate Comparison
Data Method
Rate
(mmol/kgZVI/day)
ZVI Longevity
(yrs) Comment
EVS Mass
Rate 1 Regression/Slope 3.07 16
May overestimate and be
less useful for decision
making
EVS Mass
Rate 2 Regression/Slope 0.24 201
WS32-Early 1-D PHREEQC 19 3 Conservatively fast; based
on “worst-case” data
WS32-Late 1-D PHREEQC 6.3 8
t0 Data Adventus TN Rates 2.3 21
Assumed constant rate and
site-specific “t0” data
EVS Mass of
Fe
Long-term rate based
on 12.5 : 1 Ratio using
WS32-Early as Rate 1 1.5 32
Incorporates changing rate
and bulk Fe data to reflect
actual conditions and
incorporate variability
Summary
 Literature range sets boundaries
 20 – 750 yrs (latter less useful)
 Developing data set
 Regression provides simple tool for prediction
 Dual rates observed and should be considered
 Early consumption followed by equilibrium
 Modeling is promising approach
 Estimates match lower range of regression
 Can provide conservative (short) predictions to
improve site planning/closure
Implications
 Micro-scale ZVI is extremely durable
 Data fit well with other observations
 Similarity to presumed P&T timeframes (30 yrs)
 How do we manage long-term?
 Is monitoring required to demonstrate complete
exhaustion?
 How can we extend confidence of this long-term
remedy to support site closure?
Acknowledgements/Questions
 Thank you.
 FMC Environmental Solutions / Adventus
 Questions?

More Related Content

What's hot

IRJET- Water Quality Assessment of Paravoor Lake
IRJET- Water Quality Assessment of Paravoor LakeIRJET- Water Quality Assessment of Paravoor Lake
IRJET- Water Quality Assessment of Paravoor LakeIRJET Journal
 
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...Philip R. Davies
 
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.04
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.042016 MRS Fall meeting-Guiqiu Zheng ES5.13.04
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.04Guiqiu (Tony) Zheng
 
2015 03-25 Rideal Berlin Philip R Davies
2015 03-25 Rideal Berlin Philip R Davies2015 03-25 Rideal Berlin Philip R Davies
2015 03-25 Rideal Berlin Philip R DaviesPhilip R. Davies
 
Synergetic treatment of waste water using different surfactants assisted nana...
Synergetic treatment of waste water using different surfactants assisted nana...Synergetic treatment of waste water using different surfactants assisted nana...
Synergetic treatment of waste water using different surfactants assisted nana...ajichemix
 
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...Stephan Irle
 
ACSSA Symposium Poster
ACSSA Symposium Poster ACSSA Symposium Poster
ACSSA Symposium Poster JING GU
 
TCE Plume Remediation via ISCR-Enhanced Bioremediation
TCE Plume Remediation via ISCR-Enhanced BioremediationTCE Plume Remediation via ISCR-Enhanced Bioremediation
TCE Plume Remediation via ISCR-Enhanced BioremediationWeirdTurnPro
 
Army Orion Park Housing Update to Moffett RAB
Army Orion Park Housing Update to Moffett RABArmy Orion Park Housing Update to Moffett RAB
Army Orion Park Housing Update to Moffett RABSteve Williams
 

What's hot (18)

IRJET- Water Quality Assessment of Paravoor Lake
IRJET- Water Quality Assessment of Paravoor LakeIRJET- Water Quality Assessment of Paravoor Lake
IRJET- Water Quality Assessment of Paravoor Lake
 
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...
2015 01-8 pr davies spectroscopic and afm studies of the functionalisation of...
 
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
 
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.04
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.042016 MRS Fall meeting-Guiqiu Zheng ES5.13.04
2016 MRS Fall meeting-Guiqiu Zheng ES5.13.04
 
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
 
Fulltext
FulltextFulltext
Fulltext
 
2015 03-25 Rideal Berlin Philip R Davies
2015 03-25 Rideal Berlin Philip R Davies2015 03-25 Rideal Berlin Philip R Davies
2015 03-25 Rideal Berlin Philip R Davies
 
Synergetic treatment of waste water using different surfactants assisted nana...
Synergetic treatment of waste water using different surfactants assisted nana...Synergetic treatment of waste water using different surfactants assisted nana...
Synergetic treatment of waste water using different surfactants assisted nana...
 
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...
SWCNT Growth from Chiral and Achiral Carbon Nanorings: Prediction of Chiralit...
 
17 Salt Reconsolidation
17 Salt Reconsolidation17 Salt Reconsolidation
17 Salt Reconsolidation
 
05 Safety Case Experiences in The Netherlands
05 Safety Case Experiences in The Netherlands05 Safety Case Experiences in The Netherlands
05 Safety Case Experiences in The Netherlands
 
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
 
Ce453 (1)csdcdscdcd
Ce453 (1)csdcdscdcdCe453 (1)csdcdscdcd
Ce453 (1)csdcdscdcd
 
Chromatography: Anions and Metals Analysis for Waters Impacted by Hydraulic F...
Chromatography: Anions and Metals Analysis for Waters Impacted by Hydraulic F...Chromatography: Anions and Metals Analysis for Waters Impacted by Hydraulic F...
Chromatography: Anions and Metals Analysis for Waters Impacted by Hydraulic F...
 
ACSSA Symposium Poster
ACSSA Symposium Poster ACSSA Symposium Poster
ACSSA Symposium Poster
 
TCE Plume Remediation via ISCR-Enhanced Bioremediation
TCE Plume Remediation via ISCR-Enhanced BioremediationTCE Plume Remediation via ISCR-Enhanced Bioremediation
TCE Plume Remediation via ISCR-Enhanced Bioremediation
 
Army Orion Park Housing Update to Moffett RAB
Army Orion Park Housing Update to Moffett RABArmy Orion Park Housing Update to Moffett RAB
Army Orion Park Housing Update to Moffett RAB
 
16 Reconsolidation of granular salt (DAEF report)
16 Reconsolidation of granular salt (DAEF report)16 Reconsolidation of granular salt (DAEF report)
16 Reconsolidation of granular salt (DAEF report)
 

Similar to Predicting Operational Life of ZVI 2012

Long Term Monitoring Data 2013
Long Term Monitoring Data 2013Long Term Monitoring Data 2013
Long Term Monitoring Data 2013James Peale
 
Successful ISCR-Enhanced Bioremediation - Summer 2010
Successful ISCR-Enhanced Bioremediation - Summer 2010Successful ISCR-Enhanced Bioremediation - Summer 2010
Successful ISCR-Enhanced Bioremediation - Summer 2010James Peale
 
Examples of CCS R&D programs in the US
Examples of CCS R&D programs in the USExamples of CCS R&D programs in the US
Examples of CCS R&D programs in the USGlobal CCS Institute
 
Occurrence and Attenuation 2014
Occurrence and Attenuation 2014Occurrence and Attenuation 2014
Occurrence and Attenuation 2014James Peale
 
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...inventy
 
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...Technological Challenges and Opportunities for CO2 Capture and Sequestration ...
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...Energy Network marcus evans
 
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Global CCS Institute
 
C:\Documents And Settings\Jbalent\My Documents\Tio061610
C:\Documents And Settings\Jbalent\My Documents\Tio061610C:\Documents And Settings\Jbalent\My Documents\Tio061610
C:\Documents And Settings\Jbalent\My Documents\Tio061610Jean Balent
 
Desorption of TCE from MGP DNAPL 2011
Desorption of TCE from MGP DNAPL 2011Desorption of TCE from MGP DNAPL 2011
Desorption of TCE from MGP DNAPL 2011James Peale
 
Reduction of cu o and cu2o with h2 h embedding and kinetics effects in the ...
Reduction of cu o and cu2o with h2   h embedding and kinetics effects in the ...Reduction of cu o and cu2o with h2   h embedding and kinetics effects in the ...
Reduction of cu o and cu2o with h2 h embedding and kinetics effects in the ...Luciana Pirone
 
Life Cycle Assessment of Wastewater Treatment Plant.pptx
Life Cycle Assessment of Wastewater Treatment Plant.pptxLife Cycle Assessment of Wastewater Treatment Plant.pptx
Life Cycle Assessment of Wastewater Treatment Plant.pptxAbdulSameeu3
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Sirris
 
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...Global CCS Institute
 
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...Integrated Carbon Observation System (ICOS)
 
REU poster Adam Saleh
REU poster Adam SalehREU poster Adam Saleh
REU poster Adam SalehAdam Saleh
 
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...IEA-ETSAP
 

Similar to Predicting Operational Life of ZVI 2012 (20)

Long Term Monitoring Data 2013
Long Term Monitoring Data 2013Long Term Monitoring Data 2013
Long Term Monitoring Data 2013
 
Successful ISCR-Enhanced Bioremediation - Summer 2010
Successful ISCR-Enhanced Bioremediation - Summer 2010Successful ISCR-Enhanced Bioremediation - Summer 2010
Successful ISCR-Enhanced Bioremediation - Summer 2010
 
Snehesh-Presentation-PDF
Snehesh-Presentation-PDFSnehesh-Presentation-PDF
Snehesh-Presentation-PDF
 
Novak2012
Novak2012Novak2012
Novak2012
 
Examples of CCS R&D programs in the US
Examples of CCS R&D programs in the USExamples of CCS R&D programs in the US
Examples of CCS R&D programs in the US
 
Occurrence and Attenuation 2014
Occurrence and Attenuation 2014Occurrence and Attenuation 2014
Occurrence and Attenuation 2014
 
CLRA MSSS 2015 Walker Winnipeg
CLRA MSSS 2015 Walker WinnipegCLRA MSSS 2015 Walker Winnipeg
CLRA MSSS 2015 Walker Winnipeg
 
CCUS in the USA: Activity, Prospects, and Academic Research - plenary present...
CCUS in the USA: Activity, Prospects, and Academic Research - plenary present...CCUS in the USA: Activity, Prospects, and Academic Research - plenary present...
CCUS in the USA: Activity, Prospects, and Academic Research - plenary present...
 
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...
Investigation on the Effect of TiO2 and H2O2 for the Treatment of Inorganic C...
 
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...Technological Challenges and Opportunities for CO2 Capture and Sequestration ...
Technological Challenges and Opportunities for CO2 Capture and Sequestration ...
 
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
Perspectives on the role of CO2 capture and utilisation (CCU) in climate chan...
 
C:\Documents And Settings\Jbalent\My Documents\Tio061610
C:\Documents And Settings\Jbalent\My Documents\Tio061610C:\Documents And Settings\Jbalent\My Documents\Tio061610
C:\Documents And Settings\Jbalent\My Documents\Tio061610
 
Desorption of TCE from MGP DNAPL 2011
Desorption of TCE from MGP DNAPL 2011Desorption of TCE from MGP DNAPL 2011
Desorption of TCE from MGP DNAPL 2011
 
Reduction of cu o and cu2o with h2 h embedding and kinetics effects in the ...
Reduction of cu o and cu2o with h2   h embedding and kinetics effects in the ...Reduction of cu o and cu2o with h2   h embedding and kinetics effects in the ...
Reduction of cu o and cu2o with h2 h embedding and kinetics effects in the ...
 
Life Cycle Assessment of Wastewater Treatment Plant.pptx
Life Cycle Assessment of Wastewater Treatment Plant.pptxLife Cycle Assessment of Wastewater Treatment Plant.pptx
Life Cycle Assessment of Wastewater Treatment Plant.pptx
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...
 
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
 
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...
Steinhoff, Tobias: Uncertainty analysis for calculations of the marine carbon...
 
REU poster Adam Saleh
REU poster Adam SalehREU poster Adam Saleh
REU poster Adam Saleh
 
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
Energy modeling approach to the global energy-mineral nexus: Exploring metal ...
 

Predicting Operational Life of ZVI 2012

  • 1. B-055, in: T.C. Fox and H.V. Rectanus (Chairs). Remediation of Chlorinated and Recalcitrant Compounds—2012. Eighth International Conference on Remediation of Chlorinated and Recalcitrant Compounds (Monterey, CA; May 2012). ISBN 978-0-9819730-5-0, ©2012 Battelle Memorial Institute, Columbus, OH, www.battelle.org/chlorcon. Predicting the Operational Life of Zero-Valent Iron during ISCR-Enhanced Bioremediation of TCE DNAPL James Peale (jpeale@maulfoster.com) and Erik Bakkom (Maul Foster & Alongi, Inc., Portland, Oregon, USA) Jim Mueller, Josephine Molin, and Andrzej Przepiora (Adventus Americas Inc., Freeport, IL, USA) Background/Objectives. Groundwater at an active manufacturing facility on an 80-acre site in Portland, Oregon, was impacted by TCE and its degradation products. Operations at the facility began in 1980, and included the use of TCE from approximately 1980 to 1989. TCE and/or TCE-containing wastewater were released to the subsurface in the early 1980s, roughly between 1980 and 1984. In 2006, concentrations of TCE and cis- 1,2-dichloroethene (DCE) in the primary release area ranged as high as 592,000 and 90,000 µg/L (respectively) at depths ranging from approximately 50 to 110 ft below ground surface (bgs). Although not observed during drilling or groundwater sampling, the presence of TCE DNAPL was inferred by concentrations approaching 50% of the aqueous solubility limit. Approach/Activities. Based upon bench and field pilot studies, ISCR-enhanced bioremediation was selected for primary source area treatment and implemented in early 2009. Implementation consisted of an approximately 150 foot-long permeable reactive barrier (PRB) consisting of EHC® and KB-1®, installed at depths ranging from approx- imately 40 to 112 ft bgs using direct-push technology. Groundwater data were collected from 23 performance monitoring wells located upgradient, within, and downgradient of the PRB. Early data confirmed the success of the approach, with 99.99% TCE mass removal less than a year following completion, with many wells below the USEPA MCL (5 µg/L). Results/Lessons Learned. While the performance data indicated successful remediation of TCE DNAPL, residual concentrations of degradation products (primarily cis-1,2-DCE and vinyl chloride) prompted questions regarding the long-term stability of the zero- valent iron (ZVI) component of the EHC material. The primary mechanism resulting in reduced effectiveness of ZVI is consumption of iron by processes such as corrosion, reduction of chlorinated VOCs, reduction of nitrate, and reduction of sulfate. Pre- injection groundwater concentration data were used to estimate the aggregate rate of ZVI consumption based on the total amount of ZVI injected, with a predicted operational life of the ZVI ranging from 14-60 years. Subsequent performance data (including iron, dissolved oxygen, nitrate, sulfate, and CVOC) will be used to further evaluate the predicted operational life. Modeling will be completed using publically available iron corrosion/consumption calculations and geochemical models. These data and calculations will be presented and compared to available data from other sites.
  • 2. PREDICTING THE OPERATIONAL LIFE OF ZERO-VALENT IRON DURING ISCR-ENHANCED BIOREMEDIATION OF TCE AND TCE DNAPL James G.D. Peale, RG Erik I. Bakkom, PE (Maul Foster & Alongi Inc.) Josephine Molin Jim Mueller Andrzej Przepiora (FMC Environmental Solutions/Adventus) May 2012
  • 3.  Site Overview  Technology Summary  Problem Statement  Analysis  Results  Summary  Implications TOPICS
  • 4.  Former MGP waste site redeveloped for manufacturing in 1970s  80+ acres adjacent to Portland Harbor NPL site  TCE or TCE+wastewater released from a recycling system (1980-1985)  Impacts from release discovered in 2002  Source Zone  Impacts from about 15-34 m bgs  TCE up to 592,000 ug/L (DNAPL levels)  No TCE DNAPL observed  Cis-1,2-DCE up to 90,800 ug/L  Very little VC (< 100 ug/L) Site Overview
  • 6. Technology Summary  EHC  Powdered blend of zero-valent iron (ZVI) and hydrophilic organic carbon  Creates strongly reducing conditions in groundwater for in situ chemical reduction (ISCR)  ISCR results in abiotic dechlorination and supports anaerobic bacteria  KB-1  Anaerobic consortium of dechlorinating bacteria  Includes dehalococcoides sp.  Requires ORP < -75 mV
  • 7. Technology Summary  EHC+KB-1 Full-Scale Implementation  46 m x 21 m x 3 m PRB – Source area only  Injected from ~12 – 34 m bgs  Supplemental upgradient areas  200+ injection points  ~269,400 kg EHC  1,831 L KB-1  Direct-push drilling  23 Performance Monitoring Wells  Group 1 – Upgradient or within injection zone  Group 2 – Downgradient of injection zone
  • 10. Technology Summary  Insert TCE normalized plot?  Subset of wells with pre-injection TCE > 11,000 ug/L y = 0.1145e-0.011x R² = 0.5859 y = 0.0352e-0.007x R² = 0.4188 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00 1.E+01 0 100 200 300 400 500 600 700 800 900 C/C0(ug/L) Time Following Injection (d) TCE DNAPL Predicted TCE DNAPL Not Predicted Predicted Wells Not Predicted Wells
  • 11. Problem Statement  Remedial action objective is 11,000 ug/L  Threshold indicator for TCE DNAPL  Achieved in less than 12 months  Mean TCE 3 ug/L  Declining cDCE  Abiotic products confirm ZVI performance  Dhc counts 107 – 108  Question: how long can this continue?  Will we see rebound?
  • 12. Problem Statement  How long can we rely on ZVI for residual CVOCs?  ZVI Consumers  Corrosion by water  Oxidation by CVOCs  Oxidation by sulfate  Wide range for longevity in experience and literature  15 years for granular ZVI  7 years for micro-scale ZVI  20-750 years (Henderson et al., 2007)
  • 13. Problem Statement y = -18.852x + 764496 R² = 0.9788 Predicts ZVI Exhaustion in 16 yrs y = -1.5096x + 65608 R² = 0.4784 Predict ZVI Exhaustion in 201 yrs 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 12/18/2008 7/6/2009 1/22/2010 8/10/2010 2/26/2011 9/14/2011 4/1/2012 DissolvedFe(Kg) Date Rate 1 Rate 2 Linear Trend Linear Trend
  • 14. Analysis  Literature rates applied using t0 data  10 – 20 yrs  Bulk mass estimates (time-dependent)  3D kriging of total mass of Fe over time  10 – 200 yrs based on regression  Geochemical modeling – PHREEQC  Step 1: Inverse to simulate measured chemistry assuming batch system  Step 2: 1-D transport model to model flowing system
  • 15. Analysis - Geochemistry  Data from well WS-32-76  Geochemical trends  Highest concentrations of iron (dissolved and total)  TOC and CaCO3 indicative of carbon fermentation from the emplaced EHC  “Worst case” – highest EHC consumption indicated or inferred
  • 16. Analysis - Geochemistry Data from well WS-32-76
  • 17. Analysis – Input Parameters  Input parameters used in geochemical and transport model
  • 18. Background conditions (∑Fe=1.3E-3 M, ∑C=1.1E-2 M, and ∑S=4.3E-3 M); Fe(OH)2(a), amakinite [Fe(OH)2], pyrite (FeS2] and siderite [FeCO3] were assumed as equilibrium mineral phases. Analysis - Geochemistry 5 months after EHC injections (∑Fe=6.5E-2 M, ∑C=7.2E-2 M, and ∑S=4.3E-3 M). Methane generation was suppressed for equilibrium calculations.
  • 19. Analysis - Model  Good fits for model
  • 20. Results  Difference between Fe(t) and Fe(d) indicates precipitation  Siderite (supersaturation); Fe-sulfides?  Observed Fe controlled by:  DNAPL/CVOC reduction  Methanogenesis, sulfate reduction  Requires carbon fermentation  “Early” ZVI corrosion rate ~ 19 mmol/kgZVI/day  Higher than expected; worst-case data set  Predicts consumption of ZVI in injection + 10 years  Useful?
  • 21. Results – Rate Comparison Data Method Rate (mmol/kgZVI/day) ZVI Longevity (yrs) Comment EVS Mass Rate 1 Regression/Slope 3.07 16 May overestimate and be less useful for decision making EVS Mass Rate 2 Regression/Slope 0.24 201 WS32-Early 1-D PHREEQC 19 3 Conservatively fast; based on “worst-case” data WS32-Late 1-D PHREEQC 6.3 8 t0 Data Adventus TN Rates 2.3 21 Assumed constant rate and site-specific “t0” data EVS Mass of Fe Long-term rate based on 12.5 : 1 Ratio using WS32-Early as Rate 1 1.5 32 Incorporates changing rate and bulk Fe data to reflect actual conditions and incorporate variability
  • 22. Summary  Literature range sets boundaries  20 – 750 yrs (latter less useful)  Developing data set  Regression provides simple tool for prediction  Dual rates observed and should be considered  Early consumption followed by equilibrium  Modeling is promising approach  Estimates match lower range of regression  Can provide conservative (short) predictions to improve site planning/closure
  • 23. Implications  Micro-scale ZVI is extremely durable  Data fit well with other observations  Similarity to presumed P&T timeframes (30 yrs)  How do we manage long-term?  Is monitoring required to demonstrate complete exhaustion?  How can we extend confidence of this long-term remedy to support site closure?
  • 24. Acknowledgements/Questions  Thank you.  FMC Environmental Solutions / Adventus  Questions?