SlideShare a Scribd company logo
1 of 19
Download to read offline
FIELD ENGINEERING LIMITED
PROSERVE
OGABIRI GAS GATHERING PROJECT.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF
OGABIRI GATHERING PROJECT.
DCC NUMBER: PROS/OGBR/PIP/RPT/151003
RO2 01/12/2015 IFR A.R.O. A.M. E.C.U.
RO1 04/11/2015 IDC A.R.O. A.M. E.C.U.
Revision Date: Status: Issued by Checked by Approved by
COMPANY
Approval
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 2 of 19
TABLE OF CONTENTS
Page
List of Illustrations --------------------------------------------------------------------------------- 3
List of Tables --------------------------------------------------------------------------------------- 3
List of Abbreviations ------------------------------------------------------------------------------ 3
1.0 INTRODUCTION -------------------------------------------------------------------------- 5
1.1 BACKGROUND ----------------------------------------------------------------------- 6
1.2 SCOPE OF WORK --------------------------------------------------------------------- 7
1.3 ACKNOWLEDGEMENT -------------------------------------------------------------- 7
1.4 DESIGN INTERFACE ------------------------------------------------------------------ 8
2.0 FORWARD ------------------------------------------------------------------------------- 10
3.0 TECHNICAL DATA FOR OGABIRI GAS GATHERING PROJECT ---------- 11
3.1 DIMENSION FOR PIPELINES -------------------------------------------------------- 11
3.2 QUANTITIES ---------------------------------------------------------------------------- 12
3.3 ANTICORROSION --------------------------------------------------------------------- 13
3.4 RESULTS OF DETAILED DESIGN AND ENGINEERING --------------------- 14
4.0 CONCLUSION -------------------------------------------------------------------------- 17
REFERENCE DOCUMENT-----------------------------------------------------------------------------17
DOCUMENT HIERARCHY-----------------------------------------------------------------------------17
LIST OF ILLUSTRATION
Fig.1.0 Map Outlay of Ogabiri Gas Gathering Project------------------------------------------------ 6
Fig.1.1 Pipesim Simulation Network of the Ogabiri Gas Gathering Project-----------------------8
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 3 of 19
Fig.1.2 Hysis Simulation Network of the Ogabiri Gas Gathering Project----------------------9
LIST OF TABLES
Table.3.1. Dimension for Pipelines -------------------------------------------------------------------8
Table.3.2.Quantities ------------------------------------------------------------------------------------12
Table.3.3.Anti-corrosion -------------------------------------------------------------------------------13
Table.3.4. Result of Detailed Design and Engineering --------------------------------------------14
LIST OF ABBREVIATIONS/ACRONYMS
ASME– American Society of Mechanical Engineering.
ASTM– American Society of Testing and Material.
13 Cr - 13-Chrome
16” - Twenty inches
o
C - Degrees Celsius
C/S – Cladded Steel
CFC – Chlorofluorocarbon
CO - Carbon monoxide
CO2 - Carbon dioxide
DNA – Deoxyribonucleic Acid.
DSAW - Double Submerged Arc Welded
ELPS – Escravos Lagos Pipeline System.
ERW - Electric Resistance Welded
FBE - Fusion Bonded Epoxy.
FEED – Front End Engineering Drawing.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 4 of 19
GHG – Greenhouse Gas.
GRE - Glass Reinforced Epoxy
HDPE - High Density Polyethylene
HCFC – Hydrochlorofluocarbon
ISO - International Standard Organization
M/F - Manifold
m/s - meter per second
NGC – Nigerian Gas Company.
NNPC – Nigerian National Petroleum Corporation.
NO2 - Nitrogen dioxide
N2O – Di-nitrogen oxide
NO- Nitrous oxide
NOx – Nitrogen-Oxygen compounds.
OPEC – Organization of Petroleum Exporting Countries.
PVC - Polyvinyl casing
ROW - Right of Way
RTP - Reinforced Thermoplastic
SCF – Standard Cubic Feet.
SPDC - Shell Petroleum Development Company
UNFCCC – United Nations Framework Convention on Climate Change.
NGS– Nigerian Gas Station.
API– American Petroleum Institute.
WAGC– West African Gas Company.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 5 of 19
1.0 INTRODUCTION
The world as a global village is confronted presently with the threat of extinction as a result of incessant
emission of dangerous gases such as carbon dioxide(CO2), NOx (N2O,NO,NO2), Hydrogen Sulfide(H2S),
Halocarbons(CFCs and HCFCs), methane, HO radicals, etc. These are responsible for the destruction of
the stratospheric ozone layer, that protects the earth from harmful ultraviolet radiation, also known as
Green House Gases (GHG), and has subjected the global community to a disastrous ecological imbalance
known as Ozone Layer Depletion, which resulted to a catastrophic phenomenon called Global Warming,
a precursor of climate change and other pandemic effects, such as the damaging of the DNA of plants and
animals, skin cancers, cataracts, etc.
These gases are mainly anthropogenic in nature (i.e. caused by human factors) and are mostly due to gas
flaring. No wander, the United Nations in the Frame Work Convention on climate change (UNFCCC)
known as Kyoto Protocol, declared the above gases as Green House Gases, and they are mainly caused by
gas flaring. This resulted in the United Nations resolution to stop gas flaring.
A recent data released from the Nigerian National Petroleum Corporation (NNPC), that oil and gas
companies in Nigeria burn over $3.5 to $5 billion yearly from over 257 flow stations in the Niger Delta.
That specifically, the country flared about 17.15 per cent of the 95,471 metric tons of gas produced in
June 2015 alone. Also, the Organization of Petroleum Exporting Countries (OPEC) stated in 2015
Statistical Report, that Nigeria produced 86,325.2 million standard cubic meters in 2014. Also, NNPC
disclosed that Nigeria lost up to $868.8 million, about =N=173.76 billion to gas flaring in 2014.Using the
Nigeria Gas Company’s(NGC) price of $3 per 1000 SCF of gas at the current exchange rate realities,, the
flaring of 289.6 billion SCF of gas translated to a loss of $868.8 million, an equivalent of =N=173.76
billion. Specifically, the oil and gas company produced 2.524 trillion SCF of gas, utilized 2.235 trillion
SCF and flared 289.6 billion SCF.
Against these backdrops and the likes of it, Nigeria came up with a legislation to stop gas flaring. This
gave birth to the present gas monetization process in Nigeria, for which Ogabiri Gas Gathering project is
the nucleus.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 6 of 19
1.1 BACKGROUND
Fig.1.0 Map Outlay of Ogabiri Gas Gathering Project.
Ogabiri Gas Gathering Project is made up of five flow stations/facilities, thus: Ibugben, Ogabiri-1,
Ogabiri-2, Rumokun-1 and Rumokun-2, with the central gas gathering facility located at Ogabiri-1,
gathering gases from Ibugben, Rumokun-1 and 2 respectively, via gas pipelines, existing along the right
of way. Then, en Route Ogabiri-2, where the new Gas Treatment and Compression Facilities are to be
installed. Here, the gas will be treated according to the West African Gas Pipelines’ specification before
exiting to the NGC Excravos-Lagos Pipeline Systems (ELPS) via a 4.5km new right of way.
1.2 SCOPE OF WORK.
The Field Engineering Limited’s Ogabiri Gas Gathering Project contract scope of this work covers the
preparation of Pipelines Material Datasheets for the entire flow stations and their corresponding pipeline
connections, that made up the Ogabiri Gas Gathering Project. To achieve this, the entire Ogabiri Projects’
various streams’gas and water compositons and conditions were simulated using PIPESIM and HYSIS.
The design simulation of the various pipeline systems connecting the entire facilities en route the
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 7 of 19
Escravos- Lagos-Pipelines-System (ELPS), was done using PIPESIM and HYSIS simulations, as
presented in the tables below.
The design conditions, compositions, calculation results, codes, etc, of the high pressure gas line systems
of the entire project facilities as shown in the tables below. Pipeline testing is also included to ensure
compliance to ISO, ASME and ASTM specifications.
1.3 ACKNOWLEDGEMENT.
The contractor(our company), Field Engineering Limited, do hereby express their profound gratitude to
Shell Petroleum Development Company(SPDC), Nigeria, and their partner Nestoil Nigeria Limited, for
the opportunity to execute on their behalf, the Ogabiri Gas Gathering Project.
A contract project of this magnitude could not have been satisfactorily executed without the active
support, co-operation and understanding, as well as abiding patience of the SPDC and Nestoil staff that
are intimately connected with the project. In this regard, we sincerely thank Dr. Chris Ucheobi, the Head
of the K2S Engineering Department, Mr. Lovel Omoanreghan and Mrs. Roseline Uzuegbu, of Nestoil
Nigeria Limited, respectively. Also, Adedotun, Taiwo, Oladipo, facilitators of the training consultants to
Nestoil.
Our company’s appreciation and thanks go to the chiefs, community leaders and youths of the respective
communities involved directly or indirectly for the conducive atmosphere enjoyed during the execution of
this project. Our special gratitude also goes to the youth leaders of the respective communities involved,
for their invaluable maturity, assistance and roles towards a hitch-free execution of this project contract.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 8 of 19
1.4 DESIGN INTERFACE.
Fig.1.1 Pipsim Simulation Network of the Ogabiri Gas Gathering Project.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 9 of 19
Fig.1.2 Hysis Simulation Network of the Ogabiri Gas Gathering Project
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 10 of 19
The 37 km Ogabiri Gas Gathering Project via existing Right of Way (ROW), en route the bushy/swampy
terrain of the communities involved, thus; Ibugben, Rumokun and Ogabiri, connecting the Ogabiri Gas
Gathering Facility, from where the gas will be transported to NGS Excravos via ELPS pipeline route. The
pipeline will interface at the other end with a Pig Launcher/Receivers, as well as other tie-in integration
requirements.
Pipeline Design Teams will interface with these other teams: Process Engineering, Mechanical
Engineering, Piping, Civil/Structural Engineering as well as Electrical Engineering & Instrumentations
Engineering, for the success of the project and will during the course of this project, exchange inputs with
the afore-mentioned disciplines. The Pipeline teams will also interface with the project management team
for effective and timely delivery of the entire project.
2.0 FORWARD
This document shall be read along with the following documents:
Detailed Pipeline Design Report for Nine Kilometer Pipeline Connecting the Ibugben Flow
Station and Ogabiri-1 Manifold: No. PROS/OGBR/RPT/151/003 and other teams’ reports.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 11 of 19
3.0 TECHNICAL DATA FOR THE GAS PIPELINES
3.1 DIMENSIONS FOR PIPELINES
Table 3.1 Dimension for Pipelines.
PARAMETERS. GAS REQUIREMENTS.
IBUGBEN
(Ibugben to
Ogabiri-1
M/F)
RUMOKU
N-1
(Rumokun-
1 to
Ogabiri-1
M/F)
RUMOKU
N-2
(Rumokun-
2 to
Ogabiri-1
M/F)
OGABIRI-1
M/F
(Ogabiri-1
M/F passing
through
{Ogabiri-2
M/F} to
CPF)
CPF to
ELPS.
NPS(INCH) 38 38 42 42 28
OUTSIDE DIAMETER(mm)
(B31.8)
1050.8 1000.7 1050.8 1067.3 701.0
WALL THICKNESS(mm) 12.7 12.7 12.7 12.7 12.7
CORROSION
ALLOWANCE(mm)
1.0 1.0 1.0 1.0 1.0
DESIGN TEMPERATURE
MAXIMUM(0
C)
29.4 26.7 29.4 26.7 51.3
AVERAGE LENGHT OF
PIPE(M)
9,000.00 12,000.00 8,500.00 3000.00 4,500.00
JOINT FACTOR 0.8 0.8 0.8 0.8 0.8
DIMENSION STANDARD API 5L API 5L API 5L API 5L API 5L
MATERIAL DESCRIPTION API 5L X60 API 5L
X60
API 5L
X60
API 5L X60 API 5L
X60
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 12 of 19
3.2 QUANTITIES
Table 3.2 Quantities.
PLAIN END MASS(km) 298.26 298.26 298.26 330.21 218.7
1
PARAMETERS GAS REQIREMENTS
IBUGBEN
(Ibugben to
Ogabiri-1 M/F)
RUMOKUN-1
(Rumokun-1 to
Ogabiri-1 M/F)
RUMOKUN-2
(Rumokun-2 to
Ogabiri-1 M/F)
OGABIRI-1
M/F
(Ogabiri-1 M/F
passing through
Ogabiri-2
{M/F} to CPF)
CPF TO ELPS.
THICKNESS(mm) 12.7 12.7 12.7 12.7 12.7
REQUIRED
LENGTH(mm)
9,000,000.00 12,000,000.00 8,500,000.00 3,000,000.00 4,500,000.00
ESCALATION
30%(mm)
2,700,000.00 3,600,000.00 2,550,000.00 900,000.00 1,350,000.00
TOTAL
LENGTH(mm)
11,700,000.00 15,600,000.00 11,050000.00 3,900,000.00 5,850,000.00
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 13 of 19
3.3 ANTI-CORROSION.
Table 3.3 Anti-corrosion.
PARAMETER PIPE
EXTERNAL COATING 3-LAYER POLYETHYLENE COATING
NOTES:
1. The average length of deliverable pipes shall be 12.0m, though a minimum of 90% of
Pipes between 11m and 12.5m may be allowed.
2. There should be end bevelling of an angle of 30o
for plain-end pipes, with respect to
API 5L specification.
3. The actual quantity is verifiable in the Results of Detailed Design and Engineering below.
4. The length given here represents the preliminary pipe length and bends
requirement. K2S Department of Nestoil Nigeria Limited shall confirm the above
ground, on-ground and underground pipes.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 14 of 19
3.4 RESULTS OF DETAILED DESIGN AND ENGINEERING.
Table 3.4 Results of the Detailed Design and Engineering.
S/N PARAMETER
DESCRIPTION
DATA UNIT
1 PROCESS IBUGB
EN(Ibug
ben to
Ogabiri-
1 M/F)
RUMO
KUN-
1(Rumo
kun-1 to
Ogabiri-
1 M/F)
RUMOK
UN-
2(Rumok
un-2 to
Ogabiri-1
M/F)
OGABIRI
-
1(Ogabiri
-1 M/F
passing
through
Ogabiri-
2{M/F}
to CPF)
CPF TO
ELPS.
1.1 Gas Inlet Temperature. 29.44 26.67 29.44 26.67 51.27 O
C
1.2 Gas Inlet Pressure. 4000 4200 4000 3938 6000 KPa
1.3 Gas Inlet Molar Flow. 4.98 10.08 28.95 30.82 81.16 MMS
CFD
1.4 Pipeline Temperature
Change.
1.994 0.5568 0.8201 26.00 1.266 O
C
1.5 Pipeline Pressure
Drop.
4.785 2.778 62.42 3938 65.09 KPa
1.6 Pipeline Heat-loss. 2.172e+
004
234.3 3.059e+0
04
64.95 1.820e+
005
KJ/h
1.7 Gas Outlet
Temperature.
27.45 28.89 25.85 25.12 50.00 O
C
1.8 Gas Outlet Pressure. 3995 4197 3938 3866 5935 KPa
1.9 Gas Outlet Molar
Flow.
4.980 0.2024 28.95 75.01 81.16 MMS
CFD
1.10 Design life 25 25 25 25 25 Yrs
1.11 Minimum Bend
Radius:
1.11.1 Cold Bending Radius 10508 10007 10508 10673 7005 MM
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 15 of 19
1.11.2 Hot Bending Radius 4203.2 4002.8 4203.2 4269.2 2802 MM
1.11.3 With Other Bending
Devices
2101.6 2001.4 2101.6 2134.6 1401 MM
1.12 Pipe outside diameter 1050.8 1000.7 1050.8 1067.3 701.0 MM
1.13 Pipe inside diameter 1025.4 975.3 1025.4 1041.9 675.1 MM
1.14 Pipe wall thickness
(Mainline seasonal
swamp/land) section
12.7 12.7 12.7 12.7 12.7 MM
1.15 Pipe wall thickness
(mainline river/road
crossing) section
NONE NONE NONE NONE NONE MM
1.16 Pipe wall thickness
(Major barrels)
12.7 12.7 12.7 12.7 12.7 MM
1.17 Pipe Grade API 5L
X60
API 5L
X60
API 5L
X60
API 5L
60
API 5L
60
NA
1.18 Flow Velocity Range 15.24 –
4.27
15.24 –
4.27
15.24 –
4.27
15.24 –
4.27
15.24 –
4.27
M/S
2 TOPOGRAPHICAL
2.1 Pipeline length 9.00 12.00 8.50 3.00 4.50 KM
2.2 River Crossings None None None None None None
2.3 Rivers Crossing Block
Valves
(Upstream/Down
stream of Rivers
Crossings)
None None None None None None
2.4 Creek crossing ≥ 20m None None None None None None
2.5 Creek crossing < 20m None None None None None None
2.6 Road crossing ≥ 15m None None None None None None
2.7 Road crossing < 15m None None None None None None
2.8 Burial depth
(underwater cover @
creeks) - below
mudline.
None None None None None M
2.9 Burial Depth
(underwater cover @
river crossing) – below
mud cut.
None None None None None M
2.10 Burial Depth
(minimum cover) –
1.5 1.5 1.5 1.5 1.5 M
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 16 of 19
Rural Road Crossing
by
2.11 Burial Depth
(Minimum cover
below undisturbed
ground surface) –
Major Road Crossing
by Thrust Bore
1.0 1.0 1.0 1.0 1.0 M
3. CORROSION
CONTROL
3.1 Corrosion Allowance 0.1 0.1 0.1 0.1 0.1 MM/
YR
3.2 External Concrete
Coating (Swamp/River
Sections)
80 80 80 80 80 MM
3.3 External Anti-
Corrosion Coating (3-
Layer Polyethylene)
3.2 3.2 3.2 3.2 3.2 MM
3.4 Internal Coating None None None None None -NA-
3.5 Cathodic Protection
(By Impressed
Current)
Yes Yes Yes Yes Yes -NA-
3.6 Corrosion Monitoring
(By Intelligent Pig)
Yes Yes Yes Yes Yes -NA-
3.7 Electrical Insulation
(By Insulating Joints
@ above/below
ground
transitions)
Yes Yes Yes Yes Yes -NA-
3.8 Corrosion Inhibition
Yes
Yes Yes Yes Yes Yes
4 ANCILLIARY
EQUIPMENT
4.1 Pig Launcher /
Receiver
Yes Yes Yes Yes Yes NO
4.2 Mixer Yes Yes Yes Yes Yes NO
4.3 Slug Catcher Yes Yes Yes Yes Yes NO
4.4 Water Splitter Yes Yes Yes Yes Yes NO
4.5 Booster Compressor Yes Yes Yes Yes Yes NO
5 ENVIRONMENTAL
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 17 of 19
5.1 Maximum Wind
Speed.
20.5 20.5 20.5 20.5 20.5 M/S
5.2 Average Daily
Relative
Humidity(Maximum)
97 97 97 97 97 %
5.3 Average Daily
Relative
Humidity(Minimum)
83 83 83 83 83 %
5.4 Average Daily
Relative
Humidity(Mean)
72 72 72 72 72 %
5.5 Ambient temperature
(Maximum)
29.4 29.4 29.4 29.4 29.4 0
C
5.6 Ambient Temperature
(Minimum)
18 18 18 18 18 0
C
5.7 Mean Maximum
Hourly Rainfall
100 100 100 100 MM
5.8 Mean Maximum
Monthly
Rainfall(occurs in
September)
355 355 355 355 355 MM
5.9 Average Annual
Rainfall
2800 2800 2800 2800 2800 MM
4.0 CONCLUSION
This project was carefully executed with enough up-to-date science and technology, which guaranteed
strict compliance and attainment to internationally accepted standards of pipeline for transportation of
hydrocarbon natural gas, without compromising the ecological sanctity of the concerned area, being
guided with the Environmental Impact Assessment(E.I.A), conducted before the take off of this project
execution.
REFERENCE DOCUMENTS.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 18 of 19
The choice of material and equipment, design, construction, maintenance as well as repair of equipment
and facilities covered by the industry guidelines shall comply with the latest edition of the references
listed below, unless specifically noted.
DOCUMENT HIERARCHY.
Should there be any conflicts with respect to any/some of the documents used in this project, reference
should be made to the following listed documents arranged in an order of descending priority, thus:
1. Nigerian Law.
2. The contract.
3. Ogabiri FEED approved documents.
4. WAGC Guidelines and Standards.
5. WAGC Design and Engineering Practices.
6. Industry Guidelines and Standards.
7. SPDC’s Kolo Creek – Rumuekpe T/L Replacement EIA Report.
8. The Guardian: www.ngrguardiannews.com>Features>Weekend.
9. Requirements Concerning Pipes and Pressure Vessels.
- International Association of Classification Societies.
10.Welded Steel Pipe Design Manual 2007.
(Merits, Design Standards, Technical and References)
American Iron and Steel Institute.
Publication Number D631-0807-e
11.Gas Transmission System Design and Selection.
Session 3 Gas Transmission System Design Material Selection EP.
12.Guidelines for the Design of Buried Pipe.
American Life Alliance.
THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING
PROJECT.
DCC NUMBER
PROS/OGBR/PPL/RPT/151
003
Revision
: Y01
Status : IDC
DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy
:DESIGN
Rev. Date :
PROS/OGBR/PPL/RPT/151003.
Page 19 of 19
July 2001(with added agenda through February 2005)
13.ASME B31.8: Gas Transmission and Distribution Piping Systems.
49 CFR 192.619 (a) (1) (i)
14.Restoration of Right of Way
8, August 2008. < http://www.ngaa.org/cms/33/1339/65/84.aspx>
15.Trenching for New Pipelines.
8, August, 2008. <http:www.ngaa.org/cms/33/1339/65/73.aspx>
16.Stringing, Welding and Coating Pipe Segments.
8,August, 2008. <http://www.ngaa.org/cms/33/1339/65/70.aspx>
17.Assuring the Integrity of Natural Gas Pipeline.
Posakony, G.J. et al.
Topical Report. GRI-91/0366, Chicago, 1993.
18.The Design and Location of Gas Transmission Pipeline Using Risk Analysis Techniques, Risk and
Reliabilty and Limit State Conference, Aberdeen, May,1996.
Hopkins,P., Hopkins,H.F., I Corder.
19.Pipelines Onland: Design, Construction and Installation, Steel For Oil and Gas, British Standard
Institute, 1992.
Anon. , Code of Practice for Pipelines, BS 8010 Part 2.8.

More Related Content

What's hot

Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guideram111eg
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)Velmurugan Sivaraman
 
Piping interview
Piping interviewPiping interview
Piping interviewAkhilesh Kumar
 
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Pradeep Dhondi
 
Introduction - Artificial lift
Introduction - Artificial liftIntroduction - Artificial lift
Introduction - Artificial liftAndi Anriansyah
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and designHĂ©ctor Nguema Ondo
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentationMohamed Gaafar
 
Well Completion Design.pdf
Well Completion Design.pdfWell Completion Design.pdf
Well Completion Design.pdfmmody4
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerVarun Patel
 
Piping material-specification
Piping material-specificationPiping material-specification
Piping material-specificationChiragShah127
 
Tubing string
Tubing stringTubing string
Tubing stringElsayed Amer
 
Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenationsumit handa
 
Asme Code Calculations Cylindrical Components
Asme Code Calculations  Cylindrical ComponentsAsme Code Calculations  Cylindrical Components
Asme Code Calculations Cylindrical ComponentsAbdulbari Hajamohaideen
 
Design for Overpressure and Underpressure Protection
Design for Overpressure and Underpressure ProtectionDesign for Overpressure and Underpressure Protection
Design for Overpressure and Underpressure ProtectionThapa Prakash (TA-1)
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreMohamed Abdelshafy Abozeima
 
PIPING AND INSTRUMENTATION DIAGRAMS.pdf
PIPING AND INSTRUMENTATION DIAGRAMS.pdfPIPING AND INSTRUMENTATION DIAGRAMS.pdf
PIPING AND INSTRUMENTATION DIAGRAMS.pdfeldoctol
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanksbernard347
 
Shell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonShell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonJuan Pablo Hernandez
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API BasedVijay Sarathy
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1Om Pratap Singh
 

What's hot (20)

Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guide
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
Piping interview
Piping interviewPiping interview
Piping interview
 
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
 
Introduction - Artificial lift
Introduction - Artificial liftIntroduction - Artificial lift
Introduction - Artificial lift
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and design
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
Well Completion Design.pdf
Well Completion Design.pdfWell Completion Design.pdf
Well Completion Design.pdf
 
Fundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas EngineerFundamental of Pipes for Oil & Gas Engineer
Fundamental of Pipes for Oil & Gas Engineer
 
Piping material-specification
Piping material-specificationPiping material-specification
Piping material-specification
 
Tubing string
Tubing stringTubing string
Tubing string
 
Pressure Relief Devices_Presenation
Pressure Relief Devices_PresenationPressure Relief Devices_Presenation
Pressure Relief Devices_Presenation
 
Asme Code Calculations Cylindrical Components
Asme Code Calculations  Cylindrical ComponentsAsme Code Calculations  Cylindrical Components
Asme Code Calculations Cylindrical Components
 
Design for Overpressure and Underpressure Protection
Design for Overpressure and Underpressure ProtectionDesign for Overpressure and Underpressure Protection
Design for Overpressure and Underpressure Protection
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and more
 
PIPING AND INSTRUMENTATION DIAGRAMS.pdf
PIPING AND INSTRUMENTATION DIAGRAMS.pdfPIPING AND INSTRUMENTATION DIAGRAMS.pdf
PIPING AND INSTRUMENTATION DIAGRAMS.pdf
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Shell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparisonShell and tube heat exchanger design comparison
Shell and tube heat exchanger design comparison
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API Based
 
Pressure Reliveing Devices1
Pressure Reliveing Devices1Pressure Reliveing Devices1
Pressure Reliveing Devices1
 

Viewers also liked

Offshore pipelines design, analysis & method
Offshore pipelines   design, analysis & methodOffshore pipelines   design, analysis & method
Offshore pipelines design, analysis & methodThanh Tran
 
Part 5 structural design of pipelines
Part 5 structural design of pipelinesPart 5 structural design of pipelines
Part 5 structural design of pipelinesGasforlife Polysource
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore ApproachMohd Zaini Baharum
 
Subsea Pipeline Engineering
Subsea Pipeline EngineeringSubsea Pipeline Engineering
Subsea Pipeline EngineeringpetroEDGE
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design ReportRAPHAEL AGORUA
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline Sarah Busef
 
Gas Pipeline Design
Gas Pipeline DesignGas Pipeline Design
Gas Pipeline Designiyaselex
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesvinod kumar
 
Pipeline Design Philosophy
Pipeline Design PhilosophyPipeline Design Philosophy
Pipeline Design PhilosophyRAPHAEL AGORUA
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerationsalco345ua
 
Modes of transportation - Pipelines
Modes of transportation  - PipelinesModes of transportation  - Pipelines
Modes of transportation - PipelinesCP default
 
Pipeline basic
Pipeline basicPipeline basic
Pipeline basicmageshyess
 
PHMSA: Safety of Gas Transmission & Gathering Pipelines Summary
PHMSA: Safety of Gas Transmission & Gathering Pipelines SummaryPHMSA: Safety of Gas Transmission & Gathering Pipelines Summary
PHMSA: Safety of Gas Transmission & Gathering Pipelines SummaryProject Consulting Services, Inc.
 
South Stream Offshore Pipeline Brochure
South Stream Offshore Pipeline BrochureSouth Stream Offshore Pipeline Brochure
South Stream Offshore Pipeline BrochureSimon Van Boesschoten
 
LNG Philippines - Situationer
LNG Philippines - SituationerLNG Philippines - Situationer
LNG Philippines - Situationernoelgamboaylopez
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Pipeline construction and its types
Pipeline construction and its typesPipeline construction and its types
Pipeline construction and its typesprsmed
 
Oil and Gas second edition
Oil and Gas second editionOil and Gas second edition
Oil and Gas second editionGulfam Raza
 

Viewers also liked (20)

INIO2014 Presentation
INIO2014 PresentationINIO2014 Presentation
INIO2014 Presentation
 
Offshore pipelines design, analysis & method
Offshore pipelines   design, analysis & methodOffshore pipelines   design, analysis & method
Offshore pipelines design, analysis & method
 
Part 5 structural design of pipelines
Part 5 structural design of pipelinesPart 5 structural design of pipelines
Part 5 structural design of pipelines
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore Approach
 
Subsea Pipeline Engineering
Subsea Pipeline EngineeringSubsea Pipeline Engineering
Subsea Pipeline Engineering
 
Pipeline Design Report
Pipeline Design ReportPipeline Design Report
Pipeline Design Report
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline
 
Pipeline Construction
Pipeline ConstructionPipeline Construction
Pipeline Construction
 
Gas Pipeline Design
Gas Pipeline DesignGas Pipeline Design
Gas Pipeline Design
 
over veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelinesover veiw on desighn of offshore pipelines
over veiw on desighn of offshore pipelines
 
Pipeline Design Philosophy
Pipeline Design PhilosophyPipeline Design Philosophy
Pipeline Design Philosophy
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerations
 
Modes of transportation - Pipelines
Modes of transportation  - PipelinesModes of transportation  - Pipelines
Modes of transportation - Pipelines
 
Pipeline basic
Pipeline basicPipeline basic
Pipeline basic
 
PHMSA: Safety of Gas Transmission & Gathering Pipelines Summary
PHMSA: Safety of Gas Transmission & Gathering Pipelines SummaryPHMSA: Safety of Gas Transmission & Gathering Pipelines Summary
PHMSA: Safety of Gas Transmission & Gathering Pipelines Summary
 
South Stream Offshore Pipeline Brochure
South Stream Offshore Pipeline BrochureSouth Stream Offshore Pipeline Brochure
South Stream Offshore Pipeline Brochure
 
LNG Philippines - Situationer
LNG Philippines - SituationerLNG Philippines - Situationer
LNG Philippines - Situationer
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Pipeline construction and its types
Pipeline construction and its typesPipeline construction and its types
Pipeline construction and its types
 
Oil and Gas second edition
Oil and Gas second editionOil and Gas second edition
Oil and Gas second edition
 

Similar to Pipeline Design

PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTRAPHAEL AGORUA
 
IRJET- Applications of Alternative Fuels in Maritime Industry
IRJET- Applications of Alternative Fuels in Maritime IndustryIRJET- Applications of Alternative Fuels in Maritime Industry
IRJET- Applications of Alternative Fuels in Maritime IndustryIRJET Journal
 
Co2 capture-technologies
Co2 capture-technologiesCo2 capture-technologies
Co2 capture-technologiesDzung Le
 
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Global CCS Institute
 
Atlantic Council - Darren Mollot
Atlantic Council - Darren MollotAtlantic Council - Darren Mollot
Atlantic Council - Darren MollotGlobal CCS Institute
 
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLY
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLYPRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLY
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLYiQHub
 
1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-mainHeri Faisandra
 
Detlef Stolten at BASF Science Symposium 2015
Detlef Stolten at BASF Science Symposium 2015Detlef Stolten at BASF Science Symposium 2015
Detlef Stolten at BASF Science Symposium 2015BASF
 
AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813Global CCS Institute
 
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...theijes
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...atlanticcouncil
 
Carbon Capture and Storage
Carbon Capture and StorageCarbon Capture and Storage
Carbon Capture and StorageAshokaNarayanan3
 
Anup.Shepati_1B.pdf green hydrogen storage and production
Anup.Shepati_1B.pdf green hydrogen storage and productionAnup.Shepati_1B.pdf green hydrogen storage and production
Anup.Shepati_1B.pdf green hydrogen storage and productionmoazrezk507
 
1-s2.0-S1876610211008265-main.pdf
1-s2.0-S1876610211008265-main.pdf1-s2.0-S1876610211008265-main.pdf
1-s2.0-S1876610211008265-main.pdfShahFaisal672527
 
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesRenewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesJaapaz
 
Capstone Final
Capstone FinalCapstone Final
Capstone FinalConnor Jarvis
 

Similar to Pipeline Design (20)

PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
 
IRJET- Applications of Alternative Fuels in Maritime Industry
IRJET- Applications of Alternative Fuels in Maritime IndustryIRJET- Applications of Alternative Fuels in Maritime Industry
IRJET- Applications of Alternative Fuels in Maritime Industry
 
Co2 capture-technologies
Co2 capture-technologiesCo2 capture-technologies
Co2 capture-technologies
 
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
 
WtE-Gulf forum presentation
WtE-Gulf forum presentationWtE-Gulf forum presentation
WtE-Gulf forum presentation
 
Atlantic Council - Darren Mollot
Atlantic Council - Darren MollotAtlantic Council - Darren Mollot
Atlantic Council - Darren Mollot
 
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
 
Ijaret 06 10_020
Ijaret 06 10_020Ijaret 06 10_020
Ijaret 06 10_020
 
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLY
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLYPRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLY
PRODUCTION & LOGISTICS FOR AN IN-MARKET FRAC SAND SUPPLY
 
1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main1 s2.0-s1876610217320210-main
1 s2.0-s1876610217320210-main
 
Detlef Stolten at BASF Science Symposium 2015
Detlef Stolten at BASF Science Symposium 2015Detlef Stolten at BASF Science Symposium 2015
Detlef Stolten at BASF Science Symposium 2015
 
AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813
 
CCUS_Mobile
CCUS_MobileCCUS_Mobile
CCUS_Mobile
 
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...
Benefits and Challenges of Implementing Carbon Capture and Sequestration Tech...
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
 
Carbon Capture and Storage
Carbon Capture and StorageCarbon Capture and Storage
Carbon Capture and Storage
 
Anup.Shepati_1B.pdf green hydrogen storage and production
Anup.Shepati_1B.pdf green hydrogen storage and productionAnup.Shepati_1B.pdf green hydrogen storage and production
Anup.Shepati_1B.pdf green hydrogen storage and production
 
1-s2.0-S1876610211008265-main.pdf
1-s2.0-S1876610211008265-main.pdf1-s2.0-S1876610211008265-main.pdf
1-s2.0-S1876610211008265-main.pdf
 
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder ResiduesRenewable Energy From Municipal Solid Waste And Automobile Shredder Residues
Renewable Energy From Municipal Solid Waste And Automobile Shredder Residues
 
Capstone Final
Capstone FinalCapstone Final
Capstone Final
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 

Pipeline Design

  • 1. FIELD ENGINEERING LIMITED PROSERVE OGABIRI GAS GATHERING PROJECT. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GATHERING PROJECT. DCC NUMBER: PROS/OGBR/PIP/RPT/151003 RO2 01/12/2015 IFR A.R.O. A.M. E.C.U. RO1 04/11/2015 IDC A.R.O. A.M. E.C.U. Revision Date: Status: Issued by Checked by Approved by COMPANY Approval
  • 2. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 2 of 19 TABLE OF CONTENTS Page List of Illustrations --------------------------------------------------------------------------------- 3 List of Tables --------------------------------------------------------------------------------------- 3 List of Abbreviations ------------------------------------------------------------------------------ 3 1.0 INTRODUCTION -------------------------------------------------------------------------- 5 1.1 BACKGROUND ----------------------------------------------------------------------- 6 1.2 SCOPE OF WORK --------------------------------------------------------------------- 7 1.3 ACKNOWLEDGEMENT -------------------------------------------------------------- 7 1.4 DESIGN INTERFACE ------------------------------------------------------------------ 8 2.0 FORWARD ------------------------------------------------------------------------------- 10 3.0 TECHNICAL DATA FOR OGABIRI GAS GATHERING PROJECT ---------- 11 3.1 DIMENSION FOR PIPELINES -------------------------------------------------------- 11 3.2 QUANTITIES ---------------------------------------------------------------------------- 12 3.3 ANTICORROSION --------------------------------------------------------------------- 13 3.4 RESULTS OF DETAILED DESIGN AND ENGINEERING --------------------- 14 4.0 CONCLUSION -------------------------------------------------------------------------- 17 REFERENCE DOCUMENT-----------------------------------------------------------------------------17 DOCUMENT HIERARCHY-----------------------------------------------------------------------------17 LIST OF ILLUSTRATION Fig.1.0 Map Outlay of Ogabiri Gas Gathering Project------------------------------------------------ 6 Fig.1.1 Pipesim Simulation Network of the Ogabiri Gas Gathering Project-----------------------8
  • 3. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 3 of 19 Fig.1.2 Hysis Simulation Network of the Ogabiri Gas Gathering Project----------------------9 LIST OF TABLES Table.3.1. Dimension for Pipelines -------------------------------------------------------------------8 Table.3.2.Quantities ------------------------------------------------------------------------------------12 Table.3.3.Anti-corrosion -------------------------------------------------------------------------------13 Table.3.4. Result of Detailed Design and Engineering --------------------------------------------14 LIST OF ABBREVIATIONS/ACRONYMS ASME– American Society of Mechanical Engineering. ASTM– American Society of Testing and Material. 13 Cr - 13-Chrome 16” - Twenty inches o C - Degrees Celsius C/S – Cladded Steel CFC – Chlorofluorocarbon CO - Carbon monoxide CO2 - Carbon dioxide DNA – Deoxyribonucleic Acid. DSAW - Double Submerged Arc Welded ELPS – Escravos Lagos Pipeline System. ERW - Electric Resistance Welded FBE - Fusion Bonded Epoxy. FEED – Front End Engineering Drawing.
  • 4. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 4 of 19 GHG – Greenhouse Gas. GRE - Glass Reinforced Epoxy HDPE - High Density Polyethylene HCFC – Hydrochlorofluocarbon ISO - International Standard Organization M/F - Manifold m/s - meter per second NGC – Nigerian Gas Company. NNPC – Nigerian National Petroleum Corporation. NO2 - Nitrogen dioxide N2O – Di-nitrogen oxide NO- Nitrous oxide NOx – Nitrogen-Oxygen compounds. OPEC – Organization of Petroleum Exporting Countries. PVC - Polyvinyl casing ROW - Right of Way RTP - Reinforced Thermoplastic SCF – Standard Cubic Feet. SPDC - Shell Petroleum Development Company UNFCCC – United Nations Framework Convention on Climate Change. NGS– Nigerian Gas Station. API– American Petroleum Institute. WAGC– West African Gas Company.
  • 5. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 5 of 19 1.0 INTRODUCTION The world as a global village is confronted presently with the threat of extinction as a result of incessant emission of dangerous gases such as carbon dioxide(CO2), NOx (N2O,NO,NO2), Hydrogen Sulfide(H2S), Halocarbons(CFCs and HCFCs), methane, HO radicals, etc. These are responsible for the destruction of the stratospheric ozone layer, that protects the earth from harmful ultraviolet radiation, also known as Green House Gases (GHG), and has subjected the global community to a disastrous ecological imbalance known as Ozone Layer Depletion, which resulted to a catastrophic phenomenon called Global Warming, a precursor of climate change and other pandemic effects, such as the damaging of the DNA of plants and animals, skin cancers, cataracts, etc. These gases are mainly anthropogenic in nature (i.e. caused by human factors) and are mostly due to gas flaring. No wander, the United Nations in the Frame Work Convention on climate change (UNFCCC) known as Kyoto Protocol, declared the above gases as Green House Gases, and they are mainly caused by gas flaring. This resulted in the United Nations resolution to stop gas flaring. A recent data released from the Nigerian National Petroleum Corporation (NNPC), that oil and gas companies in Nigeria burn over $3.5 to $5 billion yearly from over 257 flow stations in the Niger Delta. That specifically, the country flared about 17.15 per cent of the 95,471 metric tons of gas produced in June 2015 alone. Also, the Organization of Petroleum Exporting Countries (OPEC) stated in 2015 Statistical Report, that Nigeria produced 86,325.2 million standard cubic meters in 2014. Also, NNPC disclosed that Nigeria lost up to $868.8 million, about =N=173.76 billion to gas flaring in 2014.Using the Nigeria Gas Company’s(NGC) price of $3 per 1000 SCF of gas at the current exchange rate realities,, the flaring of 289.6 billion SCF of gas translated to a loss of $868.8 million, an equivalent of =N=173.76 billion. Specifically, the oil and gas company produced 2.524 trillion SCF of gas, utilized 2.235 trillion SCF and flared 289.6 billion SCF. Against these backdrops and the likes of it, Nigeria came up with a legislation to stop gas flaring. This gave birth to the present gas monetization process in Nigeria, for which Ogabiri Gas Gathering project is the nucleus.
  • 6. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 6 of 19 1.1 BACKGROUND Fig.1.0 Map Outlay of Ogabiri Gas Gathering Project. Ogabiri Gas Gathering Project is made up of five flow stations/facilities, thus: Ibugben, Ogabiri-1, Ogabiri-2, Rumokun-1 and Rumokun-2, with the central gas gathering facility located at Ogabiri-1, gathering gases from Ibugben, Rumokun-1 and 2 respectively, via gas pipelines, existing along the right of way. Then, en Route Ogabiri-2, where the new Gas Treatment and Compression Facilities are to be installed. Here, the gas will be treated according to the West African Gas Pipelines’ specification before exiting to the NGC Excravos-Lagos Pipeline Systems (ELPS) via a 4.5km new right of way. 1.2 SCOPE OF WORK. The Field Engineering Limited’s Ogabiri Gas Gathering Project contract scope of this work covers the preparation of Pipelines Material Datasheets for the entire flow stations and their corresponding pipeline connections, that made up the Ogabiri Gas Gathering Project. To achieve this, the entire Ogabiri Projects’ various streams’gas and water compositons and conditions were simulated using PIPESIM and HYSIS. The design simulation of the various pipeline systems connecting the entire facilities en route the
  • 7. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 7 of 19 Escravos- Lagos-Pipelines-System (ELPS), was done using PIPESIM and HYSIS simulations, as presented in the tables below. The design conditions, compositions, calculation results, codes, etc, of the high pressure gas line systems of the entire project facilities as shown in the tables below. Pipeline testing is also included to ensure compliance to ISO, ASME and ASTM specifications. 1.3 ACKNOWLEDGEMENT. The contractor(our company), Field Engineering Limited, do hereby express their profound gratitude to Shell Petroleum Development Company(SPDC), Nigeria, and their partner Nestoil Nigeria Limited, for the opportunity to execute on their behalf, the Ogabiri Gas Gathering Project. A contract project of this magnitude could not have been satisfactorily executed without the active support, co-operation and understanding, as well as abiding patience of the SPDC and Nestoil staff that are intimately connected with the project. In this regard, we sincerely thank Dr. Chris Ucheobi, the Head of the K2S Engineering Department, Mr. Lovel Omoanreghan and Mrs. Roseline Uzuegbu, of Nestoil Nigeria Limited, respectively. Also, Adedotun, Taiwo, Oladipo, facilitators of the training consultants to Nestoil. Our company’s appreciation and thanks go to the chiefs, community leaders and youths of the respective communities involved directly or indirectly for the conducive atmosphere enjoyed during the execution of this project. Our special gratitude also goes to the youth leaders of the respective communities involved, for their invaluable maturity, assistance and roles towards a hitch-free execution of this project contract.
  • 8. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 8 of 19 1.4 DESIGN INTERFACE. Fig.1.1 Pipsim Simulation Network of the Ogabiri Gas Gathering Project.
  • 9. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 9 of 19 Fig.1.2 Hysis Simulation Network of the Ogabiri Gas Gathering Project
  • 10. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 10 of 19 The 37 km Ogabiri Gas Gathering Project via existing Right of Way (ROW), en route the bushy/swampy terrain of the communities involved, thus; Ibugben, Rumokun and Ogabiri, connecting the Ogabiri Gas Gathering Facility, from where the gas will be transported to NGS Excravos via ELPS pipeline route. The pipeline will interface at the other end with a Pig Launcher/Receivers, as well as other tie-in integration requirements. Pipeline Design Teams will interface with these other teams: Process Engineering, Mechanical Engineering, Piping, Civil/Structural Engineering as well as Electrical Engineering & Instrumentations Engineering, for the success of the project and will during the course of this project, exchange inputs with the afore-mentioned disciplines. The Pipeline teams will also interface with the project management team for effective and timely delivery of the entire project. 2.0 FORWARD This document shall be read along with the following documents: Detailed Pipeline Design Report for Nine Kilometer Pipeline Connecting the Ibugben Flow Station and Ogabiri-1 Manifold: No. PROS/OGBR/RPT/151/003 and other teams’ reports.
  • 11. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 11 of 19 3.0 TECHNICAL DATA FOR THE GAS PIPELINES 3.1 DIMENSIONS FOR PIPELINES Table 3.1 Dimension for Pipelines. PARAMETERS. GAS REQUIREMENTS. IBUGBEN (Ibugben to Ogabiri-1 M/F) RUMOKU N-1 (Rumokun- 1 to Ogabiri-1 M/F) RUMOKU N-2 (Rumokun- 2 to Ogabiri-1 M/F) OGABIRI-1 M/F (Ogabiri-1 M/F passing through {Ogabiri-2 M/F} to CPF) CPF to ELPS. NPS(INCH) 38 38 42 42 28 OUTSIDE DIAMETER(mm) (B31.8) 1050.8 1000.7 1050.8 1067.3 701.0 WALL THICKNESS(mm) 12.7 12.7 12.7 12.7 12.7 CORROSION ALLOWANCE(mm) 1.0 1.0 1.0 1.0 1.0 DESIGN TEMPERATURE MAXIMUM(0 C) 29.4 26.7 29.4 26.7 51.3 AVERAGE LENGHT OF PIPE(M) 9,000.00 12,000.00 8,500.00 3000.00 4,500.00 JOINT FACTOR 0.8 0.8 0.8 0.8 0.8 DIMENSION STANDARD API 5L API 5L API 5L API 5L API 5L MATERIAL DESCRIPTION API 5L X60 API 5L X60 API 5L X60 API 5L X60 API 5L X60
  • 12. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 12 of 19 3.2 QUANTITIES Table 3.2 Quantities. PLAIN END MASS(km) 298.26 298.26 298.26 330.21 218.7 1 PARAMETERS GAS REQIREMENTS IBUGBEN (Ibugben to Ogabiri-1 M/F) RUMOKUN-1 (Rumokun-1 to Ogabiri-1 M/F) RUMOKUN-2 (Rumokun-2 to Ogabiri-1 M/F) OGABIRI-1 M/F (Ogabiri-1 M/F passing through Ogabiri-2 {M/F} to CPF) CPF TO ELPS. THICKNESS(mm) 12.7 12.7 12.7 12.7 12.7 REQUIRED LENGTH(mm) 9,000,000.00 12,000,000.00 8,500,000.00 3,000,000.00 4,500,000.00 ESCALATION 30%(mm) 2,700,000.00 3,600,000.00 2,550,000.00 900,000.00 1,350,000.00 TOTAL LENGTH(mm) 11,700,000.00 15,600,000.00 11,050000.00 3,900,000.00 5,850,000.00
  • 13. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 13 of 19 3.3 ANTI-CORROSION. Table 3.3 Anti-corrosion. PARAMETER PIPE EXTERNAL COATING 3-LAYER POLYETHYLENE COATING NOTES: 1. The average length of deliverable pipes shall be 12.0m, though a minimum of 90% of Pipes between 11m and 12.5m may be allowed. 2. There should be end bevelling of an angle of 30o for plain-end pipes, with respect to API 5L specification. 3. The actual quantity is verifiable in the Results of Detailed Design and Engineering below. 4. The length given here represents the preliminary pipe length and bends requirement. K2S Department of Nestoil Nigeria Limited shall confirm the above ground, on-ground and underground pipes.
  • 14. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 14 of 19 3.4 RESULTS OF DETAILED DESIGN AND ENGINEERING. Table 3.4 Results of the Detailed Design and Engineering. S/N PARAMETER DESCRIPTION DATA UNIT 1 PROCESS IBUGB EN(Ibug ben to Ogabiri- 1 M/F) RUMO KUN- 1(Rumo kun-1 to Ogabiri- 1 M/F) RUMOK UN- 2(Rumok un-2 to Ogabiri-1 M/F) OGABIRI - 1(Ogabiri -1 M/F passing through Ogabiri- 2{M/F} to CPF) CPF TO ELPS. 1.1 Gas Inlet Temperature. 29.44 26.67 29.44 26.67 51.27 O C 1.2 Gas Inlet Pressure. 4000 4200 4000 3938 6000 KPa 1.3 Gas Inlet Molar Flow. 4.98 10.08 28.95 30.82 81.16 MMS CFD 1.4 Pipeline Temperature Change. 1.994 0.5568 0.8201 26.00 1.266 O C 1.5 Pipeline Pressure Drop. 4.785 2.778 62.42 3938 65.09 KPa 1.6 Pipeline Heat-loss. 2.172e+ 004 234.3 3.059e+0 04 64.95 1.820e+ 005 KJ/h 1.7 Gas Outlet Temperature. 27.45 28.89 25.85 25.12 50.00 O C 1.8 Gas Outlet Pressure. 3995 4197 3938 3866 5935 KPa 1.9 Gas Outlet Molar Flow. 4.980 0.2024 28.95 75.01 81.16 MMS CFD 1.10 Design life 25 25 25 25 25 Yrs 1.11 Minimum Bend Radius: 1.11.1 Cold Bending Radius 10508 10007 10508 10673 7005 MM
  • 15. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 15 of 19 1.11.2 Hot Bending Radius 4203.2 4002.8 4203.2 4269.2 2802 MM 1.11.3 With Other Bending Devices 2101.6 2001.4 2101.6 2134.6 1401 MM 1.12 Pipe outside diameter 1050.8 1000.7 1050.8 1067.3 701.0 MM 1.13 Pipe inside diameter 1025.4 975.3 1025.4 1041.9 675.1 MM 1.14 Pipe wall thickness (Mainline seasonal swamp/land) section 12.7 12.7 12.7 12.7 12.7 MM 1.15 Pipe wall thickness (mainline river/road crossing) section NONE NONE NONE NONE NONE MM 1.16 Pipe wall thickness (Major barrels) 12.7 12.7 12.7 12.7 12.7 MM 1.17 Pipe Grade API 5L X60 API 5L X60 API 5L X60 API 5L 60 API 5L 60 NA 1.18 Flow Velocity Range 15.24 – 4.27 15.24 – 4.27 15.24 – 4.27 15.24 – 4.27 15.24 – 4.27 M/S 2 TOPOGRAPHICAL 2.1 Pipeline length 9.00 12.00 8.50 3.00 4.50 KM 2.2 River Crossings None None None None None None 2.3 Rivers Crossing Block Valves (Upstream/Down stream of Rivers Crossings) None None None None None None 2.4 Creek crossing ≥ 20m None None None None None None 2.5 Creek crossing < 20m None None None None None None 2.6 Road crossing ≥ 15m None None None None None None 2.7 Road crossing < 15m None None None None None None 2.8 Burial depth (underwater cover @ creeks) - below mudline. None None None None None M 2.9 Burial Depth (underwater cover @ river crossing) – below mud cut. None None None None None M 2.10 Burial Depth (minimum cover) – 1.5 1.5 1.5 1.5 1.5 M
  • 16. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 16 of 19 Rural Road Crossing by 2.11 Burial Depth (Minimum cover below undisturbed ground surface) – Major Road Crossing by Thrust Bore 1.0 1.0 1.0 1.0 1.0 M 3. CORROSION CONTROL 3.1 Corrosion Allowance 0.1 0.1 0.1 0.1 0.1 MM/ YR 3.2 External Concrete Coating (Swamp/River Sections) 80 80 80 80 80 MM 3.3 External Anti- Corrosion Coating (3- Layer Polyethylene) 3.2 3.2 3.2 3.2 3.2 MM 3.4 Internal Coating None None None None None -NA- 3.5 Cathodic Protection (By Impressed Current) Yes Yes Yes Yes Yes -NA- 3.6 Corrosion Monitoring (By Intelligent Pig) Yes Yes Yes Yes Yes -NA- 3.7 Electrical Insulation (By Insulating Joints @ above/below ground transitions) Yes Yes Yes Yes Yes -NA- 3.8 Corrosion Inhibition Yes Yes Yes Yes Yes Yes 4 ANCILLIARY EQUIPMENT 4.1 Pig Launcher / Receiver Yes Yes Yes Yes Yes NO 4.2 Mixer Yes Yes Yes Yes Yes NO 4.3 Slug Catcher Yes Yes Yes Yes Yes NO 4.4 Water Splitter Yes Yes Yes Yes Yes NO 4.5 Booster Compressor Yes Yes Yes Yes Yes NO 5 ENVIRONMENTAL
  • 17. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 17 of 19 5.1 Maximum Wind Speed. 20.5 20.5 20.5 20.5 20.5 M/S 5.2 Average Daily Relative Humidity(Maximum) 97 97 97 97 97 % 5.3 Average Daily Relative Humidity(Minimum) 83 83 83 83 83 % 5.4 Average Daily Relative Humidity(Mean) 72 72 72 72 72 % 5.5 Ambient temperature (Maximum) 29.4 29.4 29.4 29.4 29.4 0 C 5.6 Ambient Temperature (Minimum) 18 18 18 18 18 0 C 5.7 Mean Maximum Hourly Rainfall 100 100 100 100 MM 5.8 Mean Maximum Monthly Rainfall(occurs in September) 355 355 355 355 355 MM 5.9 Average Annual Rainfall 2800 2800 2800 2800 2800 MM 4.0 CONCLUSION This project was carefully executed with enough up-to-date science and technology, which guaranteed strict compliance and attainment to internationally accepted standards of pipeline for transportation of hydrocarbon natural gas, without compromising the ecological sanctity of the concerned area, being guided with the Environmental Impact Assessment(E.I.A), conducted before the take off of this project execution. REFERENCE DOCUMENTS.
  • 18. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 18 of 19 The choice of material and equipment, design, construction, maintenance as well as repair of equipment and facilities covered by the industry guidelines shall comply with the latest edition of the references listed below, unless specifically noted. DOCUMENT HIERARCHY. Should there be any conflicts with respect to any/some of the documents used in this project, reference should be made to the following listed documents arranged in an order of descending priority, thus: 1. Nigerian Law. 2. The contract. 3. Ogabiri FEED approved documents. 4. WAGC Guidelines and Standards. 5. WAGC Design and Engineering Practices. 6. Industry Guidelines and Standards. 7. SPDC’s Kolo Creek – Rumuekpe T/L Replacement EIA Report. 8. The Guardian: www.ngrguardiannews.com>Features>Weekend. 9. Requirements Concerning Pipes and Pressure Vessels. - International Association of Classification Societies. 10.Welded Steel Pipe Design Manual 2007. (Merits, Design Standards, Technical and References) American Iron and Steel Institute. Publication Number D631-0807-e 11.Gas Transmission System Design and Selection. Session 3 Gas Transmission System Design Material Selection EP. 12.Guidelines for the Design of Buried Pipe. American Life Alliance.
  • 19. THIRTY-SEVEN KILOMETER PIPELINE MATERIAL DATASHEET OF OGABIRI GAS GATHERING PROJECT. DCC NUMBER PROS/OGBR/PPL/RPT/151 003 Revision : Y01 Status : IDC DISCIPLINE : PIPELINE System/Subsystem : Document type: Philosophy :DESIGN Rev. Date : PROS/OGBR/PPL/RPT/151003. Page 19 of 19 July 2001(with added agenda through February 2005) 13.ASME B31.8: Gas Transmission and Distribution Piping Systems. 49 CFR 192.619 (a) (1) (i) 14.Restoration of Right of Way 8, August 2008. < http://www.ngaa.org/cms/33/1339/65/84.aspx> 15.Trenching for New Pipelines. 8, August, 2008. <http:www.ngaa.org/cms/33/1339/65/73.aspx> 16.Stringing, Welding and Coating Pipe Segments. 8,August, 2008. <http://www.ngaa.org/cms/33/1339/65/70.aspx> 17.Assuring the Integrity of Natural Gas Pipeline. Posakony, G.J. et al. Topical Report. GRI-91/0366, Chicago, 1993. 18.The Design and Location of Gas Transmission Pipeline Using Risk Analysis Techniques, Risk and Reliabilty and Limit State Conference, Aberdeen, May,1996. Hopkins,P., Hopkins,H.F., I Corder. 19.Pipelines Onland: Design, Construction and Installation, Steel For Oil and Gas, British Standard Institute, 1992. Anon. , Code of Practice for Pipelines, BS 8010 Part 2.8.