SlideShare a Scribd company logo
1 of 23
Abdul Qadir
1
 Introduction
 Onsite and offsite power supply
 Description of Accidents
 Effects of faults on plant’s components.
 General Analysis
 Event summery
 Event scale
2
3
The forsmark unit 1 is a 1010 MWe ,2928Mwth BWR
plant, located in Sweden ,designed by ASEA Atom with
two turbine generator and commissioned in 1980.
Status of the plant at site
 Foresmark 1
Electrical fault occurred at this plant
 Foresmark 2
This unit was Shut down for refueling and maintenance
at time of fault
 Foresmark 3
This unit was operating at full load but not affected b/c
it is connected with other switchyard.
 The event at Forsmark nuclear station revealed several
design and operational oversights that could lead to
significant challenge to nuclear safety.
4
Electric power system of Forsmark 1 is divided as follows
 Offsite power supply
There are two independent electric power supply line .
 400KV
 70KV gas turbine
 On site power supply
Four 6.6 KV trains with each sized for 50% ECCS.
Four 500 v EDG secured buses
Four 500V battery secured buses
Four 220 AC power system(UPS)
5
6
7
 On 25th July 2005 date plant was operated at full power
and at the time 13:20:20 A dis-connector in the400 kV
switchyard opens during maintenance , creating an arc
and a two phase short circuit.
 The short circuit at the switchyard caused a grid
voltage fluctuation resulting in momentary
depression of the system voltage in response to the
gird voltage fluctuation the voltage regulator on the
main generator responded to restore the system
voltage.(No.NG-T-3.8 page 15) .
8
 At same time of transient The generator backup
protection system disconnected Both generator circuit
breakers trip on under voltage, i.e. disconnecting the
station from the 400 kV from the grid and the control
system aligned the full output of the main generator to
supply power to the house loads.
 At the instant of switching to house load operation,
the high voltage output of the generator resulted in a
brief but significant overvoltage. This high voltage
variation fed through the transformer which supply
the local power system and some other safety system
in the plants.
9
The event generated two transients on the power supply to
the unit.
 The first was an over voltage transient that causes the
failure of two un-interruptiple power supply
 The second was a low frequency transient that causes
disconnection of the off-site power to the safety related
bus bar.
 70KV gird and gas turbine :
The 70KV system remained available through out the event,
however ,the back up gas turbine did not start requested as
standby. The cause of this was lack of adequate
maintenance.
10
 Reactor
 Reactor output is reduced by a partial scram.
Changeover to house load operation and dumping of
steam to the condenser.
 The unit went to house load operation for a short
period of time before signal were received for reactor
trip, isolation of the primary containment and the
start of the reactor safety.
 The reactor core remained cooled throughout the
event
11
 Generator
 When short circuit happened generator circuit breaker
open at same time and disconnect the station from
400 kV gird.
 Both generator circuit breaker was trip on low power
(up to 5MW) at time 36 and 43 second.
 Turbine
 One turbine tripped due to low governing oil pressure
at o5 second
 Second turbine stop due to the high pressure in the
turbine condenser At 33 sec.
12
 UPS system
 At the instant of switching to house load operation,
the maximum voltage approximately 130 % of rated
voltage was experienced by the onsite power system
until the voltage regulator reduced the voltage down to
a normal rating.
 The typical system and component of UPS was design
to withstand from 85%-110% percent overvoltage and
under voltage.
 This over voltage resulted in loss of power from the 2
out of 4 UPS AC grid in trains A and B. where as train
C and D were unaffected by the transient.
13
14
• The battery backed UPS
220v AC system is
intended to supply
equipment that is essential
for safe shutdown of the
reactor .
• At 02 second rectifier in
the UPS system s (A and B
subs) trips on a control
fault, and thee inverter in
the same systems trip on
under voltage.
 These 220V AC systems were necessary for the
operation of the emergency diesel generators (EDG)
and the equipment that measure the water level and
pressure in the reactor pressure vessel.
 The loss of two 220v AC bus bars caused loss of several
isolation signal and also several information in the
main control room.
15
 Emergency Diesel generator
 One EDG is connected with each sub of 500 V
 In he event of disturbance ,start command are issued
automatically to the four diesel generator (one on each
sub).All diesel generator started automatically .
 Connection of EDG electric out put to the subs is
dependent on the availability of the UPS AC Power in
the respective sub, so two generator connected with
sub A and B was failed to connect, where as two other
diesel generator in sub C and D supplied power to the
internal network throughout the entire incident.
16
 Ac network supplies the equipment that measure the
water level and pressure in the reactor pressure vessel.
As two of the four instrumentation systems were not
working . this resulted in an automatic scram of the
reactor .
 In the reactor scram ,all the control rod must be
inserted into the core and indication is provided in the
control room when they fully inserted ,but in this case
the loss of power on sub A and B meant that there was
no indication for half of the control rods.
 In this event two out of four trains in each safety
system were operationally available (SAF, Core spray
and Containment spray system) 17
 The reactor was then initially cooled by dumping
steam from the reactor pressure vessel to the
condensation pool in the reactor enclosure ,and by
pumping in water via the two auxiliary fee water
pumps supplied from subs C and D. This reduce the
pressure from 70 bar to 6 bar within 30 minute ,and
the water level in the reactor vessel fell to a lowest level
of 1.9 m above the top of the core.
18
 Restoration of Electric supply
 After 22 minute control room manually connected to
sub A and B EDG to their buses with the result that
 Supervisory facility in the control room were restored.
 Motor powered insertion of the control rods was
completed in sub A and B, accompanied by indication
that all the rods were inserted.
19
 The Switchyard:
 In relation with maintenance activity in the 400KV
switchyard, misjudged the need to interlock an earth
fault protection. had the interlock been placed ,the
common bus bar protection would have isolated the
short circuit after 0.1 second.
 Operation of generator circuit breaker:
 The under frequency protection of both turbine
generator operated incorrectly. When the connection
with the switchyard was interrupted ,and the turbine
emergency stop was triggered , the under frequency
protection circuit of the generator should have tripped
the circuit breaker when the frequency had fallen below
a certain level
20
 220 V AC UPS system
 UPS system was installed over 10 years ago. The UPS
system was designed to meet the voltage level from
85% to 110% of nominal voltage. The voltage variation
that actually occurred was mush grater .
 EDG
 All EDG are started automatically ,but the Two
supplying power sub to A and B failed to connect to
their respective subs as ,to do this they require
auxiliary power from the UPS .
21
22
According to the Swedish
Nuclear Power Inspection
authority SKI, the incident
was rated 2 on the
International Nuclear Event
Scale.
Initially it was rated 1 since two
generators remained online.
But once it was discovered that
all four generators could have
failed due to the same fault,
the event was upgraded to 2. 23

More Related Content

What's hot

Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training ProgramArul Balan
 
Cspdcl microsoft power point presentation
Cspdcl microsoft power point presentationCspdcl microsoft power point presentation
Cspdcl microsoft power point presentationRamesh1189
 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comillasiam hossain
 
Fire Pump Transfer Switch Basics
Fire Pump Transfer Switch BasicsFire Pump Transfer Switch Basics
Fire Pump Transfer Switch BasicsJames S Nasby
 
Electrical 2
Electrical 2Electrical 2
Electrical 2gevsek
 
Internship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationInternship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationOluwaseun Amodu
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationSaumyadip Moitra
 
Presentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpurPresentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpurShubham Sachan
 
power house training seminar
power house training seminarpower house training seminar
power house training seminarParas kumar
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgearmichaeljmack
 
Cn 235 ac power systems
Cn 235 ac power systemsCn 235 ac power systems
Cn 235 ac power systemsgevsek
 
Lab manual psd v sem experiment no 1
Lab manual psd v sem experiment no 1Lab manual psd v sem experiment no 1
Lab manual psd v sem experiment no 1Sachin Airan
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURHARISH KUMAR
 
Report BQPS II- Saad Janjua
Report BQPS II- Saad JanjuaReport BQPS II- Saad Janjua
Report BQPS II- Saad JanjuaSaad Janjua
 

What's hot (20)

220kv substation
220kv substation220kv substation
220kv substation
 
High voltage megger electric shock Omer Saeed
High voltage megger electric shock   Omer SaeedHigh voltage megger electric shock   Omer Saeed
High voltage megger electric shock Omer Saeed
 
Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training Program
 
Cspdcl microsoft power point presentation
Cspdcl microsoft power point presentationCspdcl microsoft power point presentation
Cspdcl microsoft power point presentation
 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comilla
 
Fire Pump Transfer Switch Basics
Fire Pump Transfer Switch BasicsFire Pump Transfer Switch Basics
Fire Pump Transfer Switch Basics
 
Electrical 2
Electrical 2Electrical 2
Electrical 2
 
Internship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationInternship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission station
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
Presentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpurPresentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpur
 
power house training seminar
power house training seminarpower house training seminar
power house training seminar
 
DPL Project
DPL ProjectDPL Project
DPL Project
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgear
 
Cn 235 ac power systems
Cn 235 ac power systemsCn 235 ac power systems
Cn 235 ac power systems
 
Lab manual psd v sem experiment no 1
Lab manual psd v sem experiment no 1Lab manual psd v sem experiment no 1
Lab manual psd v sem experiment no 1
 
DPL Training .doc file
DPL Training .doc file DPL Training .doc file
DPL Training .doc file
 
ntpc
ntpcntpc
ntpc
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPUR
 
12 MWCPP PROJECT
12 MWCPP PROJECT12 MWCPP PROJECT
12 MWCPP PROJECT
 
Report BQPS II- Saad Janjua
Report BQPS II- Saad JanjuaReport BQPS II- Saad Janjua
Report BQPS II- Saad Janjua
 

Similar to Electric fault at forsmark nuclear power plant

DVC, BOKARO THERMAL PPT
DVC, BOKARO THERMAL PPTDVC, BOKARO THERMAL PPT
DVC, BOKARO THERMAL PPTSohail Akhtar
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014Kanai Banerjee
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)shovandey07
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyLeonardo ENERGY
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014pinki199319
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working modelgiriraj bairwa
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report imkanhaiyalal
 
ELECTRICITY REPORT WIND GENRATION
ELECTRICITY REPORT WIND GENRATIONELECTRICITY REPORT WIND GENRATION
ELECTRICITY REPORT WIND GENRATIONoday hatem
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)99sunilkumar
 
GRC Martin 08 16
GRC Martin 08 16GRC Martin 08 16
GRC Martin 08 16Sean Martin
 
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor Load
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor LoadPush-Pull Converter Fed Three-Phase Inverter for Residential and Motor Load
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor LoadIJPEDS-IAES
 
SUMMER TRAINNING REPORT ELECTRIC LOCOSHED KANPUR
SUMMER TRAINNING  REPORT ELECTRIC LOCOSHED  KANPURSUMMER TRAINNING  REPORT ELECTRIC LOCOSHED  KANPUR
SUMMER TRAINNING REPORT ELECTRIC LOCOSHED KANPURShivesh Ranjan
 
Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.YouTubeofficial
 
Grid Integration issues in wind
Grid Integration issues in windGrid Integration issues in wind
Grid Integration issues in windbalafet
 
牵引变流器(CI).ppt
牵引变流器(CI).ppt牵引变流器(CI).ppt
牵引变流器(CI).pptNajihah Ab.
 
Railway workshop jodhpur
Railway workshop jodhpurRailway workshop jodhpur
Railway workshop jodhpurMAHESH SONI
 
Report on minor project
Report on minor projectReport on minor project
Report on minor projectAnil Maurya
 
Knowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptxKnowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptxRilwan19
 

Similar to Electric fault at forsmark nuclear power plant (20)

lift ppt
lift pptlift ppt
lift ppt
 
DVC, BOKARO THERMAL PPT
DVC, BOKARO THERMAL PPTDVC, BOKARO THERMAL PPT
DVC, BOKARO THERMAL PPT
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power Supply
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
 
ELECTRICITY REPORT WIND GENRATION
ELECTRICITY REPORT WIND GENRATIONELECTRICITY REPORT WIND GENRATION
ELECTRICITY REPORT WIND GENRATION
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)
 
GRC Martin 08 16
GRC Martin 08 16GRC Martin 08 16
GRC Martin 08 16
 
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor Load
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor LoadPush-Pull Converter Fed Three-Phase Inverter for Residential and Motor Load
Push-Pull Converter Fed Three-Phase Inverter for Residential and Motor Load
 
SUMMER TRAINNING REPORT ELECTRIC LOCOSHED KANPUR
SUMMER TRAINNING  REPORT ELECTRIC LOCOSHED  KANPURSUMMER TRAINNING  REPORT ELECTRIC LOCOSHED  KANPUR
SUMMER TRAINNING REPORT ELECTRIC LOCOSHED KANPUR
 
Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.
 
Grid Integration issues in wind
Grid Integration issues in windGrid Integration issues in wind
Grid Integration issues in wind
 
牵引变流器(CI).ppt
牵引变流器(CI).ppt牵引变流器(CI).ppt
牵引变流器(CI).ppt
 
Railway workshop jodhpur
Railway workshop jodhpurRailway workshop jodhpur
Railway workshop jodhpur
 
Report on minor project
Report on minor projectReport on minor project
Report on minor project
 
Knowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptxKnowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptx
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Electric fault at forsmark nuclear power plant

  • 2.  Introduction  Onsite and offsite power supply  Description of Accidents  Effects of faults on plant’s components.  General Analysis  Event summery  Event scale 2
  • 3. 3 The forsmark unit 1 is a 1010 MWe ,2928Mwth BWR plant, located in Sweden ,designed by ASEA Atom with two turbine generator and commissioned in 1980.
  • 4. Status of the plant at site  Foresmark 1 Electrical fault occurred at this plant  Foresmark 2 This unit was Shut down for refueling and maintenance at time of fault  Foresmark 3 This unit was operating at full load but not affected b/c it is connected with other switchyard.  The event at Forsmark nuclear station revealed several design and operational oversights that could lead to significant challenge to nuclear safety. 4
  • 5. Electric power system of Forsmark 1 is divided as follows  Offsite power supply There are two independent electric power supply line .  400KV  70KV gas turbine  On site power supply Four 6.6 KV trains with each sized for 50% ECCS. Four 500 v EDG secured buses Four 500V battery secured buses Four 220 AC power system(UPS) 5
  • 6. 6
  • 7. 7
  • 8.  On 25th July 2005 date plant was operated at full power and at the time 13:20:20 A dis-connector in the400 kV switchyard opens during maintenance , creating an arc and a two phase short circuit.  The short circuit at the switchyard caused a grid voltage fluctuation resulting in momentary depression of the system voltage in response to the gird voltage fluctuation the voltage regulator on the main generator responded to restore the system voltage.(No.NG-T-3.8 page 15) . 8
  • 9.  At same time of transient The generator backup protection system disconnected Both generator circuit breakers trip on under voltage, i.e. disconnecting the station from the 400 kV from the grid and the control system aligned the full output of the main generator to supply power to the house loads.  At the instant of switching to house load operation, the high voltage output of the generator resulted in a brief but significant overvoltage. This high voltage variation fed through the transformer which supply the local power system and some other safety system in the plants. 9
  • 10. The event generated two transients on the power supply to the unit.  The first was an over voltage transient that causes the failure of two un-interruptiple power supply  The second was a low frequency transient that causes disconnection of the off-site power to the safety related bus bar.  70KV gird and gas turbine : The 70KV system remained available through out the event, however ,the back up gas turbine did not start requested as standby. The cause of this was lack of adequate maintenance. 10
  • 11.  Reactor  Reactor output is reduced by a partial scram. Changeover to house load operation and dumping of steam to the condenser.  The unit went to house load operation for a short period of time before signal were received for reactor trip, isolation of the primary containment and the start of the reactor safety.  The reactor core remained cooled throughout the event 11
  • 12.  Generator  When short circuit happened generator circuit breaker open at same time and disconnect the station from 400 kV gird.  Both generator circuit breaker was trip on low power (up to 5MW) at time 36 and 43 second.  Turbine  One turbine tripped due to low governing oil pressure at o5 second  Second turbine stop due to the high pressure in the turbine condenser At 33 sec. 12
  • 13.  UPS system  At the instant of switching to house load operation, the maximum voltage approximately 130 % of rated voltage was experienced by the onsite power system until the voltage regulator reduced the voltage down to a normal rating.  The typical system and component of UPS was design to withstand from 85%-110% percent overvoltage and under voltage.  This over voltage resulted in loss of power from the 2 out of 4 UPS AC grid in trains A and B. where as train C and D were unaffected by the transient. 13
  • 14. 14 • The battery backed UPS 220v AC system is intended to supply equipment that is essential for safe shutdown of the reactor . • At 02 second rectifier in the UPS system s (A and B subs) trips on a control fault, and thee inverter in the same systems trip on under voltage.
  • 15.  These 220V AC systems were necessary for the operation of the emergency diesel generators (EDG) and the equipment that measure the water level and pressure in the reactor pressure vessel.  The loss of two 220v AC bus bars caused loss of several isolation signal and also several information in the main control room. 15
  • 16.  Emergency Diesel generator  One EDG is connected with each sub of 500 V  In he event of disturbance ,start command are issued automatically to the four diesel generator (one on each sub).All diesel generator started automatically .  Connection of EDG electric out put to the subs is dependent on the availability of the UPS AC Power in the respective sub, so two generator connected with sub A and B was failed to connect, where as two other diesel generator in sub C and D supplied power to the internal network throughout the entire incident. 16
  • 17.  Ac network supplies the equipment that measure the water level and pressure in the reactor pressure vessel. As two of the four instrumentation systems were not working . this resulted in an automatic scram of the reactor .  In the reactor scram ,all the control rod must be inserted into the core and indication is provided in the control room when they fully inserted ,but in this case the loss of power on sub A and B meant that there was no indication for half of the control rods.  In this event two out of four trains in each safety system were operationally available (SAF, Core spray and Containment spray system) 17
  • 18.  The reactor was then initially cooled by dumping steam from the reactor pressure vessel to the condensation pool in the reactor enclosure ,and by pumping in water via the two auxiliary fee water pumps supplied from subs C and D. This reduce the pressure from 70 bar to 6 bar within 30 minute ,and the water level in the reactor vessel fell to a lowest level of 1.9 m above the top of the core. 18
  • 19.  Restoration of Electric supply  After 22 minute control room manually connected to sub A and B EDG to their buses with the result that  Supervisory facility in the control room were restored.  Motor powered insertion of the control rods was completed in sub A and B, accompanied by indication that all the rods were inserted. 19
  • 20.  The Switchyard:  In relation with maintenance activity in the 400KV switchyard, misjudged the need to interlock an earth fault protection. had the interlock been placed ,the common bus bar protection would have isolated the short circuit after 0.1 second.  Operation of generator circuit breaker:  The under frequency protection of both turbine generator operated incorrectly. When the connection with the switchyard was interrupted ,and the turbine emergency stop was triggered , the under frequency protection circuit of the generator should have tripped the circuit breaker when the frequency had fallen below a certain level 20
  • 21.  220 V AC UPS system  UPS system was installed over 10 years ago. The UPS system was designed to meet the voltage level from 85% to 110% of nominal voltage. The voltage variation that actually occurred was mush grater .  EDG  All EDG are started automatically ,but the Two supplying power sub to A and B failed to connect to their respective subs as ,to do this they require auxiliary power from the UPS . 21
  • 22. 22
  • 23. According to the Swedish Nuclear Power Inspection authority SKI, the incident was rated 2 on the International Nuclear Event Scale. Initially it was rated 1 since two generators remained online. But once it was discovered that all four generators could have failed due to the same fault, the event was upgraded to 2. 23