1. Randgold's Lorraine Gold Mine GOLD MINING MAN AND MATERIALS HANDLING PLC engineering, equipment supply and commissioning of the man-riding and ore belts.
2. Engineering, equipment supply and commissioning Main contractor CHI Control appointed AGE Engineering to carry out the PLC engineering, equipment supply and commissioning of the man-riding and ore belts project at Randgold's Lorraine Gold Mine in the Free State. This project, although only one month in duration was very sophisticated in that it called for an interface from the Modbusto the Allen Bradley soft starters Scan Port. The Allen Bradley PLC interfaced to an AFE SCADA data panel via Modbus an AFE data panel interfaced to an existing SCADA via Modbus AGE Technologies Contact us 011 869 3925 www.age.co.za