2. Kurva S Aktivitas berdasarkan bobot keuangan
2 3 4 5 6 9 10 11 12 13 16 17 18 19 20 23 24 25 26 27 30 31
Analisis Sistem 5,300,000IDR 13 5.13% 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.33
Desain Aplikasi 6,000,000IDR 6 5.81% 1.0 1.0 1.0 1.0 1.0 0.81
Implementasi 50,000,000IDR 15 48.40% 3.0 3.0 3.0 3.0 3.0 3.0
Testing 13,000,000IDR 4 12.58%
Instalasi 9,000,000IDR 12 8.71%
Maintenance 20,000,000IDR 13 19.36%
Total 103,300,000IDR 100.00% 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 1.4 1.4 1.33 1.0 1.0 0.81 3.0 3.0 3.0 3.0 3.0 3.0
0.4 0.8 1.2 1.6 2.0 2.4 2.8 3.2 3.6 4.0 5.4 6.8 8.1 9.1 10.1 10.9 13.9 16.9 19.9 22.9 25.9 28.9
Daftar Kegiatan
Total Akumulatif
JanuariHarga
Durasi
(hari)
bobot
Waktu Pelaksanaan
1 2 3 6 7 8 9 10 13 14 15 16 17 20 21 22 23 24 27 28
Analisis Sistem 5,300,000IDR 13 5.13%
Desain Aplikasi 6,000,000IDR 6 5.81%
Implementasi 50,000,000IDR 15 48.40% 3.0 3.0 3.0 3.0 3.0 3.0 3.0 4.7 4.7
Testing 13,000,000IDR 4 12.58% 3.0 3.0 3.0 3.58
Instalasi 9,000,000IDR 12 8.71% 0.72 0.72 0.72 0.72 0.72 0.72 0.72
Maintenance 20,000,000IDR 13 19.36%
Total 103,300,000IDR 100.00% 3.0 3.0 3.0 3.0 3.0 3.0 3.0 4.7 4.7 3.0 3.0 3.0 3.58 0.72 0.72 0.72 0.72 0.72 0.72 0.72
31.9 34.9 37.9 40.9 43.9 46.9 49.9 54.6 59.3 62.3 65.3 68.3 71.9 72.6 73.4 74.1 74.8 75.5 76.2 77.0
Daftar Kegiatan
Total Akumulatif
Waktu Pelaksanaan
FebruariHarga
Durasi
(hari)
bobot
1 2 3 6 7 8 9 10 13 14 15 16 17 20 21 22 23 24
Analisis Sistem 5,300,000IDR 13 5.13% 100
Desain Aplikasi 6,000,000IDR 6 5.81% 80
Implementasi 50,000,000IDR 15 48.40% 60
Testing 13,000,000IDR 4 12.58% 40
Instalasi 9,000,000IDR 12 8.71% 0.72 0.72 0.72 0.72 0.79 20
Maintenance 20,000,000IDR 13 19.36% 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.60 0
Total 103,300,000IDR ###### 0.72 0.72 0.72 0.72 0.79 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.6
77.7 78.4 79.1 79.8 80.6 82.1 83.6 85.1 86.6 88.0 89.5 91.0 92.5 94.0 95.4 96.9 98.4 100.0
Daftar Kegiatan Grafik
Total Akumulatif
Waktu Pelaksanaan
MaretHarga
Durasi
(hari)
bobot
3. Kurva S Aktivitas berdasarkan Progress Output Pekerjaan Proyek
2 3 4 5 6 9 10 11 12 13 16 17 18 19 20 23 24 25 26 27 30 31
Analisis Sistem 5,300,000IDR 13 5.13% 0.4 0.4 0.4 0.4 0.4 0.4 0.0 0.0 1.2 0.4 0.4 0.4 0.33
Desain Aplikasi 6,000,000IDR 6 5.81% 1.0 1.0 0.0 2.0 1.0 0.81
Implementasi 50,000,000IDR 15 48.40% 3.0 2.0 2.0 2.0 2.0 7.0
Testing 13,000,000IDR 4 12.58%
Instalasi 9,000,000IDR 12 8.71%
Maintenance 20,000,000IDR 13 19.36%
Total 103,300,000IDR 100.00% 0.4 0.4 0.4 0.4 0.4 0.4 0.0 0.0 1.2 0.4 1.4 1.4 0.33 2.0 1.0 0.81 3.0 2.0 2.0 2.0 2.0 7.0
0.4 0.8 1.2 1.6 2.0 2.4 2.4 2.4 3.6 4.0 5.4 6.8 7.1 9.1 10.1 10.9 13.9 15.9 17.9 19.9 21.9 28.9
Daftar Kegiatan
Total Akumulatif
JanuariHarga
Durasi
(hari)
bobot
Waktu Pelaksanaan
1 2 3 6 7 8 9 10 13 14 15 16 17 20 21 22 23 24 27 28
Analisis Sistem 5,300,000IDR 13 5.13%
Desain Aplikasi 6,000,000IDR 6 5.81%
Implementasi 50,000,000IDR 15 48.40% 0.0 0.0 9.0 1.0 1.0 7.0 3.0 2.7 6.7
Testing 13,000,000IDR 4 12.58% 3.0 2.0 2.0 5.58
Instalasi 9,000,000IDR 12 8.71% 0.00 0.00 0.00 1.00 1.00 1.00 1.00
Maintenance 20,000,000IDR 13 19.36%
Total 103,300,000IDR 100.00% 0.0 0.0 9.0 1.0 1.0 7.0 3.0 2.7 6.7 3.0 2.0 2.0 5.58 0.00 0.00 0.00 1.00 1.00 1.00 1.00
28.9 28.9 37.9 38.9 39.9 46.9 49.9 52.6 59.3 62.3 64.3 66.3 71.9 71.9 71.9 71.9 72.9 73.9 74.9 75.9
Daftar Kegiatan
Total Akumulatif
Waktu Pelaksanaan
FebruariHarga
Durasi
(hari)
bobot
1 2 3 6 7 8 9 10 13 14 15 16 17 20 21 22 23 24
Analisis Sistem 5,300,000IDR 13 5.13% 100
Desain Aplikasi 6,000,000IDR 6 5.81% 80
Implementasi 50,000,000IDR 15 48.40% 60
Testing 13,000,000IDR 4 12.58% 40
Instalasi 9,000,000IDR 12 8.71% 1.00 1.00 1.00 1.00 0.71 20
Maintenance 20,000,000IDR 13 19.36% 1.00 1.00 1.00 1.00 1.00 1.00 2.00 2.00 2.00 2.00 2.00 2.00 1.36 0
Total 103,300,000IDR 100.00% 1.00 1.00 1.00 1.00 0.71 1.00 1.00 1.00 1.00 1.00 1.00 2.00 2.00 2.00 2.00 2.00 2.00 1.36
76.9 77.9 78.9 79.9 80.6 81.6 82.6 83.6 84.6 85.6 86.6 88.6 90.6 92.6 94.6 96.6 98.6 100.0
Daftar Kegiatan Grafik
Total Akumulatif
Waktu Pelaksanaan
MaretHarga
Durasi
(hari)
bobot