Vere Christopher Holmes has over 12 years of experience in commissioning, pre-commissioning, and testing offshore and onshore oil and gas facilities. He has extensive expertise operating pumps and other equipment for tasks like nitrogen purging, leak testing, flooding, pigging, and chemical cleaning. He provides supervision and ensures work is done safely and meets client and environmental standards. Holmes aims to fully utilize his experience for ongoing professional development and company benefit.
1. Resume
My Objective:
TO WORK TO FULL POTENTIAL AND TO USE MY EXPERIENCE FOR THE BETTERMENT OF THE COMPANY I SERVE AND TO DO EACH ASSIGNMENT
AS REQUIRED AND TO DO IT SAFELY KEEPING IN MIND PEOPLE AND THE ENVIRONMENT .
Experience & Expertise Summary :
12+ years experience in commissioning and Pre – commissioning, Offshore & Onshore.
Fracturing, Cementing, Water-Injection, Chemical cleaning, Flooding, Pigging, De-watering, Hydro-testing, Nitrogen /
Helium leak testing, Nitrogen purging, Nitrogen vaporising, Nitrogen de-canting, Air-drying. operating various pump
equipment - power packs, Vanex, Thomson Kelly pump, Worthington pump, Rough Ryder, HP Kolfor pump, Gorman Rupp,
Oasis pump ,all centrifugal flooding pumps, Hydro ton ,Chemical injection pump. Hydac Filter unit, Twin Filter unit’s ,
Lighting Towers, Generators, Compressors. Rig up & down of Equipment, Electric & Gas welding. Fabrication, Carpentry and
Painting jobs. Administration, Client Briefing, Procedure writing, Preparing Test packs and liaison with clients and
representatives.
E – Learning Course’s: Safety & Technical:
Valve Safety. Confined Space Emergency Rescue. Process & Pipeline services
Aerial Lift Safety. Personal Protective Equipment. Nitrogen -1
Hand Safety. Preventing Spills. Hot Work
Fire Safety. Confined Space Entry. Chemical Service - 1
Electrical Safety. Accident Investigation. Rigging
Hydrogen Sulphide Safety. Hazard Recognition. Cementing
Back Safety. Hazard Communication. Gas Well Testing
Oil Field Safety. lips , Trips & Falls.
Pipeline Safety. Incident Investigation.
First Aid. Marine Security.
Job Safety Analysis.
Training – General Management & Technical:
*Nitrogen Pump Operator II *Fire Fighting *BOSIET Cert No: 20807 – Expiry Date: 24.07.2017.
*Pigging Operator II *First Aid *H2S - Expiry Date: 30.05.2017.
*Hydro – Test Operator II *Safety *BP Five Star Programme.
*Site Induction & Supervisor Course *BP Golden Rules.
Work Experience & Responsibilities / All Dates are based on rotation or job completion:
*Client: Maersk Oil Qatar Location: A – Platform / Qatar offshore. Date: 28th May ’15 to 19th Jun ‘15
Company: EnerMech. Project: Purging & Leak Detection.
Roll Played: Supervisor .
*Client: Chevron Location: Barrow Island/Western Australia. Date: 22nd Aug’ 14 to Jan ‘15
Company : Baker Hughes Project: Gorgon - Pigging & Air Drying.
Roll Played: Supervisor .
*Client: Technip / Chiyoda Location: Ras Laffan / Qatar . Date: 31st Mar ’14 to Aug’14
Company: EnerMech. Project: Leak Detection.
Roll Played: N2 pump operator / Rig up of equipment / Tapping & tagging using P&ID’s / Use portable leak detector .
*Client: Oryx / Gasal Location: Ras Laffan / Qatar Date: 05th Mar ’14 to 30th Mar ‘14
Company: EnerMech Project: Header pressurisation with Nitrogen.
Roll Played: Supervisor Nitrogen pumping operations .
*Client: Maersk Oil ( Offshore ) Location: Al Shaheen A – Location / Qatar Date: 22nd Jan ’14 to 20th Feb ’14
Company: EnerMech. Project: Leak Detection / Nitrogen purging.
Roll Played: Supervisor Nitrogen Helium leak detection / Nitrogen Purging .
*Client: Adma / Adco / Zadco Offshore Location: Abu Dhabi Date: 12th Jul ’13 to 29th Aug ‘13
Company: A - Hak Industrial services Project: Leak Detection.
Roll Played: Supervisor / Operate Nitrogen Pump .
*Client: BP / Azfen / Amec Location: COP/ WC Topside Project – Baku Date: 17th Mar ’13 to 17th Jun’13
Company: Baker Hughes Project: Leak Detection.
Roll Played: Operator - Rig up equip / Taping & Tagging using P&ID’s/ Line walk with the client rep / Using Mass Spec
2. *Client: Hiesco / KOC Location: Ahmadi, Kuwait Date: 01st Dec’12 to 24th Dec ‘12
Company: Halliburton / Qatar. Project: Pigging & Air drying.
Roll Played: Supervisor .
*Client: Black Cat/ Panorama/QP Location: Dokhan Qatar Date: 05th Nov’12 to 30th Nov’12
Company: Halliburton / Qatar Project: Pigging & Vacuum Air- Drying.
Roll Played: Supervisor .
*Client: Tengizchevoil Location: Tengiz Kazakhstan Date: 19th Jul’12 to 10th Sept’12
Company: Halliburton / Qatar Project: Nitrogen Purging ( Turnaround ).
Roll Played: Supervisor. .
*Client: Cpecc Location: Fujairah UAE Date: 11th Apr’12 to 12th Jun’12
Company: Halliburton / Abu Dhabi Project: Leak Detection.
Roll Played: Supervisor .
*Client: Cpecc Location: Abu Dhabi Date: 02nd Feb’12 to 20th Mar’12
Company: Halliburton / Abu Dhabi Project: Leak Detection.
Roll Played: Supervisor .
*Client: Hyundai / Toyo Location: Ras Laffan Qatar Date: 28th May’11 to 21st Nov’11
Company: BJ Services / Qatar Project: Leak Detection.
Roll Played: Supervisor .
*Client: Hyundai / Toyo Location: Ras Laffan Qatar Date: 12th Mar’11 to 08th Apr’11
Company: BJ Services / Qatar Project: Leak Detection
Roll Played: Supervisor .
*Client: Dolphin Energy, QChem, Pearl GTL, CHC Location: Ras Laffan Qatar Date: 03rd Jan’10 to 05th Feb’10
Company: EnerMech / Qatar Project: Leak Detection, Nitrogen Purging.
Roll Played: Operator & Supervise complete preparations for the job at hand .
*Client: NPCC Location: Musaffa Abu Dhabi Date: 10th Nov’09 to 18th Nov’09
Company: BJ Services UAE Project: Chemical Cleaning & Leak Detection.
Roll Played : Operator / supervise & monitor activities during test preparations including operating Nitrogen pump .
*Client: Descon Location: Das Island Abu Dhabi Date: 03rd Oct’09 to 06th Nov’09
Company: BJ Services UAE Project: Leak Detection.
Roll Played: Nitrogen Pump Operator .
*Client: BP Location: Sangachal / Baku Date: 04th Jun’09 to 20th Jul’09
Company: BJ Services UAE Project: Leak Detection & Nitrogen Purging.
Roll Played: Nitrogen Pump Operator .
*Client: BP Location: Sangachal / Baku Date: 28th May’09 to 03rd Jun’09
Company: BJ Services UAE Project: Chemical Cleaning & Leak Detection.
Roll Played: Operator / Nitrogen & Flooding pumps .
*Client: BP Location: Sangachal / Baku Date: 23rd Feb’09 to 28th Mar’09
Company: BJ Services UAE Project: Leak Detection.
Roll Played: Operator Nitrogen Pump .
*Client: SPS / McDermott Location: Beach Side / Baku Date: 10th Feb’09 to 16th Feb’09
Company: BJ Services UAE Project: Integrity Leak Test of Jumper Spool.
Roll Played: Operator Hydro ton pressurising pump .
*Client: BP Location: DWG Platform / Baku Date: 30th Jan’09 to 8th Feb’09
Company: BJ Services UAE Project: Hydro – Test on East Manifold.
Roll Played: Operator Hydro ton pressurising pump .
*Client: BP Location: Diving Support Vessel / Baku Date: 27th Nov’08 to3rd Dec’08
Company: BJ Services UAE Project: Integrity Test of Subsea Umbilical Pipeline (Hydro – Test).
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: SPS / McDermott Location: Beach Side / Baku Date: 22nd Sept’08 to 6th Oct’09
Company: BJ Services UAE Project: Integrity Test on 8” Flexible Umbilical Pipeline (Hydro – Test).
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: BP Location: Shah Deniz / Baku Date: 25th Jul’08 to 28th Aug’08
Company: BJ Services UAE Project: 14’’Pipeline Produced water Hydro – Test.
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: BP Location: DWG – PCWU Platform / Baku Date: 10th Dec’07 to 21th Jul’08
Company: BJ Services UAE Project: Hydro – Testing, Pigging, Flooding, De-watering & Gauging.
Roll Played: Operator Pressurising & Flooding Pumps.
*Client: Qatar Gas Location: Ras Laffan / Qatar Date: 26th Aug’07 to 1st Oct’07
Company: BJ Services UAE Project: Hydro – Testing, Pigging, Flooding, De-watering & Gauging.
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: Global Location: Ras Al Khaima / UAE Date: 11th Jul’07 to 21st Aug’07
Company: BJ Services UAE Project: Hydro – Testing, Pigging, Flooding, Gauging & Nitrogen Purging.
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: Leighton / SPM Location: Cochin / India Date: 20th Apr’07 to 31st May’07
Company: BJ Services UAE Project: Flooding & Hydro – Testing.
3. Roll Played: Operator Pressurising & Flooding Pumps .
*Client: BP Location: PSA – 2 Yevlax / Azerbaijan Date: 04th Feb’07 to 11th Feb’07
Company: BJ Services UAE Project: Hydro – Testing & Nitrogen Purging.
Roll Played: Operator Pressurising & Flooding Pumps .
*Client: BP Location: East Azri Offshore / Baku Date: 06th Oct’06 to 11th Oct’06
Company: BJ Services UAE Project: Hydro – Testing.
Roll Played: Operator Pressurizing & Flooding Pumps .
*Client: BP Location: Sangachal / Baku Date: 02nd Oct’06 to 05th Oct’06
Company: BJ Services UAE Project: Flooding & Hydro - Testing.
Roll Played: Operator Pressurizing & Flooding Pumps .
*Client: BP Location: Sangachal / Baku Date: 08th Sept’06 to 27th Sept’06
Company: BJ Services UAE Project: Flooding & Hydro - Testing.
Roll Played: Operator Pressurizing & Flooding Pumps .
*Client: BP Location: Sohar Power Plant / Oman Date: 04th Aug’06 to10th Aug’06
Company: BJ Services UAE Project: Chemical Cleaning.
Roll Played: Rigging up equipment and running off pumps & inspecting system .
*Client: BP Location: Sangachal / Baku Date: 18th Feb’06 to 15th Jun’06
Company: BJ Services UAE Project: Chemical Cleaning & Leak Detection.
Roll Played: Operator / Flooding & Nitrogen pumps .
Previous Work Experience / Roll / Date
Company: S.K. Ghanty & Son’s Location: Asansol / India Date: 01st Jul’85 to 15th Apr’87.
Roll Played: Carpenter.
Company: St.Vincent’s Tech School Location: Asansol (WB)/ India Date: Oct’91 to 15th Apr’95.
Roll Played: Carpenter / Fabricator / Fitter / Painter.
Company: News Television ( India ) Ltd Location: Delhi / India Date: 05th Jan’98 to 18th Feb’99
Roll Played: Service Engineer.
Company: Cable Television Network Location: Asansol (WB) India Date: May’99 to May’04
Roll Played: Service Engineer.
Client: GEECL Location: Asansol (WB) India Date: June’ 04 to Nov’04.
Company: BJ Services / India. Roll Played: Fracturing Operator / BJ Services India.
Client: Reliance Location: Shadol ( MP ) India Date: Feb’05 to Apr’05
Company: BJ Services / India Roll Played: Fracturing Operator / BJ Services India.
Client: Cairn Energy Location: Barmer ( Rajas ) India Date: 05th May’05 to 24th Nov’05.
Company: BJ Services / India Roll Played: Operator / Water Injection.
Client: GEECL Location: Asansol (WB) India Date: Jan’06 to Feb’06
Company: BJ Services / India Roll Played: Operator / Cementing.
Personal Details:
Name: Vere Christopher Holmes.
Father’s Name: Late – Mr. Evelyn Sherlock Holmes.
Qualifications: Junior Engineering Diploma ( JED ) Electrical’s, Industrial Trade Institute ( ITI ) Welding.
Nationality: Indian.
Date of Birth: 22nd July 1965.
Marital Status: YES.
Passport Details:
Passport Number: Z2217415.
Issue & Expiry Date: 30.06.11 / 29.06.21.
Place of Issue: Calcutta ( Kolkata )
Correspondence Address: Dreamland Apartments, Beside City Montessori School,
1st floor, Flat no: 3, Hill View Park ( North ),
PO + PS Asansol, Pin No: 713304, West Bengal, INDIA.
e.mail ID: christopher_nvholmes@yahoo.co.in
nvchristopherholmes@gmail.com
Mobile Number: +91 9732158098 ( India ).
+974 33310058 ( Qatar ).