Is a project’s fate preordained? Does a project’s past suggest its likely future? Can anything be done to influence that future when the current signs aren’t promising? Payson Hall has participated in and reviewed many projects during his thirty-year career in software development. Without claiming mystical or magical powers, Payson shares problem symptoms he has observed and discusses strategies for isolating and correcting them. He helps you learn to identify “problem seeds” that can grow into larger issues over time. For example, when a task exceeds its planned duration, questions that might help identify the cause include: Are the people assigned to the task working on something else? Has the schedule shifted the task into holidays, training, or vacations? Are tasks blocked awaiting information, materials, or approvals? Was the work clearly defined to begin with? Payson introduces a diagnostic framework that helps you determine the next steps in an investigation to identify root causes of project issues you observe and to formulate possible remedies.
Scaling API-first – The story of a global engineering organization
ADC-BSC EAST 2013 Keynote: Reading the Tea Leaves: Predicting a Project’s Future
1.
WK2
Keynote
11/13/2013 12:45 PM
"Reading the Tea Leaves:
Predicting a Project's Future"
Presented by:
Payson Hall
Catalysis Group, Inc.
Brought to you by:
340 Corporate Way, Suite 300, Orange Park, FL 32073
888‐268‐8770 ∙ 904‐278‐0524 ∙ sqeinfo@sqe.com ∙ www.sqe.com
2. Payson Hall
Catalysis Group, Inc.
A systems engineer and project management consultant, Payson Hall is a
founding member of Catalysis Group, Inc. Formally trained as a software
engineer and computer scientist, Payson has performed and consulted on
a variety of hardware and software systems integration projects in both the
public and private sectors throughout North America and Europe during his
thirty-year professional career. He has been a writer and featured speaker
on topics of systems integration, project management, and risk
management. Payson's rare combination of IT project management
experience and communication skills has made him a valued member of
many project review and project oversight teams.
23. Symptoms, Diagnosis & Treatment of
Common Project Management Problems
Introduction
Even well managed projects encounter challenges. People closest to a project often have insights regarding project problems; however, their
proximity to the consequences of problems can sometimes lead to lost perspective and overlooked causes. This reference is designed to support
project management by supporting objective analysis and remediation of project problems. The table is intended as a supplement to assist project
managers with problem diagnosis and treatment, not a substitute for sound project management practices.
Project goals exist in three dimensions:
• Scope – Deliverables, quality goals, process constraints, overall project size and boundaries
• Schedule – Delivery target dates, milestone dates, expected task completion dates
• Resources – People, equipment, facilities, materials, and funding
The dimensions are inter-related and problems in one dimension tend to cause problems in one or both of the others. For example, if a key
resource becomes unavailable to a project, it will likely have an impact on the delivery schedule and/or functionality and quality of work products
until the problem is resolved.
Because projects are complex systems of cause and effect, diagnosing root causes can be challenging. The “symptom” that is observed may be
the source of the problem, a contributing factor, or the middle of a chain of causes and effects. Just as a physician must explore alternative
potential causes from a patient’s presenting symptoms, this reference provides the project manager with questions to assist in the diagnosis of
other causes and contributing factors.
The reference presents information on troubleshooting project problems. It is roughly organized into four categories best matching the problem or
“symptom” of a problem that is observed:
• Scope: Quality, performance, process, or boundary related symptoms
• Schedule: Schedule slippage symptoms
• Resource: Personnel performance, human resource consumption, budget issues
• Other: A catch-all category for classic symptoms and issues that don’t neatly fit into the categories above
Symptoms are listed under each heading and matched with Diagnostics, questions that may be helpful to clarify or focus thinking about the
symptoms. Information obtained using diagnostic questions will assist in identification of Possible Causes and selection among related Possible
Remedies. While the reference is not exhaustive, it is hoped that it can aid with the rapid identification and resolution of project issues.
As you use the table, it is important to keep in mind that symptoms may have multiple causes or potential causes. Tasks exceeding their schedule
estimates may be a result of poor estimation, poor performance, lack of skills, lack of tools, increasing scope of the task, a key contributor getting
the flu, or a combination of some or all of these causes.
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 1
24. Diagnostics
Possible Causes
Possible Remedies
Clarifying/Focusing Questions
Potential Contributing Factors
Remedial Action
Scope/Quality Symptoms
Symptom: Project Scope appears to be expanding, but the Charter has not changed.
Have users or sponsors requested
Inadequate change control –
Revisit change management process and assure that only
functionality, performance, or quality
Changes are being accepted without
sponsor-authorized changes to scope are allowed to modify
standards beyond what was originally
the evaluation and explicit approval of the charter.
chartered?
the sponsor to expand project scope.
Revisit the planning process to assure that tasks are broken to
Is the change control process been
Failure to document scope and
an appropriate level of detail and estimated by someone
used to document increases in project
process assumptions as part of the
competent to do the work and that estimates and task
scope and assure that changes are
charter or monitor those assumptions
definitions are reviewed prior to finalizing plans.
conscious decisions to modify the
for change.
charter?
Assure that assumptions underlying plans are documented
Initially chartered scope was
and that invalid assumptions and their impact are
Have risk items occurred that
insufficient for the project’s needs
communicated to the sponsor.
increased project scope?
(quality or performance standards
were initially inadequate for actual
Assure that mandated changes to the development
Is the development staff receiving
production use for example).
environment or business processes are documented via
contradictory guidance from client
change management to assure that sponsors understand and
staff?
Staff changes may have caused a
accept the impact of changes.
loss of organizational memory
Have personnel changes occurred in
regarding the meaning of some
Assure that the team is clear about the project boundary and
key client or project staff?
requirements or the location of project understands the process to recommend adding work to the
boundaries.
project that was initially “out of bounds”
Have quality problems arisen that have
resulted in increased needs for testing
The impact of deferred quality issues
Review earlier quality metrics and determine how quality or
or rework?
is usually amplified the longer they
performance problems might have been detected and
are deferred.
remedied earlier. Look for process improvements to assure
Have tasks from another project or
that quality problems are identified and dealt with promptly.
undertaking been moved into this
Team members may not be clear on
project?
project boundaries and expanding
Emphasize the importance of sticking to requirements and
them to include work not originally
requirements tracking in project meetings. Use requirements
What tasks were added and why?
identified as part of the project or
tracking procedures to link requirements to test cases to user
Was there insufficient planning, was
work from other projects or
acceptance.
there insufficient detail, were there
operational activity.
really unexpected things that arose?
Review requirements with lead developers often to re-affirm
that only the documented requirements are being developed.
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 2
25. Diagnostics
Possible Causes
Possible Remedies
Clarifying/Focusing Questions
Potential Contributing Factors
Remedial Action
Explain “scope creep” and how to prevent it to the project
team.
Revisit risk planning and determine whether anticipated risk
events have occurred or if new risk events have emerged that
are affecting scope.
Add lessons learned to the lessons log and avoid this in the
future on other projects.
Identify another project designed to hold “additional” tasks.
Build a “future enhancements” list to capture good ideas and
new requirements that are not part of this project so that they
can be included in a subsequent release.
Symptom: Test results report a large number of errors and/or the number of errors in new work or re-work
does not seem to decrease.
Are the sources of errors being
Mechanisms for early detection of
Look for ways to detect errors sooner in the development
identified?
errors may not be in place or may not process.
be implemented effectively.
Are the sources of error changing over
Look for trends in error sources and in types of errors to
time?
Feedback from the testing and quality identify high leverage interventions with processes or training.
assurance processes might not be
Are the types of errors consistent?
causing necessary changes in current Determine how the project processes, or staff capabilities can
process.
be changed to improve the quality of products delivered to
Is the severity of the error comparable?
testing.
If the source or type of error detected
Are the errors being detected at the
is changing over time, it may be that
Revisit project plans and verify that early error detection
earliest possible opportunity in the
testing is being more effective at
mechanisms in the plan (code reviews, design walkthroughs,
process?
finding these errors or that process
etc.) are being conducted effectively.
changes have shifted quality
Is there schedule performance
problems to new areas.
Monitor team morale and be alert for the natural friction that
pressure that is encouraging a rush
can arise between development and testing. Remind the
through design and/or coding?
Some staff may need additional
team that development of quality work products is a team goal
training with processes, tools, the
and that processes that identify faults early support those
Has the quality of testing improved
application domain, or basic
efforts.
during the life of the project?
development skills to improve work
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 3
26. Diagnostics
Possible Causes
Clarifying/Focusing Questions
Potential Contributing Factors
product quality and worker efficiency.
Are there skill issues with the staff
responsible for creating the work
products being tested?
Are there morale issues with the staff
responsible for creating the work
products being tested?
Morale issues among developers or
testers may be causing performance
or communication issues that result in
either poorer quality or greater error
reporting.
Encouraging/rewarding testers based
upon the number of faults they find
may have the unintended
consequence of causing multiple
occurrences of the same error type to
be written up as different errors, or
complex errors to be written up as
multiple errors.
Symptom: Product passes all tests but the client is dissatisfied
Have the client requirements changed
Requirements were not captured in
since the inception of the project?
sufficient detail to truly define the
users needs for the product.
Has the project context changed since
the inception of the project
Tests that sufficiently evaluate all
(regulations, strategic goals, business
aspects of the requirements were not
environment)?
developed.
Possible Remedies
Remedial Action
Beware the assumptions
“More errors found = worse quality”
“More errors found = better testing”
“Few errors found = better quality”
“Few errors found = worse testing”
What testing behavior is being
encouraged? Finding large quantities
of errors? Finding high severity errors?
Testing products quickly?
Were the initial requirements clear and
complete?
Do test plans include demonstration of
meeting requirements?
Have there been key user personnel
changes since the start of the project?
Have there been changes in
sponsorship since the start of the
project?
Requirements were not effectively
managed to adapt to changes in the
project business context.
Changes in key client personnel may
have resulted in different user
expectations.
There may be insufficient ongoing
involvement of users in the
development process.
Re-evaluate the way in which the requirements were
documented. Assure that the client approves the
requirements document. Affirm that requirements meet the
client’s expectation.
Revisit and review requirements with the client.
Re-evaluate the test plan to assure that the individual test
cases effectively cover identified requirements
New requirements may be integrated into the current project
via change management or documented for the next release
of the software.
Review the process for monitoring the user business
environment for new/changed requirements. Look for ways to
improve this process.
Work closely with the users to understand and capture recent
or expected changes in business processes.
The system may meet identified
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 4
27. Diagnostics
Clarifying/Focusing Questions
Has user staff been involved in the
development or review of designs and
test criteria?
How could user feedback have been
solicited earlier in the development
process to detect user satisfaction
issues sooner?
Is usability an issue?
Is performance an issue?
Is user training an issue?
Possible Causes
Potential Contributing Factors
requirements but be difficult to use or
have performance issues.
Have users received sufficient
effective training and documentation
about the use of the system to enable
them to utilize it effectively?
Possible Remedies
Remedial Action
Look for ways to continually re-validate that the system being
built is consistent with the written requirements and needs of
system users.
Gather data from the users by observing them interact with the
system for an extended period of time and encourage them to
comment about their frustration. Look for usability issues and
places where expectations may not be consistent with
requirements. Look also for opportunities to improve training
or documentation.
Begin building an enhancement list for the next release of the
product so that users feel that concerns have been heard and
to assure that good ideas are captured.
Is available documentation sufficient?
Symptom: Agreed upon processes and rules are not being consistently followed
Are the rules and process
If rules or process requirements are
Rules and process requirements should be clearly written
requirements clear?
not clear, they cannot be complied
(examples improve the effectiveness of documented rules and
with.
processes)
Are the rules and process
requirements necessary?
If people don’t understand why rules
Written rules and process requirements should include a brief
and process constraints are in place,
description of why the rule or process is in place.
Are the rationale for processes and
they will not comply with them
rules clearly stated?
consistently.
The team should have ready access to documentation
explaining rules and process requirements.
Are project staff aware of rules and
If an organization does not appear to
process constraints?
be serious about enforcing rules and
The team should receive sufficient training and support to
process constraints, teams will tend to facilitate compliance.
Do project staff have sufficient skill and ignore rules and process
experience to effectively comply with
requirements that appear to get in the Periodically, rules and processes should be revisited with the
rules and process constraints?
way of getting the project completed.
team to look for process improvements and provide the team
a chance to offer input to the rules.
Has the organization required
If there is no apparent consequence
consistent compliance with rules and
for breaking rules or violating process Exceptions to rules and processes should be conscious
process constraints?
requirements, people tend to ignore
decisions made by the project manager.
them.
Does the team have sufficient time and
The team must receive an unambiguous message that
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 5
28. Diagnostics
Clarifying/Focusing Questions
resources to comply with rules and
process requirements?
Are the same people continuing to
ignore or subvert rules and processes
after repeated intervention?
Possible Causes
Possible Remedies
Potential Contributing Factors
If the team does not have the tools,
time, or skills to comply with rules,
they will tend to ignore them.
Remedial Action
compliance with rules and processes is expected, and that if
this causes changes in estimates or the project plan, the
changes should be communicated to the project manager.
If rules and process requirements are
clearly communicated and
understood, and team members with
the skills and tools to comply with
them refuse to comply after repeated
intervention, this is sabotage or
insubordination
When new personnel are added to the team, rule and process
information should be explicitly shared with them as part of
orientation.
Sabotage or insubordination are personnel issues that should
be promptly handled as such. Left untreated, they undermine
morale, discipline, and the cohesiveness of the project team.
Resource Symptoms
Symptom: Tasks are tending to consume more human resources than estimated in the project plans.
Has the scope of tasks changed since
Initial estimates were incorrect.
Estimates should be created by individuals competent to do
they were estimated?
the work.
Insufficient expert input into the
Do the people working on the tasks
identification, definition, and
Estimates should be written, and should specify the
have a comparable level of skill to the
estimation of project tasks.
assumptions upon which they are based, including the team
ones envisioned for the tasks when it
size, skill levels, processes to be used, performance
was estimated?
Assumptions underlying task
environment and scope of the task.
estimates were incorrect.
Are people working on tasks devoted
When tasks materially vary from their estimates (over or
full time to the project or are they being Quality problems are being introduced under), particularly if trends are noted among types of tasks or
diluted with other projects or
earlier in the project, causing later
tasks estimated by the same estimator, or tasks performed by
operational responsibilities?
tasks to exceed their estimates.
the same doer; estimates should be reviewed to understand
When quality problems are not dealt
whether the scope of the work has changed, the anticipated
Have initial assumptions about the
with promptly, subsequent task
resources have changed, the assumptions underlying the
work or the work environment proven
resource needs tend to grow as
estimate have changed, or the estimation process needs
to be incorrect?
deferred problems must be corrected. improvement.
Have process errors or quality
problems occurred that required
unanticipated rework?
New tools and processes introduced
after estimation sometimes invalidate
earlier estimates.
Is resource consumption being
accurately tracked at a task level?
Task resource consumption may not
be reported accurately.
Project Symptom & Diagnostic Aid V1.0
Review the project charter to determine appropriate
optimization response. Can additional resources be allocated
to problem tasks to recover schedule? Can the scope of tasks
be modified to better fit the budget?
Revisit similar estimates for tasks not yet completed and refine
where necessary.
www.catalysisgroup.com
Page 6
29. Diagnostics
Clarifying/Focusing Questions
Are any tasks being reported as
completing with less resource than
initially allocated?
Have new tools or processes been
introduced that effect task doer’s
efficiency either short term (climbing
the learning curve or stabilizing a new
development environment) or longer
term (utilizing more complex tools)?
Are task completion criteria clear?
Possible Causes
Potential Contributing Factors
If task completion criteria are not
clear, task doers may be doing more
than required to complete tasks.
Possible Remedies
Remedial Action
Use the change management process to inform sponsors,
users and team members of any material changes to
schedule, scope or resource targets.
Monitor task performance after the introduction of changes to
tools and processes to identify whether, after a reasonable
learning curve, estimates need to be modified up or down for
work that has not been completed and will utilize the new tools
or methods.
Monitor the impact of changes in tools and processes to
assure that the expected cost benefit of the change is
achieved. Consider backing out changes that prove to be ill
advised or immature.
Status reporting of task resource consumption by team
member should occur on a regular basis so that trends and
issues can be promptly identified and handled.
Clearly defined completion criteria should be specified for all
tasks. This is the foundation of good estimation and also
provides task doers with a discrete target so that they can stop
work as soon as the completion criteria are met.
Symptom: Unanticipated tasks (tasks not included in the project plan) are consuming substantial project resources
Has the scope of the project changed? Plans omitted tasks that were
Project plans should be developed by people competent to do
necessary to achieving the chartered
the work, and developed at a level of detail sufficient to
Are changes being approved using the scope.
capture the work to be done.
change management process?
Plans may not have been developed
Project plans and estimates should be revisited periodically to
Have risk events occurred that caused
at level of detail sufficient to identify
look for trends in missed tasks or highly variant estimates.
unanticipated tasks?
all required work.
Risk events that occur should be documented and the change
Have external forces increased the
Changes in the project context may
management process used to assure that sponsors and users
amount of work (new regulations,
be invalidating estimates
are willing to incur the additional cost, schedule and scope
required changes to work environment
impact of the risk event.
such as new tools or modified
The team may be expanding the
processes)?
scope of the project with unChange management processes should be used to inform
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 7
30. Diagnostics
Clarifying/Focusing Questions
Has the team discovered work that was
not originally anticipated and included
in the plan?
Are the un-anticipated tasks work that
must occur and was omitted from the
original plans or optional work that is
being included?
Possible Causes
Potential Contributing Factors
anticipated tasks.
Risk events may have occurred
whose consequences are being
handled without conscious
acknowledgment
Possible Remedies
Remedial Action
sponsors of refinement to estimates and provide an
opportunity to revisit the schedule and scope of the project.
Assumptions about project context should be reviewed
periodically to determine whether they impact project scope.
Assure that the team is clear about the project boundary and
understands the process to recommend adding work to the
project that was initially “out of bounds”
Risks that have occurred become project issues that may
result in change management activities
Risk events that have occurred and were not previously
identified as potential risks may indicated deficiencies with the
current level of risk planning.
Symptom: Tasks monetary costs are exceeding planning estimates
Has the scope of tasks changed since
Initial estimates were incorrect.
they were estimated?
Insufficient expert input into the
Have initial assumptions about the
identification, definition, and
work or the work environment proven
estimation of project tasks.
to be incorrect?
Assumptions underlying task
Have process errors or quality
estimates were incorrect.
problems occurred that required
unanticipated rework?
Quality problems being introduced
earlier in the project are causing later
Is resource consumption being
tasks to exceed their estimates.
accurately tracked at a task level?
When quality problems are not dealt
with promptly, subsequent task
Have fees for services increased?
resource needs tend to grow as
deferred problems must be corrected.
Have fees for materials increased
beyond what was
Procuring products, services and
anticipated/budgeted?
equipment at the last minute
frequently drives up costs.
Did budget estimates include an
Project Symptom & Diagnostic Aid V1.0
Estimates should be created by individuals competent to do
the work.
Estimates should be written, and should specify the
assumptions upon which they are based.
When tasks materially vary from their estimates (over or
under), particularly if trends are noted among types of tasks or
tasks estimated by the same estimator; estimates should be
reviewed to understand whether the scope of the work has
changed, anticipated costs have changed, the assumptions
underlying the estimate have changed, or the estimation
process needs improvement.
Review the project charter to determine appropriate
optimization response. Can additional resources be allocated
to problem tasks to recover schedule? Can the scope of tasks
be modified to better fit the budget?
Revisit similar estimates for tasks not yet completed and refine
where necessary.
www.catalysisgroup.com
Page 8
31. Diagnostics
Clarifying/Focusing Questions
inflation factor?
Possible Causes
Possible Remedies
Potential Contributing Factors
Remedial Action
Are materials and equipment that have
been procured being used?
Use the change management process to inform sponsors,
users and team members of any material changes to
schedule, scope or resource targets.
Are overhead costs (equipment rentals
or facilities charges) increasing
because of schedule delays?
Status reporting of task budget consumption should occur on
a regular basis so that trends and issues can be promptly
identified and handled.
Are products, services and travel being
procured in sufficient volume and with
sufficient lead time to allow discounts?
Consider negotiating discounts for products and services
procured in bulk or with substantial lead times.
Schedule Symptoms
Symptom: Tasks are exceeding their planned duration
Are the resources assigned to the task
The task may be consuming more
working on other project tasks or
resources than originally estimated.
assigned to other project or operational Tasks that consume more resources
duties?
than originally estimated frequently
also exceed their schedule estimates.
Has a schedule shift caused tasks to
straddle holidays, training, or vacation
Project resources may not have the
of team members allocated to the
availability that was originally
task?
anticipated when durations were
calculated.
Has the resource consumption of the
task remained consistent with original
Inefficiency is introduced when team
estimates?
members are required to work on
multiple tasks concurrently.
Are tasks being held up waiting for
approvals or sign offs?
Tasks may not be broken down to
sufficient level of detail to highlight
Are tasks being held up waiting for
dependencies on information or
materials, equipment or information?
approvals.
Are tasks starting when they were
scheduled?
Project Symptom & Diagnostic Aid V1.0
Task dependencies in the project plan
may be incorrect.
Compare actual resource consumption of tasks with observed
duration. Generally, dealing with increased resource
requirements must occur before addressing corresponding
schedule impacts.
Review task dependencies for accuracy.
Review task definitions and break down tasks to highlight
external dependencies and approvals.
Look for trends (kind of task, task doer) to focus further
analysis.
Review productivity estimates for project resources. Generally
it is ill advised to expect more than 30 hours per week of
productive project time from full time resources. This must be
further adjusted to account for holidays, vacation, training,
other project work and any other substantial resource
commitments.
Task duration predictions are normally derived from resource
estimates and assumptions about the availability of team
members to do the work. When duration estimates are
www.catalysisgroup.com
Page 9
32. Diagnostics
Clarifying/Focusing Questions
What are the assumptions about team
member availability during a typical
work week?
How were duration estimates created?
Is there a disruption in the work
environment that is causing
interruptions in task work?
Possible Causes
Potential Contributing Factors
Project resource productivity may
have been over-estimated.
Duration estimates may not be based
upon resource estimates.
Interruptions in task work introduce
two factors that increase schedule,
the overhead of stopping and starting
the task, as well as the off-task time
of the interruption.
Some unexpected factor may be
affecting durations or performance.
Symptom: Tasks are not performed in the specified order
Is the desired order of task
The assignment of tasks is not being
performance clear?
clearly stated, including the order in
which they are to be performed.
Are team members encouraged to
Team members may work on aspects
complete one task before starting
of the project they like first.
another unless blocked?
Task dependencies may not be
Are task dependencies correct?
correct or may be incomplete.
Are team members informing their
team leaders or project managers
when they are blocked on a task?
Possible Remedies
Remedial Action
inaccurate, working backward through availability
assumptions, skill assumptions, and resource estimates is
usually instructive.
Work to minimize interruptions in task work. This can be
accomplished by trying to eliminate unnecessary meetings,
providing productive work space, assuring that staff have
reliable and efficient equipment (computers, copy machines,
networks, printers, etc.)
Discuss schedule variances with the team to discover root
causes.
Review project schedule during the regularly scheduled
project meetings.
Review project task assignments with each person.
Pass out task assignments in a tangible form, such as emails
or a form. Link tasks assigned to their line-location in the
project schedule.
Print an oversized copy of the project schedule and display in
a common area.
Make sure that task owners understand their responsibility to
perform tasks in the prescribed order.
Other Symptoms
Symptom: Stakeholders are blocking tasks (not providing timely feedback on reviews or holding up document approvals)
Does the communication plan clearly
Stakeholders may have concerns
The communication plan should identify which stakeholders
identify stakeholder roles?
about the work product or document
have project responsibility and authority to approve work
they have been reviewing.
products.
Do tasks exist in the project plan for
stakeholder review and sign off?
Stakeholders may be unclear whether The impact of stakeholder delays should be communicated to
or not they have the authority to
stakeholders to give them a chance to provide feedback and
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 10
33. Diagnostics
Clarifying/Focusing Questions
Have stakeholders been contacted to
understand what concerns are holding
up their tasks?
Has a change order been filed to
reflect the schedule, scope and
resource implications of the delay?
Have turn around expectations been
clearly defined and communicated to
stakeholders in writing?
Possible Causes
Potential Contributing Factors
approve a work product.
Stakeholders may be unaware of the
impact that their delays have on the
project.
Possible Remedies
Remedial Action
take appropriate action. If delays continue, change orders
should be filed to communicate the impact of delays to the
sponsor.
Stakeholders may be unaware of the
expectations surrounding their turn
around.
Are the planning assumptions related
to document approval and turnaround
clearly documented?
Is the authority for review or approval
clearly assigned in the project charter
or task descriptions?
Symptom: A team member is struggling to solve a technical problem or struggling to get tasks done in a time that is realistic
How is the problem being approached? The problem may be beyond the skill
Provide mentoring if the issue can be narrowly defined and
of the staff members trying to solve it. targeted mentoring will help.
Does the problem resemble one with
which the team has experience?
Problem solving training may be
Provide opportunity to take training classes.
necessary.
Is the approach to solving the problem
Switch personnel and obtain someone that has a background
rational?
External expertise may be necessary. appropriate to this technical problem or task.
Are multiple avenues of resolution
being sought?
Consider outside expertise to assist with specialized
technology.
Are appropriate internal and external
experts being sought?
Provide problem analysis and problem solving training to the
staff.
What has been tried thus far?
Symptom: A team member is not providing the expected amount of time to the project.
What activities are competing with the
The team member may have been
Talk with the person and determine why they have not been
project for his or her attention?
redirected to other tasks by his or her
putting in the required number of hours.
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 11
34. Diagnostics
Clarifying/Focusing Questions
Possible Causes
Possible Remedies
Potential Contributing Factors
supervisor.
Have the average hours per week
expected from the team member been
documented as part of computing the
duration of the team member’s tasks?
The team member may have other
activities competing for his or her
attention.
Is the team member’s supervisor
aware of the time commitment and
willing to support the project?
The team member may not be
available to the project because of
personal issues.
Remedial Action
Talk to their supervisor or other project managers to resolve
scheduling issues.
Emphasize the importance of their role on the project and limit
their hours to only the work that requires their special effort.
Seek to adjust resource assignments to back fill if possible.
If the resource issue cannot be resolved, submit a change
If personal issues are competing for
request to the sponsor to document the change in assigned
the team member’s time, is a
resources and the schedule or scope implications to the
replacement person available for the
project.
project?
Symptom: Status reports are not being read
Does the communication plan specify
Status reports are too long.
Design status reports to be exception-based.
the content and timing of status
reports?
Status report doesn’t contain the
Ensure the status report contains information that is relevant
information that is really relevant to
to all dimensions of the project.
Have the content, format and
understanding the status of all the
frequency of status reports been
dimensions of the project.
Ensure the status reports accurately reflect project status.
reviewed with the sponsor recently?
Status reports have been too
Is the project still a priority with the
optimistic or untrustworthy.
sponsor?
The sponsor may be become
Has sponsorship changed?
complacent
Symptom: Staff from another department is not being fully compliant or cooperative.
Have expectations for external staff
Staff from another department may
Discuss the issue with the individual. Identify priority conflicts
participation and cooperation been
have higher priorities as assigned by
or other issues contributing to the problem. Review the
clearly communicated to the
their manager.
priority of the project in the context of the competing priorities.
organization?
Expectations may not have been
If discussion with the individual does not resolve the problem
clearly communicated.
or if the individual does not believe that the priority of the
project is higher than other assigned work, discuss the issue
with the individual’s manager or supervisor. Verify priorities,
amount of time and commitment to your project.
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 12
35. Diagnostics
Possible Causes
Possible Remedies
Clarifying/Focusing Questions
Potential Contributing Factors
Remedial Action
If this is not sufficient, discuss the issue with your sponsor and
seek assistance with the organizational issues or changes to
the project schedule boundaries to account for resulting
schedule impacts.
Project team members may have
concerns about the success of the
project. Project teams frequently
know before the project manager and
sponsor when a project is in trouble.
Speak individually with all members of the project team on a
regular basis to provide opportunities to get their perspectives
on the project, what is working well, what is not working well,
their concerns, and their suggestions about how the project
could be better accomplished.
Team members may not believe they
are being fairly compensated or
recognized for their work.
Involve team members in the discussion of decisions that
affect the way that they work.
Symptom: Team morale is low
Does the team have concerns about
the project’s ability to meets its
objectives?
Is the team being pushed hard to make
unrealistic goals?
Is the team being rewarded for their
work?
Are personnel issues being dealt with
promptly and fairly?
Are team members putting in
excessive overtime?
Are any individuals having personal
issues that should be dealt with?
Is the team comfortable with the quality
of the work products they are
producing?
Is there an absence of humor on the
project?
Individual team members may have
personnel issues that need attention
before they can contribute.
Failure to handle discipline or
performance issues with team
members who are not doing their
share may be damaging morale or
cohesiveness of the group.
Many team members take the quality
of their work very seriously and
morale may suffer if they believe that
the quality of their work is inadequate.
Poor morale can cause a spiral of
poorer morale.
Take the time to publicly recognize team members who are
performing well.
Deal promptly, fairly, and privately with performance or
discipline issues.
Look for ways to encourage humor that do not make individual
team members the focus of jokes.
Regularly emphasize that team members have permission to
approach the project manager with suggestions, questions or
concerns.
If a project is not on track to meet its schedule, scope or
resource goals, communicate that information to the sponsor
and assure that the team is involved and aware of any
changes to the goals or approach.
If financial compensation is unavailable, look for ways to use
choice assignments, training opportunities, or allocation of
new equipment as rewards for the team.
If personal problems are causing a disruption, request
additional resources be brought to bear to relieve the troubled
Project Symptom & Diagnostic Aid V1.0
www.catalysisgroup.com
Page 13
36. Diagnostics
Possible Causes
Clarifying/Focusing Questions
Potential Contributing Factors
Possible Remedies
Remedial Action
team member of project responsibilities and deal with the
problem.
Symptom: Team resists timely and accurate status reporting for their tasks
Are status reporting requirements
Reporting requirements may not be
Assure status reporting requirements are clear.
clear?
clear.
Assure the team understands how status information is used.
What is the consequence of inaccurate Team may not understand how the
or untimely status?
data is used.
Assure team understands the value of status information.
Have expectations been clearly
communicated?
Team may not see value in data
reported.
Has the rationale for gathering status
been communicated?
There may be a perception or history
that reported status information
results in negative consequences.
Is status information being used
constructively?
Project Symptom & Diagnostic Aid V1.0
Team may resist status because “it
takes too much time” or is seen as
administrative rather than project
work.
Assure that all information gathered is used constructively.
Assure that the format of status information gathered is
focused and can be reported efficiently.
Consider adding brief status reporting and team meeting tasks
to the project plan to reinforce the perception that status
reporting is a necessary project activity.
www.catalysisgroup.com
Page 14