This document summarizes progress on sediment dredging and regulating pond renovation work at a wastewater treatment plant over the past week. It discusses: dredging of spoil banks 1-3 and sediment areas; installation of outflow pipes and pellet scales; daily and weekly reporting; and plans for next week's work including dredging volumes, outflow pipe installation, and documentation. Visuals show dredging, spoil bank reinforcement, and sediment removal areas. Overall progress was 24.3% of the plan with a delay of 27.3%.