SlideShare a Scribd company logo
1 of 39
DESIGN OF
MARKET
Group Members
■ Amjad Ali
■ Junaid Ijaz
■ Fazal Hussain
■ Zubair
■ Rana Ahsan
■ Sohaib Arshad
Contents
■ Objective
■ Problem Statement
■ Proposed Designs
■ Design of Steel Structure
■ Design of Concrete Structure
■ Bill of Quantities
■ Scheduling
■ Letter to Client
Objective
To propose two solutions for the design of the structure.
To analyze both solution and to adopt one solution that is
more feasible.
To make rough estimate of time for the completion of
construction works.
To determine the construction cost of project.
Problem Statement
■ Design of covered market with following
Specifications.
The roofed area is to be 650 x 260 feet with a clear roof height of
30’.
Entrance 10.0 ft wide are required between 23 ft long sections of
wall.
The roof is required to overhang the perimeter enclosure by
32.75 ft on all sides.
Supporting columns are to have a minimum spacing of 45 ft
internally and externally
The ground floor will be raised above general ground level by 4
inches.
Imposed Loading
■ Roof generally: 13 psf
■ Ground floor: 105 psf
Site Conditions
■ The site is flat.
■ The wind load on the structure can be taken as 35 psf.
■ Ground Conditions:
■ 0 ft to 16.5 ft – very soft clay and silt (Allowable soil pressure = 1 ksf)
■ Below 16.5 ft - strong limestone and hard sandstone (Allowable
pressure = 80 ksf)
Proposed Designs
We proposed two solutions for the design of the structure:
■ Design using steel frame with concrete foundation.
■ Design using reinforced concrete.
Design of light weight Steel
Structure
■ First proposed structural designs on which we decided to work was
steel design.
■ It was like a hipped roof to which a steel frame was supporting.
■ We provides 15 degree slope on each side.
■ The highest point of the slab was the middle section and gradually
decreasing towards the edges in all directions.
TopView
■ We drawn the whole covered area of the building inAutoCAD
software.
SectionViews
Limitations
This idea was rejected because of some limitations.
■ HighWind Load
■ Limited Software knowledge
Design using
reinforced
concrete.
Design of
Steel
Structure
up
Down
Design Of Concrete Structure
■ Second proposed solution was to design it using reinforced
concrete and following the ACI code.
■ We divided our slab into small huts of sizes 49.56 x 49.85.
■ Each hut was further divided into smaller panels of sizes 15.52’x
16.44
■ By using cross beams to reduce the required depth of the slab.
■ There are total 48panels and 65 columns (13 along 650’& 5
along 260’) supporting these panels.
Design Approach
■ The shape of the building was drawn in AutoCAD ,we divided it
into panels of 49.6’x 49.58’.
■ Each panel was of hut like shape.
■ We calculated the total load that is applied on the structure.
For example, wind load of 35 psf and imposed loading of 13 psf.
■ Slab, was divided into panels in the first step. Slab type was
coming out to be one-way.
■ Load from slab was transferred on to the beam
including the dead load of the slab.
■ There are three types of beams.
■ Then load transferred from beams to columns, now
this load was including the dead loads of slab
DESIGN OF
STRUCTURE
DESIGN
OF SLAB
DESIGN
OF
BEAMS
DESIGN
OF
COLUMN
S
DESIGN
OF
FOOTIN
G
Bill of Quantities (BOQ)
Bill of Quantities(BOQ)
SCHEDULING
SCHEDULING
SCHEDULING
References
■ Design of Concrete Structure by Nelson
■ PRC Lectures
■ ACI CODE
■ MRS
THANK
YOU!!

More Related Content

What's hot

Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visitPui San
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report briefMomo Poyi
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABsToe Myint Naing
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Case study steel composite structure
Case study  steel composite structureCase study  steel composite structure
Case study steel composite structureShahin MB
 

What's hot (9)

Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Case study steel composite structure
Case study  steel composite structureCase study  steel composite structure
Case study steel composite structure
 
Site report
Site reportSite report
Site report
 

Similar to Design of Market

Flat slab design
Flat slab designFlat slab design
Flat slab designMoussa Rili
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.CADmantra Technologies
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid ArchitectsDhanveersinh Chavda
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....ManoharManu993491
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Building construction mini project
Building construction mini projectBuilding construction mini project
Building construction mini projectZarnoshKtk
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelBlake Johnson
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN) CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN) Hamza Waheed
 

Similar to Design of Market (20)

Flat slab design
Flat slab designFlat slab design
Flat slab design
 
Folded plates
Folded platesFolded plates
Folded plates
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.
 
TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION. TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION.
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
 
flat Slab
flat Slabflat Slab
flat Slab
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid Architects
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Turning torso
Turning torsoTurning torso
Turning torso
 
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Building construction mini project
Building construction mini projectBuilding construction mini project
Building construction mini project
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN) CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
 

Recently uploaded

COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 

Recently uploaded (20)

COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 

Design of Market

  • 2. Group Members ■ Amjad Ali ■ Junaid Ijaz ■ Fazal Hussain ■ Zubair ■ Rana Ahsan ■ Sohaib Arshad
  • 3. Contents ■ Objective ■ Problem Statement ■ Proposed Designs ■ Design of Steel Structure ■ Design of Concrete Structure ■ Bill of Quantities ■ Scheduling ■ Letter to Client
  • 4. Objective To propose two solutions for the design of the structure. To analyze both solution and to adopt one solution that is more feasible. To make rough estimate of time for the completion of construction works. To determine the construction cost of project.
  • 5. Problem Statement ■ Design of covered market with following Specifications. The roofed area is to be 650 x 260 feet with a clear roof height of 30’. Entrance 10.0 ft wide are required between 23 ft long sections of wall. The roof is required to overhang the perimeter enclosure by 32.75 ft on all sides. Supporting columns are to have a minimum spacing of 45 ft internally and externally The ground floor will be raised above general ground level by 4 inches.
  • 6. Imposed Loading ■ Roof generally: 13 psf ■ Ground floor: 105 psf Site Conditions ■ The site is flat. ■ The wind load on the structure can be taken as 35 psf. ■ Ground Conditions: ■ 0 ft to 16.5 ft – very soft clay and silt (Allowable soil pressure = 1 ksf) ■ Below 16.5 ft - strong limestone and hard sandstone (Allowable pressure = 80 ksf)
  • 7. Proposed Designs We proposed two solutions for the design of the structure: ■ Design using steel frame with concrete foundation. ■ Design using reinforced concrete.
  • 8. Design of light weight Steel Structure ■ First proposed structural designs on which we decided to work was steel design. ■ It was like a hipped roof to which a steel frame was supporting. ■ We provides 15 degree slope on each side. ■ The highest point of the slab was the middle section and gradually decreasing towards the edges in all directions.
  • 9. TopView ■ We drawn the whole covered area of the building inAutoCAD software.
  • 11. Limitations This idea was rejected because of some limitations. ■ HighWind Load ■ Limited Software knowledge
  • 13. Design Of Concrete Structure ■ Second proposed solution was to design it using reinforced concrete and following the ACI code. ■ We divided our slab into small huts of sizes 49.56 x 49.85. ■ Each hut was further divided into smaller panels of sizes 15.52’x 16.44 ■ By using cross beams to reduce the required depth of the slab.
  • 14. ■ There are total 48panels and 65 columns (13 along 650’& 5 along 260’) supporting these panels.
  • 15. Design Approach ■ The shape of the building was drawn in AutoCAD ,we divided it into panels of 49.6’x 49.58’. ■ Each panel was of hut like shape. ■ We calculated the total load that is applied on the structure. For example, wind load of 35 psf and imposed loading of 13 psf. ■ Slab, was divided into panels in the first step. Slab type was coming out to be one-way.
  • 16.
  • 17. ■ Load from slab was transferred on to the beam including the dead load of the slab. ■ There are three types of beams. ■ Then load transferred from beams to columns, now this load was including the dead loads of slab
  • 20.
  • 21.
  • 23.
  • 24.
  • 26.
  • 27.
  • 29.
  • 30.
  • 33.
  • 37.
  • 38. References ■ Design of Concrete Structure by Nelson ■ PRC Lectures ■ ACI CODE ■ MRS

Editor's Notes

  1. a) High Wind Load When we tried to proceed to model and design these members of frame, we calculated loads, the wind load for this frame structure was so challenging. In case of steel, the dead load is very low as compare to concrete so to cater upward wind load in case of a light weight steel frame, we had to take very seriously the joints and the concrete foundation too. Otherwise wind would lift off the whole frame and structure would collapse. b) Limited Software knowledge When we decided to model the frame on ETABS software because we had some basic know how about analyzing some structure on software, but for modeling it was our first try, but we faced a problem of having a little knowledge about the design of steel structures and software as well. we tried to get some knowledge about the method from internet, how to model a frame on the software, but we realized that the time was too short to learn software and steel design code to model such challenging frame.