SlideShare a Scribd company logo
1 of 14
Estimation of
Capital Investments
Dr. K. Shahzad Baig
Memorial University of Newfoundland (MUN) Canada
Capital Investments
Capital : Amount required to start a business
Fixed-Capital Investment
The capital needed to supply the necessary manufacturing and
plant facilities is called the fixed-capital investment
Working Capital:
Working Capital
required to utilize
fixed assets
Working Capital refers to
short term funds, to meet
operating expenses.
In simple ‘Working Capital is
a fund required by firm
to finance day-to-day operations
Estimation of Capital Investment
Direct Costs
1. Purchased equipment
2. Purchased-equipment
installation
3. Instrumentation and controls
4. Piping
5. Electrical equipment and
materials
6. Buildings (including services)
7. Yard improvements
8. Service facilities
9. Land
• Indirect Costs
1. Engineering and supervision
2. Construction expenses
3. Contractor’s fee
4. Contingency
Types of Capital Cost Estimate
1. Order-of-magnitude estimate (ratio estimate)
2. Study estimate (factored estimate)
3. Preliminary estimate (budget authorization estimate;
scope estimate)
4. Definitive estimate (project control estimate)
5. Detailed estimate (contractor’s estimate)
Order-Of-Magnitude Estimates
This estimate is generally used by management in feasibility
studies, for evaluating the best process, the establishment of
plant size and the economic feasibility of the project.
• For the preparation of the OOM, the estimator requires the
following general and engineering information:
– Plant capacity
– General Scope Description
– Process Block Diagrams
– General geographic location
– The cost of a similar previous project
Method of estimation:
The cost of the present project is determined by the ratio
method.
The price of the previous project is adjusted for size (capacity)
by using the 6-10th's rule. The size adjusted cost is then adjusted
for inflation by using published price indices.
– Other Methods
Turn over ratio method, fixed investments per ton of capacity
6-10th rule is given next
Cost Capacity Relation.
The six-tenths or 0 .6, rule. This equation permits the user to
obtain a cost for an equipment item of a different size when the
cost for given size is known.
The 6-10ths rule
𝐶2 = 𝐶1
𝑆2
𝑆1
𝑛
C1 = Cost for equipment Capacity S1
C2 = Cost for equipment Capacity S2
n = an exponent t
The exponent varies between 0.30 to 1.20
depending upon the cost of equipment
Cost Capacity Exponent
For most process equipment, the exponent varies between 0.4
and 0.8 with an average value of about 0.6. When the exponent
is unknown, this value may be used.
If we assume that for an equipment item, a cost-capacity
exponent is 0.6, doubling the capacity will increase the cost
about 50–60%, not 100%. The economy of scale is reflected in
the exponent.
If the exponent is less than 1.0, there is an economy of scale. As
n approaches the value of 1, the economy of scale disappears.
• An exponent greater than 1.0 is a negative economy of scale
and multiple equipment units should be used.
Problem Statement:
Recently a cast iron leaf pressure filter with 100 ft2 was
purchased for clarifying an inorganic liquid stream for
$15,000. In a similar application, the company will need a
450 ft2 cast iron leaf pressure filter. The size exponent f
or this type filter is 0.6. Estimate the purchased price of
the 450 ft2 unit.
𝐶𝑜𝑠𝑡450 = 𝐶𝑜𝑠𝑡100
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦450
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦100
0.6
= 15000
450
100
0.6
= $ 37050
Following books were used in preparation of notes
 Blank, L., Tarquin. A. 2005. Engineering Economy. 6th Edition, McGraw-Hill.
 Eschenbach, T. G. 2003. Engineering Economy”, 2nd Edition, Oxford University Press
 Riggs, J. L., Bedworth, D. D., Randhawa, S. U. 1996. Engineering Economics”, 4th Edition, Tata
McGraw-Hill.
 Riggs, J. L., West. T. M. 1986. Essentials of Engineering Economics”, 2nd Edition, McGraw-Hill.
 Peter, M. S., Timmerhaus, K. D. 1991. Plant Design and Economics for Chemical Engineers. 4th
Edition, McGraw-Hill.

More Related Content

What's hot

Matlab for Chemical Engineering
Matlab for Chemical EngineeringMatlab for Chemical Engineering
Matlab for Chemical EngineeringDebarun Banerjee
 
Multi Effect Evaporators
Multi Effect EvaporatorsMulti Effect Evaporators
Multi Effect EvaporatorsNishant Arora
 
Types of Crystallizers
Types of CrystallizersTypes of Crystallizers
Types of CrystallizersMuhammad Ahmad
 
Distillery Industry Waste and Its Treatment
Distillery Industry Waste and Its TreatmentDistillery Industry Waste and Its Treatment
Distillery Industry Waste and Its TreatmentLakhan Kumar
 
material balance and its applications
material balance and its applicationsmaterial balance and its applications
material balance and its applicationsKarnav Rana
 
Material balance with chemical reaction
Material balance with chemical reactionMaterial balance with chemical reaction
Material balance with chemical reactionJayJawalge
 
Single and multiple effective evaporator (mee)
Single and multiple effective evaporator (mee)Single and multiple effective evaporator (mee)
Single and multiple effective evaporator (mee)Sumer Pankaj
 
Leaching equipmnts
Leaching equipmntsLeaching equipmnts
Leaching equipmntsNandy 91
 
Anaerobic digestion
Anaerobic digestionAnaerobic digestion
Anaerobic digestionpritiverma34
 
LEACHING ( MASS TRANSFER OPERATION)
LEACHING ( MASS TRANSFER OPERATION)LEACHING ( MASS TRANSFER OPERATION)
LEACHING ( MASS TRANSFER OPERATION)LDCE
 
BIOMASS GASIFICATION
BIOMASS GASIFICATION BIOMASS GASIFICATION
BIOMASS GASIFICATION P RP
 
Selection Criteria of a Plant
Selection Criteria of a PlantSelection Criteria of a Plant
Selection Criteria of a Plantankur19june
 
Introduction of Effluent Treatment Plant
Introduction of Effluent Treatment PlantIntroduction of Effluent Treatment Plant
Introduction of Effluent Treatment PlantAkash Tikhe
 

What's hot (20)

Matlab for Chemical Engineering
Matlab for Chemical EngineeringMatlab for Chemical Engineering
Matlab for Chemical Engineering
 
Leaching
LeachingLeaching
Leaching
 
Multi Effect Evaporators
Multi Effect EvaporatorsMulti Effect Evaporators
Multi Effect Evaporators
 
Types of Crystallizers
Types of CrystallizersTypes of Crystallizers
Types of Crystallizers
 
Distillery Industry Waste and Its Treatment
Distillery Industry Waste and Its TreatmentDistillery Industry Waste and Its Treatment
Distillery Industry Waste and Its Treatment
 
cross flow filtration
cross flow filtrationcross flow filtration
cross flow filtration
 
Electrodialysis
ElectrodialysisElectrodialysis
Electrodialysis
 
material balance and its applications
material balance and its applicationsmaterial balance and its applications
material balance and its applications
 
Leaching
LeachingLeaching
Leaching
 
Material balance with chemical reaction
Material balance with chemical reactionMaterial balance with chemical reaction
Material balance with chemical reaction
 
Single and multiple effective evaporator (mee)
Single and multiple effective evaporator (mee)Single and multiple effective evaporator (mee)
Single and multiple effective evaporator (mee)
 
Leaching equipmnts
Leaching equipmntsLeaching equipmnts
Leaching equipmnts
 
Anaerobic digestion
Anaerobic digestionAnaerobic digestion
Anaerobic digestion
 
LEACHING ( MASS TRANSFER OPERATION)
LEACHING ( MASS TRANSFER OPERATION)LEACHING ( MASS TRANSFER OPERATION)
LEACHING ( MASS TRANSFER OPERATION)
 
BIOMASS GASIFICATION
BIOMASS GASIFICATION BIOMASS GASIFICATION
BIOMASS GASIFICATION
 
Particle Technology and Characterisation
Particle Technology and CharacterisationParticle Technology and Characterisation
Particle Technology and Characterisation
 
Reactor Design 1
Reactor Design 1Reactor Design 1
Reactor Design 1
 
Selection Criteria of a Plant
Selection Criteria of a PlantSelection Criteria of a Plant
Selection Criteria of a Plant
 
Introduction of Effluent Treatment Plant
Introduction of Effluent Treatment PlantIntroduction of Effluent Treatment Plant
Introduction of Effluent Treatment Plant
 
Batch Distillation
Batch DistillationBatch Distillation
Batch Distillation
 

Similar to Estimation of Capital Investments

Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial ApplicationK. Shahzad Baig
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
 
energysimulation01-170601095924.pdf
energysimulation01-170601095924.pdfenergysimulation01-170601095924.pdf
energysimulation01-170601095924.pdfShree Sowmya Chinta
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial toolsOmid Aminzadeh Gohari
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsAnjumNaveed12
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyAditya Deshpande
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptxSulemanAhmad21
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
cost estimation and break even analysis
cost estimation and break even analysiscost estimation and break even analysis
cost estimation and break even analysisDr Naim R Kidwai
 
Comparison between SAM and RETScreen
Comparison between SAM and RETScreenComparison between SAM and RETScreen
Comparison between SAM and RETScreenAnkit Thiranh
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lectureArul Kumar
 
UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION PremanandDesai
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC AKSHAY SHARMA
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdfMaheshBika
 

Similar to Estimation of Capital Investments (20)

CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial Application
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Production Costs
Production CostsProduction Costs
Production Costs
 
energysimulation01-170601095924.pdf
energysimulation01-170601095924.pdfenergysimulation01-170601095924.pdf
energysimulation01-170601095924.pdf
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial tools
 
Energy simulation & analysis
Energy simulation & analysisEnergy simulation & analysis
Energy simulation & analysis
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skills
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
 
Cost managment
Cost managmentCost managment
Cost managment
 
CCP Material
CCP MaterialCCP Material
CCP Material
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptx
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
cost estimation and break even analysis
cost estimation and break even analysiscost estimation and break even analysis
cost estimation and break even analysis
 
Comparison between SAM and RETScreen
Comparison between SAM and RETScreenComparison between SAM and RETScreen
Comparison between SAM and RETScreen
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lecture
 
UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION UNIT - 01 INTRODUCTION
UNIT - 01 INTRODUCTION
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
 
CCP Material.pdf
CCP Material.pdfCCP Material.pdf
CCP Material.pdf
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdf
 

More from K. Shahzad Baig

Nominal and Effective Interest Rate
Nominal and Effective Interest RateNominal and Effective Interest Rate
Nominal and Effective Interest RateK. Shahzad Baig
 
Interest Why Engineers should know ?
InterestWhy Engineers should know ?InterestWhy Engineers should know ?
Interest Why Engineers should know ?K. Shahzad Baig
 
Projects, Investment, Profitability
Projects, Investment, ProfitabilityProjects, Investment, Profitability
Projects, Investment, ProfitabilityK. Shahzad Baig
 
Taxes and Insurance Engineering point of view
Taxes and InsuranceEngineering point of viewTaxes and InsuranceEngineering point of view
Taxes and Insurance Engineering point of viewK. Shahzad Baig
 
Estimation of Fixed Capital Cost
Estimation of Fixed Capital CostEstimation of Fixed Capital Cost
Estimation of Fixed Capital CostK. Shahzad Baig
 
Summary of Production Costs
Summary of Production CostsSummary of Production Costs
Summary of Production CostsK. Shahzad Baig
 
Purchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentPurchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentK. Shahzad Baig
 
Mass Transfer Equipment Cost
Mass Transfer Equipment CostMass Transfer Equipment Cost
Mass Transfer Equipment CostK. Shahzad Baig
 
HEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSHEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSK. Shahzad Baig
 
Gross Profit, Net Profit
Gross Profit, Net ProfitGross Profit, Net Profit
Gross Profit, Net Profit K. Shahzad Baig
 
Fluctuation of money value with time
Fluctuation of money value with timeFluctuation of money value with time
Fluctuation of money value with timeK. Shahzad Baig
 
Economics for Engineers, Why ?
Economics for Engineers, Why ?Economics for Engineers, Why ?
Economics for Engineers, Why ?K. Shahzad Baig
 
Psychrometric chart, How to read
Psychrometric chart, How to readPsychrometric chart, How to read
Psychrometric chart, How to readK. Shahzad Baig
 
The mole and chemical compounds
The mole and chemical compounds The mole and chemical compounds
The mole and chemical compounds K. Shahzad Baig
 

More from K. Shahzad Baig (20)

Income tax
Income taxIncome tax
Income tax
 
Nominal and Effective Interest Rate
Nominal and Effective Interest RateNominal and Effective Interest Rate
Nominal and Effective Interest Rate
 
Interest Why Engineers should know ?
InterestWhy Engineers should know ?InterestWhy Engineers should know ?
Interest Why Engineers should know ?
 
Projects, Investment, Profitability
Projects, Investment, ProfitabilityProjects, Investment, Profitability
Projects, Investment, Profitability
 
Taxes and Insurance Engineering point of view
Taxes and InsuranceEngineering point of viewTaxes and InsuranceEngineering point of view
Taxes and Insurance Engineering point of view
 
Estimation of Fixed Capital Cost
Estimation of Fixed Capital CostEstimation of Fixed Capital Cost
Estimation of Fixed Capital Cost
 
Summary of Production Costs
Summary of Production CostsSummary of Production Costs
Summary of Production Costs
 
Purchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentPurchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous Equipment
 
Mass Transfer Equipment Cost
Mass Transfer Equipment CostMass Transfer Equipment Cost
Mass Transfer Equipment Cost
 
HEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSHEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTS
 
Gross Profit, Net Profit
Gross Profit, Net ProfitGross Profit, Net Profit
Gross Profit, Net Profit
 
Manufacturing Costs
Manufacturing Costs Manufacturing Costs
Manufacturing Costs
 
Capital Investment
Capital InvestmentCapital Investment
Capital Investment
 
Location of an industry
Location of an industryLocation of an industry
Location of an industry
 
Fluctuation of money value with time
Fluctuation of money value with timeFluctuation of money value with time
Fluctuation of money value with time
 
Economics for Engineers, Why ?
Economics for Engineers, Why ?Economics for Engineers, Why ?
Economics for Engineers, Why ?
 
Psychrometric chart, How to read
Psychrometric chart, How to readPsychrometric chart, How to read
Psychrometric chart, How to read
 
The Scientific Methods
The Scientific MethodsThe Scientific Methods
The Scientific Methods
 
The Nuclear Atom
The Nuclear Atom The Nuclear Atom
The Nuclear Atom
 
The mole and chemical compounds
The mole and chemical compounds The mole and chemical compounds
The mole and chemical compounds
 

Recently uploaded

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 

Recently uploaded (20)

POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 

Estimation of Capital Investments

  • 1. Estimation of Capital Investments Dr. K. Shahzad Baig Memorial University of Newfoundland (MUN) Canada
  • 2. Capital Investments Capital : Amount required to start a business
  • 3. Fixed-Capital Investment The capital needed to supply the necessary manufacturing and plant facilities is called the fixed-capital investment
  • 4. Working Capital: Working Capital required to utilize fixed assets Working Capital refers to short term funds, to meet operating expenses. In simple ‘Working Capital is a fund required by firm to finance day-to-day operations
  • 5. Estimation of Capital Investment Direct Costs 1. Purchased equipment 2. Purchased-equipment installation 3. Instrumentation and controls 4. Piping 5. Electrical equipment and materials 6. Buildings (including services) 7. Yard improvements 8. Service facilities 9. Land
  • 6. • Indirect Costs 1. Engineering and supervision 2. Construction expenses 3. Contractor’s fee 4. Contingency
  • 7. Types of Capital Cost Estimate 1. Order-of-magnitude estimate (ratio estimate) 2. Study estimate (factored estimate) 3. Preliminary estimate (budget authorization estimate; scope estimate) 4. Definitive estimate (project control estimate) 5. Detailed estimate (contractor’s estimate)
  • 8. Order-Of-Magnitude Estimates This estimate is generally used by management in feasibility studies, for evaluating the best process, the establishment of plant size and the economic feasibility of the project. • For the preparation of the OOM, the estimator requires the following general and engineering information: – Plant capacity – General Scope Description – Process Block Diagrams – General geographic location – The cost of a similar previous project
  • 9. Method of estimation: The cost of the present project is determined by the ratio method. The price of the previous project is adjusted for size (capacity) by using the 6-10th's rule. The size adjusted cost is then adjusted for inflation by using published price indices. – Other Methods Turn over ratio method, fixed investments per ton of capacity 6-10th rule is given next
  • 10. Cost Capacity Relation. The six-tenths or 0 .6, rule. This equation permits the user to obtain a cost for an equipment item of a different size when the cost for given size is known. The 6-10ths rule 𝐶2 = 𝐶1 𝑆2 𝑆1 𝑛 C1 = Cost for equipment Capacity S1 C2 = Cost for equipment Capacity S2 n = an exponent t The exponent varies between 0.30 to 1.20 depending upon the cost of equipment
  • 11. Cost Capacity Exponent For most process equipment, the exponent varies between 0.4 and 0.8 with an average value of about 0.6. When the exponent is unknown, this value may be used. If we assume that for an equipment item, a cost-capacity exponent is 0.6, doubling the capacity will increase the cost about 50–60%, not 100%. The economy of scale is reflected in the exponent. If the exponent is less than 1.0, there is an economy of scale. As n approaches the value of 1, the economy of scale disappears. • An exponent greater than 1.0 is a negative economy of scale and multiple equipment units should be used.
  • 12. Problem Statement: Recently a cast iron leaf pressure filter with 100 ft2 was purchased for clarifying an inorganic liquid stream for $15,000. In a similar application, the company will need a 450 ft2 cast iron leaf pressure filter. The size exponent f or this type filter is 0.6. Estimate the purchased price of the 450 ft2 unit.
  • 14. Following books were used in preparation of notes  Blank, L., Tarquin. A. 2005. Engineering Economy. 6th Edition, McGraw-Hill.  Eschenbach, T. G. 2003. Engineering Economy”, 2nd Edition, Oxford University Press  Riggs, J. L., Bedworth, D. D., Randhawa, S. U. 1996. Engineering Economics”, 4th Edition, Tata McGraw-Hill.  Riggs, J. L., West. T. M. 1986. Essentials of Engineering Economics”, 2nd Edition, McGraw-Hill.  Peter, M. S., Timmerhaus, K. D. 1991. Plant Design and Economics for Chemical Engineers. 4th Edition, McGraw-Hill.