Project Brief • Looking following projects :
33/11 KV PSS Paliganj.
33/11 KV PSS Nabautpur.
33/11 KV PSS Dhanarua
33/11 KV Kaura
33/11 KV PSS Beldharichak
33/11 KV PSS Athmalgola
33/11 KV PSS Ghoswari
Agumentation of 16 no old PSS at Patna District
11 no 33 KV Bay Extn & 11 no 11 KV Bay Extn
RE works of 1254 Village in nalanda district.
33 KV Line, 11 KV Line works
Re-conducting 33KV & 11 KV Line
33 KV Bay Extension & 11 KV Bay Extension
Work Profile Project Management Consultancy at Patna
• Supervision of works; all Concreting work in 33/11 KV Sub-station to be done in his or
Field Engineers presence only.
• Keep proper records of the Contractors' activities and work progress;
• Ensure that the respective Contractor(s) are properly administered;
• Assist the Team Leader with the review of the Contractors' Work Program and scheme
for the deployment of plant, equipment and machinery;
• Strictly monitor the progress of work for timely completion of the project;
• Supervision, scrutiny, approving the final setting out by the Contractor.
• Assisting the Team Leader with updating drawings, setting up quantity and quality
control procedures and review of contractors' method of construction;
• Monitoring Contractors' operations including adherence to safety and environmental
• Assisting field engineers for issuing site instructions;
• Assisting the Team Leader with the preparation of Variation orders;
• Maintaining a record set of working drawings;
• Maintaining construction records;
• Joint verification with SBPDCL for recording of Measurements of completed
• Bill evaluation of Contractors' Claims;
• Quality control of works; verification of Bus-Bar stringing, alignments in Sub-Stations in
types of lines, inspection of works, acceptance and rejection of the completed works;
• Verification of Contractors' monthly estimates of the completed works and preparation of Interim Certificates;
• Conducting and keeping record of minutes of the weekly site meetings;
• Preparing monthly Progress Reports;
• Final inspection of works;
• Verification of Contractors' Statements at completion;
• Compilation and verification of "As-Built Drawings and Preparation of contract Completion Reports.
Bharat Bijlee Ltd Airoli Mumbai 12th May 2011- 31st
Dec 2013
Designation • Manager (Projects)
Project Brief • Looking following projects :-
1) 132 KV Bay EXTENSION of Renuka Sugar Mill, Gujrat
2) 132 KV Bay Extension Silk Road Chennai
3) 132 KV & 66 KV Bay extension Ultratech Cemant, Gujrat
4) 132 KV Bay extension Sri Ram EPC, Chennai
2. Work Profile Project Management at Airoli, Mumbai
• Finalize Civil/Erection Sub Contracts and mobilize Site as per schedule
• Finalization of vendors & contractor.
• Co-ordinate with consultant for design issue..
• Ensure timely submission of documents/manufacturing/inspection/dispatch of material from Vendors and IDTO
Partners
• Ensure effective site closure and provide service during warranty.
• Ensure effective cost control and positive cash flow.
• Coordination between our design deptt, client & supplier.
• Coordinate with supply chain management for vendor order finalization.
• Vendor development.
• BOQ Preparation from drawing.
• Procurement planning & material reconciliation..
• Material Inspection & take dispatch clearance from customer.
• Scheduling of project network in MS Project and its regular updating after the analysis of critical points.
• Coordinate between site & office.
• Preparing monthly, quarterly revenue, cost & collection.
• Weekly JSR Review.
• Preparing progress report & submit to customer.
• Monthly Safety review with safety coordinator.
• Follow up with supplier.
• Responsible for inspection of material & taking clearance from customer.
• Monthly Review Cost & Revenue on SAP.
ABB LTD Faridabad 18th
JUN 2007- 20 April 2011
Designation • Astt Manager (Projects)
Project Brief • Worked for PGCIL Bihar Ph-2 PKG-B & HVPNL JBIC 006 PKG A & PKG B having 10 no of sites as follows
PGCIL BIHAR PH -2
220/132/33 KV GSS Sipara main pkg
220/132/33 KV GSS Fatuha Ext Pkg
132/33 KV GSS Jakkanpur Ext Pkg
132/33 KV GSS Jehanabad Ext Pkg
132/33 KV GSS Vaishali Ext Pkg
132/33 KV GSS Shetalpur Ext Pkg
33/11 KV Sampat chak Bay Ext
33/11 KV Pahari Bay Ext
33/11 KV Karbighia Bay Ext
33/11 KV Kuranawada Bay Ext
2) HVPNL JBIC 006 PKG A & PKG B
220/132/33 KV Chormar
132/33 KV Khairekan
132/33 KV Kurangawali
132/33 KV Dhudianwal
3) PGCIL Fatehabad & Hissar
400/220 KV Fatehabad New
400 KV Hissar Exten
RRVPNL132/33 KV Hybrid substation at SMS Stadium Jaipur
PGCIL Lucknow,Agra,Gwalior & baraillxten
400/220 KV LucknowEXTN
400/220 KV Agra EXTN
400/220 KV Gwalior EXTN
400/220 KV Baralli EXTN
3. Work Profile Project Management at Fridabad
• Finalise Civil/Erection Sub Contracts and mobilise Site as per schedule
• Coordinate with cross functional teams, viz, Engineering, SCM, Finance, Safety, Compliance, etc for necessary
inputs.
• Ensure timely submission of documents/manufacturing/inspection/despatch of material from Vendors and IDTO
Partners
• Ensure effective site closure and provide service during warranty.
• Ensure effective cost control and positive cash flow.
• Coordination between our design deptt,client & supplier.
• Coordinate with supply chain management for vendor order finalization.
• Vendor development.
• BOQ Preparation from drawing.
• Procurement planning & material reconciliation..
• Material Inspection & take dispatch clearance from customer.
• Scheduling of project network in MS Project and its regular updating after the analysis of critical points.
• Coordinate between site & office.
• Preparing monthly, quarterly revenue, cost & collection.
• Weekly JSR Review.
• Preparing progress report & submit to customer.
• Monthly Safety review with safety coordinator.
• Follow up with supplier.
• Responsible for inspection of material & taking clearance from customer.
• Monthly Review Cost & Revenue on SAP.
Areva T&D India Ltd,Vikaramganj Bihar 7TH
June 2006- 17th
June2007
Designation • Site Engineer ( Electrical )
Project Brief • Construction of seven new PSS PGCIL Bihar Pkg - G (RGGVY Projects)
33/11 KV PSS Dawat
33/11 KV PSS Surajpura
33/11 KV PSS Sanjholi
33/11 KV PSS Karakat
33/11 KV PSS Parsatuha
33/11 KV PSS Rajpur
33/11 KV PSS Chainpur
Work Profile • Incharge of electrical & civil activity
• Monitoring augmentation job.
• Monitoring 33 KV 120 km approx line job.
• Coordinate with office.
• Dealing with contractor & client at site
• Preparing daily progress report.
• Material & Collection reconciliation.
BSES Yamuna Power Ltd a unit of Reliance energy 10TH
Sep 2003- 1st
June'2006
Designation • Asst Engineer (Power Supply)
Work Profile • Having a charge of electrification of unelectrified area using concept of H.V.D.S.
• Addition of load i.e. technical feasibility increasing/decreasing of load.
• Technical feasibility for new connections of industrial & domestic load.
• Accuracy checking of energy meter using Aqua check meter.
• Lead enforcement team for stopping theft of electricity.
• Maintenance of service cable.
• Consumer handling at office also.
• In charge of commercial section of office.
• Monitoring major project & deal J.E's also
• Handling of labours contractor at the site.
• Handling I.T.I holders also.
ACADEMIC
Certificate/Degree Institute / Board Year
Bachelor of Electrical Engg Visvesvaraya Technological University, Karnataka 2003
Intermediate in Science (12th
) TPSollege, Patna, Bihar 1995
Secondary School Exam (10th
) S.G.D. Patliputra High School, Patna, Bihar 1993
ACHIEVEMENTS / AWARDS
4. Achievements /
Awards
• Awarded by A.G.M, East Delhi for reducing of theft from 65% to 55% in one year in the form of trophy
Project Work
6th
Semester
8th
Semester
UPS for cordless Telephone.
Study report on Wind Mill Power Generation
Training
Attainted one week training for capacity building by Power Grid.
Five days Training program Project Planning Analysis & Controlling program from ESI International at ABB.
one day Project Safety Management training program by ABB LTD.
one day financial related issues for project training program by ABB LTD.
one day corporate working training program by ABB LTD.
one day fun at work training program by ABB LTD.
One day SAP Training.
COMPUTER SKILLS
Project Management Tools MS Project,MS Office, SAP
Operating Systems Windows
FATHER'S NAME SRI KRISHNA DEO NARAIN (RTD EXCISE SUPTT)
DATE OF BIRTH 1ST
MARCH 1979
SALARY DETAILS
Present Salary 9.25 LPA
Expexted Salary Negotiable
OBJECTIVES
I have experience in Electrical Engineering. I have handled the important portfolio in very good manner. My work experience has honed my
analytical and interpersonal skills and instilled a very high confidence level, which will be a great advantage. With my rich on the site
experience and fairly decent academics I assure you of my sincerity and I promise that given an opportunity to serve in your esteemed
organization, I will deliver the best and will surpass your expectations.
Place:
Date: Sandeep Saurabh