SlideShare a Scribd company logo
1 of 10
Download to read offline
1
QUANTITATIVE RISK ASSESSMENT – ROAD
TRANSPORT INFRASTRUCTURE DEVELOPMENT
PROJECT PREPARATION PERSPECTIVE
Subir Kumar Podder1
ABSTRACT
The paper is aimed at outlining an approach for Quantitative Risk
Assessment employing stochastic analysis (with a triangular distribution)
so as to determine the combined influence of the dictating parameters on
probabilities. It is appreciated that in the perspective of Road Transport
Development Projects, and more specifically the Economic Analysis
carried out in Feasibility Studies for Road Improvement and
Rehabilitation Projects, such dictating parameters are Traffic and Project
Cost. Accordingly the paper aims at an approach for determining the
impact (on Traditional Economic Analysis Instruments like EIRR, NPV)
under a combined influence of the aforesaid two parameters. Such
analysis requires treading a step beyond that what is required when
probabilities are ascertained separately, and is the focus of this paper.
1. INTRODUCTION
Quantitative Risk Analysis – It provides a means of
estimating the probability that the project NPV will fall
below zero, or that the project EIRR will fall below the
opportunity cost of capital.
More explicitly, the quantitative risk analysis involves
randomly selecting values for the variables from the
probability distribution determined; combining these
values with all base case values to give an EIRR (or NPV)
result; and repeating such a calculation a large number of
times to provide a large number of EIRR (or NPV)
estimates. These estimates are then summarized in a
distribution, key features of which is the proportion of
EIRR values that fall below (i) the opportunity cost of
capital (say 12 per cent), (ii) the most likely forecast values
(i.e. the value which the analysis actually yielded). The
objective is to estimate the probability that the project
might turn out to be unacceptable.
Traditionally, the principle of risk analysis is based on
random simulations carried out assuming a triangular
probability distribution with predetermined minimum,
most likely and maximum limits. The most likely values are
those assumed for the base case situation, whilst the lower
and upper limits that are to be applied for risk analysis in
road feasibility studies are expressed in terms of percentage
(%) of the base-case2
values.3
1
Consultant (Highways), LEA Associates South Asia Pvt.
Ltd, New Delhi, INDIA
2
The base-case refers to Estimated Project Cost and
Estimated Traffic. Risks triggered by changes from these
Triangular Probability Distribution - The triangular
distribution is typically used as a subjective description of a
population for which there is only limited sample data, and
especially in cases where the relationship between variables
is known but data is scarce. It is based on knowledge of the
maximum and minimum and an “Inspired guess” as to the
modal value. [For this reason the triangular distribution has
been called a “lack of knowledge” distribution]. The
triangular distribution is often used in business decision
making4
, particularly in simulations. Generally, when not
much data is known about the distribution of an outcome,
(say, only its smallest and largest values are known), it is
possible to use the uniform distribution. But if the most
likely outcome is also known, then the outcome can be
simulated by a triangular distribution.5
In probability
theory and statistics, the triangular distribution is a
continuous probability distribution with lower limit a, upper
limit b and mode c, where a < b and a <= c <= b. The
probability density function (pdf) is given by:
..................(1)
The cumulative distribution function (cdf) is given by:
............(1A)
There are generally no fixed criteria for using such a result
in ascertaining the acceptability of the Project Viability.
estimates, measured in terms of impacts on the economic
parameters, are essentially what the the quantitative risk
assessment is aimed at.
3
The adopted values (i.e. % of base-case values) are
generally those that the Terms of Reference for a particular
project specify. However, generally they are the same that
are accounted for Sensitivity Analysis performed under an
Economic Analysis.
4
The triangular distribution, along with the Beta
distribution, is also widely used in project management (as
an input into PERT and hence critical path method (CPM))
to model events which take place within an interval defined
by a minimum and maximum value.
5
Source: Wikipedia, the free encyclopedia
2
However, high risk probabilities may be associated with
projects that have a high expected NPV (or EIRR).6
Pertinence to Road Development Projects - Risk
analysis, carried out under Feasibility Studies, for road
transport development projects is concerned with the
probability or likelihood of the following:
 Construction costs increasing/ decreasing by a
certain percentage than that for the base-case;
&
 Traffic growth occurring at a lower/higher rate
than that assumed in the base case situation.
Such probabilities get determined employing the principles
of random simulations assuming a triangular probability
distribution.
Continuing from above, intrinsic to the triangular
probability distribution are the boundary conditions
(upper and lower limits7
, as well as the mode value i.e. the
most likely value). Very often the prescribed values for the
upper and lower limits are as follows:
UPPER LIMIT:
1) Construction Cost – 90 % of the Base Case
(i.e. the Favoured Alternative)
2) Traffic Growth – 110% of the Base Case
(i.e. the Favoured Alternative)
LOWER LIMIT:
1) Construction Cost – 120 % of the Base Case
(i.e. the Favoured Alternative)
2) Traffic Growth – 75% of the Base Case (i.e.
the Favoured Alternative)
6
Source: Page 157, Appendix 21, Guidelines for the
Economic Analysis of Projects, Economic and Development
Resource Center, the Asian Development Bank, February
1997.
7
It is imperative that the (i) Upper Limits correspond to the
scenario where the %-change to the variables lend a higher
EIRR (or NPV); and (ii) Lower Limits correspond to the
scenario where the %-change to the variables lend a lower
EIRR (or NPV), when compared to the EIRR (or NPV) of
the Favoured Alternative (the most likely value i.e. that the
analysis yields with the Base Case values).
2. THE CONVENTIONAL PRACTICE
With the boundary conditions in place, as stated
immediately above, the stochastic analysis, as often
practiced, essentially involves the following steps:
 Establishing the probability distribution function
(pdf), assuming a triangular probability distribution,
for changes in EIRR triggered by COST
 Making Random Simulations to arrive at a large
number of estimates (of EIRR)
 Establishing the cumulative distribution function
(cdf) [it essentially summarises the estimates]
 Interpreting the results which essentially is
determining the proportion of EIRR values that fall
below (i) the opportunity cost of capital (say 12 per
cent), (ii) the most likely forecast values (i.e. the
value which the analysis actually yielded), (iii) the
central estimates (say the mean value).
The analysis is then repeated for changes in EIRR as
triggered by changes to TRAFFIC.
The aforesaid steps can be performed using a MS EXCEL
spreadsheet analysis8
that employs in-built functions to
generate random functions and then the One Way Data
Table to trigger the simulations required.
3. BASIC STOCHASTIC PRINCIPLES FOR
BIVARIATE RANDOM VARIABLES – AN
INTRODUCTION
3.1 BASIC PRINCIPLES
Basic principles on which this paper banks upon are
presented briefly next.
pdf » Probability Density Function f(x)
[pdf is not a probability, it can have value >1.0]
Any function can be a pdf if the following are satisfied:
f(x) ≥ 0 and
1
8
The spreadsheet analysis generally uses the uniform
random number function [RAND()] in Excel to simulate
various discrete or continuous outcomes, without the use of
add-ins such as @RISK or Crystal Ball, both of which are
programs that are often recommended for performing
stochastic analysis [For instance, the “Procedural Guide to
Economic Road Feasibility Studies, MOWHC, Government
of Uganda, (March 2006)”]. By the use of lookup tables,
the simulation repeats itself.
3
Also, F(x) = P[X ≤ x] =
Here, cdf » Cumulative Distribution Function F(x).
Extracts9
are used here for pertinent explanations.
Further,
P[x ≥ a] = 1 - P[X ≤ a]
This is illustrated below.
3.2 BI-VARIATE DISTRIBUTIONS
Continuing from the above, for a two-dimensional random
variable (X,Y), where both X and Y are continuous random
variables, the Bi-variate Distributions are as follows:
Joint pdf of (X,Y):
 For a continuous r.v. (X, Y), the joint probability density
function f(x,y) is defined as
1) f(x,y) > = 0
2) , 	
 The joint pdf, f(x,y) is not a probability
Joint cdf of (X,Y):
F(x, y) = P [ X<= x, Y < = y ]
= , 	
9
Source: Extracts from NPTEL, Lecture No. # 02,
Bivariate Distributions, Stochastic Hydrology, Prof. P. P.
Mujumdar, Department of Civil Engineering, Indian
Institute of Science, Bangalore.
3.3 MARGINAL DENSITY FUNCTIONS
The marginal density functions of bi-variate continuous
random variables relate essentially to probability of a
particular variable irrespective of the value that the other
random variable takes The marginal density functions, g(x)
and h(y), of X & Y respectively are defined as follows:
	 	 	 	 	 , 	 	
	 	 	 	 	 ,
These are in fact derived from the joint pdf f(x,y), as
follows:
P [c <= X <= d] = P [c <= X <= d, - <= Y <=  ]
= 	 , 	
	 	 	
From the definitions of pdf’s it is thus seen that g(x) is in
fact the original pdf of the r.v. (random variable) X. Thus,
	 	 	 	 	 , 	 	
	 	 	 	 	 , 	 	
Similarly for the r.v. (random variable) Y
3.4 CONDITIONAL DISTRIBUTION
The conditional distribution of X given Y=y is defined as:
g (x / y) = f (x, y) / h (y), h (y) > 0
The conditional distribution of Y given X=x is defined as:
h (y / x) = f (x, y) / g (x), g (x) > 0
While the conditional pdfs satisfy all conditions for a pdf,
the Cumulative Conditional Distributions are:
⁄ 	 ⁄ 	
	 	⁄ 	 	 	⁄ 	
With the aforesaid explanations for the fundamentals of a
bivariate distribution (for continuous random variables),
the following requirement for stochastic independence
can be concluded upon.
4
3.5 INDEPENDENT RANDOM VARIABLES
When the two random variables are independent, we have
g(x/y) = g(x), and h(y/x) = h(y)
i.e the conditional pdf is equal to the marginal pdf
Therefore,
g (x / y) = f (x, y) / h (y)
g (x) = f (x, y) / h (y)
So, f (x, y) = g (x) . h (y)
So it is concluded that for X and Y to be stochastically
independent,
f(x,y) = g(x) h(y)
The following example illustrates this (taken from Ref. 2).
4. TRIANGULAR DISTRIBUTION - BASICS
4.1 PERTINENT PROPERTIES
Continuing with the discussions on triangular distribution,
in Section-1 above, relevant properties are as follows.
Fundamental properties10,11
:
4.2 GENERATING RANDOM VARIATES
Carrying out random simulations being basic requirements,
as mentioned in Section-2 above, the following expressions
10
http://en.wikipedia.org/wiki/Triangular_distribution
11
These properties find specific relevance to parameter
estimation using Method of Moments
5
are used in generating12
the random variates for a
triangular distribution.
................... (2)
4.3 PARAMETER ESTIMATION
While the aforesaid equation allows generating random
variates which follow a triangular distribution, the next step
is estimating parameters defining the distribution which
essentially are the values for a, b and c in eqn. (1).
The methods used for Parameter Estimation are:
(i) Method of Matching Points – Is a simple but
Approximate Method, hence may be used for first
approximations.
(ii) Method of Moments13
(MoM) – In this method
equating the first ‘m’-moments of the population to the
sample estimates of the first ‘m’-moments results in ‘m’
equations to solve for ‘m’-unknown parameters.
(iii) Method of Maximum Likelihood (ML) – Is based on
maximising a likelihood function, and is preferred over
Method of Moments. A brief14
follows:
12
http://www.asianscientist.com/books/wp-content/uploads/
2013/06/5720_chap1.pdf
13
First Moment – Mean, Second Moment – Variance, Third
Moment – Skewness, Fourth Moment – Kurtosis etc. It is to
be appreciated that the properties mentioned in Section
4.1 finds relevance owing to their requirements for
Parameter Estimation using the Method of Moments.
14
For details references can be made to: NPTEL, Lecture
No. # 07, Parameter Estimation, Stochastic Hydrology,
Prof. P. P. Mujumdar, Department of Civil Engineering,
Indian Institute of Science, Bangalore
However triangular distribution poses specific problems in
the use of ML for parameter estimation. While there are
different literature15
,16
,17
available on this and the aspects
that can be adopted for addressing such difficulties, the one
that this paper has used is that given in Reference-1218
.
Extending that mentioned in (17), Reference 12 presents a
simplified version that requires solving numerically a single
equation given next:
............... (3)
While details are presented in Reference-12, the unique
solution to Eqn. (3) is the intersection of the function g(q)
with the positive diagonal of the unit square [Shown
subsequently in Section 8.1 of this paper].
15
Joo, Y. and Casella, G. (2001), Predictive distributions in
risk analysis and estimation for the triangular distribution,
Envoronmetrics, 12: 647-658, doi: 10.1002/env.489: This
mentions that estimation using quantile least squares is
preferable to ML for ‘triangular distribution’.
16
Source: Page 28, Reference12: The package @RISKS
allows definition of a triangular distribution by specifying a
lower quantile ap, a most likely value m and an upper
quantile br, such that a < ap <= m <= br < b. This avoids
having to specify the lower and upper extremes a and b that
by definition have a zero likelihood of occurrence. The
software @RISKS does not provide details, however,
regarding how the bounds a and b are calculated given
values for ap , m and br. [Note: m is same as c, in eqn (1,2)]
17
Source: Page 28, Reference12: Keefer and Bodily (1983)
formulated this problem in terms of two quadratic equations
from which the unknowns a and b had to be solved
numerically for the values p=0.05 and r=0.95.
18
Can be accessed from site:
http://en.wikipedia.org/wiki/Triangular_distribution.
6
5. FRAMING OF THE PROBLEM
Continuing with the bivariate probability discussed above
(in Section-3), in the perspective of the Quantitative Risk
Analysis pertinent to Road Infrastructure Development
Projects described at the onset (in Section 1), let us consider
two variables C and T influence of which get manifested in
the variable E19
.
The following (C and T) are differences w.r.t. base
values for C and T respectively, and the corresponding E
values (EC and ET) resulting from changes to C/T.
C  EC     T  ET 
‐12  2.2  ‐13  ‐1.4 
‐8  1.4  ‐10  ‐0.8 
‐4  0.5  ‐8  ‐0.4 
0  0  0  0 
4  ‐1.1  3  0.6 
8  ‐1.9  4  1 
12  ‐2.2     18  2 
The following are graphical representations of the aforesaid
monotonously decreasing / increasing functions.
In line with the conventional practice, mentioned in
Section-2 earlier, the probability distribution functions (pdf)
for changes in E (E) are determined separately next, as
triggered by changes in C (C) and changes in T (T)
respectively. A triangular distribution gets assumed, as we
derive the pdfs, given next, using eqn. (1).
19
While C and T are typically COST and TRAFFIC, E is
EIRR (or NPV) as described in Section-1 above.
.................... (4)
The following describes the ‘parameter estimation’ in
establishing the pdf for ET
20
and Ec in line with eqn. (3)
described in Section 4.3 earlier.
Table 1-1 Parameter Estimates
Pursuant to the traditional practice, simulations (to arrive
at a large number of estimates for either of the cases, EC
and ET) can be performed using eqn (2). Using such
estimates proportions of EC and ET values that fall below a
threshold21
or other central estimates (say mean) can be
derived (separately for impacts of C and T). However this
paper is aimed at determining the combined influence of
the variables C and T on E.
20
Goal Seek Function in MS-Excel has been used to
facilitate the trial and error involved [in the assumption of
‘q’].
21
For road infrastructure development projects this is 12
per cent, the cut-off EIRR which is generally considered as
the opportunity cost of capital).
7
6. THE PROPOSED APPROACH - BASICS
Continuing from discussions in Section-3.3 earlier,
marginal density functions of bi-variate continuous random
variables relate essentially to probability of a particular
variable irrespective of the value that the other random
variable takes.
Now in regard to estimating Economic Internal Rate of
Return (EIRR) for Road Infrastructure Development
Projects, Project Cost and Traffic Growth are independent
entities. As described at the onset, in Section-1, prescribed
boundary conditions are used in the economic analysis
(traditionally such analysis entails Sensitivity Analysis22
and Quantitative Risk Analysis). Accordingly therefore the
following analysis assumes that impact of C and T on
E being not dependent, the distributions23
for C and T
can be construed as marginal distributions. Using the
values for supports derived through a triangular pdf, the
marginal density functions (are essentially those given
under eqn. 4) g(EC) and g(ET) are24
:
.................... (5)
Now from the conditionality for stochastic independence,
discussed in Section-3.5 earlier, we have
f(E) = g(EC) x g(ET) ............. (6)
Therefore the pdf for E
.................... (7)
22
It is appreciated that unlike traditionally performed
Quantitative Risk Analysis, traditionally Sensitivity
Analysis considers a worst scenario of increased Project
Cost together with reduced Traffic. Hence the relevance of
this paper finds credence.
23
Given in Section-5
24
Nomenclatures used are in accordance with those given
in Section-3 of this paper
So the cumulative distribution function (cdf) is25
:
.................... (8)
This, together with conventional simulations using
triangular distribution, forms the basis for the proposed
approach. The details are presented in the subsequent
section.
7. THE PROPOSED APPROACH –
FORMULATION
The proposed approach is based on mathematical
computation for the RHS of eqn.-8, equated to probability –
computations for the LHS of eqn.-8.
7.1 MATHEMATICAL COMPUTATIONS
The RHS of eqn.-8 is essentially
	
.................... (9)
Considering x to represent Ec, then the limits are either
-2.75 & Ec OR 0 & Ec, depending on value of Ec.
Considering y to represent ET, then the limits are either
-1.79 & ET OR 0 & ET, depending on value of ET.
For example,
Say for certain Ec and ET, the calculations using eqn (9)
yields P [E] = 0.699 ~ 0.7.
7.2 PROBABILITY COMPUTATIONS
As mentioned above, the LHS of eqn.-8 is addresses using
the principles of probability, as detailed next.
25
“Joint cdf” in Section 3.2 may be referred
8
Step 1: Using the estimated parameters a,b,c as given in
Table 1-1 , random simulations were carried out for Ec.
For such simulations Eqn.-2 and the uniform random
number function RAND( ) in MS Excel get used.
Step 2: Similar simulations are then carried out for ET.
Steps 3: Pursuant to stochastic independency, on which the
approach is based, multiplying the above, as shown below,
yield simulations for E.
Table 1-2 Simulated Data for E
Steps 4: A triangular distribution, with mode ( = c )26
= 0 is
applied to the simulated data in Table 1-2.
Table 1- 3 Parameter Estimates for DE
26
Note: c is same as m that Eqn (3) mentions
As may be seen the supports that get derived from
‘parameter estimation’ using27
the Method of Maximum
Likelihood (ML) [Eqn.-3] are:
a = -0.250, c = 0, b = 0.258
Steps 5: With the aforesaid supports, and using Eqn.-1 and
Eq.-1A pdf and cdf respectively was determined for E.
The following graphs show this.
The following table gives the probabilities for E.
Equation-1A provides P values for corresponding X (=E).
Table 1-4 Probabilities for E with Triangular
Distribution
For example,
As may be seen from the shaded row in Table 1-4, the
probability P [E < = 0.06] = 0.702 ~ 0.7.
27
The initial estimates ap and br, [say a =ap = -0.2 and b =
br = 0.21 shown in the Table 1-3] can be derived either
using “Method of Matching Points” or “Method of
Moment”, described in Section 4.3 earlier.
9
7.3 INFERENCE
(a) Inferring from Section 7.1 and Section 7.2, equating
the separate computations for RHS and LHS of Eqn-
(8), does yield useful information on the combined
influence of Ec and ET on E.
(b) Now that there exist definite relations,
C with Ec and T with ET,
as shown in Section 528
earlier, inference (a) above can also
be interpreted as “the combined influence of C and T on
E can be arrived at”.
8. RELEVANT DISCUSSIONS
8.1 UNIQUE SOLUTIONS FOR ML METHOD
This section is aimed at the unique solution of Eqn. (3)
mentioned under Section 4.3 earlier. In this regard it is
recalled, as mentioned under Footnote-16, for solutions to
the estimates of parameters for the ML method “Keefer and
Bodily (1983) formulated this problem in terms of two
quadratic equations from which the unknowns a and b had
to be solved numerically for the values p=0.05 (i.e. r = 1-p
=0.95).” Also recalled, Section 4.3 was concluded stating
that it has been established analytically that “the unique
solution to Eqn. (3) is the intersection of the function g(q)
with the positive diagonal of the unit square.” While the
following graph presents this, the subsequent table shows
the derivations for p = 0.02 (i.e. r = 0.08).
28
The monotonously decreasing / increasing functions
given in the graphs in Section-5
Given that for each value of p there is a unique q, it is
imperative that different sets of parameters29
a and b exist.
The following figure shows the different sets (of a and b )
for the particular sample considered in this paper.
8.2 GOODNESS OF FIT
As may be seen from Step-4, Section 7.2, a triangular
distribution is applied to the simulated E data.
It is appreciated that:
1. The sample size, obtained through simulations,
considered herein is less (just 20). A larger sample is
however to be considered in practice, to yield more
reliable estimates.
2. Also, other distributions might be a better fit. While the
aspect of goodness of fit30,31
is not attended to in this
paper, the following is a frequency analysis to present
some idea on the level of appropriateness in adopting
the triangular distribution for the set of data considered.
29
The parameter c (or m, see note-28) however remains
same. For the case under consideration, a and b being
departures from the most likely estimate (mode) c is ‘0’.
30
For details references can be made to: NPTEL, Lecture
No. # 28, Goodness of Fit, Stochastic Hydrology, Prof. P.
P. Mujumdar, Department of Civil Engineering, Indian
Institute of Science, Bangalore
31
For details the following may also be referred to:
Statistical Methods in Hydrology, Charles T. Haan, The
IOWA State University press, 1977.
10
Table 1-4, presented in Section 7.2, provides
probabilities corresponding to the sample population
shown in the Frequency Table above.
3. Continuing from above, probabilities with a Normal
Distribution corresponding to the same set follows. The
differences are obvious when seen against those for
triangular distribution given in Table 1-4.
4. The following is a graphical representation.
5. Implications of “Goodness of Fit”, using the aforesaid
results, can be perceived from the following :
Triangular distribution:
P [E <= 0.060]= 0.7(i.e. 70%)
Normal distribution:
P [E <= 0.104]= 0.7 (i.e. 70%)
P [E < = 0.060] = 0.324 (i.e. 32%)
9. SUMMARY
While it is a practice for Sensitivity Analysis32
to ascertain
the worst scenario involving the negative effects of all the
deciding parameters, often the same is not practiced for
Quantitative Risk Analysis in Road Infrastructure
Development Projects. This paper attempts to present a
means for ascertaining probabilities of such combined
impacts. Further, this allows for opportunities to reallocate
resources at a future date (subsequent to an Economic
Analysis) in the event changes are frequented for a
particular parameter (say33
, a decrease in Traffic Growth
rate, which thus necessitates reduction to the Project Cost
so as to have the EIRR within an acceptable limit).
However the paper restricts itself to bi-variate continuous
random variables. Given that Traffic and Project-Cost are
the primary elements which get considered in an economic
analysis, a bi-variate distribution however finds relevance.
Applicable fundamentals of probability / stochastic analysis
are revisited for working engineers to have a ready
appreciation. It is appreciated that the same approach may
even be extended to other domains of engineering by
highway engineers.
REFERNCES:
1. Guidelines for the Economic Analysis of Projects,
Economic and Development Resource Center, the
Asian Development Bank, February 1997
2. NPTEL, Lectures on Stochastic Hydrology, Prof. P. P.
Mujumdar, Department of Civil Engineering, Indian
Institute of Science, Bangalore
3. Procedural Guide to Economic Road Feasibility
Studies, MOWHC, Government of Uganda, (March
2006)
4. http://en.wikipedia.org/wiki/Triangular_distribution
5. http://www.asianscientist.com/books/wp-
content/uploads/ 2013/06/5720_chap1.pdf
32
Footnote 22 may be referred to
33
Section 7.3 elaborates this with an example

More Related Content

What's hot

Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. projectAnupamDubey34
 
A lognormal reliability design model
A lognormal reliability design modelA lognormal reliability design model
A lognormal reliability design modeleSAT Journals
 
PEMF2_SDM_2012_Ali
PEMF2_SDM_2012_AliPEMF2_SDM_2012_Ali
PEMF2_SDM_2012_AliMDO_Lab
 
The Sample Average Approximation Method for Stochastic Programs with Integer ...
The Sample Average Approximation Method for Stochastic Programs with Integer ...The Sample Average Approximation Method for Stochastic Programs with Integer ...
The Sample Average Approximation Method for Stochastic Programs with Integer ...SSA KPI
 
International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)inventionjournals
 
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cut
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cutEnhance interval width of crime forecasting with ARIMA model-fuzzy alpha cut
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cutTELKOMNIKA JOURNAL
 
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...ijmpict
 
Experimental design
Experimental designExperimental design
Experimental designSandip Patel
 
Statistical database, problems and mitigation
Statistical database, problems and mitigationStatistical database, problems and mitigation
Statistical database, problems and mitigationBikrant Gautam
 
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective Optimization
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective OptimizationHybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective Optimization
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective OptimizationeArtius, Inc.
 
Application of linear programming technique for staff training of register se...
Application of linear programming technique for staff training of register se...Application of linear programming technique for staff training of register se...
Application of linear programming technique for staff training of register se...Enamul Islam
 
Real time clustering of time series
Real time clustering of time seriesReal time clustering of time series
Real time clustering of time seriescsandit
 
AIAA-SciTech-ModelSelection-2014-Mehmani
AIAA-SciTech-ModelSelection-2014-MehmaniAIAA-SciTech-ModelSelection-2014-Mehmani
AIAA-SciTech-ModelSelection-2014-MehmaniOptiModel
 
evaluation in infomation retrival
evaluation in infomation retrivalevaluation in infomation retrival
evaluation in infomation retrivaljetaime
 
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...ijscmcj
 

What's hot (20)

Ignou 10 no. project
Ignou 10 no. projectIgnou 10 no. project
Ignou 10 no. project
 
A lognormal reliability design model
A lognormal reliability design modelA lognormal reliability design model
A lognormal reliability design model
 
PEMF2_SDM_2012_Ali
PEMF2_SDM_2012_AliPEMF2_SDM_2012_Ali
PEMF2_SDM_2012_Ali
 
G0211056062
G0211056062G0211056062
G0211056062
 
The Sample Average Approximation Method for Stochastic Programs with Integer ...
The Sample Average Approximation Method for Stochastic Programs with Integer ...The Sample Average Approximation Method for Stochastic Programs with Integer ...
The Sample Average Approximation Method for Stochastic Programs with Integer ...
 
International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)International Journal of Business and Management Invention (IJBMI)
International Journal of Business and Management Invention (IJBMI)
 
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cut
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cutEnhance interval width of crime forecasting with ARIMA model-fuzzy alpha cut
Enhance interval width of crime forecasting with ARIMA model-fuzzy alpha cut
 
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...
A NEW APPROACH IN DYNAMIC TRAVELING SALESMAN PROBLEM: A HYBRID OF ANT COLONY ...
 
Experimental design
Experimental designExperimental design
Experimental design
 
Statistical database, problems and mitigation
Statistical database, problems and mitigationStatistical database, problems and mitigation
Statistical database, problems and mitigation
 
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective Optimization
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective OptimizationHybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective Optimization
Hybrid Multi-Gradient Explorer Algorithm for Global Multi-Objective Optimization
 
Operations research
Operations researchOperations research
Operations research
 
Ch1 slides
Ch1 slidesCh1 slides
Ch1 slides
 
Application of linear programming technique for staff training of register se...
Application of linear programming technique for staff training of register se...Application of linear programming technique for staff training of register se...
Application of linear programming technique for staff training of register se...
 
Real time clustering of time series
Real time clustering of time seriesReal time clustering of time series
Real time clustering of time series
 
Ch13 slides
Ch13 slidesCh13 slides
Ch13 slides
 
AIAA-SciTech-ModelSelection-2014-Mehmani
AIAA-SciTech-ModelSelection-2014-MehmaniAIAA-SciTech-ModelSelection-2014-Mehmani
AIAA-SciTech-ModelSelection-2014-Mehmani
 
Ch11 slides
Ch11 slidesCh11 slides
Ch11 slides
 
evaluation in infomation retrival
evaluation in infomation retrivalevaluation in infomation retrival
evaluation in infomation retrival
 
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...
Volatility Forecasting - A Performance Measure of Garch Techniques With Diffe...
 

Viewers also liked

Schedule risk identification
Schedule risk identificationSchedule risk identification
Schedule risk identificationvishal kachwah
 
OIRA Road Transport
OIRA Road TransportOIRA Road Transport
OIRA Road TransportINRSfrance
 
Risk management standard
Risk management standardRisk management standard
Risk management standardLuis Vitiritti
 
Is The Sky Falling? Segmented Risk Identification Questions
Is The Sky Falling? Segmented Risk Identification QuestionsIs The Sky Falling? Segmented Risk Identification Questions
Is The Sky Falling? Segmented Risk Identification QuestionsChristopher Gentry, PMP, ITILv3
 
Risk identification
Risk identificationRisk identification
Risk identificationmurukkada
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniquesMarco De Santis, PMP, CFPP
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification TechniquesRicardo Viana Vargas
 
Risk-management
 Risk-management Risk-management
Risk-managementUmesh Gupta
 

Viewers also liked (9)

Effective work related road risk management
Effective work related road risk managementEffective work related road risk management
Effective work related road risk management
 
Schedule risk identification
Schedule risk identificationSchedule risk identification
Schedule risk identification
 
OIRA Road Transport
OIRA Road TransportOIRA Road Transport
OIRA Road Transport
 
Risk management standard
Risk management standardRisk management standard
Risk management standard
 
Is The Sky Falling? Segmented Risk Identification Questions
Is The Sky Falling? Segmented Risk Identification QuestionsIs The Sky Falling? Segmented Risk Identification Questions
Is The Sky Falling? Segmented Risk Identification Questions
 
Risk identification
Risk identificationRisk identification
Risk identification
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniques
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification Techniques
 
Risk-management
 Risk-management Risk-management
Risk-management
 

Similar to Quantitative Risk Assessment - Road Development Perspective

An approximate possibilistic
An approximate possibilisticAn approximate possibilistic
An approximate possibilisticcsandit
 
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...Waqas Tariq
 
Techniques in marketing research
Techniques in marketing researchTechniques in marketing research
Techniques in marketing researchSunny Bose
 
5.0 -Chapter Introduction
5.0 -Chapter Introduction5.0 -Chapter Introduction
5.0 -Chapter IntroductionSabrina Baloi
 
V. pacáková, d. brebera
V. pacáková, d. breberaV. pacáková, d. brebera
V. pacáková, d. breberalogyalaa
 
Tteng 441 traffic engineering fall 2021 part2
Tteng 441 traffic engineering fall 2021 part2 Tteng 441 traffic engineering fall 2021 part2
Tteng 441 traffic engineering fall 2021 part2 Wael ElDessouki
 
Estimating project development effort using clustered regression approach
Estimating project development effort using clustered regression approachEstimating project development effort using clustered regression approach
Estimating project development effort using clustered regression approachcsandit
 
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACH
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACHESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACH
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACHcscpconf
 
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Ahmed Ebid
 
Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...IRJET Journal
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsAnjumNaveed12
 
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...MFOZOUNI
 
Correation, Linear Regression and Multilinear Regression using R software
Correation, Linear Regression and Multilinear Regression using R softwareCorreation, Linear Regression and Multilinear Regression using R software
Correation, Linear Regression and Multilinear Regression using R softwareshrikrishna kesharwani
 
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...IJERA Editor
 
Information-Flow Analysis of Design Breaks up
Information-Flow Analysis of Design Breaks upInformation-Flow Analysis of Design Breaks up
Information-Flow Analysis of Design Breaks upEswar Publications
 
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENT
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENTPROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENT
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENTIRJET Journal
 

Similar to Quantitative Risk Assessment - Road Development Perspective (20)

An approximate possibilistic
An approximate possibilisticAn approximate possibilistic
An approximate possibilistic
 
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...
Particle Swarm Optimization in the fine-tuning of Fuzzy Software Cost Estimat...
 
Techniques in marketing research
Techniques in marketing researchTechniques in marketing research
Techniques in marketing research
 
5.0 -Chapter Introduction
5.0 -Chapter Introduction5.0 -Chapter Introduction
5.0 -Chapter Introduction
 
Druker
DrukerDruker
Druker
 
V. pacáková, d. brebera
V. pacáková, d. breberaV. pacáková, d. brebera
V. pacáková, d. brebera
 
Tteng 441 traffic engineering fall 2021 part2
Tteng 441 traffic engineering fall 2021 part2 Tteng 441 traffic engineering fall 2021 part2
Tteng 441 traffic engineering fall 2021 part2
 
Estimating project development effort using clustered regression approach
Estimating project development effort using clustered regression approachEstimating project development effort using clustered regression approach
Estimating project development effort using clustered regression approach
 
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACH
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACHESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACH
ESTIMATING PROJECT DEVELOPMENT EFFORT USING CLUSTERED REGRESSION APPROACH
 
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil Optimum penetration depth of cantilever sheet pile walls in dry granular soil
Optimum penetration depth of cantilever sheet pile walls in dry granular soil
 
Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skills
 
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...
8064-an-excel-spreadsheet-and-vba-macro-for-model-selection-and-predictor-imp...
 
PeterLoh_Dissertation
PeterLoh_DissertationPeterLoh_Dissertation
PeterLoh_Dissertation
 
Correation, Linear Regression and Multilinear Regression using R software
Correation, Linear Regression and Multilinear Regression using R softwareCorreation, Linear Regression and Multilinear Regression using R software
Correation, Linear Regression and Multilinear Regression using R software
 
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...
Comparison of Cost Estimation Methods using Hybrid Artificial Intelligence on...
 
Information-Flow Analysis of Design Breaks up
Information-Flow Analysis of Design Breaks upInformation-Flow Analysis of Design Breaks up
Information-Flow Analysis of Design Breaks up
 
01677377
0167737701677377
01677377
 
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENT
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENTPROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENT
PROBABILISTIC SEISMIC HAZARD ANALYSIS FOR SEISMIC RISK ASSESSMENT
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 

Quantitative Risk Assessment - Road Development Perspective

  • 1. 1 QUANTITATIVE RISK ASSESSMENT – ROAD TRANSPORT INFRASTRUCTURE DEVELOPMENT PROJECT PREPARATION PERSPECTIVE Subir Kumar Podder1 ABSTRACT The paper is aimed at outlining an approach for Quantitative Risk Assessment employing stochastic analysis (with a triangular distribution) so as to determine the combined influence of the dictating parameters on probabilities. It is appreciated that in the perspective of Road Transport Development Projects, and more specifically the Economic Analysis carried out in Feasibility Studies for Road Improvement and Rehabilitation Projects, such dictating parameters are Traffic and Project Cost. Accordingly the paper aims at an approach for determining the impact (on Traditional Economic Analysis Instruments like EIRR, NPV) under a combined influence of the aforesaid two parameters. Such analysis requires treading a step beyond that what is required when probabilities are ascertained separately, and is the focus of this paper. 1. INTRODUCTION Quantitative Risk Analysis – It provides a means of estimating the probability that the project NPV will fall below zero, or that the project EIRR will fall below the opportunity cost of capital. More explicitly, the quantitative risk analysis involves randomly selecting values for the variables from the probability distribution determined; combining these values with all base case values to give an EIRR (or NPV) result; and repeating such a calculation a large number of times to provide a large number of EIRR (or NPV) estimates. These estimates are then summarized in a distribution, key features of which is the proportion of EIRR values that fall below (i) the opportunity cost of capital (say 12 per cent), (ii) the most likely forecast values (i.e. the value which the analysis actually yielded). The objective is to estimate the probability that the project might turn out to be unacceptable. Traditionally, the principle of risk analysis is based on random simulations carried out assuming a triangular probability distribution with predetermined minimum, most likely and maximum limits. The most likely values are those assumed for the base case situation, whilst the lower and upper limits that are to be applied for risk analysis in road feasibility studies are expressed in terms of percentage (%) of the base-case2 values.3 1 Consultant (Highways), LEA Associates South Asia Pvt. Ltd, New Delhi, INDIA 2 The base-case refers to Estimated Project Cost and Estimated Traffic. Risks triggered by changes from these Triangular Probability Distribution - The triangular distribution is typically used as a subjective description of a population for which there is only limited sample data, and especially in cases where the relationship between variables is known but data is scarce. It is based on knowledge of the maximum and minimum and an “Inspired guess” as to the modal value. [For this reason the triangular distribution has been called a “lack of knowledge” distribution]. The triangular distribution is often used in business decision making4 , particularly in simulations. Generally, when not much data is known about the distribution of an outcome, (say, only its smallest and largest values are known), it is possible to use the uniform distribution. But if the most likely outcome is also known, then the outcome can be simulated by a triangular distribution.5 In probability theory and statistics, the triangular distribution is a continuous probability distribution with lower limit a, upper limit b and mode c, where a < b and a <= c <= b. The probability density function (pdf) is given by: ..................(1) The cumulative distribution function (cdf) is given by: ............(1A) There are generally no fixed criteria for using such a result in ascertaining the acceptability of the Project Viability. estimates, measured in terms of impacts on the economic parameters, are essentially what the the quantitative risk assessment is aimed at. 3 The adopted values (i.e. % of base-case values) are generally those that the Terms of Reference for a particular project specify. However, generally they are the same that are accounted for Sensitivity Analysis performed under an Economic Analysis. 4 The triangular distribution, along with the Beta distribution, is also widely used in project management (as an input into PERT and hence critical path method (CPM)) to model events which take place within an interval defined by a minimum and maximum value. 5 Source: Wikipedia, the free encyclopedia
  • 2. 2 However, high risk probabilities may be associated with projects that have a high expected NPV (or EIRR).6 Pertinence to Road Development Projects - Risk analysis, carried out under Feasibility Studies, for road transport development projects is concerned with the probability or likelihood of the following:  Construction costs increasing/ decreasing by a certain percentage than that for the base-case; &  Traffic growth occurring at a lower/higher rate than that assumed in the base case situation. Such probabilities get determined employing the principles of random simulations assuming a triangular probability distribution. Continuing from above, intrinsic to the triangular probability distribution are the boundary conditions (upper and lower limits7 , as well as the mode value i.e. the most likely value). Very often the prescribed values for the upper and lower limits are as follows: UPPER LIMIT: 1) Construction Cost – 90 % of the Base Case (i.e. the Favoured Alternative) 2) Traffic Growth – 110% of the Base Case (i.e. the Favoured Alternative) LOWER LIMIT: 1) Construction Cost – 120 % of the Base Case (i.e. the Favoured Alternative) 2) Traffic Growth – 75% of the Base Case (i.e. the Favoured Alternative) 6 Source: Page 157, Appendix 21, Guidelines for the Economic Analysis of Projects, Economic and Development Resource Center, the Asian Development Bank, February 1997. 7 It is imperative that the (i) Upper Limits correspond to the scenario where the %-change to the variables lend a higher EIRR (or NPV); and (ii) Lower Limits correspond to the scenario where the %-change to the variables lend a lower EIRR (or NPV), when compared to the EIRR (or NPV) of the Favoured Alternative (the most likely value i.e. that the analysis yields with the Base Case values). 2. THE CONVENTIONAL PRACTICE With the boundary conditions in place, as stated immediately above, the stochastic analysis, as often practiced, essentially involves the following steps:  Establishing the probability distribution function (pdf), assuming a triangular probability distribution, for changes in EIRR triggered by COST  Making Random Simulations to arrive at a large number of estimates (of EIRR)  Establishing the cumulative distribution function (cdf) [it essentially summarises the estimates]  Interpreting the results which essentially is determining the proportion of EIRR values that fall below (i) the opportunity cost of capital (say 12 per cent), (ii) the most likely forecast values (i.e. the value which the analysis actually yielded), (iii) the central estimates (say the mean value). The analysis is then repeated for changes in EIRR as triggered by changes to TRAFFIC. The aforesaid steps can be performed using a MS EXCEL spreadsheet analysis8 that employs in-built functions to generate random functions and then the One Way Data Table to trigger the simulations required. 3. BASIC STOCHASTIC PRINCIPLES FOR BIVARIATE RANDOM VARIABLES – AN INTRODUCTION 3.1 BASIC PRINCIPLES Basic principles on which this paper banks upon are presented briefly next. pdf » Probability Density Function f(x) [pdf is not a probability, it can have value >1.0] Any function can be a pdf if the following are satisfied: f(x) ≥ 0 and 1 8 The spreadsheet analysis generally uses the uniform random number function [RAND()] in Excel to simulate various discrete or continuous outcomes, without the use of add-ins such as @RISK or Crystal Ball, both of which are programs that are often recommended for performing stochastic analysis [For instance, the “Procedural Guide to Economic Road Feasibility Studies, MOWHC, Government of Uganda, (March 2006)”]. By the use of lookup tables, the simulation repeats itself.
  • 3. 3 Also, F(x) = P[X ≤ x] = Here, cdf » Cumulative Distribution Function F(x). Extracts9 are used here for pertinent explanations. Further, P[x ≥ a] = 1 - P[X ≤ a] This is illustrated below. 3.2 BI-VARIATE DISTRIBUTIONS Continuing from the above, for a two-dimensional random variable (X,Y), where both X and Y are continuous random variables, the Bi-variate Distributions are as follows: Joint pdf of (X,Y):  For a continuous r.v. (X, Y), the joint probability density function f(x,y) is defined as 1) f(x,y) > = 0 2) ,  The joint pdf, f(x,y) is not a probability Joint cdf of (X,Y): F(x, y) = P [ X<= x, Y < = y ] = , 9 Source: Extracts from NPTEL, Lecture No. # 02, Bivariate Distributions, Stochastic Hydrology, Prof. P. P. Mujumdar, Department of Civil Engineering, Indian Institute of Science, Bangalore. 3.3 MARGINAL DENSITY FUNCTIONS The marginal density functions of bi-variate continuous random variables relate essentially to probability of a particular variable irrespective of the value that the other random variable takes The marginal density functions, g(x) and h(y), of X & Y respectively are defined as follows: , , These are in fact derived from the joint pdf f(x,y), as follows: P [c <= X <= d] = P [c <= X <= d, - <= Y <=  ] = , From the definitions of pdf’s it is thus seen that g(x) is in fact the original pdf of the r.v. (random variable) X. Thus, , , Similarly for the r.v. (random variable) Y 3.4 CONDITIONAL DISTRIBUTION The conditional distribution of X given Y=y is defined as: g (x / y) = f (x, y) / h (y), h (y) > 0 The conditional distribution of Y given X=x is defined as: h (y / x) = f (x, y) / g (x), g (x) > 0 While the conditional pdfs satisfy all conditions for a pdf, the Cumulative Conditional Distributions are: ⁄ ⁄ ⁄ ⁄ With the aforesaid explanations for the fundamentals of a bivariate distribution (for continuous random variables), the following requirement for stochastic independence can be concluded upon.
  • 4. 4 3.5 INDEPENDENT RANDOM VARIABLES When the two random variables are independent, we have g(x/y) = g(x), and h(y/x) = h(y) i.e the conditional pdf is equal to the marginal pdf Therefore, g (x / y) = f (x, y) / h (y) g (x) = f (x, y) / h (y) So, f (x, y) = g (x) . h (y) So it is concluded that for X and Y to be stochastically independent, f(x,y) = g(x) h(y) The following example illustrates this (taken from Ref. 2). 4. TRIANGULAR DISTRIBUTION - BASICS 4.1 PERTINENT PROPERTIES Continuing with the discussions on triangular distribution, in Section-1 above, relevant properties are as follows. Fundamental properties10,11 : 4.2 GENERATING RANDOM VARIATES Carrying out random simulations being basic requirements, as mentioned in Section-2 above, the following expressions 10 http://en.wikipedia.org/wiki/Triangular_distribution 11 These properties find specific relevance to parameter estimation using Method of Moments
  • 5. 5 are used in generating12 the random variates for a triangular distribution. ................... (2) 4.3 PARAMETER ESTIMATION While the aforesaid equation allows generating random variates which follow a triangular distribution, the next step is estimating parameters defining the distribution which essentially are the values for a, b and c in eqn. (1). The methods used for Parameter Estimation are: (i) Method of Matching Points – Is a simple but Approximate Method, hence may be used for first approximations. (ii) Method of Moments13 (MoM) – In this method equating the first ‘m’-moments of the population to the sample estimates of the first ‘m’-moments results in ‘m’ equations to solve for ‘m’-unknown parameters. (iii) Method of Maximum Likelihood (ML) – Is based on maximising a likelihood function, and is preferred over Method of Moments. A brief14 follows: 12 http://www.asianscientist.com/books/wp-content/uploads/ 2013/06/5720_chap1.pdf 13 First Moment – Mean, Second Moment – Variance, Third Moment – Skewness, Fourth Moment – Kurtosis etc. It is to be appreciated that the properties mentioned in Section 4.1 finds relevance owing to their requirements for Parameter Estimation using the Method of Moments. 14 For details references can be made to: NPTEL, Lecture No. # 07, Parameter Estimation, Stochastic Hydrology, Prof. P. P. Mujumdar, Department of Civil Engineering, Indian Institute of Science, Bangalore However triangular distribution poses specific problems in the use of ML for parameter estimation. While there are different literature15 ,16 ,17 available on this and the aspects that can be adopted for addressing such difficulties, the one that this paper has used is that given in Reference-1218 . Extending that mentioned in (17), Reference 12 presents a simplified version that requires solving numerically a single equation given next: ............... (3) While details are presented in Reference-12, the unique solution to Eqn. (3) is the intersection of the function g(q) with the positive diagonal of the unit square [Shown subsequently in Section 8.1 of this paper]. 15 Joo, Y. and Casella, G. (2001), Predictive distributions in risk analysis and estimation for the triangular distribution, Envoronmetrics, 12: 647-658, doi: 10.1002/env.489: This mentions that estimation using quantile least squares is preferable to ML for ‘triangular distribution’. 16 Source: Page 28, Reference12: The package @RISKS allows definition of a triangular distribution by specifying a lower quantile ap, a most likely value m and an upper quantile br, such that a < ap <= m <= br < b. This avoids having to specify the lower and upper extremes a and b that by definition have a zero likelihood of occurrence. The software @RISKS does not provide details, however, regarding how the bounds a and b are calculated given values for ap , m and br. [Note: m is same as c, in eqn (1,2)] 17 Source: Page 28, Reference12: Keefer and Bodily (1983) formulated this problem in terms of two quadratic equations from which the unknowns a and b had to be solved numerically for the values p=0.05 and r=0.95. 18 Can be accessed from site: http://en.wikipedia.org/wiki/Triangular_distribution.
  • 6. 6 5. FRAMING OF THE PROBLEM Continuing with the bivariate probability discussed above (in Section-3), in the perspective of the Quantitative Risk Analysis pertinent to Road Infrastructure Development Projects described at the onset (in Section 1), let us consider two variables C and T influence of which get manifested in the variable E19 . The following (C and T) are differences w.r.t. base values for C and T respectively, and the corresponding E values (EC and ET) resulting from changes to C/T. C  EC     T  ET  ‐12  2.2  ‐13  ‐1.4  ‐8  1.4  ‐10  ‐0.8  ‐4  0.5  ‐8  ‐0.4  0  0  0  0  4  ‐1.1  3  0.6  8  ‐1.9  4  1  12  ‐2.2     18  2  The following are graphical representations of the aforesaid monotonously decreasing / increasing functions. In line with the conventional practice, mentioned in Section-2 earlier, the probability distribution functions (pdf) for changes in E (E) are determined separately next, as triggered by changes in C (C) and changes in T (T) respectively. A triangular distribution gets assumed, as we derive the pdfs, given next, using eqn. (1). 19 While C and T are typically COST and TRAFFIC, E is EIRR (or NPV) as described in Section-1 above. .................... (4) The following describes the ‘parameter estimation’ in establishing the pdf for ET 20 and Ec in line with eqn. (3) described in Section 4.3 earlier. Table 1-1 Parameter Estimates Pursuant to the traditional practice, simulations (to arrive at a large number of estimates for either of the cases, EC and ET) can be performed using eqn (2). Using such estimates proportions of EC and ET values that fall below a threshold21 or other central estimates (say mean) can be derived (separately for impacts of C and T). However this paper is aimed at determining the combined influence of the variables C and T on E. 20 Goal Seek Function in MS-Excel has been used to facilitate the trial and error involved [in the assumption of ‘q’]. 21 For road infrastructure development projects this is 12 per cent, the cut-off EIRR which is generally considered as the opportunity cost of capital).
  • 7. 7 6. THE PROPOSED APPROACH - BASICS Continuing from discussions in Section-3.3 earlier, marginal density functions of bi-variate continuous random variables relate essentially to probability of a particular variable irrespective of the value that the other random variable takes. Now in regard to estimating Economic Internal Rate of Return (EIRR) for Road Infrastructure Development Projects, Project Cost and Traffic Growth are independent entities. As described at the onset, in Section-1, prescribed boundary conditions are used in the economic analysis (traditionally such analysis entails Sensitivity Analysis22 and Quantitative Risk Analysis). Accordingly therefore the following analysis assumes that impact of C and T on E being not dependent, the distributions23 for C and T can be construed as marginal distributions. Using the values for supports derived through a triangular pdf, the marginal density functions (are essentially those given under eqn. 4) g(EC) and g(ET) are24 : .................... (5) Now from the conditionality for stochastic independence, discussed in Section-3.5 earlier, we have f(E) = g(EC) x g(ET) ............. (6) Therefore the pdf for E .................... (7) 22 It is appreciated that unlike traditionally performed Quantitative Risk Analysis, traditionally Sensitivity Analysis considers a worst scenario of increased Project Cost together with reduced Traffic. Hence the relevance of this paper finds credence. 23 Given in Section-5 24 Nomenclatures used are in accordance with those given in Section-3 of this paper So the cumulative distribution function (cdf) is25 : .................... (8) This, together with conventional simulations using triangular distribution, forms the basis for the proposed approach. The details are presented in the subsequent section. 7. THE PROPOSED APPROACH – FORMULATION The proposed approach is based on mathematical computation for the RHS of eqn.-8, equated to probability – computations for the LHS of eqn.-8. 7.1 MATHEMATICAL COMPUTATIONS The RHS of eqn.-8 is essentially .................... (9) Considering x to represent Ec, then the limits are either -2.75 & Ec OR 0 & Ec, depending on value of Ec. Considering y to represent ET, then the limits are either -1.79 & ET OR 0 & ET, depending on value of ET. For example, Say for certain Ec and ET, the calculations using eqn (9) yields P [E] = 0.699 ~ 0.7. 7.2 PROBABILITY COMPUTATIONS As mentioned above, the LHS of eqn.-8 is addresses using the principles of probability, as detailed next. 25 “Joint cdf” in Section 3.2 may be referred
  • 8. 8 Step 1: Using the estimated parameters a,b,c as given in Table 1-1 , random simulations were carried out for Ec. For such simulations Eqn.-2 and the uniform random number function RAND( ) in MS Excel get used. Step 2: Similar simulations are then carried out for ET. Steps 3: Pursuant to stochastic independency, on which the approach is based, multiplying the above, as shown below, yield simulations for E. Table 1-2 Simulated Data for E Steps 4: A triangular distribution, with mode ( = c )26 = 0 is applied to the simulated data in Table 1-2. Table 1- 3 Parameter Estimates for DE 26 Note: c is same as m that Eqn (3) mentions As may be seen the supports that get derived from ‘parameter estimation’ using27 the Method of Maximum Likelihood (ML) [Eqn.-3] are: a = -0.250, c = 0, b = 0.258 Steps 5: With the aforesaid supports, and using Eqn.-1 and Eq.-1A pdf and cdf respectively was determined for E. The following graphs show this. The following table gives the probabilities for E. Equation-1A provides P values for corresponding X (=E). Table 1-4 Probabilities for E with Triangular Distribution For example, As may be seen from the shaded row in Table 1-4, the probability P [E < = 0.06] = 0.702 ~ 0.7. 27 The initial estimates ap and br, [say a =ap = -0.2 and b = br = 0.21 shown in the Table 1-3] can be derived either using “Method of Matching Points” or “Method of Moment”, described in Section 4.3 earlier.
  • 9. 9 7.3 INFERENCE (a) Inferring from Section 7.1 and Section 7.2, equating the separate computations for RHS and LHS of Eqn- (8), does yield useful information on the combined influence of Ec and ET on E. (b) Now that there exist definite relations, C with Ec and T with ET, as shown in Section 528 earlier, inference (a) above can also be interpreted as “the combined influence of C and T on E can be arrived at”. 8. RELEVANT DISCUSSIONS 8.1 UNIQUE SOLUTIONS FOR ML METHOD This section is aimed at the unique solution of Eqn. (3) mentioned under Section 4.3 earlier. In this regard it is recalled, as mentioned under Footnote-16, for solutions to the estimates of parameters for the ML method “Keefer and Bodily (1983) formulated this problem in terms of two quadratic equations from which the unknowns a and b had to be solved numerically for the values p=0.05 (i.e. r = 1-p =0.95).” Also recalled, Section 4.3 was concluded stating that it has been established analytically that “the unique solution to Eqn. (3) is the intersection of the function g(q) with the positive diagonal of the unit square.” While the following graph presents this, the subsequent table shows the derivations for p = 0.02 (i.e. r = 0.08). 28 The monotonously decreasing / increasing functions given in the graphs in Section-5 Given that for each value of p there is a unique q, it is imperative that different sets of parameters29 a and b exist. The following figure shows the different sets (of a and b ) for the particular sample considered in this paper. 8.2 GOODNESS OF FIT As may be seen from Step-4, Section 7.2, a triangular distribution is applied to the simulated E data. It is appreciated that: 1. The sample size, obtained through simulations, considered herein is less (just 20). A larger sample is however to be considered in practice, to yield more reliable estimates. 2. Also, other distributions might be a better fit. While the aspect of goodness of fit30,31 is not attended to in this paper, the following is a frequency analysis to present some idea on the level of appropriateness in adopting the triangular distribution for the set of data considered. 29 The parameter c (or m, see note-28) however remains same. For the case under consideration, a and b being departures from the most likely estimate (mode) c is ‘0’. 30 For details references can be made to: NPTEL, Lecture No. # 28, Goodness of Fit, Stochastic Hydrology, Prof. P. P. Mujumdar, Department of Civil Engineering, Indian Institute of Science, Bangalore 31 For details the following may also be referred to: Statistical Methods in Hydrology, Charles T. Haan, The IOWA State University press, 1977.
  • 10. 10 Table 1-4, presented in Section 7.2, provides probabilities corresponding to the sample population shown in the Frequency Table above. 3. Continuing from above, probabilities with a Normal Distribution corresponding to the same set follows. The differences are obvious when seen against those for triangular distribution given in Table 1-4. 4. The following is a graphical representation. 5. Implications of “Goodness of Fit”, using the aforesaid results, can be perceived from the following : Triangular distribution: P [E <= 0.060]= 0.7(i.e. 70%) Normal distribution: P [E <= 0.104]= 0.7 (i.e. 70%) P [E < = 0.060] = 0.324 (i.e. 32%) 9. SUMMARY While it is a practice for Sensitivity Analysis32 to ascertain the worst scenario involving the negative effects of all the deciding parameters, often the same is not practiced for Quantitative Risk Analysis in Road Infrastructure Development Projects. This paper attempts to present a means for ascertaining probabilities of such combined impacts. Further, this allows for opportunities to reallocate resources at a future date (subsequent to an Economic Analysis) in the event changes are frequented for a particular parameter (say33 , a decrease in Traffic Growth rate, which thus necessitates reduction to the Project Cost so as to have the EIRR within an acceptable limit). However the paper restricts itself to bi-variate continuous random variables. Given that Traffic and Project-Cost are the primary elements which get considered in an economic analysis, a bi-variate distribution however finds relevance. Applicable fundamentals of probability / stochastic analysis are revisited for working engineers to have a ready appreciation. It is appreciated that the same approach may even be extended to other domains of engineering by highway engineers. REFERNCES: 1. Guidelines for the Economic Analysis of Projects, Economic and Development Resource Center, the Asian Development Bank, February 1997 2. NPTEL, Lectures on Stochastic Hydrology, Prof. P. P. Mujumdar, Department of Civil Engineering, Indian Institute of Science, Bangalore 3. Procedural Guide to Economic Road Feasibility Studies, MOWHC, Government of Uganda, (March 2006) 4. http://en.wikipedia.org/wiki/Triangular_distribution 5. http://www.asianscientist.com/books/wp- content/uploads/ 2013/06/5720_chap1.pdf 32 Footnote 22 may be referred to 33 Section 7.3 elaborates this with an example