SlideShare a Scribd company logo
1 of 13
Schedule Risk Analysis Model
(SRAM)-For Infrastructure Project
Presented by Under guidance
Vishal.R.Kachwah of
MIS :121420005 Prof. Dr. N.A.Hedaoo
1College of Engineering, Pune
AIM AND OBJECTIVES OF THE PROJECT
 The main aim of this study the application of SRAM and verify this
operates well and produces realistic results in capturing relation between
activity durations and risk factors in schedule for construction project.
 Study and understand uncertainty and risk in project scheduling .
 Calculate impact of risk in quantitative form using probablitical method with the help of
analysis software.
 Evaluate construction activity networks under risk factors by using real case study .
 This study provided schedule risk analysis guidelines for future project .
2College of Engineering, Pune
3
Risk identification
•Determines which risks may affect the project.
•Documents their characteristic.
Data collection
•Develop questionnaire to identify critical risk factors.
•Identifie Survey participants, distribuait questionnaires and conduct
in-person interviews.
Data analysis
•The risk analysis process uses Monte Carlo techniques to determine
probabilities and contingency.
Case Study
•Quantify impact of risk on a project schedule with the use of MS
Project
METHODOLOGY
College of Engineering, Pune
Position of SRAM in risk management process
METHODOLOGY
Risk identification and classification.
Qualitative and Quantitative Risk analysis
Conduct case study of a infrastructure
project and Quantify impact of risk on
a project schedule.
4College of Engineering, Pune
Risk assessment survey
Questionnaire
5College of Engineering, Pune
 Delphi technique is way to reach qualitative result
 Historical data are unavailable
 Activity is rather unclear
 The questionnaire was developed by examining past studies to extract risk
factors that are more appropriate infrastructure project.
 The questionnaire was divided into two parts.
 The first part included questions regarding the respondent’s
 The second part consisted of a total risk factors
6College of Engineering, Pune
 Consultants (PMC)
 Project managers
 Construction managers
 Planners
The budget values of projects that run by the interviewed persons range from 50 cr to
200 cr and the Experience range from 5 to 15 years
 The type of contact persons are for survey
 Pilot study
Survey methodology
 We have to achieve response rate > 40 %
7College of Engineering, Pune
Risk Identification
Resources
Labour
Equipment
Material
Site
conditions
Environmental
Sub-surface
Site location
Project
parties
Owner
Design and
Architecture
Contractor
Project management
Consultant
Project
features
Financial
Political
The second part consisted of a total of 4
main factor 12 sub factor.
Total 60 risk factor cover in this survey
which collected form four deferent
research work.
8College of Engineering, Pune
Risk factor = Severity factor * Frequency of occurrence factor ( 3 )
Description Descriptor RANK Probability
Even Chance project Almost
certain
Very high >50%
One in Every 4
project
Likely High >25%
One in every 10
project
Possible Moderate >10%
One in Every 20
project
Unlikely Low >5%
Less than 1 in 20
project
Rare Very Low <5%
RANK Schedule
Very high >3 Month
High 2to3 Month
Moderate 1to2 Month
Low 2to4 Week
Very Low <2 Week
Probability matrix. Impact matrix
9College of Engineering, Pune
The Software use for future work
 Simulation and risk analysis using Palisade’s @RISK
 It gives equal weight to each 3‐point estimate. That is, no attempt is made to assess the likelihood
of each outcome.
 Interdependence between risks, as well as their ultimate impact on the project plan’s targets
 For scheduling project using Microsoft project
10College of Engineering, Pune
Case Study
Name of project:
Design And Construction Bridge Over River
Pawna, flyover & ROB On Kalewadi Phata To
Dhehu Alandi Road Pune
• Client : PCMC
• Contractor: Gammon India Limited
• Consultant : C. V. Kand Counsultant Pvt .Ltd
• Contract Value: 99,41,78,125/-Rupees
• Status: On going
BAR CHART
11
Jul
2015
Aug
2015
Sept
2015
Oct
2015
Nov
2015
Dec
2015
Jan
2016
Feb
2016
Mar
2016
Apr
2016
May
2016
Literature Review
Collection of Data
Analysis of data
Results and
Interpretation
Dissertation
Writing
College of Engineering, Pune
REFERENCE
1. Iyer, K. and Jha, K. (2006). “Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects", This
paper is part of the Journal of Construction Engineering and Management , Vol. 132, No. 8, August 1, 2006.
2. Long D. Nguyen,Duc H. Phan, and Llewellyn C. M. Tang. “Simulating Construction Duration for Multistory Buildings with
Controlling Activities”, Journal of Construction Engineering and Management, ASCE,09 January 2013
3. Mohamed Sayed Bassiony Ahmed Abd El-Karim a,Omar Aly Mosa El Nawawy , Ahmed Mohamed Abdel-Alim “Identification
and assessment of risk factors affecting construction projects".HBRC Journal, science direct, Online publication date: 1-Jun-2015
4. Damien Schatteman; Willy Herroelen; Stijn Van de Vonder .“Methodology for Integrated Risk Management and Proactive
Scheduling of Construction Projects”. Journal of Construction Engineering and Management, ASCE, Online publication date: 01
November 2008
5. Dho H J, Khaled E. “Fast and accurate risk evaluation for scheduling large-scale construction projects”. Journal of Construction
Engineering and Management, American Society of Civil Engineers ,Online publication date:2011
6. Subramanyan, H., Sawant, P., and Bhatt, V. (2012). "Construction Project Risk Assessment: Development of Model Based on
Investigation of Opinion of Construction Project Experts from India" Journal of Construction Engineering and Management,
American Society of Civil Engineers ,Online publication date:2012
7. Ahuja, H. N., and Nandakumar, V. (1985). "Simulation model to forecast project completion time" . Journal of Construction
Engineering and Management, American Society of Civil Engineers ,Online publication date:1985
8. Mulholland, B., and Christian, J.“Risk assessment in construction schedules” .Journal of Construction Engineering and
Management, American Society of Civil Engineers ,Online publication date: 01 January 1999.
12College of Engineering, Pune
THANK YOU
13College of Engineering, Pune

More Related Content

Similar to Schedule risk identification

RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIOIAEME Publication
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docxRISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docxdaniely50
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: ReviewIRJET Journal
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Loren Schwappach
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paperMolay Reja
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdfRidaShahid36
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectIOSRJMCE
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqDr. Amarjeet Singh
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - FinalRifan Fhazi
 

Similar to Schedule risk identification (20)

RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docxRISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
RISK RESPONSE STRATEGIES AND PERFORMANCE OF PROJECTS IN KIRINYAGA .docx
 
project management
project managementproject management
project management
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway Project
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Schedule risk identification

  • 1. Schedule Risk Analysis Model (SRAM)-For Infrastructure Project Presented by Under guidance Vishal.R.Kachwah of MIS :121420005 Prof. Dr. N.A.Hedaoo 1College of Engineering, Pune
  • 2. AIM AND OBJECTIVES OF THE PROJECT  The main aim of this study the application of SRAM and verify this operates well and produces realistic results in capturing relation between activity durations and risk factors in schedule for construction project.  Study and understand uncertainty and risk in project scheduling .  Calculate impact of risk in quantitative form using probablitical method with the help of analysis software.  Evaluate construction activity networks under risk factors by using real case study .  This study provided schedule risk analysis guidelines for future project . 2College of Engineering, Pune
  • 3. 3 Risk identification •Determines which risks may affect the project. •Documents their characteristic. Data collection •Develop questionnaire to identify critical risk factors. •Identifie Survey participants, distribuait questionnaires and conduct in-person interviews. Data analysis •The risk analysis process uses Monte Carlo techniques to determine probabilities and contingency. Case Study •Quantify impact of risk on a project schedule with the use of MS Project METHODOLOGY College of Engineering, Pune Position of SRAM in risk management process
  • 4. METHODOLOGY Risk identification and classification. Qualitative and Quantitative Risk analysis Conduct case study of a infrastructure project and Quantify impact of risk on a project schedule. 4College of Engineering, Pune Risk assessment survey
  • 5. Questionnaire 5College of Engineering, Pune  Delphi technique is way to reach qualitative result  Historical data are unavailable  Activity is rather unclear  The questionnaire was developed by examining past studies to extract risk factors that are more appropriate infrastructure project.  The questionnaire was divided into two parts.  The first part included questions regarding the respondent’s  The second part consisted of a total risk factors
  • 6. 6College of Engineering, Pune  Consultants (PMC)  Project managers  Construction managers  Planners The budget values of projects that run by the interviewed persons range from 50 cr to 200 cr and the Experience range from 5 to 15 years  The type of contact persons are for survey  Pilot study Survey methodology  We have to achieve response rate > 40 %
  • 7. 7College of Engineering, Pune Risk Identification Resources Labour Equipment Material Site conditions Environmental Sub-surface Site location Project parties Owner Design and Architecture Contractor Project management Consultant Project features Financial Political The second part consisted of a total of 4 main factor 12 sub factor. Total 60 risk factor cover in this survey which collected form four deferent research work.
  • 8. 8College of Engineering, Pune Risk factor = Severity factor * Frequency of occurrence factor ( 3 ) Description Descriptor RANK Probability Even Chance project Almost certain Very high >50% One in Every 4 project Likely High >25% One in every 10 project Possible Moderate >10% One in Every 20 project Unlikely Low >5% Less than 1 in 20 project Rare Very Low <5% RANK Schedule Very high >3 Month High 2to3 Month Moderate 1to2 Month Low 2to4 Week Very Low <2 Week Probability matrix. Impact matrix
  • 9. 9College of Engineering, Pune The Software use for future work  Simulation and risk analysis using Palisade’s @RISK  It gives equal weight to each 3‐point estimate. That is, no attempt is made to assess the likelihood of each outcome.  Interdependence between risks, as well as their ultimate impact on the project plan’s targets  For scheduling project using Microsoft project
  • 10. 10College of Engineering, Pune Case Study Name of project: Design And Construction Bridge Over River Pawna, flyover & ROB On Kalewadi Phata To Dhehu Alandi Road Pune • Client : PCMC • Contractor: Gammon India Limited • Consultant : C. V. Kand Counsultant Pvt .Ltd • Contract Value: 99,41,78,125/-Rupees • Status: On going
  • 11. BAR CHART 11 Jul 2015 Aug 2015 Sept 2015 Oct 2015 Nov 2015 Dec 2015 Jan 2016 Feb 2016 Mar 2016 Apr 2016 May 2016 Literature Review Collection of Data Analysis of data Results and Interpretation Dissertation Writing College of Engineering, Pune
  • 12. REFERENCE 1. Iyer, K. and Jha, K. (2006). “Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects", This paper is part of the Journal of Construction Engineering and Management , Vol. 132, No. 8, August 1, 2006. 2. Long D. Nguyen,Duc H. Phan, and Llewellyn C. M. Tang. “Simulating Construction Duration for Multistory Buildings with Controlling Activities”, Journal of Construction Engineering and Management, ASCE,09 January 2013 3. Mohamed Sayed Bassiony Ahmed Abd El-Karim a,Omar Aly Mosa El Nawawy , Ahmed Mohamed Abdel-Alim “Identification and assessment of risk factors affecting construction projects".HBRC Journal, science direct, Online publication date: 1-Jun-2015 4. Damien Schatteman; Willy Herroelen; Stijn Van de Vonder .“Methodology for Integrated Risk Management and Proactive Scheduling of Construction Projects”. Journal of Construction Engineering and Management, ASCE, Online publication date: 01 November 2008 5. Dho H J, Khaled E. “Fast and accurate risk evaluation for scheduling large-scale construction projects”. Journal of Construction Engineering and Management, American Society of Civil Engineers ,Online publication date:2011 6. Subramanyan, H., Sawant, P., and Bhatt, V. (2012). "Construction Project Risk Assessment: Development of Model Based on Investigation of Opinion of Construction Project Experts from India" Journal of Construction Engineering and Management, American Society of Civil Engineers ,Online publication date:2012 7. Ahuja, H. N., and Nandakumar, V. (1985). "Simulation model to forecast project completion time" . Journal of Construction Engineering and Management, American Society of Civil Engineers ,Online publication date:1985 8. Mulholland, B., and Christian, J.“Risk assessment in construction schedules” .Journal of Construction Engineering and Management, American Society of Civil Engineers ,Online publication date: 01 January 1999. 12College of Engineering, Pune
  • 13. THANK YOU 13College of Engineering, Pune