SlideShare a Scribd company logo
1 of 10
Goindwal Sahib Thermal Power Plant
INTRODUCTION:
On its website in 2011, GVK stated that the project was 600-megawatt while a February 2011
investor presentation described the project as a 540 megawatt plant comprising two 270
generating units (units 1 and 2). The Central Electricity Authority describes it as a 540 MW
project.
In its 2010-2011 annual report GVK stated that "during February 2011 your Company has
executed a Memorandum of Understanding (MOU) with the Punjab State Power Corporation
Limited for implementation of 1320 MW Power Project (Phase-II), in the State of Punjab. For
this purpose GVK Power (Khadur Sahib) Private Limited, a SPV has been incorporated as a
step down subsidiary through GVK Energy Limited to implement the Coal based thermal power
project with super-critical technology, proposed to be developed in the additional land at the
existing Goindwal Sahib site in Tarn Taran District, Punjab."
GVK has lobbied for the the Punjab government to approve the expansion of the project by an
additional 1,320 megawatts. The company received a terms of reference toward this expansion
(units 3 and 4) in 2011, and completed an environmental impact assessment for the units in
2013.
In April 2014 it was reported that GVK had approached India's NTPC to buy the Goindwal
power station, as GVK has not been able to commission its newly constructed 2 x 270 MW units
because it could not arrange coal from the two coal blocks allocated to it. The first unit was
expected to be commissioned in August 2014.
In May 2014 GVK said it will start power generation at its 540 MW Goindwal Sahib plant as
soon as the station received a coal linkage, and had no plans to sell the facility to NTPC.
In July 2014 the Punjab government said the Centre had agreed to grant coal to the 540 MW
plant, enabling GVK to commence energy production.
In August 2015 GVK Chairman GVK Reddy said the coal mine allocation to the Goindwal Sahib
project had been cancelled. The company still planned to put the plant into operation, but
commissioning is subject to allocation of coal.
Unit 1 was commissioned in February 2016 and unit 2 in March 2016 A Swiss company, IMR
Metallurgical Resources, has agreed to supply coal from South Africa to the plant. The company
also has been allotted 12 lakh tonnes of unused coal by Coal India Limited.
Coal supply
GVK states on its website that coal for the project will be sourced from "the company’s own coal
mines at Tokisud and Seregarha, Jharkhand." GVK has established another subsidiary, GVK
Coal (Tokisud) Company Private Limited, to develop the Tokisud coal mine in Hazaribagh
district in Jharkhand.
On its website GVK states this plant will be supplied with coal from the "Tokisud and Sereghara
mine blocks have mine-able reserves of 52 million tonnes and 100 million tonnes respectively."
The company states that the "Tokisud Open Cast mining block, located 50 kms north-west of
Ranchi City in the State of Jharkhand, is being developed into a captive coal mine.” Elsewhere
on its website the company states that GVK Power (Goindwal Sahib) Limited is "developing a
600 MW coal based Thermal Power Plant at Goindwal Sahib, in Punjab. The Company has
initialed the draft Power Purchase Agreement with Punjab State Electricity Board ("PSEB") in
December 2006." GVK has stated that the power purchase agreement runs for 25 years.
In a February 2011 investor presentation GVK states that it has entered into a "Coal
Transportation Agreement" with Indian Railways to transport coal to the plant. GVK stated that 2
million tonnes of coal a year would be supplied from the Tokisud coal mine and 1 million tonnes
a year from the Seregarha coal mine.
The coal mine allocation was cancelled by the Supreme Court in 2014.
Project Details
Sponsor: GVK
Location: Goindwal Sahib village, Khadur Sahib taluk, Taran Taran district, Punjab
Coordinates: 31.3841396, 75.1465032 (exact)
Status:
 Units 1 & 2: Operating
 Units 3 & 4: Pre-permit development
Capacity:
 Unit 1: 270 MW
 Unit 2: 270 MW
 Unit 3: 660 MW
 Unit 4: 660 MW
Type:
Projected in service: 2016 (Units 1-2)
Coal Type:
Coal Source:
Estimated annual CO2:
Source of financing:
Permits and applications:
 Units 1 & 2: Environmental Clearance, India MoEF, May 9, 2008; Environmental Clearance
Amendment and Extension, India MoEF, February 19, 2014
 Units 3 & 4: Terms of Reference, India MoEF, July 26, 2011; Environmental Impact
Assessment, June, 2013
Working procedure
First Coal rake arrives at Goindwal Sahib Thermal Power
Plant
Goindwal SahibTPPcrosseda significantmilestonewiththe arrival of the firstCoal rake at the project
site on18 October2015. The projectteamperformedthe PoojaArchana/Ardaas to markthis special
occasion.The unloadingandstackingof coal wascarriedout througha processwhichinvolvedweighing
of coal rake throughin-motionweighbridge,tipplingof coal,transferringtocoal stockyardthrough
conveyorandfinallystackingof coal throughcoal stacker machine.Thisimportantdevelopmentbrings
us anotherstepclosertothe operationsof the plant.
Transferring of coal at coal stockyard through conveyor system
Wagon unloading coal at wagon tippler
Thermal Power Plants:
Thermal power plants use water as working fluid. Nuclear and coal based power plants fall
under this category. The way energy from fuel gets transformed into electricity forms the
working of a power plant. In a thermal power plant a steam turbine is rotated with help of
high pressure and high temperature steam and this rotation is transferred to a generator to
produce electricity.
Fig.1 Power is produced in thermal power plants by rotating steam turbine
Energy absorption from steam
When turbine blades get rotated by high pressure high temperature steam, the steam loses its
energy. This in turn will result in a low pressure and low temperature steam at the outlet of
the turbine. Here steam is expanded till saturation point is reached. Since there is no heat
addition or removal from the steam, ideally entropy of the steam remains same. This change
is depicted in the following p-v and T-s diagrams. If we can bring this low pressure, low
temperature steam back to its original state, then we can produce electricity continuously.
Fig.2 Pressure and temperature drop of steam when turbine absorbs energy from it
Use of Condenser:
Compressing a fluid which is in gaseous state requires a huge amount of energy, so before
compressing the fluid it should be converted into liquid state. A condenser is used for this
purpose, which rejects heat to the surrounding and converts steam into liquid. Ideally there
will not be any pressure change during this heat rejection process, since the fluid is free to
expand in a condenser. Changes in fluid are shown in the p-v and T-s diagram below.
Fig.3 Use of condenser in order to transform vapor into liquid state
Pump
At exit of the condenser fluid is in liquid state, so we can use a pump to raise the pressure.
During this process the volume and temperature (2-3 deg.C rise)of fluid hardly changes, since
it is in liquid state. Now the fluid has regained its original pressure.
Fig.4 Compressor pumps the fluid to its original pressure
Heat Addition in Boiler & Rankine Cycle
Here external heat is added to the fluid in order to bring fluid back to its original
temperature. This heat is added through a heat exchanger called a boiler. Here the pressure
of the fluid remains the same, since it is free to expand in heat exchanger tubes.
Temperature rises and liquid gets transformed to vapor and regains its original temperature.
This completes the thermodynamic cycle of a thermal power plant, called Rankine Cycle. This
cycle can be repeated and continuous power production is possible.
Fig.5 Heat addition at boiler brings the fluid to its original temperature
Condenser Heat Rejection - Cooling Tower
In order to reject heat from the condenser a colder liquid should make contact with it. In a
thermal power plant continuous supply of cold liquid is produced with the help of a cooling
tower. Cold fluid from the cooling tower absorbs heat from a condenser and gets heated, this
heat is rejected to the atmosphere via natural convection with the help of a cooling tower.
Boiler furnace for Heat Addition
Heat is added to the boiler with help of a boiler furnace. Here fuel reacts with air and
produces heat. In a thermal power plant, the fuel can be either coal or nuclear. When coal is
used as a fuel it produces a lot of pollutants which have to be removed before ejecting to the
surroundings. This is done using a series of steps, the most important of them is an electro
static precipitator (ESP) which removes ash particles from the exhaust. Now much cleaner
exhaust is ejected into the atmosphere via a stack
Fig.6 Main accessories of Rankine cycle - Cooling tower, Boiler furnace, ESP & Chimney
Optimizing a Thermal plant performance
There are various flow parameters which have to be fine-tuned in order to get optimum
performance from a thermal power plant.Lowering the condenser temperature or raising the
average boiler temperature will result in a high efficiency power plant cycle according to the
2nd law of thermodynamics (Carnot efficiency),most of the performance improving
technologies are working on this idea. Some latest trends are listed below.
1. Expanding Turbine After Saturation
Expanding the steam in the turbine even after reaching the saturation point may be a dangerous affair.
As the steam goes below saturation, wetness of the steam increases. These condensed water droplets
collide with the turbine blades rotating at a high speed, thus it can cause extreme tip erosion to the
blades. Turbine blade tip erosion is shown in figure below. But as you expand more you will be able
to absorb more energy from the steam, thus increasing power plant efficiency. Up to 15% wetness
level is considered to be safe for steam turbine operation. So most of the steam turbine will expand up
to this point in order to extract maximum energy from the fluid. This is shown in figure below.
Fig.7 Expanding turbine below saturation point in order to gain maximum power from steam
1. Raising average boiler temperature
If you can increase the average heat addition temperature of the boiler, that will result in a power
plant with higher efficiency. One way to do this is to increase the compressor pressure. This will shift
the saturation point of the fluid to a higher level, thus providing higher average temperature of heat
addition. This is shown in the figure below. The blue line represents change in the cycle after raising
the compressor pressure.
Fig.8 Raising compressor pressure in order achieve higher average boiler temperature

More Related Content

What's hot

PRASHANT ABSTRACT NTPC ANTA
PRASHANT ABSTRACT NTPC ANTAPRASHANT ABSTRACT NTPC ANTA
PRASHANT ABSTRACT NTPC ANTAprashant shukla
 
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTA
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTAPRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTA
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTAprashant shukla
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 
21st Century Coal Power Plants
21st Century Coal Power Plants21st Century Coal Power Plants
21st Century Coal Power PlantsJeffrey Phillips
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadPawan Agrawal
 
Coal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaCoal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaGalih Honggo Baskoro
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipatpratikguptateddy
 
Ntpc anta training presentation
Ntpc anta training presentation Ntpc anta training presentation
Ntpc anta training presentation nishant pareek
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Prashant Shukla ppt on NTPC Anta
Prashant Shukla ppt on NTPC AntaPrashant Shukla ppt on NTPC Anta
Prashant Shukla ppt on NTPC Antaprashant shukla
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCADITYA ARYAN
 
INTRODUCTION project apurv (1)
INTRODUCTION project apurv (1)INTRODUCTION project apurv (1)
INTRODUCTION project apurv (1)apurv rathore
 

What's hot (20)

PRASHANT ABSTRACT NTPC ANTA
PRASHANT ABSTRACT NTPC ANTAPRASHANT ABSTRACT NTPC ANTA
PRASHANT ABSTRACT NTPC ANTA
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTA
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTAPRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTA
PRASHANT SEMINAR REPORT CONTENT TABLE NTPC ANTA
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
21st Century Coal Power Plants
21st Century Coal Power Plants21st Century Coal Power Plants
21st Century Coal Power Plants
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC Faridabad
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Presentation1
Presentation1Presentation1
Presentation1
 
Coal Fired Power Plant in Indonesia
Coal Fired Power Plant in IndonesiaCoal Fired Power Plant in Indonesia
Coal Fired Power Plant in Indonesia
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Ntpc anta training presentation
Ntpc anta training presentation Ntpc anta training presentation
Ntpc anta training presentation
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
NTPC Farakka
NTPC FarakkaNTPC Farakka
NTPC Farakka
 
Prashant Shukla ppt on NTPC Anta
Prashant Shukla ppt on NTPC AntaPrashant Shukla ppt on NTPC Anta
Prashant Shukla ppt on NTPC Anta
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
INTRODUCTION project apurv (1)
INTRODUCTION project apurv (1)INTRODUCTION project apurv (1)
INTRODUCTION project apurv (1)
 

Viewers also liked

Subsea control down under subsea internet of things
Subsea control down under subsea internet of thingsSubsea control down under subsea internet of things
Subsea control down under subsea internet of thingsBrendan Hyland
 
Demand by Ankit Singh
Demand by Ankit SinghDemand by Ankit Singh
Demand by Ankit SinghAnkit Singh
 
Campionati di calcio CSI Vallecamonica - Comunicato N°5
Campionati di calcio CSI Vallecamonica - Comunicato N°5Campionati di calcio CSI Vallecamonica - Comunicato N°5
Campionati di calcio CSI Vallecamonica - Comunicato N°5Giuliano Ganassi
 
東京の宣伝動画案
東京の宣伝動画案東京の宣伝動画案
東京の宣伝動画案yuta nakajima
 
Los cuentos fantásticos
Los cuentos fantásticosLos cuentos fantásticos
Los cuentos fantásticosCarlaMessina82
 
Safety of nuclear power plant operation. Lecture 2.
Safety of nuclear power plant operation. Lecture 2.Safety of nuclear power plant operation. Lecture 2.
Safety of nuclear power plant operation. Lecture 2.Dmitry Samokhin
 
Chapitre 30 - VII. La nouvelle interprétation
Chapitre 30 - VII. La nouvelle interprétation Chapitre 30 - VII. La nouvelle interprétation
Chapitre 30 - VII. La nouvelle interprétation Pierrot Caron
 
41 principles retinal detachment surgery
41 principles retinal detachment surgery41 principles retinal detachment surgery
41 principles retinal detachment surgeryMohamad Jeffrey Ismail
 

Viewers also liked (14)

Subsea control down under subsea internet of things
Subsea control down under subsea internet of thingsSubsea control down under subsea internet of things
Subsea control down under subsea internet of things
 
Demand by Ankit Singh
Demand by Ankit SinghDemand by Ankit Singh
Demand by Ankit Singh
 
Power point práctica 7
Power point práctica 7Power point práctica 7
Power point práctica 7
 
Campionati di calcio CSI Vallecamonica - Comunicato N°5
Campionati di calcio CSI Vallecamonica - Comunicato N°5Campionati di calcio CSI Vallecamonica - Comunicato N°5
Campionati di calcio CSI Vallecamonica - Comunicato N°5
 
東京の宣伝動画案
東京の宣伝動画案東京の宣伝動画案
東京の宣伝動画案
 
Oaxaca
OaxacaOaxaca
Oaxaca
 
distribution CV
distribution CVdistribution CV
distribution CV
 
Los cuentos fantásticos
Los cuentos fantásticosLos cuentos fantásticos
Los cuentos fantásticos
 
Safety of nuclear power plant operation. Lecture 2.
Safety of nuclear power plant operation. Lecture 2.Safety of nuclear power plant operation. Lecture 2.
Safety of nuclear power plant operation. Lecture 2.
 
Chapitre 30 - VII. La nouvelle interprétation
Chapitre 30 - VII. La nouvelle interprétation Chapitre 30 - VII. La nouvelle interprétation
Chapitre 30 - VII. La nouvelle interprétation
 
41 principles retinal detachment surgery
41 principles retinal detachment surgery41 principles retinal detachment surgery
41 principles retinal detachment surgery
 
Normal postpartum
Normal postpartumNormal postpartum
Normal postpartum
 
SHORT STATURE
SHORT STATURESHORT STATURE
SHORT STATURE
 
Astro bio energetic a
Astro bio energetic aAstro bio energetic a
Astro bio energetic a
 

Similar to Goindwal sahib thermal power plant

kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar hariom nagar
 
Anil thermal power plant
Anil thermal power plantAnil thermal power plant
Anil thermal power plantANIL SHARMA
 
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...Navin Pathak
 
compalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxcompalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxVishalSen33
 
Summer Training Report Of OTPC
Summer Training Report Of OTPCSummer Training Report Of OTPC
Summer Training Report Of OTPCArijit Roy
 
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,ReportMAHENDRA MEENA
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
ramgarh gas thermal power plant training report by bhagu
ramgarh gas thermal power plant training report by bhaguramgarh gas thermal power plant training report by bhagu
ramgarh gas thermal power plant training report by bhaguBhagu Bhatia Devikot
 
Summer Training Report on thermal power plant
Summer Training Report on thermal power plantSummer Training Report on thermal power plant
Summer Training Report on thermal power plantMohdAreebQureshi
 
2X500 MW Steel Thermal Power Station
2X500 MW Steel Thermal Power Station2X500 MW Steel Thermal Power Station
2X500 MW Steel Thermal Power Stationshreyansh sahu
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRahul Jalan
 

Similar to Goindwal sahib thermal power plant (20)

kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Anil thermal power plant
Anil thermal power plantAnil thermal power plant
Anil thermal power plant
 
steam turbine presentations
steam turbine presentationssteam turbine presentations
steam turbine presentations
 
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...Summer training report at uttpar pradesh rajay viduat utpadan          nigam ...
Summer training report at uttpar pradesh rajay viduat utpadan nigam ...
 
compalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxcompalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docx
 
NTPC Singrauli
NTPC SingrauliNTPC Singrauli
NTPC Singrauli
 
hard bind arj
hard bind arjhard bind arj
hard bind arj
 
Summer Training Report Of OTPC
Summer Training Report Of OTPCSummer Training Report Of OTPC
Summer Training Report Of OTPC
 
report on VTPS
report on VTPSreport on VTPS
report on VTPS
 
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report Kalisindh Super  Thermal Power Plant,Jhalawar,Rajasthan ,Report
Kalisindh Super Thermal Power Plant,Jhalawar,Rajasthan ,Report
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
ramgarh gas thermal power plant training report by bhagu
ramgarh gas thermal power plant training report by bhaguramgarh gas thermal power plant training report by bhagu
ramgarh gas thermal power plant training report by bhagu
 
Summer Training Report on thermal power plant
Summer Training Report on thermal power plantSummer Training Report on thermal power plant
Summer Training Report on thermal power plant
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
2X500 MW Steel Thermal Power Station
2X500 MW Steel Thermal Power Station2X500 MW Steel Thermal Power Station
2X500 MW Steel Thermal Power Station
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
NTPC Dadri Gas plant
NTPC Dadri Gas plantNTPC Dadri Gas plant
NTPC Dadri Gas plant
 
project -2
project -2project -2
project -2
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 

Goindwal sahib thermal power plant

  • 1. Goindwal Sahib Thermal Power Plant INTRODUCTION: On its website in 2011, GVK stated that the project was 600-megawatt while a February 2011 investor presentation described the project as a 540 megawatt plant comprising two 270 generating units (units 1 and 2). The Central Electricity Authority describes it as a 540 MW project. In its 2010-2011 annual report GVK stated that "during February 2011 your Company has executed a Memorandum of Understanding (MOU) with the Punjab State Power Corporation Limited for implementation of 1320 MW Power Project (Phase-II), in the State of Punjab. For this purpose GVK Power (Khadur Sahib) Private Limited, a SPV has been incorporated as a step down subsidiary through GVK Energy Limited to implement the Coal based thermal power project with super-critical technology, proposed to be developed in the additional land at the existing Goindwal Sahib site in Tarn Taran District, Punjab." GVK has lobbied for the the Punjab government to approve the expansion of the project by an additional 1,320 megawatts. The company received a terms of reference toward this expansion (units 3 and 4) in 2011, and completed an environmental impact assessment for the units in 2013. In April 2014 it was reported that GVK had approached India's NTPC to buy the Goindwal power station, as GVK has not been able to commission its newly constructed 2 x 270 MW units because it could not arrange coal from the two coal blocks allocated to it. The first unit was expected to be commissioned in August 2014. In May 2014 GVK said it will start power generation at its 540 MW Goindwal Sahib plant as soon as the station received a coal linkage, and had no plans to sell the facility to NTPC. In July 2014 the Punjab government said the Centre had agreed to grant coal to the 540 MW plant, enabling GVK to commence energy production. In August 2015 GVK Chairman GVK Reddy said the coal mine allocation to the Goindwal Sahib project had been cancelled. The company still planned to put the plant into operation, but commissioning is subject to allocation of coal.
  • 2. Unit 1 was commissioned in February 2016 and unit 2 in March 2016 A Swiss company, IMR Metallurgical Resources, has agreed to supply coal from South Africa to the plant. The company also has been allotted 12 lakh tonnes of unused coal by Coal India Limited. Coal supply GVK states on its website that coal for the project will be sourced from "the company’s own coal mines at Tokisud and Seregarha, Jharkhand." GVK has established another subsidiary, GVK Coal (Tokisud) Company Private Limited, to develop the Tokisud coal mine in Hazaribagh district in Jharkhand. On its website GVK states this plant will be supplied with coal from the "Tokisud and Sereghara mine blocks have mine-able reserves of 52 million tonnes and 100 million tonnes respectively." The company states that the "Tokisud Open Cast mining block, located 50 kms north-west of Ranchi City in the State of Jharkhand, is being developed into a captive coal mine.” Elsewhere on its website the company states that GVK Power (Goindwal Sahib) Limited is "developing a 600 MW coal based Thermal Power Plant at Goindwal Sahib, in Punjab. The Company has initialed the draft Power Purchase Agreement with Punjab State Electricity Board ("PSEB") in December 2006." GVK has stated that the power purchase agreement runs for 25 years. In a February 2011 investor presentation GVK states that it has entered into a "Coal Transportation Agreement" with Indian Railways to transport coal to the plant. GVK stated that 2 million tonnes of coal a year would be supplied from the Tokisud coal mine and 1 million tonnes a year from the Seregarha coal mine. The coal mine allocation was cancelled by the Supreme Court in 2014. Project Details Sponsor: GVK Location: Goindwal Sahib village, Khadur Sahib taluk, Taran Taran district, Punjab Coordinates: 31.3841396, 75.1465032 (exact) Status:  Units 1 & 2: Operating  Units 3 & 4: Pre-permit development
  • 3. Capacity:  Unit 1: 270 MW  Unit 2: 270 MW  Unit 3: 660 MW  Unit 4: 660 MW Type: Projected in service: 2016 (Units 1-2) Coal Type: Coal Source: Estimated annual CO2: Source of financing: Permits and applications:  Units 1 & 2: Environmental Clearance, India MoEF, May 9, 2008; Environmental Clearance Amendment and Extension, India MoEF, February 19, 2014  Units 3 & 4: Terms of Reference, India MoEF, July 26, 2011; Environmental Impact Assessment, June, 2013 Working procedure First Coal rake arrives at Goindwal Sahib Thermal Power Plant Goindwal SahibTPPcrosseda significantmilestonewiththe arrival of the firstCoal rake at the project site on18 October2015. The projectteamperformedthe PoojaArchana/Ardaas to markthis special occasion.The unloadingandstackingof coal wascarriedout througha processwhichinvolvedweighing of coal rake throughin-motionweighbridge,tipplingof coal,transferringtocoal stockyardthrough conveyorandfinallystackingof coal throughcoal stacker machine.Thisimportantdevelopmentbrings us anotherstepclosertothe operationsof the plant.
  • 4. Transferring of coal at coal stockyard through conveyor system Wagon unloading coal at wagon tippler
  • 5. Thermal Power Plants: Thermal power plants use water as working fluid. Nuclear and coal based power plants fall under this category. The way energy from fuel gets transformed into electricity forms the working of a power plant. In a thermal power plant a steam turbine is rotated with help of high pressure and high temperature steam and this rotation is transferred to a generator to produce electricity. Fig.1 Power is produced in thermal power plants by rotating steam turbine Energy absorption from steam When turbine blades get rotated by high pressure high temperature steam, the steam loses its energy. This in turn will result in a low pressure and low temperature steam at the outlet of the turbine. Here steam is expanded till saturation point is reached. Since there is no heat addition or removal from the steam, ideally entropy of the steam remains same. This change is depicted in the following p-v and T-s diagrams. If we can bring this low pressure, low temperature steam back to its original state, then we can produce electricity continuously.
  • 6. Fig.2 Pressure and temperature drop of steam when turbine absorbs energy from it Use of Condenser: Compressing a fluid which is in gaseous state requires a huge amount of energy, so before compressing the fluid it should be converted into liquid state. A condenser is used for this purpose, which rejects heat to the surrounding and converts steam into liquid. Ideally there will not be any pressure change during this heat rejection process, since the fluid is free to expand in a condenser. Changes in fluid are shown in the p-v and T-s diagram below. Fig.3 Use of condenser in order to transform vapor into liquid state Pump At exit of the condenser fluid is in liquid state, so we can use a pump to raise the pressure. During this process the volume and temperature (2-3 deg.C rise)of fluid hardly changes, since it is in liquid state. Now the fluid has regained its original pressure.
  • 7. Fig.4 Compressor pumps the fluid to its original pressure Heat Addition in Boiler & Rankine Cycle Here external heat is added to the fluid in order to bring fluid back to its original temperature. This heat is added through a heat exchanger called a boiler. Here the pressure of the fluid remains the same, since it is free to expand in heat exchanger tubes. Temperature rises and liquid gets transformed to vapor and regains its original temperature. This completes the thermodynamic cycle of a thermal power plant, called Rankine Cycle. This cycle can be repeated and continuous power production is possible. Fig.5 Heat addition at boiler brings the fluid to its original temperature
  • 8. Condenser Heat Rejection - Cooling Tower In order to reject heat from the condenser a colder liquid should make contact with it. In a thermal power plant continuous supply of cold liquid is produced with the help of a cooling tower. Cold fluid from the cooling tower absorbs heat from a condenser and gets heated, this heat is rejected to the atmosphere via natural convection with the help of a cooling tower. Boiler furnace for Heat Addition Heat is added to the boiler with help of a boiler furnace. Here fuel reacts with air and produces heat. In a thermal power plant, the fuel can be either coal or nuclear. When coal is used as a fuel it produces a lot of pollutants which have to be removed before ejecting to the surroundings. This is done using a series of steps, the most important of them is an electro static precipitator (ESP) which removes ash particles from the exhaust. Now much cleaner exhaust is ejected into the atmosphere via a stack Fig.6 Main accessories of Rankine cycle - Cooling tower, Boiler furnace, ESP & Chimney Optimizing a Thermal plant performance There are various flow parameters which have to be fine-tuned in order to get optimum performance from a thermal power plant.Lowering the condenser temperature or raising the
  • 9. average boiler temperature will result in a high efficiency power plant cycle according to the 2nd law of thermodynamics (Carnot efficiency),most of the performance improving technologies are working on this idea. Some latest trends are listed below. 1. Expanding Turbine After Saturation Expanding the steam in the turbine even after reaching the saturation point may be a dangerous affair. As the steam goes below saturation, wetness of the steam increases. These condensed water droplets collide with the turbine blades rotating at a high speed, thus it can cause extreme tip erosion to the blades. Turbine blade tip erosion is shown in figure below. But as you expand more you will be able to absorb more energy from the steam, thus increasing power plant efficiency. Up to 15% wetness level is considered to be safe for steam turbine operation. So most of the steam turbine will expand up to this point in order to extract maximum energy from the fluid. This is shown in figure below. Fig.7 Expanding turbine below saturation point in order to gain maximum power from steam 1. Raising average boiler temperature If you can increase the average heat addition temperature of the boiler, that will result in a power plant with higher efficiency. One way to do this is to increase the compressor pressure. This will shift the saturation point of the fluid to a higher level, thus providing higher average temperature of heat addition. This is shown in the figure below. The blue line represents change in the cycle after raising the compressor pressure.
  • 10. Fig.8 Raising compressor pressure in order achieve higher average boiler temperature