SlideShare a Scribd company logo
1 of 40
Download to read offline
08. Classification of Canals
B.Sc. Civil Engineering 8th Semester
Muhammad Ajmal (PhD)
Lecturer
Agri. Engg. Deptt.
CE-402 Irrigation Engineering
1
Classification of Canals
 Canal
❖ It is an artificial cross secrtion constructed on the ground to carry water to the
field either from a reservoir, tank or river.
2
Types of Canals
(BASED ON SOURCE OF SUPPLY)
Permanent or Perennial
Canal
Non-Perennial Canal
Inundation Canal
Those canals which get continuous supplies by
permanent source of supply like a river or reservoir are
called as permanent canals or perennial canals. These
irrigate the field throughout the year with equitable rate
of flow.
These are the canals which irrigate the field for only
one part of the year usually during summer season or at
the beginning and end of winter season, called as non-
perennial canals. These canals take-off from rivers
which do not have assured supply throughout the year.
Draws its supplies from a river only during the high stages of
the river. No regulator is provided at the head of such canal.
This draws lot of quantity of silt which is really beneficial for
the crops.
3
Types of Canals
(BASED ON FUNCTION)
• Carries water from its source to agricultural fields.
Irrigation Canal
• Used for transport of goods. Sometimes these are also
used for irrigation purposes.
Navigation Canal
• Used to carry water for generation of hydroelectricity.
Power Canal
• Feeds two or more canals.
Feeder Canal
Note: A canal can serve more than one purpose 4
Types of Canals
(BASED ON ALIGNMENT)
Watershed Canal or Ridge Canal
Contour Canal
Side Slope Canal
5
Watershed canal or Ridge canal
Fig. Canal Alignment
6
Watershed canal or Ridge canal
7
Watershed canal or Ridge canal (Contd.)
➢ The canal which is aligned along any natural watershed (ridge line) is called a
watershed canal, or a ridge canal.
➢ Aligning a canal (main canal or branch canal or distributary) on the ridge ensures
gravity irrigation on both sides of the canal.
➢ Thus between two major streams, there is the main watershed (ridge line), which
divides the drainage area of the two streams.
➢ Since the drainage flows away from the ridge, no drainage can cross a canal aligned on
the ridge. Thus, a canal aligned on the watershed saves the cost of construction of cross-
drainage works.
8
Contour Canal
 A contour canal is an artificially-dug
navigable canal which closely follows the
contour line of the land it traverses in order
to avoid costly engineering works such as
boring a tunnel through higher ground,
building an embankment over lower
ground, or constructing a canal lock (or
series of locks) to change the level.
9
Contour Canal
➢ Watershed canal along the ridge line are not found economical in hill areas where the
river flows in the valley well below the watershed.
➢ In fact, the ridge line (watershed) may be hundred of meters above the river. It therefore
becomes virtually impossible to take the canal on top of such a higher ridge line.
➢ In such conditions, contour canals are usually constructed.
➢ A contour canal irrigates only on one side because the area on the other side is higher.
➢ As the drainage flow is always at right angles to the ground contour. Such a channel
would definitely have to cross natural drains and streams, necessitating construction of
cross drainage structures.
10
Side Slope Canal
 A side slope canal is that which is aligned at
right angles to the contours; i.e. along the
side slopes.
 Since such a canal runs parallel to the
natural drainage flow, it usually does not
intercept drainage channels, thus avoiding the
construction of cross-drainage structures.
 It is a canal which is aligned roughly at right
angle to contours of the country but not on
watershed or valley.
11
Types of Canals
(BASED ON DISCHARGE)
Main Canal
Branch Canal
Major Distributary
Minor Distributary
Water Course
12
Source: Lecture Notes
Prof. Dr. M. R. Kabir
Types of Canals
(Based on lining provided or not)
• Bed and banks made up of natural soil.
• Water velocities higher than 0.7 m/s are not tolerable.
• High seepage and conveyance water losses.
• Profuse growth of aquatic weeds retards the flow
Unlined
Canal
• Lining of impervious material on its bed and banks to
prevent the seepage of water.
• Different types of lining used e.g. concrete, brick or
burnt clay tile, boulder, etc.
Lined
Canal
13
AN UNLINED CANAL
14
A LINED CANAL
15
Types of Canals
(Based on Financial output)
• Those canals which yield a net revenue to the nation
after full development of irrigation in the area.
• Profuse growth of aquatic weeds retards the flow
Productive
canals
• Those canals which apply water to a low income
community for irrigation purposes to protect community
from famine.
Protective
canals
16
Types of Irrigation Canals
17
 In irrigation canal design two important factors has to be counted (i) quantity of silt carried by canal
and (ii) type of boundary of canal. There are three types of channel based on factors. They are (a)
Alluvial (b) Non-alluvial and (c) Rigid Boundary or Lined
(a) Alluvial channels: are those which are excavated in alluvial soil, and carry sufficient silt in water.
The boundary of such canal is of silt known as alluvium. The silt content in canal depend on the
velocity of flow. At high velocity more silt scouring at bottom of canal occurs, while at low velocity
minimum silt deposition occurs. To design a channel in such area a non silting nor scouring velocity
has to be adopted.
(b) Non alluvial channels: These channel are excavated in non alluvial soil like, rock, loam or clay.
Such channels usually have no silting problem as water flow with non silting velocity
(c) Rigid Boundary channels: Those channels which have sides and bottom of rigid materials. Lined
channels are rigid boundary channels.
Cross Section of Irrigation Canal
 This section is partly in cutting and partly in filling and aims in balancing the quantity of
earth work in excavation with that in filling.
 When the NSL is above the top of the bank, the entire canal section will have to be in
cutting, and it shall be called ‘canal in cutting’.
 Similarly, when the NSL is lower than the bed level of the canal, the entire canal section
will have to be built in filling, and it is called ‘canal in filling’.
18
FSL= Full Supply Level
NSL=Natural Surface Level
Components of Cross- Section
 Side slope
 Berm
 Freeboard
 Bank
 Service road
 Back Berm or Counter Berm
 Spoil Bank
 Borrow Pit
19
Side Slope
 The side slopes should be such that they are stable, depending upon the type of the soil.
 A comparatively steeper slope can be provided in cutting rather than in filling, as the soil in
the former case shall be more stable.
20
Sr. No. Type of Soil Slope in Cutting Slope in Filling
1 Clayey Soil 1.5 : 1 2 : 1
2 Sandy Soil 3 : 1 4 : 1
3 Loamy Soil 1.5 : 1 2 : 1
4 Gravel Soil 0.75 : 1 1.25 : 1
5 Hard Rock 0.25 : 1 ----
6 Soft Rock 0.5 : 1 ----
Berm
 Berm is the horizontal distance left at ground level between the toe of the bank and the
top edge of cutting.
21
 Purposes of Berms
❖ They give additional strength to the banks and provide protection against erosion and breaches.
❖ They provide a scope for future widening of the canal.
Freeboard
❖ The margin between FSL and bank level is known as freeboard.
❖ The amount of freeboard depends upon the discharge of the channel.
❖ Recommended minimum freeboard = 0.5 m
22
Bank
 The primary purpose of banks is to retain water.
 This can be used as means of communication and as inspection paths.
23
Service Road
 These are provided on canals for inspection purposes, and may simultaneously serve
as the means of communication in remote areas.
Dowla: As a measure of safety in driving, dowlas with side slopes of 1.5: 1 to 2:1, are provided
along the banks.
24
Back Berm or Counter Berm
 Even after providing sufficient section for bank embankment, the saturation gradient line may
cut the downstream end of the bank.
 In such a case, the saturation line can be kept covered at least by 0.5 m with the help of
counter berms as shown in figure below.
25
Spoil Bank
 When the earthwork in excavation exceeds earthworks in filling, the extra earth has to be
disposed of economically.
 Economical mode of its disposal may be collecting this soil on the edge of the bank
embankment itself.
26
Borrow Pit
 When earthwork in filling exceeds the earthwork in excavation, the earth has to be
brought from somewhere.
 The pits, which are dug for bringing earth, are known as borrow pits.
 If such pits are excavated outside the channel, they are known as external borrow pits, and if
they are excavated somewhere within the channel, they are known as internal borrow pits.
 Internal borrow pits are more preferred than external one.
27
 The inside borrow pit may be located at the center of
canal.
 The idea behind this is that the borrow pits will act as
water pockets where the silt will be deposited and
ultimately the canal bed will get levelled up.
Balancing Depth
28
 A canal section will be economical when earth work involved at a particular section has an
equal amount of cut and fill. Usually a canal section has a part in cutting and part in filling as
shown in fig.
 If the amount of cut is equal to the amount of fill, it has to be paid for once only.
Definition
 For a given C/S there is always only one depth of cutting for which the cutting and filling
will be equal. The depth is known as balancing depth.
If h = vertical height of top of bank
from the bed of canal.
b = bed width of the channel.
t = top width of the canal bank.
n:1 = side slope of bank in filling.
z:1 = side slope of canal in cutting.
d = full supply depth of canal.
y = depth of cutting.
Area of the cut = by + zy2 = y(b + zy)
Area of fill = 2[(h – y)t + n(h-y)2]
Balancing Depth
Equating the area of cut and fill:
y(b + z y) = 2[(h – y)t + n(h-y)2 ]
b y+ zy2 = 2th + 2nh2 – 2nhy – 2ty – 2nhy + 2ny2
y2 (2n – z) – (b + 4nh + 2t)y + 2h(t + nh) =0
From this equation the balancing depth of the canal
may be determined.
A canal is usually constructed with side slope of 1:1 in
cutting and a slope 1.5:1 in filling.
Putting n = 1.5 and z =1 in above equation.
We get;
y2 – (b/2 + 3h + t)y + h (t + 3/2 h)=0
Example
 Calculate the balancing depth for a channel section having a bed width equal to 18 m and side
slopes of 1:1 in cutting and 2:1 in filling. The bank embankments are kept 3.0 m higher than the
ground level (berm level) and crest width of banks is kept as 2.0 m.
Solution: Let d be the balancing depth, i.e. the depth for which excavation and filling becomes
equal.
30
Example (Contd.)
Area of cutting = (18 + d) d m2
Area of filling = 2(2+14)/2×3 = 48 m2
Equating cutting and filling, we get
(18 + d) d = 48
or, d2 + 18d – 48 = 0
or, d = 2.35 m (neglecting –ve sign), Balancing depth = 2.35 m
31
Canal Lining and its Advantages
➢ It is the treatment given to the canal bed and banks to make the canal section impervious.
➢ Water Conservation: Lining a canal results in reduction in water losses, as water losses in
unlined irrigation canals can be high.
➢ No seepage of water into adjacent land or roads: If canal banks are highly permeable, the
seepage of water will cause very wet or waterlogged conditions, or even standing water on
adjacent fields or roads. Lining of such a canal can solve this problem.
➢ Reduced canal dimensions: The resistance to flow of a lined canal is less than that of an
unlined canal, and thus the flow velocity will be higher in the lined canal . Therefore, with the
higher velocity, the canal cross-section for a lined canal can be smaller than that of an unlined
canal.
➢ Reduced maintenance: Maintenance costs for the following issues are eliminated using lining
of canals.
❖ Periodical removal of silt deposited on the beds and sides of canals.
❖ Removal of weeds and water canals.
❖ Minor repairs like plugging of cracks, uneven settlements of banks, etc. 32
Types of lining
Hard Surface Lining
Cast Insitu Cement
Concrete Lining
Shotcrete or Plastic
Lining
Cement Concrete Tile
Lining or Brick Lining
Asphaltic Concrete
Lining
Boulder Lining
Earth Type Lining
Compacted Earth
Lining
Soil Cement Lining
33
Cast In-situ Cement Concrete Lining
Shotcrete & Plastic Lining
Canal Lining
CONCRETE LINING
Canal Lining
Concrete tiles canal lining
Canal Lining
Brick canal lining
PREFABRICATED CHANNEL
SECTION
Disadvantages
 Higher initial investment
 Repair is costly
 Shifting of outlet is costly because it involve dismantling and relaying of lining.
 Longer construction period
 Sophisticated construction equipment and labor is needed.
40

More Related Content

What's hot

CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATIONkannan1407
 
Bandhara Irrigation 1to8.pptx
Bandhara Irrigation 1to8.pptxBandhara Irrigation 1to8.pptx
Bandhara Irrigation 1to8.pptxPushkar866863
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdfSaqib Imran
 
Unlined Canal design
Unlined Canal designUnlined Canal design
Unlined Canal designPreetAwesome
 
Lined or non erodible design channel study
Lined or non erodible design channel studyLined or non erodible design channel study
Lined or non erodible design channel studyroidghozi
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)holegajendra
 
Cross drainage work
Cross drainage work Cross drainage work
Cross drainage work meetmaniya
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipatorSAGAR RAUT
 
Canal of design
Canal of designCanal of design
Canal of designPREMKUMAR
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report vikas rahangdale
 

What's hot (20)

CANAL IRRIGATION
CANAL IRRIGATIONCANAL IRRIGATION
CANAL IRRIGATION
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
 
Canal Irrigation
Canal IrrigationCanal Irrigation
Canal Irrigation
 
Spillways
SpillwaysSpillways
Spillways
 
Bandhara Irrigation 1to8.pptx
Bandhara Irrigation 1to8.pptxBandhara Irrigation 1to8.pptx
Bandhara Irrigation 1to8.pptx
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdf
 
Hydraulic structures
Hydraulic structuresHydraulic structures
Hydraulic structures
 
Unlined Canal design
Unlined Canal designUnlined Canal design
Unlined Canal design
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Storage head works
Storage head worksStorage head works
Storage head works
 
Duty delta etc
Duty delta etcDuty delta etc
Duty delta etc
 
Lined or non erodible design channel study
Lined or non erodible design channel studyLined or non erodible design channel study
Lined or non erodible design channel study
 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2
 
Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)Introduction to irrigation engineering 19 07 1 (1)
Introduction to irrigation engineering 19 07 1 (1)
 
Cross drainage work
Cross drainage work Cross drainage work
Cross drainage work
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
Canal of design
Canal of designCanal of design
Canal of design
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report
 
Sediment Transport
Sediment TransportSediment Transport
Sediment Transport
 

Similar to 08. Classification of Canals.pdf

Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canalsaibabu48
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemMitaliShelke
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigationSAGAR RAUT
 
Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Kiran Mane
 
Irrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxIrrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxAliFurqan6
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantagesabdqadeer
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxMaloth3
 
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfCIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfRamenRoyAEKHSD2PWRD
 
10. Kenedy's and Lacey's Theory (Supply).pdf
10. Kenedy's and Lacey's Theory (Supply).pdf10. Kenedy's and Lacey's Theory (Supply).pdf
10. Kenedy's and Lacey's Theory (Supply).pdfMuhammadAjmal326519
 
Canal Regulation & Canal Types
Canal Regulation & Canal TypesCanal Regulation & Canal Types
Canal Regulation & Canal TypesAbbasZafar3
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworksJimit Shah
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Mulugeta Abera
 

Similar to 08. Classification of Canals.pdf (20)

Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution system
 
Canal Irrigation
Canal IrrigationCanal Irrigation
Canal Irrigation
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptx
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
 
Canal design
Canal designCanal design
Canal design
 
Irrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxIrrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptx
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
 
06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptx
 
Canals
CanalsCanals
Canals
 
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfCIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
 
10. Kenedy's and Lacey's Theory (Supply).pdf
10. Kenedy's and Lacey's Theory (Supply).pdf10. Kenedy's and Lacey's Theory (Supply).pdf
10. Kenedy's and Lacey's Theory (Supply).pdf
 
Canal Regulation & Canal Types
Canal Regulation & Canal TypesCanal Regulation & Canal Types
Canal Regulation & Canal Types
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1
 

More from MuhammadAjmal326519

16. Water Logging and Salinity Part -2.pdf
16. Water Logging and Salinity Part -2.pdf16. Water Logging and Salinity Part -2.pdf
16. Water Logging and Salinity Part -2.pdfMuhammadAjmal326519
 
15. Water Logging and Salinity Part-1.pdf
15. Water Logging and Salinity Part-1.pdf15. Water Logging and Salinity Part-1.pdf
15. Water Logging and Salinity Part-1.pdfMuhammadAjmal326519
 
18. Dams Stability & Environmental Impact.pdf
18. Dams Stability & Environmental Impact.pdf18. Dams Stability & Environmental Impact.pdf
18. Dams Stability & Environmental Impact.pdfMuhammadAjmal326519
 
17. Ten large dams in Pakistan1.pdf
17. Ten large dams in Pakistan1.pdf17. Ten large dams in Pakistan1.pdf
17. Ten large dams in Pakistan1.pdfMuhammadAjmal326519
 
13. Canal Outlets & other Head Regulators.pdf
13. Canal Outlets & other Head Regulators.pdf13. Canal Outlets & other Head Regulators.pdf
13. Canal Outlets & other Head Regulators.pdfMuhammadAjmal326519
 
14. Waterlogging Supplymentary materials.pdf
14. Waterlogging Supplymentary materials.pdf14. Waterlogging Supplymentary materials.pdf
14. Waterlogging Supplymentary materials.pdfMuhammadAjmal326519
 
17. Ten large dams in Pakistan.docx
17. Ten large dams in Pakistan.docx17. Ten large dams in Pakistan.docx
17. Ten large dams in Pakistan.docxMuhammadAjmal326519
 
14. What-you-need-to-know-about-Waterlogging (Supply).pdf
14. What-you-need-to-know-about-Waterlogging (Supply).pdf14. What-you-need-to-know-about-Waterlogging (Supply).pdf
14. What-you-need-to-know-about-Waterlogging (Supply).pdfMuhammadAjmal326519
 
18. Environmental Impacts of Dams (Supply).pdf
18. Environmental Impacts of Dams (Supply).pdf18. Environmental Impacts of Dams (Supply).pdf
18. Environmental Impacts of Dams (Supply).pdfMuhammadAjmal326519
 
10. Silt Theories [Kennedy's Theory-I].pdf
10. Silt Theories [Kennedy's Theory-I].pdf10. Silt Theories [Kennedy's Theory-I].pdf
10. Silt Theories [Kennedy's Theory-I].pdfMuhammadAjmal326519
 
11. Silt Theories [Lacey's Theory].pdf
11. Silt Theories [Lacey's Theory].pdf11. Silt Theories [Lacey's Theory].pdf
11. Silt Theories [Lacey's Theory].pdfMuhammadAjmal326519
 
17. Large Dams-Questions and Answers (Supply).docx
17. Large Dams-Questions and Answers (Supply).docx17. Large Dams-Questions and Answers (Supply).docx
17. Large Dams-Questions and Answers (Supply).docxMuhammadAjmal326519
 
04. Water Resources of Pakistan.pdf
04. Water Resources of Pakistan.pdf04. Water Resources of Pakistan.pdf
04. Water Resources of Pakistan.pdfMuhammadAjmal326519
 
03. Water Requirements of Crops (Supply).pdf
03. Water Requirements of Crops (Supply).pdf03. Water Requirements of Crops (Supply).pdf
03. Water Requirements of Crops (Supply).pdfMuhammadAjmal326519
 

More from MuhammadAjmal326519 (20)

19. Dam Solved Problems.pdf
19. Dam Solved Problems.pdf19. Dam Solved Problems.pdf
19. Dam Solved Problems.pdf
 
16. Water Logging and Salinity Part -2.pdf
16. Water Logging and Salinity Part -2.pdf16. Water Logging and Salinity Part -2.pdf
16. Water Logging and Salinity Part -2.pdf
 
15. Water Logging and Salinity Part-1.pdf
15. Water Logging and Salinity Part-1.pdf15. Water Logging and Salinity Part-1.pdf
15. Water Logging and Salinity Part-1.pdf
 
18. Dams Stability & Environmental Impact.pdf
18. Dams Stability & Environmental Impact.pdf18. Dams Stability & Environmental Impact.pdf
18. Dams Stability & Environmental Impact.pdf
 
exercises 2 supplementary.pdf
exercises 2 supplementary.pdfexercises 2 supplementary.pdf
exercises 2 supplementary.pdf
 
17. Ten large dams in Pakistan1.pdf
17. Ten large dams in Pakistan1.pdf17. Ten large dams in Pakistan1.pdf
17. Ten large dams in Pakistan1.pdf
 
13. Canal Outlets & other Head Regulators.pdf
13. Canal Outlets & other Head Regulators.pdf13. Canal Outlets & other Head Regulators.pdf
13. Canal Outlets & other Head Regulators.pdf
 
05. Diversion Headworks-1.pdf
05. Diversion Headworks-1.pdf05. Diversion Headworks-1.pdf
05. Diversion Headworks-1.pdf
 
14. Waterlogging Supplymentary materials.pdf
14. Waterlogging Supplymentary materials.pdf14. Waterlogging Supplymentary materials.pdf
14. Waterlogging Supplymentary materials.pdf
 
12. Canal Head Regulators.2.pdf
12. Canal Head Regulators.2.pdf12. Canal Head Regulators.2.pdf
12. Canal Head Regulators.2.pdf
 
17. Ten large dams in Pakistan.docx
17. Ten large dams in Pakistan.docx17. Ten large dams in Pakistan.docx
17. Ten large dams in Pakistan.docx
 
07. Diversion Headworks-3.pdf
07. Diversion Headworks-3.pdf07. Diversion Headworks-3.pdf
07. Diversion Headworks-3.pdf
 
14. What-you-need-to-know-about-Waterlogging (Supply).pdf
14. What-you-need-to-know-about-Waterlogging (Supply).pdf14. What-you-need-to-know-about-Waterlogging (Supply).pdf
14. What-you-need-to-know-about-Waterlogging (Supply).pdf
 
14. Cross Drainage Works.pdf
14. Cross Drainage Works.pdf14. Cross Drainage Works.pdf
14. Cross Drainage Works.pdf
 
18. Environmental Impacts of Dams (Supply).pdf
18. Environmental Impacts of Dams (Supply).pdf18. Environmental Impacts of Dams (Supply).pdf
18. Environmental Impacts of Dams (Supply).pdf
 
10. Silt Theories [Kennedy's Theory-I].pdf
10. Silt Theories [Kennedy's Theory-I].pdf10. Silt Theories [Kennedy's Theory-I].pdf
10. Silt Theories [Kennedy's Theory-I].pdf
 
11. Silt Theories [Lacey's Theory].pdf
11. Silt Theories [Lacey's Theory].pdf11. Silt Theories [Lacey's Theory].pdf
11. Silt Theories [Lacey's Theory].pdf
 
17. Large Dams-Questions and Answers (Supply).docx
17. Large Dams-Questions and Answers (Supply).docx17. Large Dams-Questions and Answers (Supply).docx
17. Large Dams-Questions and Answers (Supply).docx
 
04. Water Resources of Pakistan.pdf
04. Water Resources of Pakistan.pdf04. Water Resources of Pakistan.pdf
04. Water Resources of Pakistan.pdf
 
03. Water Requirements of Crops (Supply).pdf
03. Water Requirements of Crops (Supply).pdf03. Water Requirements of Crops (Supply).pdf
03. Water Requirements of Crops (Supply).pdf
 

Recently uploaded

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

08. Classification of Canals.pdf

  • 1. 08. Classification of Canals B.Sc. Civil Engineering 8th Semester Muhammad Ajmal (PhD) Lecturer Agri. Engg. Deptt. CE-402 Irrigation Engineering 1
  • 2. Classification of Canals  Canal ❖ It is an artificial cross secrtion constructed on the ground to carry water to the field either from a reservoir, tank or river. 2
  • 3. Types of Canals (BASED ON SOURCE OF SUPPLY) Permanent or Perennial Canal Non-Perennial Canal Inundation Canal Those canals which get continuous supplies by permanent source of supply like a river or reservoir are called as permanent canals or perennial canals. These irrigate the field throughout the year with equitable rate of flow. These are the canals which irrigate the field for only one part of the year usually during summer season or at the beginning and end of winter season, called as non- perennial canals. These canals take-off from rivers which do not have assured supply throughout the year. Draws its supplies from a river only during the high stages of the river. No regulator is provided at the head of such canal. This draws lot of quantity of silt which is really beneficial for the crops. 3
  • 4. Types of Canals (BASED ON FUNCTION) • Carries water from its source to agricultural fields. Irrigation Canal • Used for transport of goods. Sometimes these are also used for irrigation purposes. Navigation Canal • Used to carry water for generation of hydroelectricity. Power Canal • Feeds two or more canals. Feeder Canal Note: A canal can serve more than one purpose 4
  • 5. Types of Canals (BASED ON ALIGNMENT) Watershed Canal or Ridge Canal Contour Canal Side Slope Canal 5
  • 6. Watershed canal or Ridge canal Fig. Canal Alignment 6
  • 7. Watershed canal or Ridge canal 7
  • 8. Watershed canal or Ridge canal (Contd.) ➢ The canal which is aligned along any natural watershed (ridge line) is called a watershed canal, or a ridge canal. ➢ Aligning a canal (main canal or branch canal or distributary) on the ridge ensures gravity irrigation on both sides of the canal. ➢ Thus between two major streams, there is the main watershed (ridge line), which divides the drainage area of the two streams. ➢ Since the drainage flows away from the ridge, no drainage can cross a canal aligned on the ridge. Thus, a canal aligned on the watershed saves the cost of construction of cross- drainage works. 8
  • 9. Contour Canal  A contour canal is an artificially-dug navigable canal which closely follows the contour line of the land it traverses in order to avoid costly engineering works such as boring a tunnel through higher ground, building an embankment over lower ground, or constructing a canal lock (or series of locks) to change the level. 9
  • 10. Contour Canal ➢ Watershed canal along the ridge line are not found economical in hill areas where the river flows in the valley well below the watershed. ➢ In fact, the ridge line (watershed) may be hundred of meters above the river. It therefore becomes virtually impossible to take the canal on top of such a higher ridge line. ➢ In such conditions, contour canals are usually constructed. ➢ A contour canal irrigates only on one side because the area on the other side is higher. ➢ As the drainage flow is always at right angles to the ground contour. Such a channel would definitely have to cross natural drains and streams, necessitating construction of cross drainage structures. 10
  • 11. Side Slope Canal  A side slope canal is that which is aligned at right angles to the contours; i.e. along the side slopes.  Since such a canal runs parallel to the natural drainage flow, it usually does not intercept drainage channels, thus avoiding the construction of cross-drainage structures.  It is a canal which is aligned roughly at right angle to contours of the country but not on watershed or valley. 11
  • 12. Types of Canals (BASED ON DISCHARGE) Main Canal Branch Canal Major Distributary Minor Distributary Water Course 12 Source: Lecture Notes Prof. Dr. M. R. Kabir
  • 13. Types of Canals (Based on lining provided or not) • Bed and banks made up of natural soil. • Water velocities higher than 0.7 m/s are not tolerable. • High seepage and conveyance water losses. • Profuse growth of aquatic weeds retards the flow Unlined Canal • Lining of impervious material on its bed and banks to prevent the seepage of water. • Different types of lining used e.g. concrete, brick or burnt clay tile, boulder, etc. Lined Canal 13
  • 16. Types of Canals (Based on Financial output) • Those canals which yield a net revenue to the nation after full development of irrigation in the area. • Profuse growth of aquatic weeds retards the flow Productive canals • Those canals which apply water to a low income community for irrigation purposes to protect community from famine. Protective canals 16
  • 17. Types of Irrigation Canals 17  In irrigation canal design two important factors has to be counted (i) quantity of silt carried by canal and (ii) type of boundary of canal. There are three types of channel based on factors. They are (a) Alluvial (b) Non-alluvial and (c) Rigid Boundary or Lined (a) Alluvial channels: are those which are excavated in alluvial soil, and carry sufficient silt in water. The boundary of such canal is of silt known as alluvium. The silt content in canal depend on the velocity of flow. At high velocity more silt scouring at bottom of canal occurs, while at low velocity minimum silt deposition occurs. To design a channel in such area a non silting nor scouring velocity has to be adopted. (b) Non alluvial channels: These channel are excavated in non alluvial soil like, rock, loam or clay. Such channels usually have no silting problem as water flow with non silting velocity (c) Rigid Boundary channels: Those channels which have sides and bottom of rigid materials. Lined channels are rigid boundary channels.
  • 18. Cross Section of Irrigation Canal  This section is partly in cutting and partly in filling and aims in balancing the quantity of earth work in excavation with that in filling.  When the NSL is above the top of the bank, the entire canal section will have to be in cutting, and it shall be called ‘canal in cutting’.  Similarly, when the NSL is lower than the bed level of the canal, the entire canal section will have to be built in filling, and it is called ‘canal in filling’. 18 FSL= Full Supply Level NSL=Natural Surface Level
  • 19. Components of Cross- Section  Side slope  Berm  Freeboard  Bank  Service road  Back Berm or Counter Berm  Spoil Bank  Borrow Pit 19
  • 20. Side Slope  The side slopes should be such that they are stable, depending upon the type of the soil.  A comparatively steeper slope can be provided in cutting rather than in filling, as the soil in the former case shall be more stable. 20 Sr. No. Type of Soil Slope in Cutting Slope in Filling 1 Clayey Soil 1.5 : 1 2 : 1 2 Sandy Soil 3 : 1 4 : 1 3 Loamy Soil 1.5 : 1 2 : 1 4 Gravel Soil 0.75 : 1 1.25 : 1 5 Hard Rock 0.25 : 1 ---- 6 Soft Rock 0.5 : 1 ----
  • 21. Berm  Berm is the horizontal distance left at ground level between the toe of the bank and the top edge of cutting. 21  Purposes of Berms ❖ They give additional strength to the banks and provide protection against erosion and breaches. ❖ They provide a scope for future widening of the canal.
  • 22. Freeboard ❖ The margin between FSL and bank level is known as freeboard. ❖ The amount of freeboard depends upon the discharge of the channel. ❖ Recommended minimum freeboard = 0.5 m 22
  • 23. Bank  The primary purpose of banks is to retain water.  This can be used as means of communication and as inspection paths. 23
  • 24. Service Road  These are provided on canals for inspection purposes, and may simultaneously serve as the means of communication in remote areas. Dowla: As a measure of safety in driving, dowlas with side slopes of 1.5: 1 to 2:1, are provided along the banks. 24
  • 25. Back Berm or Counter Berm  Even after providing sufficient section for bank embankment, the saturation gradient line may cut the downstream end of the bank.  In such a case, the saturation line can be kept covered at least by 0.5 m with the help of counter berms as shown in figure below. 25
  • 26. Spoil Bank  When the earthwork in excavation exceeds earthworks in filling, the extra earth has to be disposed of economically.  Economical mode of its disposal may be collecting this soil on the edge of the bank embankment itself. 26
  • 27. Borrow Pit  When earthwork in filling exceeds the earthwork in excavation, the earth has to be brought from somewhere.  The pits, which are dug for bringing earth, are known as borrow pits.  If such pits are excavated outside the channel, they are known as external borrow pits, and if they are excavated somewhere within the channel, they are known as internal borrow pits.  Internal borrow pits are more preferred than external one. 27  The inside borrow pit may be located at the center of canal.  The idea behind this is that the borrow pits will act as water pockets where the silt will be deposited and ultimately the canal bed will get levelled up.
  • 28. Balancing Depth 28  A canal section will be economical when earth work involved at a particular section has an equal amount of cut and fill. Usually a canal section has a part in cutting and part in filling as shown in fig.  If the amount of cut is equal to the amount of fill, it has to be paid for once only. Definition  For a given C/S there is always only one depth of cutting for which the cutting and filling will be equal. The depth is known as balancing depth.
  • 29. If h = vertical height of top of bank from the bed of canal. b = bed width of the channel. t = top width of the canal bank. n:1 = side slope of bank in filling. z:1 = side slope of canal in cutting. d = full supply depth of canal. y = depth of cutting. Area of the cut = by + zy2 = y(b + zy) Area of fill = 2[(h – y)t + n(h-y)2] Balancing Depth Equating the area of cut and fill: y(b + z y) = 2[(h – y)t + n(h-y)2 ] b y+ zy2 = 2th + 2nh2 – 2nhy – 2ty – 2nhy + 2ny2 y2 (2n – z) – (b + 4nh + 2t)y + 2h(t + nh) =0 From this equation the balancing depth of the canal may be determined. A canal is usually constructed with side slope of 1:1 in cutting and a slope 1.5:1 in filling. Putting n = 1.5 and z =1 in above equation. We get; y2 – (b/2 + 3h + t)y + h (t + 3/2 h)=0
  • 30. Example  Calculate the balancing depth for a channel section having a bed width equal to 18 m and side slopes of 1:1 in cutting and 2:1 in filling. The bank embankments are kept 3.0 m higher than the ground level (berm level) and crest width of banks is kept as 2.0 m. Solution: Let d be the balancing depth, i.e. the depth for which excavation and filling becomes equal. 30
  • 31. Example (Contd.) Area of cutting = (18 + d) d m2 Area of filling = 2(2+14)/2×3 = 48 m2 Equating cutting and filling, we get (18 + d) d = 48 or, d2 + 18d – 48 = 0 or, d = 2.35 m (neglecting –ve sign), Balancing depth = 2.35 m 31
  • 32. Canal Lining and its Advantages ➢ It is the treatment given to the canal bed and banks to make the canal section impervious. ➢ Water Conservation: Lining a canal results in reduction in water losses, as water losses in unlined irrigation canals can be high. ➢ No seepage of water into adjacent land or roads: If canal banks are highly permeable, the seepage of water will cause very wet or waterlogged conditions, or even standing water on adjacent fields or roads. Lining of such a canal can solve this problem. ➢ Reduced canal dimensions: The resistance to flow of a lined canal is less than that of an unlined canal, and thus the flow velocity will be higher in the lined canal . Therefore, with the higher velocity, the canal cross-section for a lined canal can be smaller than that of an unlined canal. ➢ Reduced maintenance: Maintenance costs for the following issues are eliminated using lining of canals. ❖ Periodical removal of silt deposited on the beds and sides of canals. ❖ Removal of weeds and water canals. ❖ Minor repairs like plugging of cracks, uneven settlements of banks, etc. 32
  • 33. Types of lining Hard Surface Lining Cast Insitu Cement Concrete Lining Shotcrete or Plastic Lining Cement Concrete Tile Lining or Brick Lining Asphaltic Concrete Lining Boulder Lining Earth Type Lining Compacted Earth Lining Soil Cement Lining 33
  • 34. Cast In-situ Cement Concrete Lining
  • 38. Canal Lining Brick canal lining PREFABRICATED CHANNEL SECTION
  • 39. Disadvantages  Higher initial investment  Repair is costly  Shifting of outlet is costly because it involve dismantling and relaying of lining.  Longer construction period  Sophisticated construction equipment and labor is needed.
  • 40. 40