Building a swimming pool T a s k Worker Category Person D a y s # of Workers Elapsed Time (days) Materials ($) Excavate Machine Operator 6 2 0 1,500.00 Frame the walls Masons 8 4 0 800.00 Install Internal Plumbing Plumber 4 2 0 700.00 Install Electricity Electrician 2 2 0 500.00 Pour concrete Masons 4 2 4 2,000.00 Install pump and filter Plumber 1 1 0 3,000.00 Total 8,500.00 Category Wage Rate $/Day Electrician 200.00 Mason 160.00 Machine Operator 120.00 P lumb er 200.00 Create a Gantt chart from the work breakdown structure. Create a PERT/CPM network showing the interdependencies of the different activ ities. How long will the project take? (Note:Don’t forget to take “elapsed time” into account.) Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project. Following are cost and schedule data for aproject that is underway. Project Cost Data Month Planned Actual 1 30 12 2 35 23 3 42 55 4 46 55 5 40 53 6 52 60 7 45 75 8 48 80 9 50 10 40 11 30 12 15 Project Schedule Data Task Planned Starting Month Planned Duration (months) A c t u al starting month Actual Duration (mths) A 1 2 2 3 B 2 3 3 5 C 4 3 6 3 so far D 6 5 7 2 so far E 8 4 Not yet begun F 10 3 Not yet begun Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance Summarize in words what you see project status tobeatthis time. Whatdo you predict regarding thefinal costandfinal schedule for the project? .