Mr. Michail Baroutzoglou is an experienced civil engineer from Greece with over 20 years of experience managing highway and infrastructure construction projects. He has worked on projects ranging from €2 million to €147.6 million in budget. His experience includes roles as an assistant site manager, construction manager, resident engineer, and project manager on highways, bridges, and other civil engineering projects. He has extensive experience supervising all aspects of construction projects including scheduling, procurement, budgeting, and ensuring safety and quality standards.
1. Experienced Civil Engineer
Personal information
First name / Surname Mr MICHAIL BAROUTZOGLOU
Address ALEXANDROU MICHAILIDI 1, THESSALONIKI, 54640, GREECE
Telephone +306937225373
E-mail mbaroutzoglou@hotmail.com
Nationality GREEK
Date of birth 18/11/1976
Marital status Married with 2 children
Work experience
Assistant Site/Project Manager
at AKTOR S.A.
June 2015 – today
Assistant Site Manager at JV
IONIOS S.A. - AKTOR S.A.
June 2014 – June 2015
Construction of: “Egnatia Odos S.A. Vertical Axes 60: Thessaloniki – Bulgarian
border”, Contractor: JV TERNA SA – AEGEK CONSTRUCTIONS SA, Budget:
€147,6M (AKTOR SA is constructing AEGEK CONSTRUCTION SA share, of
approx. €75,0M, as a sub-contractor)
Manage and oversee: procurements, orders and invoices for all materials, sub-
contractors' activities (contracts, payments, daily progress), project personnel,
mechanical equipment’s usage, progress of works on daily basis, compliance
with time and budget schedule, review and approve contractors payment
requests. Produce budget, cost and progress reports and estimates. Planning
and scheduling works. Liaise with designers, local authorities and Managing
Authority.
Civil Engineer (Self-employed)
July 2012 – May 2014
Design of a new section at an existing Rehabilitation Center in Kato Scholari,
Thessaloniki, Greece (approx. 6.000m2).
Assisted in the implementation of the designs needed to receive all the
necessary permits from the urban planning department and designed the 3D
model of the project.
Assistant Site Manager and
Quantity Surveyor at PHILIPPOS
S.A.
Oct. 2010 – July 2012
Construction of: “Serres – Amphipoli Road Axes”, Contractor: PHILIPPOS S.A.,
Budget: € 37,5M
Managed a construction site with a labor force of approx. 50 people, by
directing, coordinating and supervising day-to-day activities of all road
construction works, including earthworks (reinforced embankments), concrete
structures (post and pre - tensioned bridges and overpasses, underpasses,
bored piles, retaining walls, culverts), drainage utilities works, pavement and
asphalt works and oversaw the incorporation of materials and implementation of
all designs, in addition managed and assisted the quantity surveying team for
delivering measurement of quantities and payment statements to the
construction management agency, supervised and monitored subcontractors
and liaised with consultants, designers and local authorities to overcome
problems which arisen during construction. Produce budget, cost and progress
reports and estimates.
Civil Engineer - Project
Manager Consultant at
Egnatia Odos S.A.
Apr.2009 - Sep. 2010
Prepared standard tender documents.
Reviewed Summary Table of Works.
Reviewed claims and disputes.
Estimated budgets for new project
Monitored contracts’ terms and conditions, (similar to FIDIC conditions of
contract)
Reviewed approvals for design modifications.
Reviewed monthly progress reports submitted by the CM Regional Office
Prepared proposals, resolving problems on current projects, for the Board of
Directors.
2. Assistant Resident Engineer -
Construction Manager
Consultant at
Egnatia Odos S.A.
Oct. 2007 - May 2009
Construction of Egnatia Odos Motorway: «Section Strymonas – Peramos: From the
exit of Symbolo tunnel to Agios Andreas Interchange», Contract No.1123,
Contractor: PHILIPPOS S.A. Budget: € 34,8M
Led a team of civil engineers, and other engineering disciplines which day-to-
day supervised all highway construction works including earthworks (reinforced
embankment, rock cuts), concrete structures (post and pre - tensioned bridges
and overpasses, underpasses, retaining walls, culverts), drainage utilities
works, pavement and asphalt works, signage and safety works assuring all
structures were completed according to designs and all incorporated materials
met specifications. Checked Contractor’s payment statements, measurement of
quantities and timetables and delivered monthly progress reports and
measurements of quantities to the Senior Resident Engineer. Ensured the
Contractor carried out the Contract work in a safe manner and in compliance
with the Contract’s obligations (similar to FIDIC conditions of contract).
Resident Technical Officer
(Civil Engineer) - Construction
Manager Consultant at
Egnatia Odos S.A.
May 2006 - May 2009
Construction of the following sections of Egnatia Odos Motorway:
Strymonas – Peramos: From Strymonas Interchange to Moustheni Interchange,
Contract No.1117, Contractor: J&P AVAX S.A. Budget: € 106,0M
Strymonas – Peramos: From Moustheni Interchange to the exit of Symbolo
tunnel, Contract No.1118, Contractor: J&P AVAX S.A. Budget: € 104,5M
Sep. 2005 - Nov. 2006 Section: a) From Chrysoupolis Interchange to the crossover with the national
road west of Nestos river including Nestos tunnel b)From the exit of Nestos
tunnel to Vaniano Interchange, Contract No.966, Contractor: ATTI-KAT S.A.
Budget: € 80,0M
Supervised all highway construction works including earthworks, concrete
structures (post and pre - tensioned bridges and overpasses, underpasses,
culverts, bored piles, retaining walls), drainage, pavement, asphaltic, signage
and safety works, assuring all structures were completed according to designs
and all incorporated materials met specifications. In addition I was responsible
to check Contractor’s payment statements, measurement of quantities and
timetables and delivered monthly progress reports and measurements of
quantities to the Senior Resident Engineer. Ensured the Contractor carried out
the Contract work in a safe manner and in compliance with the Contract’s
obligations (similar to FIDIC conditions of contract).
Construction Engineer (self-
employed)
Oct. 2001 - Jan. 2002 and Mar.
2003 - 2009
Supervision and consultancy services at private constructions:
Main projects:
Construction of Rehabilitation Centre approx. 7.000m2 in Kato Scholari -
Thessaloniki, Greece, Contractor: ARMONIA S.A, Budget: € 5,0M
Construction of a complex of 42 two-story residences, approx. 6.000m2 in
Retziki-Thessaloniki, Greece, Contractor: George Kaplanidis, Budget: € 4,5M
Construction of a complex of 9 three-story residences, approx. 2.000m2 in
Panorama-Thessaloniki, Greece, Contractor: Anastasios Konstantinidis, Budget:
€ 2,0M
Supervised all structural works (reinforced concrete)
Implemented the designs of structural works on site
Prepared measurements of quantities
Military Service at Hellenic
Army
Jan. 2002 - Mar. 2003
Fulfilment of the military service as a reservists petty in the Engineer Corps.
Supervision and consultancy services for the construction of service roads in the
premises of various military camps.
3. Education
Aristotle University of
Thessaloniki
1994 - 2001
Diploma of Civil Engineer
Grade:7/10
American College of
Thessaloniki «Anatolia»
1988 - 1994
High school
Grade:18/20
Certifications and
Organizations
Contractor's Experience
Registry
2007
Class B for hydraulic and road construction projects and Class A for civil
engineering, harbor and energy projects.
Technical Chamber of Greece
2001
Member since 2001 (License to practice Civil Engineering)
Personal skills and
competences
Diligent, Conscientious, Creative, Punctilious, Ambitious
Adaptive to new situations
Quick learner
Decision maker
Languages Greek (mother tongue), English
Technical skills and
competence
Organising daily schedules for construction sites
Supervising and managing the construction of civil infrastructure (mainly
highways) and assuring safety on site
Supervising concrete constructions (post and pre - tensioned bridges and
overpasses, underpasses, bored piles, retaining walls, culverts)
Liaising with consultants, local authorities and designers to overcome
difficulties at the construction
Value Engineering
Procurement management
Financial management of all construction activities (subcontractors,
materials, suppliers, personnel)
Planning - scheduling
Budget, cost and progress reports and estimates.
Preparing tender documents, budgets and Bill of Quantities
Prepare payment statements and price revisions
Pre/post tender Quantity Surveying
Monitoring Contracts terms and conditions
Claims Management
Greek legislation for public works
FIDIC Silver & Yellow Book
Computer skills and
competences
MS Office (Word, Excel, PowerPoint)
AutoCAD – Civil 3D
Anadelta Tessera
MS Project
Primavera (beginner)
Seminars/Congresses Structured training programme: “The FIDIC design-build contracts: practical
use of the Yellow and Silver Books” (May 2013, Athens)
Pre-congress gala for HELECO 2011 (Waste Disposal) at the Technical
Chamber of Greece - Central Macedonia Department
15th National Concrete Congress (Alexandroupoli 2006, Greece)
Additional information References provided if required