SlideShare a Scribd company logo
1 of 28
Pipe Network Distribution
Md. Mehedi Hassan Masum
Lecturer
Department of Civil Engineering
Port City International University
Department of CEN, PCIU
Department of CE, CUET2
Introduction Result & Discussion Conclusion
Analysis of pipe Network
The following are the most common methods used to analyze the
Grid-system networks:
1.Hardy Cross method.
2.Computer programs (WaterCAD, Epanet, WaterGEMs etc.)
Department of CE, CUET3
Introduction Result & Discussion Conclusion
Hardy Cross Method
Assumptions
1. Water is withdrawn from nodes only, not directly from
pipes.
2. The discharge entering the system will have (+) value, and
the discharge leaving the system will have (-) value.
3. Usually neglect minor losses.
4. Assume flows for each individual pipe in the network.
5. At any junction (node) discharge input is equal to output.
6. Around any loop in the grid, the sum of head losses must
equal to zero
Department of CE, CUET4
Introduction Result & Discussion Conclusion
Hardy Cross Method
Steps
1. Assume values of Q to satisfy 𝑄 = 0.
2. Calculate 𝐻𝑓 from Q using ℎ 𝑓 = 𝐾1 𝑄2
.
3. If ℎ 𝑓 = 0, then the solution is correct.
4. If ℎ 𝑓 ≠ 0, then apply a correction factor, ∆𝑄, to all
Q and repeat from step (2).
5. For practical purposes, the calculation is usually
terminated when ℎ 𝑓< 0.01 m or ∆𝑄 < 1 L/s.
Department of CE, CUET5
Introduction Result & Discussion Conclusion
Hardy Cross Method
Steps
A reasonably efficient value of ∆𝑄 for rapid convergence is
given by;
∆𝑄 = −
𝐻𝐿
2
𝐻𝐿
𝑄
N.B. Head loss can be calculated using the Darcy-Weisbach
equation
ℎ 𝑓 = 𝜆
𝐿
𝐷
𝑉2
2𝑔
= 𝜆
𝐿
𝐷
𝑄2
2𝑔𝐴2
= 𝐾1 𝑄2
Department of CE, CUET6
Introduction Result & Discussion Conclusion
Computer Programs
𝐸𝑃𝐴𝑁𝐸𝑇 𝑊𝑎𝑡𝑒𝑟𝐺𝐸𝑀
Department of CE, CUET7
Introduction Result & Discussion Conclusion
Pipe Network System
𝐶𝑉
𝑆𝐶
𝐵
𝑆𝑀
𝑀
M : Mains
SM : Sub Main
B : Branch
SC :Service Connection
CV :CUTOFF Valve
Department of CE, CUET8
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
Department of CE, CUET9
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 02: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
Department of CE, CUET10
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
𝑊𝑇 − 1𝑊𝑇 − 2
Department of CE, CUET11
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 1)
Department of CE, CUET12
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 2)
Department of CE, CUET13
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
Department of CE, CUET14
Introduction Result & Discussion Conclusion
Initial Assumptions
47.12 𝑙/𝑠𝑒𝑐
20𝑙/𝑠𝑒𝑐
10 𝑙/𝑠𝑒𝑐
10𝑙/𝑠𝑒𝑐
10 𝑙/𝑠𝑒𝑐
20 𝑙/𝑠𝑒𝑐
𝐴 𝐵
𝐶
𝐷
Department of CE, CUET15
Pipe name Dia (m)
Length
(m)
hf (m) Q (L/sec) hf/Q
AB 0.15 219.512 0.305773 -10 -30.5773
BC 0.2 60.98 0.08063 -20 -4.03149
CD 0.2 219.51 0.533681 27.12 19.67849
DA 0.15 115.85 0.161375 10 16.13754
Sum 1.081459 1.207208
First Trial
= -0.44792
Introduction Result & Discussion Conclusion
Department of CE, CUET16
Pipe name Dia (m)
Length
(m)
hf (m) Q (L/sec) hf/Q
AB 0.15 219.512 0.23807 -8.82374 -26.9806
BC 0.2 60.98 0.070918 -18.7568 -3.78089
CD 0.2 219.51 0.58373 28.36318 20.58055
DA 0.15 115.85 0.203993 11.24318 18.14373
Sum 1.096711 7.962748
First Trial
= -0.06887
Introduction Result & Discussion Conclusion
Department of CE, CUET17
Introduction Result & Discussion Conclusion
Final Discharge
47.12 𝑙/𝑠𝑒𝑐
18.76𝑙/𝑠𝑒𝑐
8.82 𝑙/𝑠𝑒𝑐
11.24𝑙/𝑠𝑒𝑐
9.94 𝑙/𝑠𝑒𝑐
20.06 𝑙/𝑠𝑒𝑐
𝐴 𝐵
𝐶
𝐷
Sewer Network Distribution
Department of CE, CUET
Md. Mehedi Hassan Masum
Lecturer
Department of Civil Engineering
Port City International University
Department of CE, CUET19
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
Department of CE, CUET20
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
Department of CE, CUET21
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 1)
Department of CE, CUET22
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 2)
Department of CE, CUET23
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
Department of CE, CUET24
Introduction Result & Discussion Conclusion
Pipe
Sub-
Area
Population
Per capita
consumpti
on (lpcd)
Water
Demand
(m3/day)
Peak
factor
% of
wastewater
Total
wastewater
(m3/day)
P1
A1 432 135 58.32 2.50 70 102.06
A2 768 135 103.68 2.50 70 181.44
A9 384 135 51.84 3.00 90 139.97
P2
A3 768 135 103.68 2.50 70 181.44
A4 768 135 103.68 2.50 70 181.44
P3
A5 1152 135 155.52 2.50 70 272.16
A6 1152 135 155.52 2.50 70 272.16
A7 1152 135 155.52 2.50 70 272.16
A8 300 100 30.00 3.00 90 81.00
Total 917.76 23.50 1683.83
Table: Wastewater Generation from household
Department of CE, CUET25
Introduction Result & Discussion Conclusion
Table: Wastewater Generation from household
Pipe Sub-Area Area (sq.m) Area (ha)
Peak
infiltration
factor
(m3/ha-day)
Infiltration , I
(m3/day)
P1
A1 7432.2400 0.7432
8.7500 22.6962
A2 7618.0460 0.7618
A9 10888.2316 1.0888
P2
A3 7543.7236 0.7544
8.7500 13.1690
A4 7506.5624 0.7507
P3
A5 7580.8848 0.7581
8.7500 24.8097
A6 7618.0460 0.7618
A7 7432.2400 0.7432
A8 5722.8248 0.5723
Total 69342.7992 6.9343 60.6749
Department of CE, CUET26
Introduction Result & Discussion Conclusion
Total Wastewater Generation
Total wastewater generation =
1683.73+60.6749 = 1744.59 𝑚3/𝑑𝑎𝑦
Department of CE, CUET27
Department of CE, CUET28

More Related Content

What's hot

Intake structures
Intake structures Intake structures
Intake structures Sachin PatiL
 
Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineeringNagma Modi
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage systemManoj Mota
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn designManoj Mota
 
(Part ii)- open channels
(Part ii)- open channels(Part ii)- open channels
(Part ii)- open channelsMohsin Siddique
 
04 pipeline-channel hydraulics
04 pipeline-channel hydraulics04 pipeline-channel hydraulics
04 pipeline-channel hydraulicsAkepati S. Reddy
 
Hardy cross method of pipe network analysis
Hardy cross method of pipe network analysisHardy cross method of pipe network analysis
Hardy cross method of pipe network analysissidrarashiddar
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationVijay Kumar
 
design and analysis of water distribution System
design and analysis of water distribution Systemdesign and analysis of water distribution System
design and analysis of water distribution SystemMian Umair Afzal
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeRajdip Bhdaraka
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrographSatish Taji
 

What's hot (20)

SEWER DESIGN:
SEWER DESIGN:SEWER DESIGN:
SEWER DESIGN:
 
Intake structures
Intake structures Intake structures
Intake structures
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Hardycross method
Hardycross methodHardycross method
Hardycross method
 
Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineering
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage system
 
Application of softwares in wdn design
Application of softwares in wdn designApplication of softwares in wdn design
Application of softwares in wdn design
 
Fluid discharge
Fluid dischargeFluid discharge
Fluid discharge
 
(Part ii)- open channels
(Part ii)- open channels(Part ii)- open channels
(Part ii)- open channels
 
04 pipeline-channel hydraulics
04 pipeline-channel hydraulics04 pipeline-channel hydraulics
04 pipeline-channel hydraulics
 
Hardy cross method of pipe network analysis
Hardy cross method of pipe network analysisHardy cross method of pipe network analysis
Hardy cross method of pipe network analysis
 
Open channels
Open channelsOpen channels
Open channels
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimation
 
design and analysis of water distribution System
design and analysis of water distribution Systemdesign and analysis of water distribution System
design and analysis of water distribution System
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
ogee design
ogee designogee design
ogee design
 
Water treatment
Water treatmentWater treatment
Water treatment
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
Chapter 7 gvf
Chapter 7 gvfChapter 7 gvf
Chapter 7 gvf
 

Similar to L 5 pipe_network_analysis

Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of  MOC and Lax FDE for simulating transients in Pipe FlowsComparison of  MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of MOC and Lax FDE for simulating transients in Pipe FlowsIRJET Journal
 
A suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks designA suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks designMedhat Elzahar
 
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...IAEME Publication
 
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...Naimesh Rama
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfsauravdesignnedits
 
L 7 plumbing_design
L 7 plumbing_designL 7 plumbing_design
L 7 plumbing_designMEHEDIMASUM2
 
SEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdfSEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdfgopalkumar91649
 
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...IOSR Journals
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...Hossam Shafiq I
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...nooriasukmaningtyas
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...IJEECSIAES
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...IAEME Publication
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...IAEME Publication
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...IAEME Publication
 
Design of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the MicrocontrollerDesign of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the MicrocontrollerNooria Sukmaningtyas
 
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...AnweshBussa
 
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...Hossam Shafiq I
 

Similar to L 5 pipe_network_analysis (20)

L 6 sewer_design
L 6 sewer_designL 6 sewer_design
L 6 sewer_design
 
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of  MOC and Lax FDE for simulating transients in Pipe FlowsComparison of  MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
 
A suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks designA suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks design
 
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
 
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdf
 
L 7 plumbing_design
L 7 plumbing_designL 7 plumbing_design
L 7 plumbing_design
 
SEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdfSEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdf
 
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Design of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the MicrocontrollerDesign of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the Microcontroller
 
Load flow studies
Load flow studiesLoad flow studies
Load flow studies
 
report.pdf
report.pdfreport.pdf
report.pdf
 
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
 
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
 

More from MEHEDIMASUM2

L 2 wastewater_treatment
L 2 wastewater_treatmentL 2 wastewater_treatment
L 2 wastewater_treatmentMEHEDIMASUM2
 
L 1 organogram_demand calculation
L 1 organogram_demand calculationL 1 organogram_demand calculation
L 1 organogram_demand calculationMEHEDIMASUM2
 
L6 infiltrationr rate calculation
L6 infiltrationr rate calculationL6 infiltrationr rate calculation
L6 infiltrationr rate calculationMEHEDIMASUM2
 
L8 unit hydrograph
L8 unit hydrographL8 unit hydrograph
L8 unit hydrographMEHEDIMASUM2
 

More from MEHEDIMASUM2 (13)

L 4 pump_capacity
L 4 pump_capacityL 4 pump_capacity
L 4 pump_capacity
 
L 2 wastewater_treatment
L 2 wastewater_treatmentL 2 wastewater_treatment
L 2 wastewater_treatment
 
L 1 organogram_demand calculation
L 1 organogram_demand calculationL 1 organogram_demand calculation
L 1 organogram_demand calculation
 
L 8 septic_tank
L 8 septic_tankL 8 septic_tank
L 8 septic_tank
 
L 3 well_design
L 3 well_designL 3 well_design
L 3 well_design
 
L6 infiltrationr rate calculation
L6 infiltrationr rate calculationL6 infiltrationr rate calculation
L6 infiltrationr rate calculation
 
L5 infiltration
L5 infiltrationL5 infiltration
L5 infiltration
 
L3 evaporation
L3 evaporationL3 evaporation
L3 evaporation
 
L2 precipitation
L2 precipitationL2 precipitation
L2 precipitation
 
L4 stream flow
L4 stream flowL4 stream flow
L4 stream flow
 
L8 unit hydrograph
L8 unit hydrographL8 unit hydrograph
L8 unit hydrograph
 
L7 hydrograph
L7 hydrographL7 hydrograph
L7 hydrograph
 
L1 introduction
L1 introductionL1 introduction
L1 introduction
 

Recently uploaded

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 

Recently uploaded (20)

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 

L 5 pipe_network_analysis

  • 1. Pipe Network Distribution Md. Mehedi Hassan Masum Lecturer Department of Civil Engineering Port City International University Department of CEN, PCIU
  • 2. Department of CE, CUET2 Introduction Result & Discussion Conclusion Analysis of pipe Network The following are the most common methods used to analyze the Grid-system networks: 1.Hardy Cross method. 2.Computer programs (WaterCAD, Epanet, WaterGEMs etc.)
  • 3. Department of CE, CUET3 Introduction Result & Discussion Conclusion Hardy Cross Method Assumptions 1. Water is withdrawn from nodes only, not directly from pipes. 2. The discharge entering the system will have (+) value, and the discharge leaving the system will have (-) value. 3. Usually neglect minor losses. 4. Assume flows for each individual pipe in the network. 5. At any junction (node) discharge input is equal to output. 6. Around any loop in the grid, the sum of head losses must equal to zero
  • 4. Department of CE, CUET4 Introduction Result & Discussion Conclusion Hardy Cross Method Steps 1. Assume values of Q to satisfy 𝑄 = 0. 2. Calculate 𝐻𝑓 from Q using ℎ 𝑓 = 𝐾1 𝑄2 . 3. If ℎ 𝑓 = 0, then the solution is correct. 4. If ℎ 𝑓 ≠ 0, then apply a correction factor, ∆𝑄, to all Q and repeat from step (2). 5. For practical purposes, the calculation is usually terminated when ℎ 𝑓< 0.01 m or ∆𝑄 < 1 L/s.
  • 5. Department of CE, CUET5 Introduction Result & Discussion Conclusion Hardy Cross Method Steps A reasonably efficient value of ∆𝑄 for rapid convergence is given by; ∆𝑄 = − 𝐻𝐿 2 𝐻𝐿 𝑄 N.B. Head loss can be calculated using the Darcy-Weisbach equation ℎ 𝑓 = 𝜆 𝐿 𝐷 𝑉2 2𝑔 = 𝜆 𝐿 𝐷 𝑄2 2𝑔𝐴2 = 𝐾1 𝑄2
  • 6. Department of CE, CUET6 Introduction Result & Discussion Conclusion Computer Programs 𝐸𝑃𝐴𝑁𝐸𝑇 𝑊𝑎𝑡𝑒𝑟𝐺𝐸𝑀
  • 7. Department of CE, CUET7 Introduction Result & Discussion Conclusion Pipe Network System 𝐶𝑉 𝑆𝐶 𝐵 𝑆𝑀 𝑀 M : Mains SM : Sub Main B : Branch SC :Service Connection CV :CUTOFF Valve
  • 8. Department of CE, CUET8 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
  • 9. Department of CE, CUET9 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 02: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
  • 10. Department of CE, CUET10 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 𝑊𝑇 − 1𝑊𝑇 − 2
  • 11. Department of CE, CUET11 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 1)
  • 12. Department of CE, CUET12 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 2)
  • 13. Department of CE, CUET13 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
  • 14. Department of CE, CUET14 Introduction Result & Discussion Conclusion Initial Assumptions 47.12 𝑙/𝑠𝑒𝑐 20𝑙/𝑠𝑒𝑐 10 𝑙/𝑠𝑒𝑐 10𝑙/𝑠𝑒𝑐 10 𝑙/𝑠𝑒𝑐 20 𝑙/𝑠𝑒𝑐 𝐴 𝐵 𝐶 𝐷
  • 15. Department of CE, CUET15 Pipe name Dia (m) Length (m) hf (m) Q (L/sec) hf/Q AB 0.15 219.512 0.305773 -10 -30.5773 BC 0.2 60.98 0.08063 -20 -4.03149 CD 0.2 219.51 0.533681 27.12 19.67849 DA 0.15 115.85 0.161375 10 16.13754 Sum 1.081459 1.207208 First Trial = -0.44792 Introduction Result & Discussion Conclusion
  • 16. Department of CE, CUET16 Pipe name Dia (m) Length (m) hf (m) Q (L/sec) hf/Q AB 0.15 219.512 0.23807 -8.82374 -26.9806 BC 0.2 60.98 0.070918 -18.7568 -3.78089 CD 0.2 219.51 0.58373 28.36318 20.58055 DA 0.15 115.85 0.203993 11.24318 18.14373 Sum 1.096711 7.962748 First Trial = -0.06887 Introduction Result & Discussion Conclusion
  • 17. Department of CE, CUET17 Introduction Result & Discussion Conclusion Final Discharge 47.12 𝑙/𝑠𝑒𝑐 18.76𝑙/𝑠𝑒𝑐 8.82 𝑙/𝑠𝑒𝑐 11.24𝑙/𝑠𝑒𝑐 9.94 𝑙/𝑠𝑒𝑐 20.06 𝑙/𝑠𝑒𝑐 𝐴 𝐵 𝐶 𝐷
  • 18. Sewer Network Distribution Department of CE, CUET Md. Mehedi Hassan Masum Lecturer Department of Civil Engineering Port City International University
  • 19. Department of CE, CUET19 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
  • 20. Department of CE, CUET20 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
  • 21. Department of CE, CUET21 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 1)
  • 22. Department of CE, CUET22 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 2)
  • 23. Department of CE, CUET23 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
  • 24. Department of CE, CUET24 Introduction Result & Discussion Conclusion Pipe Sub- Area Population Per capita consumpti on (lpcd) Water Demand (m3/day) Peak factor % of wastewater Total wastewater (m3/day) P1 A1 432 135 58.32 2.50 70 102.06 A2 768 135 103.68 2.50 70 181.44 A9 384 135 51.84 3.00 90 139.97 P2 A3 768 135 103.68 2.50 70 181.44 A4 768 135 103.68 2.50 70 181.44 P3 A5 1152 135 155.52 2.50 70 272.16 A6 1152 135 155.52 2.50 70 272.16 A7 1152 135 155.52 2.50 70 272.16 A8 300 100 30.00 3.00 90 81.00 Total 917.76 23.50 1683.83 Table: Wastewater Generation from household
  • 25. Department of CE, CUET25 Introduction Result & Discussion Conclusion Table: Wastewater Generation from household Pipe Sub-Area Area (sq.m) Area (ha) Peak infiltration factor (m3/ha-day) Infiltration , I (m3/day) P1 A1 7432.2400 0.7432 8.7500 22.6962 A2 7618.0460 0.7618 A9 10888.2316 1.0888 P2 A3 7543.7236 0.7544 8.7500 13.1690 A4 7506.5624 0.7507 P3 A5 7580.8848 0.7581 8.7500 24.8097 A6 7618.0460 0.7618 A7 7432.2400 0.7432 A8 5722.8248 0.5723 Total 69342.7992 6.9343 60.6749
  • 26. Department of CE, CUET26 Introduction Result & Discussion Conclusion Total Wastewater Generation Total wastewater generation = 1683.73+60.6749 = 1744.59 𝑚3/𝑑𝑎𝑦