• Cooling systems :
1- Air
2- Oil
• Air use in Dry Transformer
• Disadvantage :
1- Not allowed to download transformers except
for a small period of time
2
- Low durability insulation
3
- The windings effect Dust and dirt
4
- Increasing the size of the windings to
follow the air
• Oil filled transformer in power Tr:
• The basic elements:
1-Oil
2- Radiators
3-Fans
4-Pumps
5-Cooling pipes
• Transformer Oil :
• Function:
• 1- Cooling
• 2- Insulation
• The Properties Transformer Oil:
1-Dielectric strength
2-Viscoisty
3-Flash Point(145 c)
4-denisty (.88/cm3 at 15 c),the efficiency of
transfer the temperature about 21 times
of Air
•Radiators:
•Fans:
• Increase the efficiency of cooling
( Forced Circulation)
Note:
1- Small Fans put in the front the Radiators
cause Vibration
2- Large Fans put Under the Radiators
• Cooling Class :
• The Characterization IEC:
1 2 3 4
internal
cooling
type
Circulation
type
External
cooling
type
Circulation
type
O N A N
Oil Natural Air Natural
•ONAN:
• Use in Small Transformer
• Advantages :
1-Simple
2-low cost
3-High Reliability
4-low noise
Disadvantages:
1-Large Radiators and high cost
2- Limited in small transformer
•ONAF:
• Use in High power Tr
• Use two fans groups and work automatic
• Distribution fans regularly
•OFAF :
ODAF:
•Multi-stage cooling:
• Change in rating value with Cooling
• What's the meaning :
ONAN/OFAF/OFAF cooling class
transformer with”45/60/75 MVA
continuous at 65 c Temperature rise:
Inactive parts auxiliary parts
• Functions of transformer oil :
1- Cooling
2- Insulation between the windings and
core and tank
• Breakdown voltage for Air up to 30kv/cm
• Breakdown voltage for Oil up to 80kv/cm
3
- Covers all metal parts to prevent
oxidation where effect on conductor
condictivity
4
- Identifies many of the faults (take sample
of the oil )
• Tank :
Types :
1-plain tank in small power Tr under 50 KVA
2-Tubed tank in medium power Tr
3-Tank with Radiators in High power Tr
• Function of Tank :
1. core and windings protection
2. Carry conductors out lines
3. Keep up transformer oil
4. Carry Radiators tubes
• Explosion vet
• Conservator Tank :
 Absorption any Expansion or contraction in
oil
 Increase oil to main tank
 The volume of Conservator Tank about 1/10
to main transformer
 At full load increase oil volume about 8%
therefore hieght oil about 30% of Conservator
Tank hieght
 increase Conservator Tank (oil level tube)
to show oil vapor color :
White Burn in insulation paper
Yellow Burn in insulation fibber and wood
Black
decomposition and burn
Oil
• Bochholz Relay:
• Breather unit :
 Contain on silica gel: crystalline salt
absorb moisture in air during entry to the
transformer
Silica gel colors:
•
color Case
Blue normal
Wardy Moisture saturation and must
change or drying in furnace
(150:200 c)
White Moisture saturation and must
change
Black Oil saturation and must change
• Oil protection system :
 The sealing in small transformer:
1- by conservator tank
2- Nitrogen-positive pressure :
- Use compressed Nitrogen about 10%
above oil in main tank
• Tap Changer :
• Tap Changer Values:
•The idea of Tap Changer :
• Example 2:
• Example 3:
• Comparison between on load and off load Tab
Changer:
On load Off load
Tr type Power Tr Distribution Tr
Points 17 point or more 3 or 5
Surrounded
condition
Cylinder filled oil Transformer oil
Change
method
Auto manual
Place Cylinder with
parallel with
coils
• HV and LV bushing (isolators) :
• Function of Skirts :
Using Corona Rings :
• Flange :
• Rod gap :
• Accessories :
1- Pressure Relief Valve:
2- Dial transformer capillary tube
3- Liquid Level Gauge:
• indicates the level of the insulating liquid in the
main transformer tank.
• The standard gage has a center marking
indicating the level at 25 C. Dial markings are
minimum -25 C - maximum.
4- Pressure-Vacuum Gauge:
• Gage readings vary with transformer temperature
changes and would normally indicate a positive
pressure.
• The gage may indicate a vacuum within the tank
when the transformer is de-energized or is
operating under light or no-load conditions in
allow ambient temperature.
• Any change in temperature indication of a leak in
the transformer seal and should be investigated
5- Oil temperature indicator :
6- Winding temperature indicator :
• K- Factor :
The ratio between the additional losses in
the energy of harmonics and eddy current
losses (4,7,13,20,30)
• K=4 (50 % non linear loads)
• K= 13 (100% non linear loads)
• Effect harmonics on connection of
windings :
• Flux on magnetizing current:
• Filter for preventing third harmonic:
• Relation between magnetizing current and
output voltage :
• Effect harmonics on Star connection
• Effect harmonics on Delta connection :
• Effect the earthing on transformer :
1- Ungrounded System:
Advantages :
1-Short circuit current very low
2- KVA SC during short very low (Short circuit level
)
Disadvantages :
1-S.c between phase and ground ,voltage increase
on other two phases
2-Short circuit current very low, protection device
not work
3-Arcing voltage occurs between phase and
ground during S.C
• Earthing System:
Solution problem Ungrounded System
• Connection methods :
1- Star Star: Y-Y
• Advantages :
1-Vp and Vs in phase where not phase
Displacement
2- low turns in phase Vp=57% of Vline
Disadvantages :
1- Vs is distorted wave
2-un balance load
3-third harmonic causes over voltage
4-
• Delta –Star :
•Advantages :
1- low current in each phase
2- third harmonic circulate in delta
3-earth fault current follow in Neutral for
star
4- Zero sequence current circulate in delta
• Delta-Delta:
•Advantages :
1-use in low voltage and high current where
Iph=57%of Iline sothat winding Tr is low in
cross section area and copper
2-third harmonic circulate in delta
Disadvantages :
1-Weak for mechanical stress and electrical
stress
2- Not neutral (N) ,if occurs fault increase
voltage on three phase
• Earthing faults in Delta-Delta connection :
• Interconnected star: (Zig Zag)
Rt
Zig Zag transformer in the earthling
• Delta-Zig Zag Connection:
• Example 1:
This number 925554 on transformer body:
Example 2 :
75554 or 025554
1 50 KVA
2 100
3 200
4 300
5 500
6 800
7 1000
8 1500
• What “s the meaning:
• BIL ( Basic impulse level :
Ability insulators inside Tr to increase in
voltage result surge or opening and
closing

More Related Content

Similar to power Tr 2 course.ppt

cooling systems of transformers
cooling systems of transformerscooling systems of transformers
cooling systems of transformersMalik Armughan
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Nageswar Rao
 
discription aboit vam and how it can works
discription aboit vam and how it  can worksdiscription aboit vam and how it  can works
discription aboit vam and how it can worksreader46
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitJimit Dhruv
 
PROTECTIVE DEVICES & MAINTENANCE.ppt
PROTECTIVE DEVICES & MAINTENANCE.pptPROTECTIVE DEVICES & MAINTENANCE.ppt
PROTECTIVE DEVICES & MAINTENANCE.pptQwer401863
 
High vacuum pump and sensors.ppt
High vacuum pump and sensors.pptHigh vacuum pump and sensors.ppt
High vacuum pump and sensors.pptFasial Ghazanfar
 
Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Nik Sharma
 
Vapour power cycles
Vapour power cyclesVapour power cycles
Vapour power cycleskrishna khot
 
Air Std Cycles.pptx
Air Std Cycles.pptxAir Std Cycles.pptx
Air Std Cycles.pptxdigitaladh
 
Transformer Protection
Transformer Protection Transformer Protection
Transformer Protection AniketAwate2
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfsuryanshsingh836763
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.Sheikh Nazmul Islam
 
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdfEthylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdfMeysamAmini4
 
Sample Question and answer for power plants
Sample Question and answer for power plantsSample Question and answer for power plants
Sample Question and answer for power plantsVikeshgond2
 

Similar to power Tr 2 course.ppt (20)

Vacumn new
Vacumn newVacumn new
Vacumn new
 
Vacuum
VacuumVacuum
Vacuum
 
cooling systems of transformers
cooling systems of transformerscooling systems of transformers
cooling systems of transformers
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
 
discription aboit vam and how it can works
discription aboit vam and how it  can worksdiscription aboit vam and how it  can works
discription aboit vam and how it can works
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
 
PROTECTIVE DEVICES & MAINTENANCE.ppt
PROTECTIVE DEVICES & MAINTENANCE.pptPROTECTIVE DEVICES & MAINTENANCE.ppt
PROTECTIVE DEVICES & MAINTENANCE.ppt
 
Oil production 2
Oil production 2Oil production 2
Oil production 2
 
High vacuum pump and sensors.ppt
High vacuum pump and sensors.pptHigh vacuum pump and sensors.ppt
High vacuum pump and sensors.ppt
 
Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE]
 
Turbo chargers
Turbo chargersTurbo chargers
Turbo chargers
 
Vapour power cycles
Vapour power cyclesVapour power cycles
Vapour power cycles
 
Air Std Cycles.pptx
Air Std Cycles.pptxAir Std Cycles.pptx
Air Std Cycles.pptx
 
cdu and vdu unit
cdu and vdu unitcdu and vdu unit
cdu and vdu unit
 
Transformer Protection
Transformer Protection Transformer Protection
Transformer Protection
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdfEthylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
 
Sample Question and answer for power plants
Sample Question and answer for power plantsSample Question and answer for power plants
Sample Question and answer for power plants
 

More from MAHMOUDMOHAMED431205

OC Relay, types,constrcution,maintenance.pptx
OC Relay, types,constrcution,maintenance.pptxOC Relay, types,constrcution,maintenance.pptx
OC Relay, types,constrcution,maintenance.pptxMAHMOUDMOHAMED431205
 
protection functions.types.maintenance,alarms.pptx
protection functions.types.maintenance,alarms.pptxprotection functions.types.maintenance,alarms.pptx
protection functions.types.maintenance,alarms.pptxMAHMOUDMOHAMED431205
 
cathodic protection and maintenance requred 3.pptx
cathodic protection and maintenance requred 3.pptxcathodic protection and maintenance requred 3.pptx
cathodic protection and maintenance requred 3.pptxMAHMOUDMOHAMED431205
 
plan for electrical technicianTraining .pptx
plan for electrical technicianTraining .pptxplan for electrical technicianTraining .pptx
plan for electrical technicianTraining .pptxMAHMOUDMOHAMED431205
 
09-2 Machine Prot. Exercises en Synchro.ppt
09-2 Machine Prot. Exercises en Synchro.ppt09-2 Machine Prot. Exercises en Synchro.ppt
09-2 Machine Prot. Exercises en Synchro.pptMAHMOUDMOHAMED431205
 
15_C_3_Numerical paralleling device_7VE6.ppt
15_C_3_Numerical paralleling device_7VE6.ppt15_C_3_Numerical paralleling device_7VE6.ppt
15_C_3_Numerical paralleling device_7VE6.pptMAHMOUDMOHAMED431205
 
09_C_3_100 percent - Stator Earth Fault Protection.ppt
09_C_3_100 percent - Stator Earth Fault Protection.ppt09_C_3_100 percent - Stator Earth Fault Protection.ppt
09_C_3_100 percent - Stator Earth Fault Protection.pptMAHMOUDMOHAMED431205
 
08_C_3_Basis Stator Earth Fault Protection.ppt
08_C_3_Basis Stator Earth Fault Protection.ppt08_C_3_Basis Stator Earth Fault Protection.ppt
08_C_3_Basis Stator Earth Fault Protection.pptMAHMOUDMOHAMED431205
 
07_C_3_Underexcitation Protection.ppt
07_C_3_Underexcitation Protection.ppt07_C_3_Underexcitation Protection.ppt
07_C_3_Underexcitation Protection.pptMAHMOUDMOHAMED431205
 

More from MAHMOUDMOHAMED431205 (20)

OC Relay, types,constrcution,maintenance.pptx
OC Relay, types,constrcution,maintenance.pptxOC Relay, types,constrcution,maintenance.pptx
OC Relay, types,constrcution,maintenance.pptx
 
protection functions.types.maintenance,alarms.pptx
protection functions.types.maintenance,alarms.pptxprotection functions.types.maintenance,alarms.pptx
protection functions.types.maintenance,alarms.pptx
 
cathodic protection and maintenance requred 3.pptx
cathodic protection and maintenance requred 3.pptxcathodic protection and maintenance requred 3.pptx
cathodic protection and maintenance requred 3.pptx
 
plan for electrical technicianTraining .pptx
plan for electrical technicianTraining .pptxplan for electrical technicianTraining .pptx
plan for electrical technicianTraining .pptx
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 
MOTOR PROTECTION.pptx
MOTOR PROTECTION.pptxMOTOR PROTECTION.pptx
MOTOR PROTECTION.pptx
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 
Single Line Diagram.pptx
Single Line Diagram.pptxSingle Line Diagram.pptx
Single Line Diagram.pptx
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
 
power cable 3.pptx
power cable 3.pptxpower cable 3.pptx
power cable 3.pptx
 
power cable 2.pptx
power cable 2.pptxpower cable 2.pptx
power cable 2.pptx
 
power cable1.ppt
power cable1.pptpower cable1.ppt
power cable1.ppt
 
MOTOR PROTECTION.pptx
MOTOR PROTECTION.pptxMOTOR PROTECTION.pptx
MOTOR PROTECTION.pptx
 
starting current of motor.pptx
starting current of motor.pptxstarting current of motor.pptx
starting current of motor.pptx
 
protection Training.pptx
protection Training.pptxprotection Training.pptx
protection Training.pptx
 
09-2 Machine Prot. Exercises en Synchro.ppt
09-2 Machine Prot. Exercises en Synchro.ppt09-2 Machine Prot. Exercises en Synchro.ppt
09-2 Machine Prot. Exercises en Synchro.ppt
 
15_C_3_Numerical paralleling device_7VE6.ppt
15_C_3_Numerical paralleling device_7VE6.ppt15_C_3_Numerical paralleling device_7VE6.ppt
15_C_3_Numerical paralleling device_7VE6.ppt
 
09_C_3_100 percent - Stator Earth Fault Protection.ppt
09_C_3_100 percent - Stator Earth Fault Protection.ppt09_C_3_100 percent - Stator Earth Fault Protection.ppt
09_C_3_100 percent - Stator Earth Fault Protection.ppt
 
08_C_3_Basis Stator Earth Fault Protection.ppt
08_C_3_Basis Stator Earth Fault Protection.ppt08_C_3_Basis Stator Earth Fault Protection.ppt
08_C_3_Basis Stator Earth Fault Protection.ppt
 
07_C_3_Underexcitation Protection.ppt
07_C_3_Underexcitation Protection.ppt07_C_3_Underexcitation Protection.ppt
07_C_3_Underexcitation Protection.ppt
 

Recently uploaded

Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 

Recently uploaded (20)

Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

power Tr 2 course.ppt

  • 1. • Cooling systems : 1- Air 2- Oil • Air use in Dry Transformer
  • 2. • Disadvantage : 1- Not allowed to download transformers except for a small period of time 2 - Low durability insulation 3 - The windings effect Dust and dirt 4 - Increasing the size of the windings to follow the air
  • 3. • Oil filled transformer in power Tr: • The basic elements: 1-Oil 2- Radiators 3-Fans 4-Pumps 5-Cooling pipes
  • 4. • Transformer Oil : • Function: • 1- Cooling • 2- Insulation • The Properties Transformer Oil: 1-Dielectric strength 2-Viscoisty 3-Flash Point(145 c) 4-denisty (.88/cm3 at 15 c),the efficiency of transfer the temperature about 21 times of Air
  • 6.
  • 7. •Fans: • Increase the efficiency of cooling ( Forced Circulation) Note: 1- Small Fans put in the front the Radiators cause Vibration 2- Large Fans put Under the Radiators
  • 8. • Cooling Class : • The Characterization IEC: 1 2 3 4 internal cooling type Circulation type External cooling type Circulation type
  • 9. O N A N Oil Natural Air Natural
  • 10.
  • 12. • Use in Small Transformer • Advantages : 1-Simple 2-low cost 3-High Reliability 4-low noise Disadvantages: 1-Large Radiators and high cost 2- Limited in small transformer
  • 13. •ONAF: • Use in High power Tr • Use two fans groups and work automatic • Distribution fans regularly
  • 15. ODAF:
  • 16. •Multi-stage cooling: • Change in rating value with Cooling
  • 17. • What's the meaning : ONAN/OFAF/OFAF cooling class transformer with”45/60/75 MVA continuous at 65 c Temperature rise:
  • 18. Inactive parts auxiliary parts • Functions of transformer oil : 1- Cooling
  • 19. 2- Insulation between the windings and core and tank • Breakdown voltage for Air up to 30kv/cm • Breakdown voltage for Oil up to 80kv/cm 3 - Covers all metal parts to prevent oxidation where effect on conductor condictivity 4 - Identifies many of the faults (take sample of the oil )
  • 20. • Tank : Types : 1-plain tank in small power Tr under 50 KVA 2-Tubed tank in medium power Tr 3-Tank with Radiators in High power Tr
  • 21. • Function of Tank : 1. core and windings protection 2. Carry conductors out lines 3. Keep up transformer oil 4. Carry Radiators tubes
  • 23. • Conservator Tank :  Absorption any Expansion or contraction in oil  Increase oil to main tank
  • 24.  The volume of Conservator Tank about 1/10 to main transformer  At full load increase oil volume about 8% therefore hieght oil about 30% of Conservator Tank hieght  increase Conservator Tank (oil level tube) to show oil vapor color :
  • 25. White Burn in insulation paper Yellow Burn in insulation fibber and wood Black decomposition and burn Oil
  • 27. • Breather unit :  Contain on silica gel: crystalline salt absorb moisture in air during entry to the transformer
  • 28. Silica gel colors: • color Case Blue normal Wardy Moisture saturation and must change or drying in furnace (150:200 c) White Moisture saturation and must change Black Oil saturation and must change
  • 29. • Oil protection system :  The sealing in small transformer: 1- by conservator tank
  • 30. 2- Nitrogen-positive pressure : - Use compressed Nitrogen about 10% above oil in main tank
  • 32. • Tap Changer Values:
  • 33. •The idea of Tap Changer :
  • 36. • Comparison between on load and off load Tab Changer: On load Off load Tr type Power Tr Distribution Tr Points 17 point or more 3 or 5 Surrounded condition Cylinder filled oil Transformer oil Change method Auto manual Place Cylinder with parallel with coils
  • 37. • HV and LV bushing (isolators) :
  • 38. • Function of Skirts : Using Corona Rings :
  • 41. • Accessories : 1- Pressure Relief Valve:
  • 42. 2- Dial transformer capillary tube
  • 43.
  • 44. 3- Liquid Level Gauge: • indicates the level of the insulating liquid in the main transformer tank. • The standard gage has a center marking indicating the level at 25 C. Dial markings are minimum -25 C - maximum.
  • 45. 4- Pressure-Vacuum Gauge: • Gage readings vary with transformer temperature changes and would normally indicate a positive pressure. • The gage may indicate a vacuum within the tank when the transformer is de-energized or is operating under light or no-load conditions in allow ambient temperature. • Any change in temperature indication of a leak in the transformer seal and should be investigated
  • 46. 5- Oil temperature indicator :
  • 47. 6- Winding temperature indicator :
  • 48.
  • 49. • K- Factor : The ratio between the additional losses in the energy of harmonics and eddy current losses (4,7,13,20,30) • K=4 (50 % non linear loads) • K= 13 (100% non linear loads)
  • 50. • Effect harmonics on connection of windings :
  • 51. • Flux on magnetizing current:
  • 52.
  • 53. • Filter for preventing third harmonic:
  • 54. • Relation between magnetizing current and output voltage :
  • 55. • Effect harmonics on Star connection
  • 56. • Effect harmonics on Delta connection :
  • 57.
  • 58. • Effect the earthing on transformer : 1- Ungrounded System:
  • 59. Advantages : 1-Short circuit current very low 2- KVA SC during short very low (Short circuit level ) Disadvantages : 1-S.c between phase and ground ,voltage increase on other two phases 2-Short circuit current very low, protection device not work 3-Arcing voltage occurs between phase and ground during S.C
  • 60. • Earthing System: Solution problem Ungrounded System • Connection methods : 1- Star Star: Y-Y
  • 61. • Advantages : 1-Vp and Vs in phase where not phase Displacement 2- low turns in phase Vp=57% of Vline Disadvantages : 1- Vs is distorted wave 2-un balance load 3-third harmonic causes over voltage 4-
  • 63. •Advantages : 1- low current in each phase 2- third harmonic circulate in delta 3-earth fault current follow in Neutral for star 4- Zero sequence current circulate in delta
  • 65. •Advantages : 1-use in low voltage and high current where Iph=57%of Iline sothat winding Tr is low in cross section area and copper 2-third harmonic circulate in delta Disadvantages : 1-Weak for mechanical stress and electrical stress 2- Not neutral (N) ,if occurs fault increase voltage on three phase
  • 66. • Earthing faults in Delta-Delta connection :
  • 68. Rt Zig Zag transformer in the earthling
  • 69. • Delta-Zig Zag Connection:
  • 70. • Example 1: This number 925554 on transformer body: Example 2 : 75554 or 025554 1 50 KVA 2 100 3 200 4 300 5 500 6 800 7 1000 8 1500
  • 71. • What “s the meaning:
  • 72. • BIL ( Basic impulse level : Ability insulators inside Tr to increase in voltage result surge or opening and closing