SlideShare a Scribd company logo
1 of 23
Download to read offline
BEF43303
POWER SYSTEM ANALYSIS AND PROTECTION
WEEK 10
DISTANCE PROTECTION
10.0 CONTENTS
10.1 Introduction to system protection
10.2 System protection components
10.3 Instrument transformers
10.1 INTRODUCTION TO SYSTEM
PROTECTION
• System protection is required to protect the system from abnormal
system operating condition.
• The typical causes of short circuit:
 Equipment insulation fails,
 Overvoltage caused by lightning or switching surges,
 Insulation contamination,
 Natural causes.
• Impossible to eliminate can be minimized through proper
maintenance.
10.1 INTRODUCTION TO SYSTEM
PROTECTION
• The impact of short circuit:
 Insulation damage,
 Conductor melting,
 Fire and explosion,
 Mechanical damage to winding and busbar.
• EHV protection system is designed to clear fault within 3 cycles.
• LV protection system typically operates within 5-20 cycles.
10.1 INTRODUCTION TO SYSTEM
PROTECTION
• The basic idea of protection system is:
 To define the undesirable conditions and look for differences
between the undesirable and permissible conditions that
relays or fuses can sense.
• It is important to remove only the faulted equipment from the
system.
• The unfaulted system needs to be retained as much as possible.
• For this course, we primarily focus on circuit breaker and relays
which are used to protect HV (115-230kV) and EHV (345-765kV).
10.1 INTRODUCTION TO SYSTEM
PROTECTION
• The definition of relay according to IEEE:
• A device whose function is to detect defective lines or
apparatus or other power system conditions of an abnormal
or dangerous nature and to initiate appropriate control
action.
• In practice, a relay is a device that closes or opens a contact when
energized.
10.1 INTRODUCTION TO SYSTEM
PROTECTION
• Problems with the protection equipment may occur within itself.
• A backup relays may be used to protect the primary relays.
• In HV and EHV systems, separate protective elements may be used
for backup relays.
• Various protective devices in the system must be properly
coordinated.
• The primary relays must operate first.
• If the primary relays fail, then backup relays should operate after a
specified time delay.
10.2 SYSTEM PROTECTION
COMPONENTS
• Protection systems have three
basic components:
 Instrument transformers,
 Relays,
 Circuit breakers.
• Figure 10.1 shows a simple
overcurrent protection
schematic.
Figure 10.1 – Overcurrent protection schematic
10.2 SYSTEM PROTECTION
COMPONENTS
Current transformer
 Function: to reproduce in its secondary winding a current I’ that is
proportional to the primary current I.
 Operation: Converts primary currents in the kA range to secondary
currents in the 0–5 ampere range.
 Advantages:
 Safety - Provides electrical isolation from the power system.
 Economy - Relays are smaller, simpler, and less expensive.
 Accuracy - Reproduce V and I over wide operating ranges.
10.2 SYSTEM PROTECTION
COMPONENTS
Relay
• Function: To discriminate between normal operation and fault
conditions.
• Operation:
 When the variables being monitored exceeds a specified
‘‘pickup’’ value,
 The operating coil causes the NO contacts to close,
 The trip coil of the circuit breaker is energized,
 The circuit breaker to open.
10.2 SYSTEM PROTECTION
COMPONENTS
Circuit breaker
• Function:
 A mechanical switch capable of interrupting fault currents and of
reclosing.
 Circuit breaker contacts are separated while carrying current.
• Operation: Based on information from instrument transformers, a
decision is made and ‘‘relayed’’ to the trip coil of the breaker, which
actually opens the power circuit.
10.2 SYSTEM PROTECTION
COMPONENTS
The design criteria of system protection system:
• Reliability: Operate dependably when fault conditions occur, even
after remaining idle for months or years. Failure to do so may result
in costly damages.
• Selectivity: Avoid unnecessary, false trips.
• Speed: Operate rapidly to minimize fault duration and equipment
damage. Any intentional time delays should be precise.
• Economy: Provide maximum protection at minimum cost.
• Simplicity: Minimize protection equipment and circuitry.
10.3 INSTRUMENT TRANSFORMERS
• There are two basic types of
instrument transformers:
 Voltage transformers (VTs),
 Current transformers (CTs).
• Figure 10.2 shows a schematic
representation for the VT and
CT.
Figure 10.2 - VT and CT schematic
10.3 INSTRUMENT TRANSFORMERS
• For system-protection purposes, VT is usually modeled as an ideal
transformer as 𝑉𝑉′ = ⁄
1 𝑛𝑛 × 𝑉𝑉.
• 𝑉𝑉𝑉 is a scaled-down representation of 𝑉𝑉 and is in phase with 𝑉𝑉.
• A standard VT secondary voltage rating is 115 V (line-to-line).
• Standard VT ratios are given in Table 10.1.
Table 10.1 - Standard VT ratios
10.3 INSTRUMENT TRANSFORMERS
• The primary winding of a CT consists of a single turn, obtained by
running the power system’s primary conductor through the CT core.
• The normal current rating of CT secondary is standardized at 5A in
the United States, and 1A in Europe.
• Standard CT ratios are given in Table 10.2.
Table 10.2 - Standard CT ratios
10.3 INSTRUMENT TRANSFORMERS
• An approximate equivalent
circuit of a CT is shown in
Figure 10.3, where:
 𝑍𝑍𝑍 - CT secondary leakage
impedance,
 𝑋𝑋𝑒𝑒 - CT excitation reactance,
 𝑍𝑍𝐵𝐵 - Impedance of
terminating device.
Figure 10.3 – CT equivalent circuit
10.3 INSTRUMENT TRANSFORMERS
• 𝑍𝑍𝐵𝐵 is also called the burden.
• It is typically less than an ohm.
• It may also be expressed as VA
at a specified current.
• The relationship between the
CT secondary voltage 𝐸𝐸𝐸 and
excitation current 𝐼𝐼𝑒𝑒 is given by
an excitation curve shown in
Figure 10.4.
Figure 10.3 – CT equivalent circuit
10.3 INSTRUMENT TRANSFORMERS
Figure 10.4 - Excitation curves for a multi-ratio bushing CT with a C100 ANSI accuracy classification
10.3 INSTRUMENT TRANSFORMERS
• 𝑍𝑍𝐵𝐵 is also called the burden.
• It is typically less than an ohm.
• It may also be expressed as VA
at a specified current.
• The relationship between the
CT secondary voltage 𝐸𝐸𝐸 and
excitation current 𝐼𝐼𝑒𝑒 is given by
an excitation curve shown in
Figure 10.4.
Figure 10.3 – CT equivalent circuit
10.3 INSTRUMENT TRANSFORMERS
Using the CT equivalent circuit and excitation curves, the following
procedure can be used to determine CT performance.
1) Assume a CT secondary output current 𝐼𝐼′.
2) Compute 𝐸𝐸′
= 𝑍𝑍′
+ 𝑍𝑍𝐵𝐵 𝐼𝐼𝐼.
3) Using E′, find 𝐼𝐼𝑒𝑒 from the excitation curve.
4) Compute 𝐼𝐼 = 𝑛𝑛 𝐼𝐼′ + 𝐼𝐼𝑒𝑒 .
5) Repeat Steps 1–4 for different values of I’, then plot I’ versus I.
10.3 INSTRUMENT TRANSFORMERS
• For simplicity, calculations are made with magnitudes rather than
with phasors.
• The CT error is the percentage difference between 𝐼𝐼′ + 𝐼𝐼𝑒𝑒 and 𝐼𝐼𝐼,
given by:
CT error =
𝐼𝐼𝑒𝑒
𝐼𝐼′ + 𝐼𝐼𝑒𝑒
× 100%
10.3 INSTRUMENT TRANSFORMERS
Example 10.3.1
Evaluate the performance of the multi-ratio CT in Figure 10.4 with
a 100:5 CT ratio, for the following secondary output currents and
burdens:
a) 𝐼𝐼𝐼 = 5𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 0.5Ω (Ans.: 2.91𝑉𝑉, 0.25𝐴𝐴, 105𝐴𝐴, 4.8%);
b) 𝐼𝐼𝐼 = 8𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 0.8Ω (Ans.: 7.06V, 0.4A, 168A, 4.8%);
c) 𝐼𝐼𝐼 = 15𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 1.5Ω (Ans.: 23.73𝑉𝑉, 20𝐴𝐴, 700𝐴𝐴, 57.1%).
Also, compute the CT error for each output current.
10.3 INSTRUMENT TRANSFORMERS
Example 10.3.2
An overcurrent relay set to operate at 8𝐴𝐴 is connected to the multi-
ratio CT in Figure 10.4 with a 100:5 CT ratio. Will the relay detect a
200A primary fault current if the burden 𝑍𝑍𝐵𝐵 is
(a) 0.8Ω (Ans.: relay will operate),
(b)3.0 Ω (Ans.: relay will not operate).
Note: For additional exercises, students may refer to Power System
Analysis and Design by Glover, Problems 10.1-10.6.

More Related Content

Similar to BEF43303_-_201620171_W10.pdf

Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersThorne & Derrick International
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar reportRahul Aman
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit iivenki249
 
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.ppt
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.pptLECT_1_E_1435_POWER_SYSTEM_PROTECTION.ppt
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.pptssuser295be9
 
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfAzizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfSultanAlSaiari1
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptThien Phan Bản
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptThien Phan Bản
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryHimmelstern
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryHimmelstern
 
FEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONFEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONDr. Rohit Babu
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMerramansaini1947
 
CPRI-Power quality report
CPRI-Power quality reportCPRI-Power quality report
CPRI-Power quality reportNageswar Rao
 
INDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYINDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYtarun1504
 
Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Dr. Rohit Babu
 
Microcontroller based multifunction_relay
Microcontroller based multifunction_relayMicrocontroller based multifunction_relay
Microcontroller based multifunction_relayRajeev Kumar
 
Power System Protection
Power System ProtectionPower System Protection
Power System ProtectionRahul Mehra
 
Introduction of switcg gear
Introduction of switcg gearIntroduction of switcg gear
Introduction of switcg gearjawaharramaya
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring SeminarSurabhi Vasudev
 

Similar to BEF43303_-_201620171_W10.pdf (20)

Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Power system protection seminar report
Power system protection seminar reportPower system protection seminar report
Power system protection seminar report
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit ii
 
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.ppt
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.pptLECT_1_E_1435_POWER_SYSTEM_PROTECTION.ppt
LECT_1_E_1435_POWER_SYSTEM_PROTECTION.ppt
 
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfAzizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
protectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.pptprotectionsettings-120425102109-phpapp01.ppt
protectionsettings-120425102109-phpapp01.ppt
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
LV switchgear FINAL.pptx
LV switchgear FINAL.pptxLV switchgear FINAL.pptx
LV switchgear FINAL.pptx
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
 
FEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONFEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTION
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
CPRI-Power quality report
CPRI-Power quality reportCPRI-Power quality report
CPRI-Power quality report
 
INDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYINDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDY
 
Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)
 
Microcontroller based multifunction_relay
Microcontroller based multifunction_relayMicrocontroller based multifunction_relay
Microcontroller based multifunction_relay
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
 
Introduction of switcg gear
Introduction of switcg gearIntroduction of switcg gear
Introduction of switcg gear
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring Seminar
 

More from LiewChiaPing

chapter4 DC to AC Converter.ppt
chapter4 DC to AC Converter.pptchapter4 DC to AC Converter.ppt
chapter4 DC to AC Converter.pptLiewChiaPing
 
chapter_2 AC to DC Converter.pptx
chapter_2 AC to DC Converter.pptxchapter_2 AC to DC Converter.pptx
chapter_2 AC to DC Converter.pptxLiewChiaPing
 
chapter_1 Intro. to electonic Devices.ppt
chapter_1 Intro. to electonic Devices.pptchapter_1 Intro. to electonic Devices.ppt
chapter_1 Intro. to electonic Devices.pptLiewChiaPing
 
Chapter 7 Application of Electronic Converters.pdf
Chapter 7 Application of Electronic Converters.pdfChapter 7 Application of Electronic Converters.pdf
Chapter 7 Application of Electronic Converters.pdfLiewChiaPing
 
Chapter 6 AC-AC Converters.pdf
Chapter 6 AC-AC Converters.pdfChapter 6 AC-AC Converters.pdf
Chapter 6 AC-AC Converters.pdfLiewChiaPing
 
Chapter 5 DC-DC Converters.pdf
Chapter 5 DC-DC Converters.pdfChapter 5 DC-DC Converters.pdf
Chapter 5 DC-DC Converters.pdfLiewChiaPing
 
Chapter 4 Inverters.pdf
Chapter 4 Inverters.pdfChapter 4 Inverters.pdf
Chapter 4 Inverters.pdfLiewChiaPing
 
Chapter 3 Controlled Rectifier.pdf
Chapter 3 Controlled Rectifier.pdfChapter 3 Controlled Rectifier.pdf
Chapter 3 Controlled Rectifier.pdfLiewChiaPing
 
Chapter 2 Uncontrolled Rectifiers.pdf
Chapter 2 Uncontrolled Rectifiers.pdfChapter 2 Uncontrolled Rectifiers.pdf
Chapter 2 Uncontrolled Rectifiers.pdfLiewChiaPing
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfLiewChiaPing
 
BEF43303_-_201620171_W13 Overcurrent Protection.pdf
BEF43303_-_201620171_W13 Overcurrent Protection.pdfBEF43303_-_201620171_W13 Overcurrent Protection.pdf
BEF43303_-_201620171_W13 Overcurrent Protection.pdfLiewChiaPing
 
BEF43303_-_201620171_W12 Overcurrent Protection.pdf
BEF43303_-_201620171_W12 Overcurrent Protection.pdfBEF43303_-_201620171_W12 Overcurrent Protection.pdf
BEF43303_-_201620171_W12 Overcurrent Protection.pdfLiewChiaPing
 
BEF43303_-_201620171_W11 Distance Protection.pdf
BEF43303_-_201620171_W11 Distance Protection.pdfBEF43303_-_201620171_W11 Distance Protection.pdf
BEF43303_-_201620171_W11 Distance Protection.pdfLiewChiaPing
 
BEF43303_-_201620171_W8 Power System Stability.pdf
BEF43303_-_201620171_W8 Power System Stability.pdfBEF43303_-_201620171_W8 Power System Stability.pdf
BEF43303_-_201620171_W8 Power System Stability.pdfLiewChiaPing
 
BEF43303_-_201620171_W7 Power System Stability.pdf
BEF43303_-_201620171_W7 Power System Stability.pdfBEF43303_-_201620171_W7 Power System Stability.pdf
BEF43303_-_201620171_W7 Power System Stability.pdfLiewChiaPing
 
BEF43303_-_201620171_W6 Analysis of Fault.pdf
BEF43303_-_201620171_W6 Analysis of Fault.pdfBEF43303_-_201620171_W6 Analysis of Fault.pdf
BEF43303_-_201620171_W6 Analysis of Fault.pdfLiewChiaPing
 
BEF43303_-_201620171_W5 Analysis of fault.pdf
BEF43303_-_201620171_W5 Analysis of fault.pdfBEF43303_-_201620171_W5 Analysis of fault.pdf
BEF43303_-_201620171_W5 Analysis of fault.pdfLiewChiaPing
 
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdf
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdfBEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdf
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdfLiewChiaPing
 
BEF43303 - 201620171 W3 Power Flow Analysis.pdf
BEF43303 - 201620171 W3 Power Flow Analysis.pdfBEF43303 - 201620171 W3 Power Flow Analysis.pdf
BEF43303 - 201620171 W3 Power Flow Analysis.pdfLiewChiaPing
 
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdfBEF43303 - 201620171 W2 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdfLiewChiaPing
 

More from LiewChiaPing (20)

chapter4 DC to AC Converter.ppt
chapter4 DC to AC Converter.pptchapter4 DC to AC Converter.ppt
chapter4 DC to AC Converter.ppt
 
chapter_2 AC to DC Converter.pptx
chapter_2 AC to DC Converter.pptxchapter_2 AC to DC Converter.pptx
chapter_2 AC to DC Converter.pptx
 
chapter_1 Intro. to electonic Devices.ppt
chapter_1 Intro. to electonic Devices.pptchapter_1 Intro. to electonic Devices.ppt
chapter_1 Intro. to electonic Devices.ppt
 
Chapter 7 Application of Electronic Converters.pdf
Chapter 7 Application of Electronic Converters.pdfChapter 7 Application of Electronic Converters.pdf
Chapter 7 Application of Electronic Converters.pdf
 
Chapter 6 AC-AC Converters.pdf
Chapter 6 AC-AC Converters.pdfChapter 6 AC-AC Converters.pdf
Chapter 6 AC-AC Converters.pdf
 
Chapter 5 DC-DC Converters.pdf
Chapter 5 DC-DC Converters.pdfChapter 5 DC-DC Converters.pdf
Chapter 5 DC-DC Converters.pdf
 
Chapter 4 Inverters.pdf
Chapter 4 Inverters.pdfChapter 4 Inverters.pdf
Chapter 4 Inverters.pdf
 
Chapter 3 Controlled Rectifier.pdf
Chapter 3 Controlled Rectifier.pdfChapter 3 Controlled Rectifier.pdf
Chapter 3 Controlled Rectifier.pdf
 
Chapter 2 Uncontrolled Rectifiers.pdf
Chapter 2 Uncontrolled Rectifiers.pdfChapter 2 Uncontrolled Rectifiers.pdf
Chapter 2 Uncontrolled Rectifiers.pdf
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdf
 
BEF43303_-_201620171_W13 Overcurrent Protection.pdf
BEF43303_-_201620171_W13 Overcurrent Protection.pdfBEF43303_-_201620171_W13 Overcurrent Protection.pdf
BEF43303_-_201620171_W13 Overcurrent Protection.pdf
 
BEF43303_-_201620171_W12 Overcurrent Protection.pdf
BEF43303_-_201620171_W12 Overcurrent Protection.pdfBEF43303_-_201620171_W12 Overcurrent Protection.pdf
BEF43303_-_201620171_W12 Overcurrent Protection.pdf
 
BEF43303_-_201620171_W11 Distance Protection.pdf
BEF43303_-_201620171_W11 Distance Protection.pdfBEF43303_-_201620171_W11 Distance Protection.pdf
BEF43303_-_201620171_W11 Distance Protection.pdf
 
BEF43303_-_201620171_W8 Power System Stability.pdf
BEF43303_-_201620171_W8 Power System Stability.pdfBEF43303_-_201620171_W8 Power System Stability.pdf
BEF43303_-_201620171_W8 Power System Stability.pdf
 
BEF43303_-_201620171_W7 Power System Stability.pdf
BEF43303_-_201620171_W7 Power System Stability.pdfBEF43303_-_201620171_W7 Power System Stability.pdf
BEF43303_-_201620171_W7 Power System Stability.pdf
 
BEF43303_-_201620171_W6 Analysis of Fault.pdf
BEF43303_-_201620171_W6 Analysis of Fault.pdfBEF43303_-_201620171_W6 Analysis of Fault.pdf
BEF43303_-_201620171_W6 Analysis of Fault.pdf
 
BEF43303_-_201620171_W5 Analysis of fault.pdf
BEF43303_-_201620171_W5 Analysis of fault.pdfBEF43303_-_201620171_W5 Analysis of fault.pdf
BEF43303_-_201620171_W5 Analysis of fault.pdf
 
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdf
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdfBEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdf
BEF43303_-_201620171_W4 Analysis of Balance and Unbalance Fault.pdf
 
BEF43303 - 201620171 W3 Power Flow Analysis.pdf
BEF43303 - 201620171 W3 Power Flow Analysis.pdfBEF43303 - 201620171 W3 Power Flow Analysis.pdf
BEF43303 - 201620171 W3 Power Flow Analysis.pdf
 
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdfBEF43303 - 201620171 W2 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W2 Power System Analysis and Protection.pdf
 

Recently uploaded

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 

Recently uploaded (20)

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 

BEF43303_-_201620171_W10.pdf

  • 1. BEF43303 POWER SYSTEM ANALYSIS AND PROTECTION WEEK 10 DISTANCE PROTECTION
  • 2. 10.0 CONTENTS 10.1 Introduction to system protection 10.2 System protection components 10.3 Instrument transformers
  • 3. 10.1 INTRODUCTION TO SYSTEM PROTECTION • System protection is required to protect the system from abnormal system operating condition. • The typical causes of short circuit:  Equipment insulation fails,  Overvoltage caused by lightning or switching surges,  Insulation contamination,  Natural causes. • Impossible to eliminate can be minimized through proper maintenance.
  • 4. 10.1 INTRODUCTION TO SYSTEM PROTECTION • The impact of short circuit:  Insulation damage,  Conductor melting,  Fire and explosion,  Mechanical damage to winding and busbar. • EHV protection system is designed to clear fault within 3 cycles. • LV protection system typically operates within 5-20 cycles.
  • 5. 10.1 INTRODUCTION TO SYSTEM PROTECTION • The basic idea of protection system is:  To define the undesirable conditions and look for differences between the undesirable and permissible conditions that relays or fuses can sense. • It is important to remove only the faulted equipment from the system. • The unfaulted system needs to be retained as much as possible. • For this course, we primarily focus on circuit breaker and relays which are used to protect HV (115-230kV) and EHV (345-765kV).
  • 6. 10.1 INTRODUCTION TO SYSTEM PROTECTION • The definition of relay according to IEEE: • A device whose function is to detect defective lines or apparatus or other power system conditions of an abnormal or dangerous nature and to initiate appropriate control action. • In practice, a relay is a device that closes or opens a contact when energized.
  • 7. 10.1 INTRODUCTION TO SYSTEM PROTECTION • Problems with the protection equipment may occur within itself. • A backup relays may be used to protect the primary relays. • In HV and EHV systems, separate protective elements may be used for backup relays. • Various protective devices in the system must be properly coordinated. • The primary relays must operate first. • If the primary relays fail, then backup relays should operate after a specified time delay.
  • 8. 10.2 SYSTEM PROTECTION COMPONENTS • Protection systems have three basic components:  Instrument transformers,  Relays,  Circuit breakers. • Figure 10.1 shows a simple overcurrent protection schematic. Figure 10.1 – Overcurrent protection schematic
  • 9. 10.2 SYSTEM PROTECTION COMPONENTS Current transformer  Function: to reproduce in its secondary winding a current I’ that is proportional to the primary current I.  Operation: Converts primary currents in the kA range to secondary currents in the 0–5 ampere range.  Advantages:  Safety - Provides electrical isolation from the power system.  Economy - Relays are smaller, simpler, and less expensive.  Accuracy - Reproduce V and I over wide operating ranges.
  • 10. 10.2 SYSTEM PROTECTION COMPONENTS Relay • Function: To discriminate between normal operation and fault conditions. • Operation:  When the variables being monitored exceeds a specified ‘‘pickup’’ value,  The operating coil causes the NO contacts to close,  The trip coil of the circuit breaker is energized,  The circuit breaker to open.
  • 11. 10.2 SYSTEM PROTECTION COMPONENTS Circuit breaker • Function:  A mechanical switch capable of interrupting fault currents and of reclosing.  Circuit breaker contacts are separated while carrying current. • Operation: Based on information from instrument transformers, a decision is made and ‘‘relayed’’ to the trip coil of the breaker, which actually opens the power circuit.
  • 12. 10.2 SYSTEM PROTECTION COMPONENTS The design criteria of system protection system: • Reliability: Operate dependably when fault conditions occur, even after remaining idle for months or years. Failure to do so may result in costly damages. • Selectivity: Avoid unnecessary, false trips. • Speed: Operate rapidly to minimize fault duration and equipment damage. Any intentional time delays should be precise. • Economy: Provide maximum protection at minimum cost. • Simplicity: Minimize protection equipment and circuitry.
  • 13. 10.3 INSTRUMENT TRANSFORMERS • There are two basic types of instrument transformers:  Voltage transformers (VTs),  Current transformers (CTs). • Figure 10.2 shows a schematic representation for the VT and CT. Figure 10.2 - VT and CT schematic
  • 14. 10.3 INSTRUMENT TRANSFORMERS • For system-protection purposes, VT is usually modeled as an ideal transformer as 𝑉𝑉′ = ⁄ 1 𝑛𝑛 × 𝑉𝑉. • 𝑉𝑉𝑉 is a scaled-down representation of 𝑉𝑉 and is in phase with 𝑉𝑉. • A standard VT secondary voltage rating is 115 V (line-to-line). • Standard VT ratios are given in Table 10.1. Table 10.1 - Standard VT ratios
  • 15. 10.3 INSTRUMENT TRANSFORMERS • The primary winding of a CT consists of a single turn, obtained by running the power system’s primary conductor through the CT core. • The normal current rating of CT secondary is standardized at 5A in the United States, and 1A in Europe. • Standard CT ratios are given in Table 10.2. Table 10.2 - Standard CT ratios
  • 16. 10.3 INSTRUMENT TRANSFORMERS • An approximate equivalent circuit of a CT is shown in Figure 10.3, where:  𝑍𝑍𝑍 - CT secondary leakage impedance,  𝑋𝑋𝑒𝑒 - CT excitation reactance,  𝑍𝑍𝐵𝐵 - Impedance of terminating device. Figure 10.3 – CT equivalent circuit
  • 17. 10.3 INSTRUMENT TRANSFORMERS • 𝑍𝑍𝐵𝐵 is also called the burden. • It is typically less than an ohm. • It may also be expressed as VA at a specified current. • The relationship between the CT secondary voltage 𝐸𝐸𝐸 and excitation current 𝐼𝐼𝑒𝑒 is given by an excitation curve shown in Figure 10.4. Figure 10.3 – CT equivalent circuit
  • 18. 10.3 INSTRUMENT TRANSFORMERS Figure 10.4 - Excitation curves for a multi-ratio bushing CT with a C100 ANSI accuracy classification
  • 19. 10.3 INSTRUMENT TRANSFORMERS • 𝑍𝑍𝐵𝐵 is also called the burden. • It is typically less than an ohm. • It may also be expressed as VA at a specified current. • The relationship between the CT secondary voltage 𝐸𝐸𝐸 and excitation current 𝐼𝐼𝑒𝑒 is given by an excitation curve shown in Figure 10.4. Figure 10.3 – CT equivalent circuit
  • 20. 10.3 INSTRUMENT TRANSFORMERS Using the CT equivalent circuit and excitation curves, the following procedure can be used to determine CT performance. 1) Assume a CT secondary output current 𝐼𝐼′. 2) Compute 𝐸𝐸′ = 𝑍𝑍′ + 𝑍𝑍𝐵𝐵 𝐼𝐼𝐼. 3) Using E′, find 𝐼𝐼𝑒𝑒 from the excitation curve. 4) Compute 𝐼𝐼 = 𝑛𝑛 𝐼𝐼′ + 𝐼𝐼𝑒𝑒 . 5) Repeat Steps 1–4 for different values of I’, then plot I’ versus I.
  • 21. 10.3 INSTRUMENT TRANSFORMERS • For simplicity, calculations are made with magnitudes rather than with phasors. • The CT error is the percentage difference between 𝐼𝐼′ + 𝐼𝐼𝑒𝑒 and 𝐼𝐼𝐼, given by: CT error = 𝐼𝐼𝑒𝑒 𝐼𝐼′ + 𝐼𝐼𝑒𝑒 × 100%
  • 22. 10.3 INSTRUMENT TRANSFORMERS Example 10.3.1 Evaluate the performance of the multi-ratio CT in Figure 10.4 with a 100:5 CT ratio, for the following secondary output currents and burdens: a) 𝐼𝐼𝐼 = 5𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 0.5Ω (Ans.: 2.91𝑉𝑉, 0.25𝐴𝐴, 105𝐴𝐴, 4.8%); b) 𝐼𝐼𝐼 = 8𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 0.8Ω (Ans.: 7.06V, 0.4A, 168A, 4.8%); c) 𝐼𝐼𝐼 = 15𝐴𝐴 and 𝑍𝑍𝐵𝐵 = 1.5Ω (Ans.: 23.73𝑉𝑉, 20𝐴𝐴, 700𝐴𝐴, 57.1%). Also, compute the CT error for each output current.
  • 23. 10.3 INSTRUMENT TRANSFORMERS Example 10.3.2 An overcurrent relay set to operate at 8𝐴𝐴 is connected to the multi- ratio CT in Figure 10.4 with a 100:5 CT ratio. Will the relay detect a 200A primary fault current if the burden 𝑍𝑍𝐵𝐵 is (a) 0.8Ω (Ans.: relay will operate), (b)3.0 Ω (Ans.: relay will not operate). Note: For additional exercises, students may refer to Power System Analysis and Design by Glover, Problems 10.1-10.6.