A summary of public information management bid results on CDOT projects compared to the engineers estimate and the value of the project. Information gathered from December 2019 to April 2020
2. Revised Specifications
CDOT standard specifications revised fall 2019
Onboarding, graphic design, and CoTrip audit tasks expanded or added
CDOT Design Engineers and Mgmt team discussed PIM should be 1% of project value
Compensation method changed from lump sum to daily rate
3. Project Bid Tab Results
December 2019 – April 2020
28 projects, total project values:
5 under 1 Million
14 between $ 1-5 Million
6 between $ 5-10 Million
3 over $10 Million
4. Public Information Bid Results
PIM bid results of 53 CDOT projects:
1% project value. Qty of projects with PIM at or above that level = 2
.6% - .9% project value = 5
.5% project value = 5
.4% project value = 7
.3% project value = 7
.2% project value = 12
.1% project value = 15
Number of PI bids equal to or above CDOT Engineers estimate = 13
Number of PI bids below the CDOT Engineers estimate = 40
5. Actual PIM Bid vs. 1% Project Value
$-
$100.00
$200.00
$300.00
$400.00
$500.00
$600.00
$700.00
$800.00
$900.00
ProjectName
C145A-077
NHPP1602-172
BR025A-046
CC080-037
FSA2873-194
STAR100-265
SHE094A-035
FBR0761-232
STR196A-001
C1211-090
STR131A-038
SHE0881-031
IM0252-473
NHPP1601-077
MTCER400-378
STA0241-065
HPP0501-067
STRR300-249
SHE0703-461
STA0504-905
PWQM240-172
STR2871-038
NHPP0881-030
STA340A-021
FBR0343-042
C0641-106
BR0343-040&FBR0343-043
STA0831-120
NHPP0502-082
NHPP0091-044
ER0361-118
STR0341-101
NHPP145A-080
STR330A-002
STA059A-036
IM0761-226
STR141A-044
SFTY2254-091
NH0503-093
STA050A-029
STR116A-001
NHPP0171-105
CC0852-106FBR0852-108
NHPP1602-169
STA0703-443
FSA0253-258
STA006A-067
PIM Actual Bid Amount vs 1% of Project Value
Winning Bid Unit Price 1% of Project Value Per Day
6. What are we worth?
1%
Meetings
Press
Releases
Web
Updates
Traffic
Advisories
Stakeholder
Mgmt
Mailings