SlideShare a Scribd company logo
Project Controls Exuctive Summary Report Month Jan-18
TEST_Project
TEST98-108-2018
Nov-17
Nov-19
9%
9%
8%
Engineering 1.0 2.0 1.0 1.0 2.0 -
Procurement 1.0 2.0 1.0 1.5 2.5 (0.5)
Construction 1.0 3.0 1.0 3.0 4.0 (1.0)
Other Cost 1.0 1.0 0.5 0.5 1.0 -
Project Cost 3.0 7.0 3.0 5.5 8.5 (1.5)
Contract Value 4.0 8.0 3.5 6.0 9.5 (1.5)
Committed Variance
Project Number
Project Name
Project Start Date
EAC
Project Planned Finish Date
Project Time elapsed %
Project Planned Progress
Project Actual Progress
Revised BudgetBudgetM USD ETC
0 2
22%20%
0% 5% 10% 15% 20%
Construction
Planned
Actual
50%46%
0% 10% 20% 30% 40% 50% 60%
Engineering
Actual
Planned
27%26%
0% 5% 10% 15% 20% 25% 30%
Procurement
Planned
Actual
25%24%
0% 5% 10% 15% 20% 25% 30%
Overall EPPC
Planned
Actual
Planned Progrees Vs. Actual Progress (January 2018 )
$0
$2
$4
$6
$8
$10
$12
$14
Jul-17
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
Jun-18
Jul-18
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Mar-19
Millions
Engineering
Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC)
$0
$50
$100
$150
$200
$250
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
Jun-18
Jul-18
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Millions
Procurement
Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC)
$0
$100
$200
$300
$400
$500
$600
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
Jun-18
Jul-18
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Mar-19
Apr-19
May-19
Jun-19
Jul-19
Aug-19
Sep-19
Millions
Overall Project KPI's
Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC)
Earned Value analysis (January 2018 )
0
0.5
1
1.5
2
2.5
3
Sum of 1-Aug Sum of 1-Sep Sum of 1-Oct Sum of 1-Nov Sum of 1-Dec Sum of 1-Jan
Planned Progrees Vs. Actual Progress (January 2018 )
ALL
CPI (Construction)
CPI (Engineering)
CPI (Overall EPPC)
CPI (Procurement)
SPI (Construction)
SPI (Engineering)
SPI (Overall EPPC)
SPI (Procurement)
Project Main points
Project Performance
9%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Project Time elapsed %
0% 2
SPI
0% 100%
SPI
0% 100%
SPI
$0
$40
$80
$120
$160
$200
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
Jun-18
Jul-18
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Mar-19
Apr-19
Millions
Construction
Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC)

More Related Content

What's hot

Construction Vital Statistics - November 2015
Construction Vital Statistics - November 2015Construction Vital Statistics - November 2015
Construction Vital Statistics - November 2015
CBIZ, Inc.
 
Construction Vital Statistics - June 2016
Construction Vital Statistics - June 2016Construction Vital Statistics - June 2016
Construction Vital Statistics - June 2016
CBIZ, Inc.
 
Construction Vital Statistics - December 2016
Construction Vital Statistics - December 2016Construction Vital Statistics - December 2016
Construction Vital Statistics - December 2016
CBIZ, Inc.
 
Construction Vital Statistics - August 2016
Construction Vital Statistics - August 2016Construction Vital Statistics - August 2016
Construction Vital Statistics - August 2016
CBIZ, Inc.
 
Construction Vital Statistics February 2017
Construction Vital Statistics February 2017Construction Vital Statistics February 2017
Construction Vital Statistics February 2017
CBIZ, Inc.
 
Factory Double sghift
Factory Double sghift Factory Double sghift
Factory Double sghift
Rashedul Hasan
 
Payment plan ss_group_sector83
Payment plan ss_group_sector83Payment plan ss_group_sector83
Payment plan ss_group_sector83
Abloom Realty Services Pvt. Ltd.
 
Construction Vital Statistics - July 2016
Construction Vital Statistics - July 2016Construction Vital Statistics - July 2016
Construction Vital Statistics - July 2016
CBIZ, Inc.
 
Construction Vital Statistics August 2018
Construction Vital Statistics August 2018Construction Vital Statistics August 2018
Construction Vital Statistics August 2018
CBIZ, Inc.
 
CDOT PIM Bid Results - Feb 2020
CDOT PIM Bid Results - Feb 2020CDOT PIM Bid Results - Feb 2020
CDOT PIM Bid Results - Feb 2020
LaSheita Sayer
 
Construction Vital Statistics - March 2016
Construction Vital Statistics - March 2016Construction Vital Statistics - March 2016
Construction Vital Statistics - March 2016
CBIZ, Inc.
 
Construction Vital Statistics July 2018
Construction Vital Statistics July 2018Construction Vital Statistics July 2018
Construction Vital Statistics July 2018
CBIZ, Inc.
 
Construction Vital Statistics - December 2015
Construction Vital Statistics - December 2015Construction Vital Statistics - December 2015
Construction Vital Statistics - December 2015
CBIZ, Inc.
 
CBIZ MHM Construction Vital Statistics - April 2016
CBIZ MHM Construction Vital Statistics - April 2016CBIZ MHM Construction Vital Statistics - April 2016
CBIZ MHM Construction Vital Statistics - April 2016
CBIZ, Inc.
 
Construction Vital Statistics - January 2016
Construction Vital Statistics - January 2016Construction Vital Statistics - January 2016
Construction Vital Statistics - January 2016
CBIZ, Inc.
 
Construction Vital Statistics - Year End 2016
Construction Vital Statistics - Year End 2016Construction Vital Statistics - Year End 2016
Construction Vital Statistics - Year End 2016
CBIZ, Inc.
 
Construction Vital Statistics October 2018
Construction Vital Statistics October 2018Construction Vital Statistics October 2018
Construction Vital Statistics October 2018
CBIZ, Inc.
 
Construction Vital Statistics March 2017
 Construction Vital Statistics March 2017 Construction Vital Statistics March 2017
Construction Vital Statistics March 2017
CBIZ, Inc.
 
Construction Vital Statistics - May 2016
Construction Vital Statistics - May 2016Construction Vital Statistics - May 2016
Construction Vital Statistics - May 2016
CBIZ, Inc.
 
Construction Vital Statistics September 2018
Construction Vital Statistics September 2018Construction Vital Statistics September 2018
Construction Vital Statistics September 2018
CBIZ, Inc.
 

What's hot (20)

Construction Vital Statistics - November 2015
Construction Vital Statistics - November 2015Construction Vital Statistics - November 2015
Construction Vital Statistics - November 2015
 
Construction Vital Statistics - June 2016
Construction Vital Statistics - June 2016Construction Vital Statistics - June 2016
Construction Vital Statistics - June 2016
 
Construction Vital Statistics - December 2016
Construction Vital Statistics - December 2016Construction Vital Statistics - December 2016
Construction Vital Statistics - December 2016
 
Construction Vital Statistics - August 2016
Construction Vital Statistics - August 2016Construction Vital Statistics - August 2016
Construction Vital Statistics - August 2016
 
Construction Vital Statistics February 2017
Construction Vital Statistics February 2017Construction Vital Statistics February 2017
Construction Vital Statistics February 2017
 
Factory Double sghift
Factory Double sghift Factory Double sghift
Factory Double sghift
 
Payment plan ss_group_sector83
Payment plan ss_group_sector83Payment plan ss_group_sector83
Payment plan ss_group_sector83
 
Construction Vital Statistics - July 2016
Construction Vital Statistics - July 2016Construction Vital Statistics - July 2016
Construction Vital Statistics - July 2016
 
Construction Vital Statistics August 2018
Construction Vital Statistics August 2018Construction Vital Statistics August 2018
Construction Vital Statistics August 2018
 
CDOT PIM Bid Results - Feb 2020
CDOT PIM Bid Results - Feb 2020CDOT PIM Bid Results - Feb 2020
CDOT PIM Bid Results - Feb 2020
 
Construction Vital Statistics - March 2016
Construction Vital Statistics - March 2016Construction Vital Statistics - March 2016
Construction Vital Statistics - March 2016
 
Construction Vital Statistics July 2018
Construction Vital Statistics July 2018Construction Vital Statistics July 2018
Construction Vital Statistics July 2018
 
Construction Vital Statistics - December 2015
Construction Vital Statistics - December 2015Construction Vital Statistics - December 2015
Construction Vital Statistics - December 2015
 
CBIZ MHM Construction Vital Statistics - April 2016
CBIZ MHM Construction Vital Statistics - April 2016CBIZ MHM Construction Vital Statistics - April 2016
CBIZ MHM Construction Vital Statistics - April 2016
 
Construction Vital Statistics - January 2016
Construction Vital Statistics - January 2016Construction Vital Statistics - January 2016
Construction Vital Statistics - January 2016
 
Construction Vital Statistics - Year End 2016
Construction Vital Statistics - Year End 2016Construction Vital Statistics - Year End 2016
Construction Vital Statistics - Year End 2016
 
Construction Vital Statistics October 2018
Construction Vital Statistics October 2018Construction Vital Statistics October 2018
Construction Vital Statistics October 2018
 
Construction Vital Statistics March 2017
 Construction Vital Statistics March 2017 Construction Vital Statistics March 2017
Construction Vital Statistics March 2017
 
Construction Vital Statistics - May 2016
Construction Vital Statistics - May 2016Construction Vital Statistics - May 2016
Construction Vital Statistics - May 2016
 
Construction Vital Statistics September 2018
Construction Vital Statistics September 2018Construction Vital Statistics September 2018
Construction Vital Statistics September 2018
 

Similar to Dashboard

BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
Vijay Pandey
 
21 Capex 22-23 Template BPCL Jan 2024.pptx
21 Capex 22-23 Template BPCL Jan 2024.pptx21 Capex 22-23 Template BPCL Jan 2024.pptx
21 Capex 22-23 Template BPCL Jan 2024.pptx
Manish Singh
 
JP Morgan Data Center Technology Town Hall 2008
JP Morgan Data Center Technology Town Hall 2008JP Morgan Data Center Technology Town Hall 2008
JP Morgan Data Center Technology Town Hall 2008
John Napier
 
Team+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 springTeam+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 spring
Jaeho Jung
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
Bruce Tharp
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
IRJET Journal
 
The Six March 19th
The Six March 19thThe Six March 19th
The Six March 19th
Ray Kad, PMP, P.Eng.
 
Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013
Pedram Danesh-Mand
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET Journal
 
004 benchmarking and productivity
004 benchmarking and productivity004 benchmarking and productivity
004 benchmarking and productivity
Dr Fereidoun Dejahang
 
Cost Forecast Report
Cost Forecast ReportCost Forecast Report
FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptx
Jeff747294
 
Scott-Macon Aerospace & Defense Monthly Update (November 2018)
Scott-Macon Aerospace & Defense Monthly Update (November 2018)Scott-Macon Aerospace & Defense Monthly Update (November 2018)
Scott-Macon Aerospace & Defense Monthly Update (November 2018)
Michael Papazis
 
CDOT PIM Bid Results Oct 2020
CDOT PIM Bid Results Oct 2020CDOT PIM Bid Results Oct 2020
CDOT PIM Bid Results Oct 2020
LaSheita Sayer
 
M20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdfM20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdf
MohammedYASEEN963424
 
Test Metrics
Test MetricsTest Metrics
Test Metrics
Devukjs
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
IRJET Journal
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0
Mark S. Mahre
 
Productivity Research Network, March 2018
Productivity Research Network, March 2018Productivity Research Network, March 2018
Productivity Research Network, March 2018
Office for National Statistics
 

Similar to Dashboard (20)

BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
 
21 Capex 22-23 Template BPCL Jan 2024.pptx
21 Capex 22-23 Template BPCL Jan 2024.pptx21 Capex 22-23 Template BPCL Jan 2024.pptx
21 Capex 22-23 Template BPCL Jan 2024.pptx
 
JP Morgan Data Center Technology Town Hall 2008
JP Morgan Data Center Technology Town Hall 2008JP Morgan Data Center Technology Town Hall 2008
JP Morgan Data Center Technology Town Hall 2008
 
Team+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 springTeam+2 energyt+storage+system final_2013 spring
Team+2 energyt+storage+system final_2013 spring
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
The Six March 19th
The Six March 19thThe Six March 19th
The Six March 19th
 
Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
004 benchmarking and productivity
004 benchmarking and productivity004 benchmarking and productivity
004 benchmarking and productivity
 
Cost Forecast Report
Cost Forecast ReportCost Forecast Report
Cost Forecast Report
 
FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptx
 
Scott-Macon Aerospace & Defense Monthly Update (November 2018)
Scott-Macon Aerospace & Defense Monthly Update (November 2018)Scott-Macon Aerospace & Defense Monthly Update (November 2018)
Scott-Macon Aerospace & Defense Monthly Update (November 2018)
 
CDOT PIM Bid Results Oct 2020
CDOT PIM Bid Results Oct 2020CDOT PIM Bid Results Oct 2020
CDOT PIM Bid Results Oct 2020
 
M20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdfM20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdf
 
Test Metrics
Test MetricsTest Metrics
Test Metrics
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
SOC-2 Compliance Status Report sample v10.0
SOC-2 Compliance Status Report   sample v10.0SOC-2 Compliance Status Report   sample v10.0
SOC-2 Compliance Status Report sample v10.0
 
Productivity Research Network, March 2018
Productivity Research Network, March 2018Productivity Research Network, March 2018
Productivity Research Network, March 2018
 

Recently uploaded

Credit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentationCredit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentation
bernanbumatay1
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
RoopaTemkar
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
dsnow9802
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
GanpatiKumarChoudhar
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
8p28uk6g
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
Make it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdfMake it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdf
Resonate Digital
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
stuwilson.co.uk
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 

Recently uploaded (20)

Credit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentationCredit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentation
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
Make it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdfMake it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdf
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 

Dashboard

  • 1. Project Controls Exuctive Summary Report Month Jan-18 TEST_Project TEST98-108-2018 Nov-17 Nov-19 9% 9% 8% Engineering 1.0 2.0 1.0 1.0 2.0 - Procurement 1.0 2.0 1.0 1.5 2.5 (0.5) Construction 1.0 3.0 1.0 3.0 4.0 (1.0) Other Cost 1.0 1.0 0.5 0.5 1.0 - Project Cost 3.0 7.0 3.0 5.5 8.5 (1.5) Contract Value 4.0 8.0 3.5 6.0 9.5 (1.5) Committed Variance Project Number Project Name Project Start Date EAC Project Planned Finish Date Project Time elapsed % Project Planned Progress Project Actual Progress Revised BudgetBudgetM USD ETC 0 2 22%20% 0% 5% 10% 15% 20% Construction Planned Actual 50%46% 0% 10% 20% 30% 40% 50% 60% Engineering Actual Planned 27%26% 0% 5% 10% 15% 20% 25% 30% Procurement Planned Actual 25%24% 0% 5% 10% 15% 20% 25% 30% Overall EPPC Planned Actual Planned Progrees Vs. Actual Progress (January 2018 ) $0 $2 $4 $6 $8 $10 $12 $14 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Millions Engineering Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC) $0 $50 $100 $150 $200 $250 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Millions Procurement Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC) $0 $100 $200 $300 $400 $500 $600 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Millions Overall Project KPI's Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC) Earned Value analysis (January 2018 ) 0 0.5 1 1.5 2 2.5 3 Sum of 1-Aug Sum of 1-Sep Sum of 1-Oct Sum of 1-Nov Sum of 1-Dec Sum of 1-Jan Planned Progrees Vs. Actual Progress (January 2018 ) ALL CPI (Construction) CPI (Engineering) CPI (Overall EPPC) CPI (Procurement) SPI (Construction) SPI (Engineering) SPI (Overall EPPC) SPI (Procurement) Project Main points Project Performance 9% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Project Time elapsed % 0% 2 SPI 0% 100% SPI 0% 100% SPI $0 $40 $80 $120 $160 $200 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 Millions Construction Cumulative Planned Value (PV) Cumulative Earned Value (EV) Cumulative Actual Cost (AC)