Geo Technical Engineering Compaction
- 5. SIVA
Copyright©2001
5
Zero Air Void Curve
All compaction points should lie
to the left of ZAV curve
- corresponds to 100% saturation
Water content
Drydensity(ρd)
Zero air void curve (S=100%)
s
ws
d
wG
G
+
=
1
:Eq
ρ
ρ
S<100%
S>100% (impossible)
- 14. SIVA
Copyright©2001
14
Compaction Control
-a systematic exercise where you check
at regular intervals whether the
compaction was done to specifications.
e.g., 1 test per
1000 m3
of
compacted soil
e.g., 1 test per
1000 m3
of
compacted soil
• Minimum dry density
• Range of water content
• Minimum dry density
• Range of water content
Field measurements (of ρd) obtained using
• sand cone
• nuclear density meter
- 15. SIVA
Copyright©2001
15
Laboratory Compaction Test
- to obtain the compaction curve and define the
optimum water content and maximum dry density for a
specific compactive effort.
hammerStandard Proctor: Modified Proctor:
• 3 layers
• 25 blows per layer
• 5 layers
• 25 blows per layer
• 2.7 kg hammer
• 300 mm drop
• 4.9 kg hammer
• 450 mm drop
1000 ml compaction mould
- 17. SIVA
Copyright©2001
Dynamic Compaction
- pounding the ground by a heavy weight
Suitable for granular soils, land fills and
karst terrain with sink holes.
Crater created by the impact
Pounder (Tamper)
solution cavities in
limestone
(to be backfilled)
Editor's Notes
- This is an Australian excavator, with height of a 3-storey building