SlideShare a Scribd company logo
1 of 17
Distributed Generation Project for Contingency Analysis and Optimal Location of
Distibuted Generation of a Wind Farm with Total Capacity of 45MW
By
1. Kiran Patel(K00368348)
2. Ejike-Ukah Christopher (K00368026)
3. Jignesh Panchal(K00355196)
4. Kshitija V. Joshi (K00369594)
Advisor- Dr. Tarek Masaud
Renewable Energy and Distributed Generation (EEEN-5303)
Department of Electrical & Computer Engineering
Texas A&M University – Kingsville
Submission Date: 12.2.2015
1. Steady State Condition
Figure 1: Simulation under Steady State condition of a 5-bus System
Figure 1 above shows the simulation of IEEE 5 Bus test system with each transmission
line having maximum capacity of 150 MVA under steady state condition using Power World
Simulator. The figure displays the various bus voltages (pu), the percentage line loading and
the active and reactive power generated at the slack/ reference bus. Figure 2 and Figure 3 below
describes the Model Explorer information of the 5 Bus system above which displays the system
information (Voltages, Load, generated P and Q). Figure 3 displays the Model explorer for the
various line loading percentage states.
Figure 2: Model Explorer showing System Information Under steady state condition
Figure 3: Line Loading Percentage under Steady state Condition
2. Contingency Cases
Contingency cases are unforeseen emergency conditions in power systems that often
lead to system outage. These cases have to be analyzed, and optimum solutions have to
be made in order to provide system reliability whenever these conditions occur. For this
report, optimal placing of distributed generation (DG) will be analyzed to clear the
contingency cases involved. The DG is a small group of wind turbines with a total
capacity of 45MW utilizing DFIG. The following are contingency cases:
A. Contingency Case 1: Outage of Transmission Line 1-2
After simulating this Contingency case on Power World Simulator, the software
provided 5 violations, and the violations are as follows:
1) 128% line overloading of transmission line 1-5
2) Voltage level of Load bus2- 0.78pu< 0.95pu
3) Voltage level of Load bus2- 0.81pu< 0.95pu
4) Voltage level of Load bus2- 0.90pu< 0.95pu
5) Voltage level of Load bus2- 0.78pu< 0.95pu
This contingency case is described in Figure 4 below. Case 1 was caused by an
outage in Transmission line 1-2, which diverted all the power transmission to
Line 1-5 in order to supply the load demand at buses 2, 3, 4, and 5. This stress
on the transmission structure caused an overloading percentage of 128% on
transmission Line 1-5, and caused a considerable voltage drop below the
permissible value (0.95 pu) for the voltage values on buses 2, 3, 4, and 5.
Figure 4: Contingency Case 1- Outage of Transmission Line 1-2
The Report for the contingency case 1 can be seen below;
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
PowerWorld Simulator 18 Educational, Optimal
Power Flow (OPF), Security Constrained OPF (SCOPF), OPF Reserves,
Available Transfer Capability (ATC), PV and QV Curves (PVQV),
Transient Stability, Geomagnetically Induced Current
Contingency Analysis
Name of Base Case: Outage of Transmission Line 1-2
Report printed at: 11/30/2015 9:48:11 PM
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Case Description and Summary
Description:
No description provided.
Characteristics:
Number of buses: 5
Number of gens: 1
Number of loads: 4
Number of switched shunts: 0
Number of AC lines/xfmrs: 6
Number of DC lines: 0
Number of areas: 1
Number of zones: 1
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Base-Case Branch Outages
None.
Base-Case Generator Outages
None.
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Bus Voltage Extremes
Bus Bus Lowest Due To Highest
Due To
Name Number Voltage Contingency Voltage
Contingency
----------------------------------------------------------------
----------------------------
Slack bus1 1 0.0000 none 0.0000
none
load bus2 2 0.7772 Outage of Transmission L 0.0000
none
load bus3 3 0.8086 Outage of Transmission L 0.0000
none
load bus4 4 0.8410 Outage of Transmission L 0.0000
none
load bus5 5 0.8988 Outage of Transmission L 0.0000
none
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Branch Flow Extremes
From To Ckt Max % Due To
Bus Bus ID Flow Contingency
----------------------------------------------------------------
---------------
Slack bus1 load bus2 1 0.000 none
Slack bus1 load bus5 1 132.976 Outage of Transmission L
load bus2 load bus3 1 0.000 none
load bus3 load bus4 1 0.000 none
load bus5 load bus3 1 0.000 none
load bus4 load bus5 1 0.000 none
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
CONTINGENCY Outage of Transmission Line 1-2
ELEMENTS:
OPEN Line 1 (Slack bus1) TO 2 (load bus2) CKT 1 | |
CHECK | 0.000000 |
APPLIED AND SKIPPED ELEMENTS:
Applied:
OPEN Line Slack bus1_138.0 (1) TO load bus2_138.0 (2)
CKT 1 | | CHECK | | Opened flow of 74.73 MVA | ELEMENT
NUMBER OF VIOLATIONS BY CATEGORY (Total = 5)
BRANCH: 1
BUS VOLTAGE: 4
INTERFACE: 0
LOAD ISLANDED: NONE
GENERATION ISLANDED: NONE
BRANCH MVA VIOLATIONS:
1 (Slack bus1) TO 5 (load bus5) CKT 1 MVA: 199.5
LIMIT: 150.0 %: 133.0 Base Case Value: 92.5
BRANCH AMP VIOLATIONS:
None.
BUS LOW VOLTAGE VIOLATIONS:
2 (load bus2) LOW V VOLT: 0.7772 LIMIT: 0.9000
Base Case Value: 0.9964
3 (load bus3) LOW V VOLT: 0.8086 LIMIT: 0.9000
Base Case Value: 0.9894
4 (load bus4) LOW V VOLT: 0.8410 LIMIT: 0.9000
Base Case Value: 0.9872
5 (load bus5) LOW V VOLT: 0.8988 LIMIT: 0.9000
Base Case Value: 1.0019
BUS HIGH VOLTAGE VIOLATIONS:
None.
INTERFACE VIOLATIONS:
None.
Solution to Contingency Case 1
Resolving Contingency Case 1 can be achieved by optimally placing the DG at a location that
will improve the system reliability. In order to obtain the optimal location the following criteria
must be observed:
1) Placing the DG on any Bus must clear all the violations on the contingency
case1.
2) Better bus voltage values on all the other buses above 0.95pu
3) Lowest Line loading in the transmission network
4) Obtaining the DG operating power factor between 0.90pu<pf<0.95
We will be analyzing the various locations for the DG that will meet the above criteria.
Placing the DG on Load bus 3: this can be shown on figure 5 below
 Placing the DG on load bus 3 clears all 5 violations for contingency case 1, thereby
meeting criteria 1.
 This meets the voltage value criterion 2 on all buses above 0.95pu.
 This has a total of 168% on all the transmission lines without overloading any
transmission line.
 The DG placed on this Bus 3 has on operating factor of 0.8983 which does not meet the
fourth criterion for DG operating Power Factor.
Figure 5: Scenario for Placing DG at Load Bus 3 after Contingency Case 1
Placing the DG on load bus 4: the simulation of this scenario is shown on Figure 6 below
 Placing the DG on Load bus 4 clears the 5 violations for contingency case 1
 Does not meet criterion 2 because all the individual voltage values are not above
0.95pu, load bus 2 & 3 have 0.92pu and 0.94pu respectively.
 This scenario has total percentage line loading of 186% on all the transmission lines
with a high line loading of 80% on line 1-5 as seen in figure 6 below.
 The Operating Factor of the DG in this scenario is 0.9283, which meets criterion 4.
Figure 6: Scenario for Placing DG at Load Bus 4 after Contingency Case 1
Placing DG on load bus 5: The simulation of this scenario can be seen in figure 7. According
the 4 criteria above, we will analyze this scenario:
 This clears the 5 violations for the contingency case 1
 This scenario does not meet criterion 2 because the voltages on Load bus 2 and 3 are
0.91pu and 0.93pu respectively.
 This scenario has a total line loading of 208% on the entire transmission network, with
an 81% line loading on line 1-5.
 The operating Power factor of the DG is 0.7724, which does not meet Criterion 4.
Figure 7: Scenario for Placing DG at Load Bus 5 after Contingency Case 1
Placing the DG on Load bus 2: Figure 8 shows the simulation of this scenario.
 This scenario clears all the 5 violations for the contingency case 1.
 Placing the DG on this bus, provides better voltage values >0.95pu on all the other
buses, therefore meeting the requirements of criterion 2.
 This has a total percentage Line loading of 137% on the entire transmission network,
which is the lowest line loading for the network compared to other scenarios.
 The operating DG power factor in this scenario is 0.9422, and this meets criterion 4.
Figure 8: Scenario for Placing DG at Load Bus 2 after Contingency Case 1 (OPTIMUM
LOCATION)
Conclusively, Placing the DG at load bus 2 meets all the criteria for optimal location of
the DG in this 5-bus system to resolve contingency case 1 which involves the outage of
transmission line 1-2. Therefore, Load bus 2 is the optimal location for placing the Distributed
generation of a wind farm of 45MW (Variable speed Wind turbine utilizing DFIG).
B. Contingency Case 2: Bus 4 MW demand has been increased to 110MW
After simulating this Contingency case on Power World Simulator, the software
provided 2 violations, and the violations are as follows:
1) 108% line overloading of transmission line 1-5
2) Voltage level on load bus 4 is 0.87pu which is below the permissible
voltage value above 0.95pu.
This contingency case 2 is described in Figure 9. Due to the low resistance and
reactance of the transmission line 1-5 compared to that of transmission line 1-2,
and the fact that transmission line 1-5 has to primarily supply the load demand at
load bus 5, 4 and 3, there is an overload of 104% - 108% of transmission line 1-
5, and there is a poor voltage value of 0.87pu at load bus 4 when the MW
demand at load bus 4 is increased to 110MW.
Figure 9: Contingency case 2-Bus 4 MW demand has been increased to 110MW
The contingency analysis report from the Power world Simulator software is as follows;
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
PowerWorld Simulator 18 Educational, Optimal
Power Flow (OPF), Security Constrained OPF (SCOPF), OPF Reserves,
Available Transfer Capability (ATC), PV and QV Curves (PVQV),
Transient Stability, Geomagnetically Induced Current
Contingency Analysis
Name of Base Case: Bus 4 MW demand has been increased to
110MW
Report printed at: 11/30/2015 10:58:06 PM
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Case Description and Summary
Description:
No description provided.
Characteristics:
Number of buses: 5
Number of gens: 1
Number of loads: 4
Number of switched shunts: 0
Number of AC lines/xfmrs: 6
Number of DC lines: 0
Number of areas: 1
Number of zones: 1
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Base-Case Branch Outages
None.
Base-Case Generator Outages
None.
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Bus Voltage Extremes
Bus Bus Lowest Due To Highest
Due To
Name Number Voltage Contingency Voltage
Contingency
----------------------------------------------------------------
----------------------------
Slack bus1 1 0.0000 none 0.0000
none
load bus2 2 0.0000 none 0.0000
none
load bus3 3 0.0000 none 0.0000
none
load bus4 4 0.8732 Bus 4 MW demand has been 0.0000
none
load bus5 5 0.0000 none 0.0000
none
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
Branch Flow Extremes
From To Ckt Max % Due To
Bus Bus ID Flow Contingency
----------------------------------------------------------------
---------------
Slack bus1 load bus2 1 0.000 none
Slack bus1 load bus5 1 108.228 Bus 4 MW demand has been
load bus2 load bus3 1 0.000 none
load bus3 load bus4 1 0.000 none
load bus5 load bus3 1 0.000 none
load bus4 load bus5 1 0.000 none
*----*----*----*----*----*----*----*----*----*----*----*----*----*---
-*
CONTINGENCY Bus 4 MW demand has been increased to 110MW
ELEMENTS:
SET LOAD AT BUS 4 (load bus4) TO 110 MW | | CHECK |
0.000000 |
APPLIED AND SKIPPED ELEMENTS:
Applied:
SET LOAD AT BUS load bus4_138.0 (4) TO 110 MW | | CHECK
| | Bus changed from 30.00MW and 5.00Mvar by 80.00MW and
0.00Mvar | ELEMENT
NUMBER OF VIOLATIONS BY CATEGORY (Total = 2)
BRANCH: 1
BUS VOLTAGE: 1
INTERFACE: 0
LOAD ISLANDED: NONE
GENERATION ISLANDED: NONE
BRANCH MVA VIOLATIONS:
1 (Slack bus1) TO 5 (load bus5) CKT 1 MVA: 162.3
LIMIT: 150.0 %: 108.2 Base Case Value: 92.5
BRANCH AMP VIOLATIONS:
None.
BUS LOW VOLTAGE VIOLATIONS:
4 (load bus4) LOW V VOLT: 0.8732 LIMIT: 0.9000
Base Case Value: 0.9872
BUS HIGH VOLTAGE VIOLATIONS:
None.
INTERFACE VIOLATIONS:
None.
Solution to Contingency Case 2
Resolving Contingency Case 2 can be achieved by optimally placing the DG at a location that
will improve the system reliability. In order to obtain the optimal location the following criteria
must be observed:
1) Placing the DG on any Bus must clear all the violations on the contingency
case1.
2) Better bus voltage values on all the other buses above 0.95pu
3) Lowest Line loading in the transmission network
4) Obtaining the DG operating power factor between 0.90pu<pf<0.95
We will be analyzing the various locations for the DG that will meet the above criteria.
Placing the DG on Load bus 2: this can be shown on figure 10 below
 This scenario clears the 2 violations for contingency case 2.
 The voltage value for load bus 4 is 0.91pu which is below the permissible limit
>0.95pu. This does not meet the requirements for criteria 2.
 This scenario has a total line loading of 284% of the entire transmission network with
91% line loading of line 1-5.
 The operating Power factor of the DG in this scenario is 0.9212, which meets criteria 4.
Figure 10: Scenario for Placing DG at Load Bus 2 after Contingency Case 2
Placing the DG on Load bus 3: this can be shown on figure 11 below
 This scenario clears the 2 violations for contingency case 2
 The voltage at bus 4 is 0.94pu which is below the permissible voltage value >0.95pu.
This does not meet the requirements of the 2nd criterion.
 This scenario has a total line loading of 250% on the entire transmission network.
 The DG has an operation power factor of 0.8659, which does not meet the requirement
of criterion 4.
Figure 11: Scenario for Placing DG at load Bus 3 after Contingency Case 2
Placing the DG on Load bus 4: this can be shown on figure 12
 This scenario clears the 2 violations for contingency case 2 and this meets the
requirements for criterion 1.
 This scenario meets the requirements for criterion 2 because all bus voltage values are
above 0.95pu.
 Total line loading of 226% of the entire transmission network. In comparison to other
scenarios, this has the lowest line loading.
 The DG operating power factor for this scenario is 0.9138, and this meets the
requirements for criterion 4.
Figure 12: Scenario for Placing DG at load Bus 4 after Contingency Case 2 (OPTIMUM
LOCATION)
Placing the DG on Load bus 5: this can be shown on figure 13
 This scenario clears the 2 violations for contingency case 2 which meets criterion 1
requirements.
 Load bus 4 has a voltage value of 0.93pu which violates the requirements for criterion
2.
 This scenario has an entire line loading of 273% for the entire transmission network.
 The DG in this scenario has an operating power factor of 0.8321, which does not meet
the power factor requirements for criterion 4.
Figure 13: Scenario for Placing DG at Load Bus 5 after Contingency Case 2
Conclusively, placing the DG at Load bus 4 meets all the criteria for optimal location of the DG
(PV bus) to solve the contingency case 2. Therefore, Load bus 4 is the optimal location for
placing the DG in this 5-bus system configuration.
3. Conclusion
After various Simulation analysis, we were able to come up with four basic criteria in
this report for the optimal location of the DG (as a PV bus) to clear the given
contingency cases, and ensure a reliable power system.

More Related Content

What's hot

POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) Mathankumar S
 
Akshay AME 544 Lab Report
Akshay AME 544 Lab ReportAkshay AME 544 Lab Report
Akshay AME 544 Lab ReportAkshay Nerurkar
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-systembabu yadav
 
Indian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTIndian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTNikunj Parashar
 
Identification of Critical Transmission Lines in Power Networks and Intention...
Identification of Critical Transmission Lines in Power Networks and Intention...Identification of Critical Transmission Lines in Power Networks and Intention...
Identification of Critical Transmission Lines in Power Networks and Intention...FasilFarhan
 
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridAnalysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridBérengère VIGNAUX
 
Traction system
Traction systemTraction system
Traction systematul giri
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training pptKaushu Deshwal
 
Electric Traction System
Electric  Traction  SystemElectric  Traction  System
Electric Traction Systemsahotaharman
 
Stability Enhancement in Nine Bus System with STATCOM
Stability Enhancement in Nine Bus System with STATCOMStability Enhancement in Nine Bus System with STATCOM
Stability Enhancement in Nine Bus System with STATCOMIOSR Journals
 
ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)Arshad Hussain
 
Online Voltage Stability Analysis using Synchrophasor Technology
Online Voltage Stability Analysis using Synchrophasor TechnologyOnline Voltage Stability Analysis using Synchrophasor Technology
Online Voltage Stability Analysis using Synchrophasor Technologyijsrd.com
 
Distribution of power supply in indian railway
Distribution of power supply in indian railwayDistribution of power supply in indian railway
Distribution of power supply in indian railwaySurajit Mondal
 
Electric traction on railways
Electric traction on railwaysElectric traction on railways
Electric traction on railwaysParvez Pathan
 
Traction Motors and Control
Traction Motors and ControlTraction Motors and Control
Traction Motors and ControlSANTOSH GADEKAR
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankitAnkit Verma
 

What's hot (20)

Performance Investigation of a Monopolar HVDC Transmission System Feeding a ...
Performance Investigation of a Monopolar HVDC Transmission  System Feeding a ...Performance Investigation of a Monopolar HVDC Transmission  System Feeding a ...
Performance Investigation of a Monopolar HVDC Transmission System Feeding a ...
 
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
 
Ueet presentation
Ueet presentationUeet presentation
Ueet presentation
 
Akshay AME 544 Lab Report
Akshay AME 544 Lab ReportAkshay AME 544 Lab Report
Akshay AME 544 Lab Report
 
Ueet presentation
Ueet presentationUeet presentation
Ueet presentation
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
 
Indian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTIndian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPT
 
Identification of Critical Transmission Lines in Power Networks and Intention...
Identification of Critical Transmission Lines in Power Networks and Intention...Identification of Critical Transmission Lines in Power Networks and Intention...
Identification of Critical Transmission Lines in Power Networks and Intention...
 
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridAnalysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
 
Traction system
Traction systemTraction system
Traction system
 
133 english correcc
133  english correcc133  english correcc
133 english correcc
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training ppt
 
Electric Traction System
Electric  Traction  SystemElectric  Traction  System
Electric Traction System
 
Stability Enhancement in Nine Bus System with STATCOM
Stability Enhancement in Nine Bus System with STATCOMStability Enhancement in Nine Bus System with STATCOM
Stability Enhancement in Nine Bus System with STATCOM
 
ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)
 
Online Voltage Stability Analysis using Synchrophasor Technology
Online Voltage Stability Analysis using Synchrophasor TechnologyOnline Voltage Stability Analysis using Synchrophasor Technology
Online Voltage Stability Analysis using Synchrophasor Technology
 
Distribution of power supply in indian railway
Distribution of power supply in indian railwayDistribution of power supply in indian railway
Distribution of power supply in indian railway
 
Electric traction on railways
Electric traction on railwaysElectric traction on railways
Electric traction on railways
 
Traction Motors and Control
Traction Motors and ControlTraction Motors and Control
Traction Motors and Control
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankit
 

Viewers also liked (6)

Prezentacja sandra cichecka
Prezentacja sandra cicheckaPrezentacja sandra cichecka
Prezentacja sandra cichecka
 
Dynamic systems project (1)
Dynamic systems project (1)Dynamic systems project (1)
Dynamic systems project (1)
 
Neuromarketing Generational Intelligence -2013
Neuromarketing Generational Intelligence -2013Neuromarketing Generational Intelligence -2013
Neuromarketing Generational Intelligence -2013
 
школа семинар-2017
школа семинар-2017школа семинар-2017
школа семинар-2017
 
Microwave devices
Microwave devicesMicrowave devices
Microwave devices
 
Food photography
Food photographyFood photography
Food photography
 

Similar to Renewableproject (1)

EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsSanthosh Kumar
 
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...IRJET Journal
 
Load Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareLoad Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareIRJET Journal
 
Emergency generator sizing and motor starting analysis
Emergency generator sizing and motor starting analysisEmergency generator sizing and motor starting analysis
Emergency generator sizing and motor starting analysisHimmelstern
 
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET Journal
 
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...IRJET Journal
 
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy Logic
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy LogicIRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy Logic
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy LogicIRJET Journal
 
Voltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution NetworkVoltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution Networkiosrjce
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...IRJET Journal
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Designphase3-120A
 
Application of SVC on IEEE 6 Bus System for Optimization of Voltage Stability
Application of SVC on IEEE 6 Bus System for Optimization of Voltage StabilityApplication of SVC on IEEE 6 Bus System for Optimization of Voltage Stability
Application of SVC on IEEE 6 Bus System for Optimization of Voltage Stabilityijeei-iaes
 
Analyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareAnalyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareArslan Sajjad
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsIRJET Journal
 
Power Flow Analysis Part No 1.pdf
Power Flow Analysis Part No 1.pdfPower Flow Analysis Part No 1.pdf
Power Flow Analysis Part No 1.pdfmfalhajri
 
Combinational load shedding using load frequency control and voltage stabili...
Combinational load shedding using load frequency control and  voltage stabili...Combinational load shedding using load frequency control and  voltage stabili...
Combinational load shedding using load frequency control and voltage stabili...IJECEIAES
 

Similar to Renewableproject (1) (20)

(6) finite
(6) finite(6) finite
(6) finite
 
EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_Questions
 
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
 
SAIEE_Word_Des_Ver 1.15_IPT
SAIEE_Word_Des_Ver 1.15_IPTSAIEE_Word_Des_Ver 1.15_IPT
SAIEE_Word_Des_Ver 1.15_IPT
 
Load Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareLoad Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP Software
 
Emergency generator sizing and motor starting analysis
Emergency generator sizing and motor starting analysisEmergency generator sizing and motor starting analysis
Emergency generator sizing and motor starting analysis
 
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic SystemIRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
IRJET- Analysis of LVRT Capability of Grid Connected Solar Photovoltaic System
 
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
 
CH1.ppt
CH1.pptCH1.ppt
CH1.ppt
 
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy Logic
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy LogicIRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy Logic
IRJET- Improvement of Voltage Stability by Placing UPFC using Fuzzy Logic
 
I010616064
I010616064I010616064
I010616064
 
Voltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution NetworkVoltage Control Using Statcom in Dg Integrated With Distribution Network
Voltage Control Using Statcom in Dg Integrated With Distribution Network
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Design
 
Application of SVC on IEEE 6 Bus System for Optimization of Voltage Stability
Application of SVC on IEEE 6 Bus System for Optimization of Voltage StabilityApplication of SVC on IEEE 6 Bus System for Optimization of Voltage Stability
Application of SVC on IEEE 6 Bus System for Optimization of Voltage Stability
 
Analyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap softwareAnalyses and monitoring of 132 k v grid using etap software
Analyses and monitoring of 132 k v grid using etap software
 
06646829
0664682906646829
06646829
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital Circuits
 
Power Flow Analysis Part No 1.pdf
Power Flow Analysis Part No 1.pdfPower Flow Analysis Part No 1.pdf
Power Flow Analysis Part No 1.pdf
 
Combinational load shedding using load frequency control and voltage stabili...
Combinational load shedding using load frequency control and  voltage stabili...Combinational load shedding using load frequency control and  voltage stabili...
Combinational load shedding using load frequency control and voltage stabili...
 

Renewableproject (1)

  • 1. Distributed Generation Project for Contingency Analysis and Optimal Location of Distibuted Generation of a Wind Farm with Total Capacity of 45MW By 1. Kiran Patel(K00368348) 2. Ejike-Ukah Christopher (K00368026) 3. Jignesh Panchal(K00355196) 4. Kshitija V. Joshi (K00369594) Advisor- Dr. Tarek Masaud Renewable Energy and Distributed Generation (EEEN-5303) Department of Electrical & Computer Engineering Texas A&M University – Kingsville Submission Date: 12.2.2015
  • 2. 1. Steady State Condition Figure 1: Simulation under Steady State condition of a 5-bus System Figure 1 above shows the simulation of IEEE 5 Bus test system with each transmission line having maximum capacity of 150 MVA under steady state condition using Power World Simulator. The figure displays the various bus voltages (pu), the percentage line loading and the active and reactive power generated at the slack/ reference bus. Figure 2 and Figure 3 below describes the Model Explorer information of the 5 Bus system above which displays the system information (Voltages, Load, generated P and Q). Figure 3 displays the Model explorer for the various line loading percentage states.
  • 3. Figure 2: Model Explorer showing System Information Under steady state condition Figure 3: Line Loading Percentage under Steady state Condition
  • 4. 2. Contingency Cases Contingency cases are unforeseen emergency conditions in power systems that often lead to system outage. These cases have to be analyzed, and optimum solutions have to be made in order to provide system reliability whenever these conditions occur. For this report, optimal placing of distributed generation (DG) will be analyzed to clear the contingency cases involved. The DG is a small group of wind turbines with a total capacity of 45MW utilizing DFIG. The following are contingency cases: A. Contingency Case 1: Outage of Transmission Line 1-2 After simulating this Contingency case on Power World Simulator, the software provided 5 violations, and the violations are as follows: 1) 128% line overloading of transmission line 1-5 2) Voltage level of Load bus2- 0.78pu< 0.95pu 3) Voltage level of Load bus2- 0.81pu< 0.95pu 4) Voltage level of Load bus2- 0.90pu< 0.95pu 5) Voltage level of Load bus2- 0.78pu< 0.95pu This contingency case is described in Figure 4 below. Case 1 was caused by an outage in Transmission line 1-2, which diverted all the power transmission to Line 1-5 in order to supply the load demand at buses 2, 3, 4, and 5. This stress on the transmission structure caused an overloading percentage of 128% on transmission Line 1-5, and caused a considerable voltage drop below the permissible value (0.95 pu) for the voltage values on buses 2, 3, 4, and 5. Figure 4: Contingency Case 1- Outage of Transmission Line 1-2
  • 5. The Report for the contingency case 1 can be seen below; *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* PowerWorld Simulator 18 Educational, Optimal Power Flow (OPF), Security Constrained OPF (SCOPF), OPF Reserves, Available Transfer Capability (ATC), PV and QV Curves (PVQV), Transient Stability, Geomagnetically Induced Current Contingency Analysis Name of Base Case: Outage of Transmission Line 1-2 Report printed at: 11/30/2015 9:48:11 PM *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Case Description and Summary Description: No description provided. Characteristics: Number of buses: 5 Number of gens: 1 Number of loads: 4 Number of switched shunts: 0 Number of AC lines/xfmrs: 6 Number of DC lines: 0 Number of areas: 1 Number of zones: 1 *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Base-Case Branch Outages None. Base-Case Generator Outages None. *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Bus Voltage Extremes Bus Bus Lowest Due To Highest Due To Name Number Voltage Contingency Voltage Contingency ---------------------------------------------------------------- ---------------------------- Slack bus1 1 0.0000 none 0.0000 none load bus2 2 0.7772 Outage of Transmission L 0.0000 none load bus3 3 0.8086 Outage of Transmission L 0.0000 none load bus4 4 0.8410 Outage of Transmission L 0.0000 none load bus5 5 0.8988 Outage of Transmission L 0.0000 none
  • 6. *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Branch Flow Extremes From To Ckt Max % Due To Bus Bus ID Flow Contingency ---------------------------------------------------------------- --------------- Slack bus1 load bus2 1 0.000 none Slack bus1 load bus5 1 132.976 Outage of Transmission L load bus2 load bus3 1 0.000 none load bus3 load bus4 1 0.000 none load bus5 load bus3 1 0.000 none load bus4 load bus5 1 0.000 none *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* CONTINGENCY Outage of Transmission Line 1-2 ELEMENTS: OPEN Line 1 (Slack bus1) TO 2 (load bus2) CKT 1 | | CHECK | 0.000000 | APPLIED AND SKIPPED ELEMENTS: Applied: OPEN Line Slack bus1_138.0 (1) TO load bus2_138.0 (2) CKT 1 | | CHECK | | Opened flow of 74.73 MVA | ELEMENT NUMBER OF VIOLATIONS BY CATEGORY (Total = 5) BRANCH: 1 BUS VOLTAGE: 4 INTERFACE: 0 LOAD ISLANDED: NONE GENERATION ISLANDED: NONE BRANCH MVA VIOLATIONS: 1 (Slack bus1) TO 5 (load bus5) CKT 1 MVA: 199.5 LIMIT: 150.0 %: 133.0 Base Case Value: 92.5 BRANCH AMP VIOLATIONS: None. BUS LOW VOLTAGE VIOLATIONS: 2 (load bus2) LOW V VOLT: 0.7772 LIMIT: 0.9000 Base Case Value: 0.9964 3 (load bus3) LOW V VOLT: 0.8086 LIMIT: 0.9000 Base Case Value: 0.9894 4 (load bus4) LOW V VOLT: 0.8410 LIMIT: 0.9000 Base Case Value: 0.9872 5 (load bus5) LOW V VOLT: 0.8988 LIMIT: 0.9000 Base Case Value: 1.0019 BUS HIGH VOLTAGE VIOLATIONS: None. INTERFACE VIOLATIONS: None.
  • 7. Solution to Contingency Case 1 Resolving Contingency Case 1 can be achieved by optimally placing the DG at a location that will improve the system reliability. In order to obtain the optimal location the following criteria must be observed: 1) Placing the DG on any Bus must clear all the violations on the contingency case1. 2) Better bus voltage values on all the other buses above 0.95pu 3) Lowest Line loading in the transmission network 4) Obtaining the DG operating power factor between 0.90pu<pf<0.95 We will be analyzing the various locations for the DG that will meet the above criteria. Placing the DG on Load bus 3: this can be shown on figure 5 below  Placing the DG on load bus 3 clears all 5 violations for contingency case 1, thereby meeting criteria 1.  This meets the voltage value criterion 2 on all buses above 0.95pu.  This has a total of 168% on all the transmission lines without overloading any transmission line.  The DG placed on this Bus 3 has on operating factor of 0.8983 which does not meet the fourth criterion for DG operating Power Factor. Figure 5: Scenario for Placing DG at Load Bus 3 after Contingency Case 1
  • 8. Placing the DG on load bus 4: the simulation of this scenario is shown on Figure 6 below  Placing the DG on Load bus 4 clears the 5 violations for contingency case 1  Does not meet criterion 2 because all the individual voltage values are not above 0.95pu, load bus 2 & 3 have 0.92pu and 0.94pu respectively.  This scenario has total percentage line loading of 186% on all the transmission lines with a high line loading of 80% on line 1-5 as seen in figure 6 below.  The Operating Factor of the DG in this scenario is 0.9283, which meets criterion 4. Figure 6: Scenario for Placing DG at Load Bus 4 after Contingency Case 1 Placing DG on load bus 5: The simulation of this scenario can be seen in figure 7. According the 4 criteria above, we will analyze this scenario:  This clears the 5 violations for the contingency case 1  This scenario does not meet criterion 2 because the voltages on Load bus 2 and 3 are 0.91pu and 0.93pu respectively.  This scenario has a total line loading of 208% on the entire transmission network, with an 81% line loading on line 1-5.  The operating Power factor of the DG is 0.7724, which does not meet Criterion 4.
  • 9. Figure 7: Scenario for Placing DG at Load Bus 5 after Contingency Case 1 Placing the DG on Load bus 2: Figure 8 shows the simulation of this scenario.  This scenario clears all the 5 violations for the contingency case 1.  Placing the DG on this bus, provides better voltage values >0.95pu on all the other buses, therefore meeting the requirements of criterion 2.  This has a total percentage Line loading of 137% on the entire transmission network, which is the lowest line loading for the network compared to other scenarios.  The operating DG power factor in this scenario is 0.9422, and this meets criterion 4.
  • 10. Figure 8: Scenario for Placing DG at Load Bus 2 after Contingency Case 1 (OPTIMUM LOCATION) Conclusively, Placing the DG at load bus 2 meets all the criteria for optimal location of the DG in this 5-bus system to resolve contingency case 1 which involves the outage of transmission line 1-2. Therefore, Load bus 2 is the optimal location for placing the Distributed generation of a wind farm of 45MW (Variable speed Wind turbine utilizing DFIG). B. Contingency Case 2: Bus 4 MW demand has been increased to 110MW After simulating this Contingency case on Power World Simulator, the software provided 2 violations, and the violations are as follows: 1) 108% line overloading of transmission line 1-5 2) Voltage level on load bus 4 is 0.87pu which is below the permissible voltage value above 0.95pu. This contingency case 2 is described in Figure 9. Due to the low resistance and reactance of the transmission line 1-5 compared to that of transmission line 1-2, and the fact that transmission line 1-5 has to primarily supply the load demand at load bus 5, 4 and 3, there is an overload of 104% - 108% of transmission line 1- 5, and there is a poor voltage value of 0.87pu at load bus 4 when the MW demand at load bus 4 is increased to 110MW.
  • 11. Figure 9: Contingency case 2-Bus 4 MW demand has been increased to 110MW
  • 12. The contingency analysis report from the Power world Simulator software is as follows; *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* PowerWorld Simulator 18 Educational, Optimal Power Flow (OPF), Security Constrained OPF (SCOPF), OPF Reserves, Available Transfer Capability (ATC), PV and QV Curves (PVQV), Transient Stability, Geomagnetically Induced Current Contingency Analysis Name of Base Case: Bus 4 MW demand has been increased to 110MW Report printed at: 11/30/2015 10:58:06 PM *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Case Description and Summary Description: No description provided. Characteristics: Number of buses: 5 Number of gens: 1 Number of loads: 4 Number of switched shunts: 0 Number of AC lines/xfmrs: 6 Number of DC lines: 0 Number of areas: 1 Number of zones: 1 *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Base-Case Branch Outages None. Base-Case Generator Outages None. *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Bus Voltage Extremes Bus Bus Lowest Due To Highest Due To Name Number Voltage Contingency Voltage Contingency ---------------------------------------------------------------- ---------------------------- Slack bus1 1 0.0000 none 0.0000 none load bus2 2 0.0000 none 0.0000 none load bus3 3 0.0000 none 0.0000 none load bus4 4 0.8732 Bus 4 MW demand has been 0.0000 none
  • 13. load bus5 5 0.0000 none 0.0000 none *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* Branch Flow Extremes From To Ckt Max % Due To Bus Bus ID Flow Contingency ---------------------------------------------------------------- --------------- Slack bus1 load bus2 1 0.000 none Slack bus1 load bus5 1 108.228 Bus 4 MW demand has been load bus2 load bus3 1 0.000 none load bus3 load bus4 1 0.000 none load bus5 load bus3 1 0.000 none load bus4 load bus5 1 0.000 none *----*----*----*----*----*----*----*----*----*----*----*----*----*--- -* CONTINGENCY Bus 4 MW demand has been increased to 110MW ELEMENTS: SET LOAD AT BUS 4 (load bus4) TO 110 MW | | CHECK | 0.000000 | APPLIED AND SKIPPED ELEMENTS: Applied: SET LOAD AT BUS load bus4_138.0 (4) TO 110 MW | | CHECK | | Bus changed from 30.00MW and 5.00Mvar by 80.00MW and 0.00Mvar | ELEMENT NUMBER OF VIOLATIONS BY CATEGORY (Total = 2) BRANCH: 1 BUS VOLTAGE: 1 INTERFACE: 0 LOAD ISLANDED: NONE GENERATION ISLANDED: NONE BRANCH MVA VIOLATIONS: 1 (Slack bus1) TO 5 (load bus5) CKT 1 MVA: 162.3 LIMIT: 150.0 %: 108.2 Base Case Value: 92.5 BRANCH AMP VIOLATIONS: None. BUS LOW VOLTAGE VIOLATIONS: 4 (load bus4) LOW V VOLT: 0.8732 LIMIT: 0.9000 Base Case Value: 0.9872 BUS HIGH VOLTAGE VIOLATIONS: None. INTERFACE VIOLATIONS: None.
  • 14. Solution to Contingency Case 2 Resolving Contingency Case 2 can be achieved by optimally placing the DG at a location that will improve the system reliability. In order to obtain the optimal location the following criteria must be observed: 1) Placing the DG on any Bus must clear all the violations on the contingency case1. 2) Better bus voltage values on all the other buses above 0.95pu 3) Lowest Line loading in the transmission network 4) Obtaining the DG operating power factor between 0.90pu<pf<0.95 We will be analyzing the various locations for the DG that will meet the above criteria. Placing the DG on Load bus 2: this can be shown on figure 10 below  This scenario clears the 2 violations for contingency case 2.  The voltage value for load bus 4 is 0.91pu which is below the permissible limit >0.95pu. This does not meet the requirements for criteria 2.  This scenario has a total line loading of 284% of the entire transmission network with 91% line loading of line 1-5.  The operating Power factor of the DG in this scenario is 0.9212, which meets criteria 4. Figure 10: Scenario for Placing DG at Load Bus 2 after Contingency Case 2
  • 15. Placing the DG on Load bus 3: this can be shown on figure 11 below  This scenario clears the 2 violations for contingency case 2  The voltage at bus 4 is 0.94pu which is below the permissible voltage value >0.95pu. This does not meet the requirements of the 2nd criterion.  This scenario has a total line loading of 250% on the entire transmission network.  The DG has an operation power factor of 0.8659, which does not meet the requirement of criterion 4. Figure 11: Scenario for Placing DG at load Bus 3 after Contingency Case 2 Placing the DG on Load bus 4: this can be shown on figure 12  This scenario clears the 2 violations for contingency case 2 and this meets the requirements for criterion 1.  This scenario meets the requirements for criterion 2 because all bus voltage values are above 0.95pu.  Total line loading of 226% of the entire transmission network. In comparison to other scenarios, this has the lowest line loading.  The DG operating power factor for this scenario is 0.9138, and this meets the requirements for criterion 4.
  • 16. Figure 12: Scenario for Placing DG at load Bus 4 after Contingency Case 2 (OPTIMUM LOCATION) Placing the DG on Load bus 5: this can be shown on figure 13  This scenario clears the 2 violations for contingency case 2 which meets criterion 1 requirements.  Load bus 4 has a voltage value of 0.93pu which violates the requirements for criterion 2.  This scenario has an entire line loading of 273% for the entire transmission network.  The DG in this scenario has an operating power factor of 0.8321, which does not meet the power factor requirements for criterion 4.
  • 17. Figure 13: Scenario for Placing DG at Load Bus 5 after Contingency Case 2 Conclusively, placing the DG at Load bus 4 meets all the criteria for optimal location of the DG (PV bus) to solve the contingency case 2. Therefore, Load bus 4 is the optimal location for placing the DG in this 5-bus system configuration. 3. Conclusion After various Simulation analysis, we were able to come up with four basic criteria in this report for the optimal location of the DG (as a PV bus) to clear the given contingency cases, and ensure a reliable power system.