SlideShare a Scribd company logo
1 of 39
Evaluate your options with Minemax &
Studio OP
Jonathon Nortier – jnortier@amcconsultants.com
& Ali Sirkeci – asirkeci@amcconsultants.com
AMC Consultants
Datamine Symposium, Perth, March 2021
Contents
2
• Introduction
• Minemax Case Studies
• Studio OP Auto design
AMC
3
Global consultancy working across the mining industry
AMC and Datamine / Minemax
4
• 30 year history with Datamine
• Datamine and Minemax’s fundamental structure and
flexibility suits project work where we are constantly faced
with new and unusual challenges.
• Auditable process
• Allows us investigate ideas to add value
5
Why Minemax
• Flexibility
• Ability to ensure
a practical
mining
schedule
• Produce
numerous
scenarios
quickly to allow
study team to
evaluate
options.
Minemax approach
When to use Minemax
6
Scoping and Pre-feasibility studies,
Minemax is especially as useful at looking
at options
- Plant size
- SMU and equipment specifications
- Fleet size
- Expansion capital and timing
- Mill blend configurations
- Multi-pit blending and product
specification limitations
- Waste dump optimisation
7
Case Studies
• Capacity Study
• TSF constrained project & Autopit
• Pit sequencing and plant feed determination
• Waste dump optimisation
8
Capacity Study
Capacity study completed at the start of PFS to define what options to take
forward.
1. Setting: Large gold mine
2. Goal: Determine the optimal plant size
3. Other objectives:
• Guidance for future studies within PFS – SMU, mining equipment class,
bench height, ultimate pit shell selection
Pit optimisation inputs
9
SMU Options
X 3
Resource
Model
Mining
Equipment
X 3
Plant Capacity
Options
X 6
Pit Optimisations
54 combinations, 16 selected
Evaluate results
Generate MM
Inventories
Stage Selection
Diluted
Models
Unit Costs
Unit Costs
Minemax inputs
10
Minemax
Staging Precedence's
Minemax inputs
11
Minemax
Staging Precedence's
Mining Inventories
Minemax inputs
12
Minemax
Staging Precedence's
Mining Inventories
Mining Unit Costs
Minemax inputs
13
Minemax
Staging Precedence's
Mining Inventories
Mining Unit Costs
Grade Bins
Minemax inputs
14
Minemax
Staging Precedence's
Mining Inventories
Mining Unit Costs
Grade Bins
Processing Unit Costs
Increasing
Minemax inputs
15
Minemax
Staging Precedence's
Mining Inventories
Mining Unit Costs
Grade Bins
Processing Unit Costs
Mining Constraints
• TMM
• Mill Target
• VRA
• Stage Limit
Scenario Options
16
Throughout the capacity study 64 options were evaluated, testing:
• Impact of ultimate shell selection
• Impact of Inferred mineral resources on plant capacity selection
• Class of mining fleet
• Bench height and SMU size
Output
17
• Results allowed the client to
clearly see the impact of
increasing the plant capacity
has on project NPV.
• Knowing the outputs had
practical schedules to back
them up improved confidence
in data presented.
NPV / Initial
Capital
NPV
Increasing plant size
Output
18
• Results allowed the
client to clearly see the
impact of increasing
the plant capacity has
on project NPV.
• Knowing the outputs
had practical
schedules to back
them up improved
confidence in data
presented.
NPV / Initial
Capital
NPV
Increasing plant size
Output Schedules
19
Increasing plant throughput
Total movement
Mining by stage
Processing tonnes
Feed grade
Stockpile inventory
Cash flow
Gold production
Outcomes of study
20
• Provided guidance on plant capacity to allow PFS to progress
• Demonstrated that selected plant capacity was robust in terms of
final pit selection, conversion (or not) Inferred material and mining
equipment selection.
• Allowed study team to set the basis of design.
Minemax allowed us to the complete the study at level of detail and
confidence that the client expected for the magnitude of the
investment decision.
21
TSF Constrained
1. Setting: Existing operation with limited TSF expansion capacity.
2. Goal: Determine the optimal pit design for TSF capacity
3. Challenges:
• Select a pit too large and high grade at depth is deferred and processing plant
underutilized or low grade feed displaces future high grade
• Select a pit too small and less high grade feed is available later in the schedule.
• Fit in with existing pit development
• Limited mining width to split final stage to improve ore presentation to the plant
TSF Constrained - Approach
22
1. Completed pit optimization
2. Assess 4 different shells as ultimate pit limits
3. Use Auto-pit to generate pit designs that tie in with existing stages
4. Test options in Minemax
Studio OP Auto design pit demonstration
23
What is Auto design
Why AMC uses Auto design?
• Helps to visualize and evaluate the access concepts & options
• Ability to ensure mine-ability of interim pit versus pit optimisation shells
• Allows quick generation of multiple options to be evaluated
Auto-design video
24
TSF Constrained - Results
25
Mill tonnes
SP balance
Cash flow
Increasing pit size
Pit 1 Pit 2 Pit 3 Pit 4
26
TSF Constrained - Results
1 2 3 4
• Pit 1 – Contained just
enough ore to fill TSF
• Pit 2 – Some excess ore
• Pit 3 – Contained enough
High and Medium grade to
fill TSF
• Pit 4 – Large pit test upper
limit
27
Pit sequencing based on plant blending
constraints
1. Setting: Laterally extensive (~10 km long) potash deposit, >200 year life
2. Goal: Determine initial 20 year pit sequence, that satisfies multiple
processing and mining constraints.
3. Challenges:
• Deposit geology variable
• Multiple ore types requiring blending
• Pit optimisation does not define suitable initial pits
Approach – Round 1
28
1. Prepare mining model
2. Pit optimization, defined long life pit limit (>200 year mine life)
3. Use Minemax to define areas of initial interest (e.g. 20 year pit):
a) Run Minemax to identify mining location “hotspots”, using initial process plant
constraints and inputs.
b) Feedback loop with process design team (multiple iterations)
• complete sensitivity analysis of mining location to changes in process basis of
design
• test various tolerance ranges for process ratios and assess subsequent affect on
mining practicalities (e.g. mining face advancement erratic or manageable?).
• trade-off between mining and processing to establish and refine blend ratios.
Mining locations
29
LG Shell RF 0.5
LG Shell RF 1
Initial mining areas
identified for
Minemax
(first 20 years)
1. LG pit shells – final pit limits
reasonably insensitive to
inputs (i.e. large step
change at low RF, small
change between RF 0.5
to 1)
2. Minemax - starting areas
sensitive to changes in
process blend constraints
Approach – Round 2
30
1. Develop mining panel “stage” designs based on Round 1 outputs
2. Complete final schedule based on:
• Panel designs,
• Vertical rate of advance and inter-panel dependencies
• Final agreed processing constraints
• Plant feed rate and stockpile limits,
• Fleet equipment hours (two different fleets)
3. Prepare output for financial model.
Background – process ratios & constraints
31
Ore 3
Ore 2b
Waste 3
Ore 2a
Ore 1
Waste 2
Waste 1
Geological
Sequence
Stream
1 Ratio
Stream
1:2
Ratio
Constraint Description
Tonnage: plant feed Stream 1 (max.)
Tonnage: plant feed Stream 2 (max.)
Ratio: tonnes Ore 1 : Ore 2
Ratio: stream 1:2 molar K+ : K+
Grade: stream 2 Kainite (min.), variable over
time
Tonnage: final product Includes plant ramp-up
Volume: mined Fleet 1 (min., max.)
Volume: mined Fleet 2 (min., max.)
Location: mining panel Initial cut (incl. advance
dewatering)
Outcomes
32
1. Multiple mining sequences developed to articulate potential
blending scenarios to the process design team to allow the
process basis of design to be set.
2. Defined optimal pit and development sequence to meet selected
process plant constraints.
3. Minemax outputs contributed to the financial model which
ultimately allowed the client to obtain significant initial project
funding.
Minemax allowed us to successfully identify and quantify the problem
and was the tool that allowed us to develop a workable solution
33
Waste Dump Optimisation
1. Setting
• Gold mine with multiple pits
2. Goal
• Determine best waste dumping strategy with and without inpit dumps
3. Challenges
• Multiple access to waste dumps and inpit dumps
Waste Dump Optimisation
Waste dump designs
• Need to be oversized
• Design to be split into
dump cells
• Haulage network
designed to link all pit
and dump combinations
Pits Waste
dump
Waste
dump
Waste Dump Optimisation
Haulage Model Haulage model
• Needs to be split into pit
and dump components
that are linked by common
nodes
• Truck related variables
linked to pit and dump
models (e.g. Travel time,
fuel burn, haul distance)
Waste dump decision tree
Waste Dump Optimisation
Benefits
• Waste dump strategy
(short vs long dumping
and truck number
smoothing)
• Limit schedule to fleet
capacity
• Acid generating waste
dumping sequencing
• Helps cost modelling,
smoothing truck
numbers, less iterations
between estimator and
scheduler.
Truck hour
dashboard
Financial
Outputs
Waste Dump Optimisation
37
Outcomes
• Defined optimal final waste dump
landform and sequence for each
schedule option
• ~15 M$ NPV improvement with inpit
dumps
• Truck hours calculated for each
scenario and optimized based
capital expenditure
Thank you
amcconsultants.com

More Related Content

What's hot

Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik
 
Dug permian plg consulting final
Dug permian   plg consulting finalDug permian   plg consulting final
Dug permian plg consulting finalPLG Consulting
 
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...Taylor Robinson
 
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...Taylor Robinson
 
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboBuilding a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboAndrew Wachtel
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7KBC (A Yokogawa Company)
 
Industrial minerals frac sand conference sept 2014
Industrial minerals frac sand conference sept 2014Industrial minerals frac sand conference sept 2014
Industrial minerals frac sand conference sept 2014PLG Consulting
 
PLG Industrial Minerals Frac Sand Presentation
PLG Industrial Minerals Frac Sand PresentationPLG Industrial Minerals Frac Sand Presentation
PLG Industrial Minerals Frac Sand PresentationPLG Consulting
 
Haynesville Re-Frac Study
Haynesville Re-Frac StudyHaynesville Re-Frac Study
Haynesville Re-Frac Study Energent Group
 
Tem Park2011
Tem Park2011Tem Park2011
Tem Park2011Debbout
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Torben Haagh
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
Energent Group: Frac Sand Trends
Energent Group: Frac Sand TrendsEnergent Group: Frac Sand Trends
Energent Group: Frac Sand TrendsTodd Bush
 
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureIntegrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureStochastic Simulation
 

What's hot (20)

Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
 
Dug permian plg consulting final
Dug permian   plg consulting finalDug permian   plg consulting final
Dug permian plg consulting final
 
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
CCS storage appraisal study, Sam Gomersall, Pale Blue Dot - UKCCSRC Strathcly...
 
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...
Permian Basin Frac Design & New Completions Technologies 2017 - frac sand sup...
 
Cold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban AreasCold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban Areas
 
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC PresentationHighbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
 
Natural Gas Basics Webinar
Natural Gas Basics WebinarNatural Gas Basics Webinar
Natural Gas Basics Webinar
 
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
 
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumboBuilding a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
Building a haul road tor T282B Dump truck with GVM 600t same as A380 jumbo
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7
 
Industrial minerals frac sand conference sept 2014
Industrial minerals frac sand conference sept 2014Industrial minerals frac sand conference sept 2014
Industrial minerals frac sand conference sept 2014
 
PLG Industrial Minerals Frac Sand Presentation
PLG Industrial Minerals Frac Sand PresentationPLG Industrial Minerals Frac Sand Presentation
PLG Industrial Minerals Frac Sand Presentation
 
Haynesville Re-Frac Study
Haynesville Re-Frac StudyHaynesville Re-Frac Study
Haynesville Re-Frac Study
 
City of Edgewater CNG Presentation
City of Edgewater CNG PresentationCity of Edgewater CNG Presentation
City of Edgewater CNG Presentation
 
Tem Park2011
Tem Park2011Tem Park2011
Tem Park2011
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
Energent Group: Frac Sand Trends
Energent Group: Frac Sand TrendsEnergent Group: Frac Sand Trends
Energent Group: Frac Sand Trends
 
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureIntegrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
 
New research into asphalt pavements, and long-life (perpetual) asphalt
New research into asphalt pavements, and long-life (perpetual) asphaltNew research into asphalt pavements, and long-life (perpetual) asphalt
New research into asphalt pavements, and long-life (perpetual) asphalt
 

Similar to 2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax

Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...irvan septyan mulyana
 
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraft
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraftAdvanced Open Pit Planning And Design 2014 For NICICo FinalDraft
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraftJustin Knight
 
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in IlukaKristy Marshall
 
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten
 
Fabio brambilla shale_gas_convegno_bocconi
Fabio brambilla shale_gas_convegno_bocconiFabio brambilla shale_gas_convegno_bocconi
Fabio brambilla shale_gas_convegno_bocconiFabio Brambilla
 
CoreMet_Company Presentation_04
CoreMet_Company Presentation_04CoreMet_Company Presentation_04
CoreMet_Company Presentation_04Willie Hefer
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN - Convención Minera
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Carl Greenstreet
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...q-Maxim
 
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptxjmbmokoena
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nick Vukovich
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Society of Petroleum Engineers
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf20JE0369GAURAVKUMAR
 
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...Crimson Publishers-Production Scheduling in Block Caving with Consideration o...
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...CrimsonPublishersAMMS
 
Innovation and technology ecosystem - minerals and metals by Sandeep gupta
Innovation and technology ecosystem - minerals and metals  by Sandeep guptaInnovation and technology ecosystem - minerals and metals  by Sandeep gupta
Innovation and technology ecosystem - minerals and metals by Sandeep guptaSandeep Gupta
 
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsTPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsKey Engineering Solutions
 
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODEL
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODELEXPLORATION AND MINING (EM) BUSINESS REFERENCE MODEL
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODELThe Open Group SA
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Modern practices for the design and
Modern practices for the design andModern practices for the design and
Modern practices for the design andOgala Oscar
 

Similar to 2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax (20)

Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
 
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraft
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraftAdvanced Open Pit Planning And Design 2014 For NICICo FinalDraft
Advanced Open Pit Planning And Design 2014 For NICICo FinalDraft
 
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka7.  Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
7. Chung Chen, Iluka - Portfolio Optimisation using Minemax in Iluka
 
Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept Engineer
 
Fabio brambilla shale_gas_convegno_bocconi
Fabio brambilla shale_gas_convegno_bocconiFabio brambilla shale_gas_convegno_bocconi
Fabio brambilla shale_gas_convegno_bocconi
 
CoreMet_Company Presentation_04
CoreMet_Company Presentation_04CoreMet_Company Presentation_04
CoreMet_Company Presentation_04
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
 
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...q-Maxim’s approach to waste reduction in  foundry application  using Taguchi ...
q-Maxim’s approach to waste reduction in foundry application using Taguchi ...
 
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx
1658902048613_MBAKO INDUSTRIAL ATTACHMENT PRESENTATION.pptx
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
 
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...Crimson Publishers-Production Scheduling in Block Caving with Consideration o...
Crimson Publishers-Production Scheduling in Block Caving with Consideration o...
 
Innovation and technology ecosystem - minerals and metals by Sandeep gupta
Innovation and technology ecosystem - minerals and metals  by Sandeep guptaInnovation and technology ecosystem - minerals and metals  by Sandeep gupta
Innovation and technology ecosystem - minerals and metals by Sandeep gupta
 
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsTPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
 
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODEL
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODELEXPLORATION AND MINING (EM) BUSINESS REFERENCE MODEL
EXPLORATION AND MINING (EM) BUSINESS REFERENCE MODEL
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Modern practices for the design and
Modern practices for the design andModern practices for the design and
Modern practices for the design and
 

Recently uploaded

APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 

Recently uploaded (20)

APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 

2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax

  • 1. Evaluate your options with Minemax & Studio OP Jonathon Nortier – jnortier@amcconsultants.com & Ali Sirkeci – asirkeci@amcconsultants.com AMC Consultants Datamine Symposium, Perth, March 2021
  • 2. Contents 2 • Introduction • Minemax Case Studies • Studio OP Auto design
  • 3. AMC 3 Global consultancy working across the mining industry
  • 4. AMC and Datamine / Minemax 4 • 30 year history with Datamine • Datamine and Minemax’s fundamental structure and flexibility suits project work where we are constantly faced with new and unusual challenges. • Auditable process • Allows us investigate ideas to add value
  • 5. 5 Why Minemax • Flexibility • Ability to ensure a practical mining schedule • Produce numerous scenarios quickly to allow study team to evaluate options. Minemax approach
  • 6. When to use Minemax 6 Scoping and Pre-feasibility studies, Minemax is especially as useful at looking at options - Plant size - SMU and equipment specifications - Fleet size - Expansion capital and timing - Mill blend configurations - Multi-pit blending and product specification limitations - Waste dump optimisation
  • 7. 7 Case Studies • Capacity Study • TSF constrained project & Autopit • Pit sequencing and plant feed determination • Waste dump optimisation
  • 8. 8 Capacity Study Capacity study completed at the start of PFS to define what options to take forward. 1. Setting: Large gold mine 2. Goal: Determine the optimal plant size 3. Other objectives: • Guidance for future studies within PFS – SMU, mining equipment class, bench height, ultimate pit shell selection
  • 9. Pit optimisation inputs 9 SMU Options X 3 Resource Model Mining Equipment X 3 Plant Capacity Options X 6 Pit Optimisations 54 combinations, 16 selected Evaluate results Generate MM Inventories Stage Selection Diluted Models Unit Costs Unit Costs
  • 13. Minemax inputs 13 Minemax Staging Precedence's Mining Inventories Mining Unit Costs Grade Bins
  • 14. Minemax inputs 14 Minemax Staging Precedence's Mining Inventories Mining Unit Costs Grade Bins Processing Unit Costs Increasing
  • 15. Minemax inputs 15 Minemax Staging Precedence's Mining Inventories Mining Unit Costs Grade Bins Processing Unit Costs Mining Constraints • TMM • Mill Target • VRA • Stage Limit
  • 16. Scenario Options 16 Throughout the capacity study 64 options were evaluated, testing: • Impact of ultimate shell selection • Impact of Inferred mineral resources on plant capacity selection • Class of mining fleet • Bench height and SMU size
  • 17. Output 17 • Results allowed the client to clearly see the impact of increasing the plant capacity has on project NPV. • Knowing the outputs had practical schedules to back them up improved confidence in data presented. NPV / Initial Capital NPV Increasing plant size
  • 18. Output 18 • Results allowed the client to clearly see the impact of increasing the plant capacity has on project NPV. • Knowing the outputs had practical schedules to back them up improved confidence in data presented. NPV / Initial Capital NPV Increasing plant size
  • 19. Output Schedules 19 Increasing plant throughput Total movement Mining by stage Processing tonnes Feed grade Stockpile inventory Cash flow Gold production
  • 20. Outcomes of study 20 • Provided guidance on plant capacity to allow PFS to progress • Demonstrated that selected plant capacity was robust in terms of final pit selection, conversion (or not) Inferred material and mining equipment selection. • Allowed study team to set the basis of design. Minemax allowed us to the complete the study at level of detail and confidence that the client expected for the magnitude of the investment decision.
  • 21. 21 TSF Constrained 1. Setting: Existing operation with limited TSF expansion capacity. 2. Goal: Determine the optimal pit design for TSF capacity 3. Challenges: • Select a pit too large and high grade at depth is deferred and processing plant underutilized or low grade feed displaces future high grade • Select a pit too small and less high grade feed is available later in the schedule. • Fit in with existing pit development • Limited mining width to split final stage to improve ore presentation to the plant
  • 22. TSF Constrained - Approach 22 1. Completed pit optimization 2. Assess 4 different shells as ultimate pit limits 3. Use Auto-pit to generate pit designs that tie in with existing stages 4. Test options in Minemax
  • 23. Studio OP Auto design pit demonstration 23 What is Auto design Why AMC uses Auto design? • Helps to visualize and evaluate the access concepts & options • Ability to ensure mine-ability of interim pit versus pit optimisation shells • Allows quick generation of multiple options to be evaluated
  • 25. TSF Constrained - Results 25 Mill tonnes SP balance Cash flow Increasing pit size Pit 1 Pit 2 Pit 3 Pit 4
  • 26. 26 TSF Constrained - Results 1 2 3 4 • Pit 1 – Contained just enough ore to fill TSF • Pit 2 – Some excess ore • Pit 3 – Contained enough High and Medium grade to fill TSF • Pit 4 – Large pit test upper limit
  • 27. 27 Pit sequencing based on plant blending constraints 1. Setting: Laterally extensive (~10 km long) potash deposit, >200 year life 2. Goal: Determine initial 20 year pit sequence, that satisfies multiple processing and mining constraints. 3. Challenges: • Deposit geology variable • Multiple ore types requiring blending • Pit optimisation does not define suitable initial pits
  • 28. Approach – Round 1 28 1. Prepare mining model 2. Pit optimization, defined long life pit limit (>200 year mine life) 3. Use Minemax to define areas of initial interest (e.g. 20 year pit): a) Run Minemax to identify mining location “hotspots”, using initial process plant constraints and inputs. b) Feedback loop with process design team (multiple iterations) • complete sensitivity analysis of mining location to changes in process basis of design • test various tolerance ranges for process ratios and assess subsequent affect on mining practicalities (e.g. mining face advancement erratic or manageable?). • trade-off between mining and processing to establish and refine blend ratios.
  • 29. Mining locations 29 LG Shell RF 0.5 LG Shell RF 1 Initial mining areas identified for Minemax (first 20 years) 1. LG pit shells – final pit limits reasonably insensitive to inputs (i.e. large step change at low RF, small change between RF 0.5 to 1) 2. Minemax - starting areas sensitive to changes in process blend constraints
  • 30. Approach – Round 2 30 1. Develop mining panel “stage” designs based on Round 1 outputs 2. Complete final schedule based on: • Panel designs, • Vertical rate of advance and inter-panel dependencies • Final agreed processing constraints • Plant feed rate and stockpile limits, • Fleet equipment hours (two different fleets) 3. Prepare output for financial model.
  • 31. Background – process ratios & constraints 31 Ore 3 Ore 2b Waste 3 Ore 2a Ore 1 Waste 2 Waste 1 Geological Sequence Stream 1 Ratio Stream 1:2 Ratio Constraint Description Tonnage: plant feed Stream 1 (max.) Tonnage: plant feed Stream 2 (max.) Ratio: tonnes Ore 1 : Ore 2 Ratio: stream 1:2 molar K+ : K+ Grade: stream 2 Kainite (min.), variable over time Tonnage: final product Includes plant ramp-up Volume: mined Fleet 1 (min., max.) Volume: mined Fleet 2 (min., max.) Location: mining panel Initial cut (incl. advance dewatering)
  • 32. Outcomes 32 1. Multiple mining sequences developed to articulate potential blending scenarios to the process design team to allow the process basis of design to be set. 2. Defined optimal pit and development sequence to meet selected process plant constraints. 3. Minemax outputs contributed to the financial model which ultimately allowed the client to obtain significant initial project funding. Minemax allowed us to successfully identify and quantify the problem and was the tool that allowed us to develop a workable solution
  • 33. 33 Waste Dump Optimisation 1. Setting • Gold mine with multiple pits 2. Goal • Determine best waste dumping strategy with and without inpit dumps 3. Challenges • Multiple access to waste dumps and inpit dumps
  • 34. Waste Dump Optimisation Waste dump designs • Need to be oversized • Design to be split into dump cells • Haulage network designed to link all pit and dump combinations Pits Waste dump Waste dump
  • 35. Waste Dump Optimisation Haulage Model Haulage model • Needs to be split into pit and dump components that are linked by common nodes • Truck related variables linked to pit and dump models (e.g. Travel time, fuel burn, haul distance) Waste dump decision tree
  • 36. Waste Dump Optimisation Benefits • Waste dump strategy (short vs long dumping and truck number smoothing) • Limit schedule to fleet capacity • Acid generating waste dumping sequencing • Helps cost modelling, smoothing truck numbers, less iterations between estimator and scheduler. Truck hour dashboard Financial Outputs
  • 37. Waste Dump Optimisation 37 Outcomes • Defined optimal final waste dump landform and sequence for each schedule option • ~15 M$ NPV improvement with inpit dumps • Truck hours calculated for each scenario and optimized based capital expenditure