Loadout
Location

Donahue Creek
Sector:

Resources

Property Type:

Construction Aggregate

Stock Market Symbol:

TSXV: HBK; Frankfurt: V7O

52-Wk Trading...
•

Victor Bryant, I.Eng; MAusIMM. - President/CEO
•

Forty four years in the mining industry – Plant Design; Commissioning...
•

Luard J. Manning, P.Eng; Director and President of L.J. Manning &
Associates

•

Life Member B.C. Professional Engineer...
•

Jim Place, P.Geo.

•

Successfully managed gravel operations in the north-west region of BC
for 10 years.

•

Supervise...
•East side of Portland Canal fjord
on protected, year round ice free
tidewater
•

Site access by helicopter,
float equippe...
•

Total Land Tenure

•

Small area only to be used

•

Major position for potential
expansion in 10 years if required

•
...
•

Gravel extraction from the Swamp Point North deposit to supply
markets in NW British Columbia



To ship 235,000 tonne...
Conveyor Longitudinal Section

Loadout Dolphin Arrangement
Mine Manager – Stan Spletzer
•

Twenty six years contracting for road building, logging, and site
preparation for a number...
•

Run-off collection pits located strategically within
the mining areas

•

Run-off from affected areas outside of mine
l...
• Initial Nisga’a Meeting 2008 Discussing
Project and Opportunities

• Metlakatla Cooperative Agreement Signed November 20...
•

Complete 10 man work camp

•

Barge load out

•

One excavator @ 226 HP ea. (170 kW)

•

Two thirty tonne trucks @ 285 ...
EHSMS – Environmental, Health & Safety Management System
A - Occupational Health and Safety Plan
B – Mine Emergency Respon...
•

Overburden (est. 0.5 m thick) stripped and stockpiled as mining
progresses

•

Concurrent revegetation where possible

...
•

Department of Fisheries and Oceans
Initial enquiry to establish any concerns or impact on aquatic habitat
Transport Can...
Following issue of the Notice of Work the following action plan will
commence:
1) Carry out assessment of timber value and...
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
Upcoming SlideShare
Loading in …5
×

Highbank Resources - MDRC Presentation

7,438 views

Published on

Highbank Resources - MDRC Presentation

Published in: Investor Relations
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
7,438
On SlideShare
0
From Embeds
0
Number of Embeds
3,510
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Highbank Resources - MDRC Presentation

  1. 1. Loadout Location Donahue Creek
  2. 2. Sector: Resources Property Type: Construction Aggregate Stock Market Symbol: TSXV: HBK; Frankfurt: V7O 52-Wk Trading Range: C$ 0.025 - C$ 0.13 Shares I&O: 73,693,999 (as at August 20, 2013) Market Capitalization: C$5.2 million (approx.)
  3. 3. • Victor Bryant, I.Eng; MAusIMM. - President/CEO • Forty four years in the mining industry – Plant Design; Commissioning and Operations with Anglo American; Fluor; Wright Engineers, and Ausenco • • Alumbrera, Argentina, 60,000 tpd Copper/Gold –Post Commissioning • Batu Hijau, Indonesia, 120,000 tpd Commissioning Manager • Project Engineer, CVRD Samarco Iron Ore Expansion, Brazil • • Major Plants: Colomac Gold Mine, NWT – Lead Metallurgical Engineer/Commissioning Manager Other operations in Zambia; Ghana; Philippines – Plant Manager Gary Musil, Diploma B.A.; 3 yrs. CGA. - CFO • Over 32 years experience in the mining industry – Financial and consulting capacities • Officer and director in numerous public companies since 1988 • Managing all financial controls for projects in S. America; Eastern Europe and across Canada • Financial controller for Dickenson Mines Ltd. and Kam-Kotia Mines Ltd. • Director and Financial Controller of Highbank Resources since 1988
  4. 4. • Luard J. Manning, P.Eng; Director and President of L.J. Manning & Associates • Life Member B.C. Professional Engineers and CIMM. • Fifty years of mining experience in operating underground and open pit mines • Has supervised and critiqued mine engineering designs including Brandywine operation of Northair; the Ruth Vermont project for Columbia River Mines and the Rabbit Lake mine for Gulf Minerals • Work experience in Latin America; Canada, and U.S.A.
  5. 5. • Jim Place, P.Geo. • Successfully managed gravel operations in the north-west region of BC for 10 years. • Supervised road construction, exploration sampling, testing and development of aggregates sources throughout B.C. • Conducted quality assurance for quarried stone products used in a major BC port project. • Advised publically traded companies in America and Mexico regarding site selection and evaluation of numerous deposits
  6. 6. •East side of Portland Canal fjord on protected, year round ice free tidewater • Site access by helicopter, float equipped aircraft, or boat • 78 miles by sea north of Prince Rupert, closest West coast port to Asian markets by 33 hours • 38 miles south of the Port of Stewart & 35 miles North of Grassy Point also a potential new LNG terminal site
  7. 7. • Total Land Tenure • Small area only to be used • Major position for potential expansion in 10 years if required • Foreshore tenure also obtained for smaller area and loadout
  8. 8. • Gravel extraction from the Swamp Point North deposit to supply markets in NW British Columbia  To ship 235,000 tonnes per year of construction quality aggregate for construction projects in the Prince Rupert area and Liquefied Natural Gas (LNG) projects  Anticipated local market will sustain operations for at least 10 years  Major expansion potential if the market demand requires.  Future shipments to the U.S.A.
  9. 9. Conveyor Longitudinal Section Loadout Dolphin Arrangement
  10. 10. Mine Manager – Stan Spletzer • Twenty six years contracting for road building, logging, and site preparation for a number of forestry operations • Operated a gravel pit in Abbotsford for six years – zero regulatory infractions during this period • Previously partner in Western Concrete until sell out in 2010 • Trained operators for bulldozers, FEL’s and trucks • Plant operators and barge loading
  11. 11. • Run-off collection pits located strategically within the mining areas • Run-off from affected areas outside of mine location diverted to settling ponds • All wash plant water settled and re-cycled • Diversion ditches rip-rapped in locations of high flow velocity • Use of silt fences and large radius ditches to reduce sediment in runoff Typical silt bag • Catchment pond water returned to site or discharged if free of sediment • Water collection sumps exfiltrate or pumped out through silt bags
  12. 12. • Initial Nisga’a Meeting 2008 Discussing Project and Opportunities • Metlakatla Cooperative Agreement Signed November 2012 • Information on current project plans provided to Nisga’a and Metlakatla in 2013. • Ongoing invitations for discussions in 2013 and 2014. • Highbank will offer training opportunities to First Nation nominees through certified programmes
  13. 13. • Complete 10 man work camp • Barge load out • One excavator @ 226 HP ea. (170 kW) • Two thirty tonne trucks @ 285 HP ea. (210 kW) • One D8 Bulldozer @ 300 HP (220 kW) • One D5 Bulldozer @ 100 HP (75 kW) • Portable Crushing & Screening Plant @ 110 kW • Camp Site generator @ 300 kW • TOTAL ESTIMATED kW’s OPERATING @ 80% eff. = 1,036 kW (Equivalent of eight medium sized family cars)
  14. 14. EHSMS – Environmental, Health & Safety Management System A - Occupational Health and Safety Plan B – Mine Emergency Response Plan C – Sediment and Erosion Control Plan D – Hazardous Materials Handling Plan E – Fuel Management and Spill Contingency Plan F – Water Management Plan G – Waste Management Plan H – Reclamation Plan I – Road Design J – Mine Development Plan K – Traffic Plan L – Invasive Species Management Plan M – Barge Load-out and Marine Safety Plan N – Chance Find Procedure O – Wildlife Management Plan
  15. 15. • Overburden (est. 0.5 m thick) stripped and stockpiled as mining progresses • Concurrent revegetation where possible • ~6.4 ha total disturbed area re-covered with overburden, seeded and planted with native trees • At project completion equipment, camp; conveyors; equipment removed
  16. 16. • Department of Fisheries and Oceans Initial enquiry to establish any concerns or impact on aquatic habitat Transport Canada – Navigable Waters Protection Conceptual plans reviewed and positive preliminary response received regarding little impact to shipping • • Archeological Survey conducted with First Nations representatives and Kleanza Consulting Ltd. No evidence of ancestral remains or habitation found • Forestry assessment carried out in 2009 Very little timber of value – but will require re-assessment
  17. 17. Following issue of the Notice of Work the following action plan will commence: 1) Carry out assessment of timber value and clear once permit is issued 2) Commence application for DFO and Transport Canada permits 3) Rehabilitate existing camp and facilities 4) Start site stripping for first mining phase, including construction of sediment collection ponds 5) Construct load out facility and bring plant equipment to site

×