SlideShare a Scribd company logo
1 of 3
Download to read offline
Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017
1 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes
PMP Project Management Process Groups and their All-Hazards Planning “P” Equivalents
PMP:
Initiating
All-Hazards:
Leg of “P”
PMP:
Planning
All-Hazards:
Meetings &
Products
PMP:
Executing
All-Hazards:
Ops “O”
PMP:
Monitor &
Control
All-Hazards:
Ongoing
Operations
PMP:
Closing
All-Hazards:
DMOB &
AARs
Project
Integration
Management
4.1 Develop
project
charter
- Initial
assessment
- Create initial
ICS 201
4.2 Project
mgmt plan
- Work
towards IAP
completion
- Stand up
C&G
4.3 Direct and
Manage
Project Work
- OSC
delegates and
oversees
progress
4.4 Monitor &
Control
Project Work
4.5 Perform
Integrated
Change
Control
- OSC receives
updates from
staff
- SITL
provides
ongoing
SITREPs
4.6 Close
Project or
Phase
- Follow
established
DMOB
process
- Schedule
AAR meeting
Project Scope
Management
5.1 Plan
Scope mgmt
5.2 Collect
Requirements
5.3 Define
scope
5.4 WBS
- Identify
issues
- Create
objectives
- Strategies
- Tactics
5.5 Validate
Scope
5.6 Control
Scope
- Re-validate
or change
objectives
each ops
period
- Expand or
contract Ops
org and
assignments
as needed
Project Time
Management
6.1 Plan
Schedule
mgmt
6.2 Define
Activities
6.3 Sequence
Activities
6.4 Estimate
Activity
Resources
6.5 Estimate
Activity
Durations
6.6 Develop
Schedule
- Set ops
periods
- Tactics Mtg
- Define Ops
org
- Complete
ICS 215s
- Set meeting
schedules
- Set PAR
schedules
- Set IAP form
due times
6.7 Control
Schedule
- Adjust Ops
periods based
on conditions
- Alter
scheduling
based on
conditions
and status
updates
- Monitor
work/rest
ratios
Project Cost
Management
7.1 Plan Cost
Mgmt
7.2 Estimate
Costs
7.3 Determine
Budget
- Work to AHJ
& agency
guidelines
- FSC burn
rate & budget
7.4 Control
Costs
- Release
personnel &
equipment
when possible
Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017
2 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes
Project Quality
Management
8.1 Plan
Quality Mgmt
- All monitor
staff
productivity
- OSC monitor
progress
8.2 Perform
Quality
Assurance
- OSC makes
resource
adjustments
based on
progress
- FOBs
provide
ongoing
information
8.43 Control
Quality
- Request
completion of
ICS 214s for
AAR
- Monitor
field activity
Project Human
Resource
Management
9.1 Plan HR
Mgmt
- RESL, LSC,
FSC establish
ordering
process based
off ICS 215
9.2 Acquire
Project Team
9.3 Develop
Project Team
9.4 Manage
Project Team
- RESL advises
OSC on
potential
issues with
resources
- Supervisors
aware of their
personnel’s
work
Project
Communications
Management
10.1 Plan
Comms Mgmt
- COML create
ICS 205 from
Tactics Mtg
-LOFR create
ICS 205A
- PIO creates
media release
plan
10.1 Manage
Comms
- ICC monitors
communicatio
ns
- GIS or other
tracking
resources
- PIO provides
scheduled
media
briefings
10.3 Control
Comms
- Monitor and
regulate
traffic
- No 10 codes
- Dedicated
channels
- JIS and JIC
coordinate
- Rumor
control
Project Risk
Management
11.1 Plan Risk
Mgmt
11.2 ID Risks
11.3 Perform
Qualitative
Risk Analysis
11.4 Perform
Quantitative
Risk Analysis
11.5 Plan Risk
Responses
- SOFR create
message per
Tactics Mtg
- MEDL
creates
medical
contingencies
- Ongoing
safety and
health
monitoring
- Develop
overall
contingency
plans
11.6 Control
Risks
- Staff with
enough SOFRs
or assistants
- Re-validate
safety and
medial
planning
- Adjust
contingency
plans as
needed
Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017
3 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes
Project
Procurement
Management
21.1 Plan
Procurement
Mgmt
- FSC and LSC
monitor
contracts and
ongoing costs
12.2 Conduct
Procurements
- LSC arranges
ongoing
feeding,
housing, &
other costs
12.3 Control
Procurements
- Ensure all
requests
move through
approved
processes,
e.g. RESL, LSC,
and FSC
12.4 Close
Procurements
- FSC closes
out financials
- DOCL closes
out
documentatio
n package
Project
Stakeholder
Management
31.1 ID
Stakeholders
- Identify
IC/UC
- Speak with
AA/Org Reps
- Speak with
AHJ
31.2 Plan
Stakeholder
Mgmt
- IC, LOFR, PSC
stay aware of
VIP, AA/Org,
AHJ issues
- Stand up
policy group
13.3 Manage
Stakeholder
Engagement
- IC, LOFR,
PSC actively
engage VIP,
AA/Org, AHJ
13.4 Control
Stakeholder
Engagement
- IC, LOFR,
PSC provide
regular
updates to
VIP, AA/Org,
AHJ

More Related Content

What's hot

IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
TIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationTIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationThe Incredible Automation Day
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C
 
6.project timemanagement
6.project timemanagement6.project timemanagement
6.project timemanagementNiranjana K.R.
 
65sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.0965sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.09flau3388
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Project planningchecklist
Project planningchecklistProject planningchecklist
Project planningchecklistbakul_kaushik
 
Project management technique PERT & CPM
Project management technique PERT & CPMProject management technique PERT & CPM
Project management technique PERT & CPMSyed Academic
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Another Project hit the wall by Eng. Hisham Zeinoun
Another Project hit the wall by Eng. Hisham ZeinounAnother Project hit the wall by Eng. Hisham Zeinoun
Another Project hit the wall by Eng. Hisham ZeinounPMILebanonChapter
 
Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Richard den Dulk
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 

What's hot (20)

IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
2016 07 cau-cv
2016 07 cau-cv2016 07 cau-cv
2016 07 cau-cv
 
IQA_Project
IQA_ProjectIQA_Project
IQA_Project
 
TIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationTIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediation
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI Coordinator
 
6.project timemanagement
6.project timemanagement6.project timemanagement
6.project timemanagement
 
65sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.0965sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.09
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Project planningchecklist
Project planningchecklistProject planningchecklist
Project planningchecklist
 
Project management technique PERT & CPM
Project management technique PERT & CPMProject management technique PERT & CPM
Project management technique PERT & CPM
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
EpM
EpMEpM
EpM
 
Another Project hit the wall by Eng. Hisham Zeinoun
Another Project hit the wall by Eng. Hisham ZeinounAnother Project hit the wall by Eng. Hisham Zeinoun
Another Project hit the wall by Eng. Hisham Zeinoun
 
Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)Management Foundation implementation introduction 2014 (public)
Management Foundation implementation introduction 2014 (public)
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 

Similar to PMP and Planning Process Equivalents

11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management OverviewDavidMcLachlan1
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overviewOleksiy Rudenko
 
File 3 original
File 3 original File 3 original
File 3 original test prod1
 
File 3 original copy 2
File 3 original copy 2File 3 original copy 2
File 3 original copy 2test prod1
 
File 3 original copy 1
File 3 original copy 1File 3 original copy 1
File 3 original copy 1test prod1
 
File 3 removed 5 words 1
File 3 removed 5 words 1File 3 removed 5 words 1
File 3 removed 5 words 1test prod1
 
File 3 removed 1 word 2
File 3 removed 1 word 2File 3 removed 1 word 2
File 3 removed 1 word 2test prod1
 
File 3 removed 5 words 2
File 3 removed 5 words 2File 3 removed 5 words 2
File 3 removed 5 words 2test prod1
 
File 3 removed 1 word 1
File 3 removed 1 word 1File 3 removed 1 word 1
File 3 removed 1 word 1test prod1
 
File 3 extra slide 2
File 3 extra slide 2File 3 extra slide 2
File 3 extra slide 2test prod1
 
File 3 removed 1 word from 5 slides 1
File 3 removed 1 word from 5 slides 1File 3 removed 1 word from 5 slides 1
File 3 removed 1 word from 5 slides 1test prod1
 
File 3 removed 1 word from 5 slides 2
File 3 removed 1 word from 5 slides 2File 3 removed 1 word from 5 slides 2
File 3 removed 1 word from 5 slides 2test prod1
 
PMP Processes as per Knowledge Area in Different Phases of Project
PMP Processes as per Knowledge Area in Different Phases of ProjectPMP Processes as per Knowledge Area in Different Phases of Project
PMP Processes as per Knowledge Area in Different Phases of ProjectAbhinav Bhardwaj
 
File 3 extra four slides 2
File 3 extra four slides 2File 3 extra four slides 2
File 3 extra four slides 2test prod1
 
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...Razali Sarudin
 
File 3 extra four slides 1
File 3 extra four slides 1File 3 extra four slides 1
File 3 extra four slides 1test prod1
 

Similar to PMP and Planning Process Equivalents (20)

11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management Overview
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
 
Pmp ITTO Complete
Pmp ITTO CompletePmp ITTO Complete
Pmp ITTO Complete
 
Nine Things-in-the-PMBoK
Nine Things-in-the-PMBoKNine Things-in-the-PMBoK
Nine Things-in-the-PMBoK
 
File 3 original
File 3 original File 3 original
File 3 original
 
File 3 original copy 2
File 3 original copy 2File 3 original copy 2
File 3 original copy 2
 
File 3 original copy 1
File 3 original copy 1File 3 original copy 1
File 3 original copy 1
 
File 3 removed 5 words 1
File 3 removed 5 words 1File 3 removed 5 words 1
File 3 removed 5 words 1
 
File 3 removed 1 word 2
File 3 removed 1 word 2File 3 removed 1 word 2
File 3 removed 1 word 2
 
File 3 removed 5 words 2
File 3 removed 5 words 2File 3 removed 5 words 2
File 3 removed 5 words 2
 
File 3 removed 1 word 1
File 3 removed 1 word 1File 3 removed 1 word 1
File 3 removed 1 word 1
 
File 3 extra slide 2
File 3 extra slide 2File 3 extra slide 2
File 3 extra slide 2
 
File 3 removed 1 word from 5 slides 1
File 3 removed 1 word from 5 slides 1File 3 removed 1 word from 5 slides 1
File 3 removed 1 word from 5 slides 1
 
File 3 removed 1 word from 5 slides 2
File 3 removed 1 word from 5 slides 2File 3 removed 1 word from 5 slides 2
File 3 removed 1 word from 5 slides 2
 
PMP Processes as per Knowledge Area in Different Phases of Project
PMP Processes as per Knowledge Area in Different Phases of ProjectPMP Processes as per Knowledge Area in Different Phases of Project
PMP Processes as per Knowledge Area in Different Phases of Project
 
File 3 extra four slides 2
File 3 extra four slides 2File 3 extra four slides 2
File 3 extra four slides 2
 
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...
AFRP - OCP Project, Construction Eng., QAQC Coordinator, QCS, and HSE Focal P...
 
Knowledge areas
Knowledge areasKnowledge areas
Knowledge areas
 
File 3 extra four slides 1
File 3 extra four slides 1File 3 extra four slides 1
File 3 extra four slides 1
 

Recently uploaded

CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 

Recently uploaded (20)

Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 

PMP and Planning Process Equivalents

  • 1. Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017 1 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes PMP Project Management Process Groups and their All-Hazards Planning “P” Equivalents PMP: Initiating All-Hazards: Leg of “P” PMP: Planning All-Hazards: Meetings & Products PMP: Executing All-Hazards: Ops “O” PMP: Monitor & Control All-Hazards: Ongoing Operations PMP: Closing All-Hazards: DMOB & AARs Project Integration Management 4.1 Develop project charter - Initial assessment - Create initial ICS 201 4.2 Project mgmt plan - Work towards IAP completion - Stand up C&G 4.3 Direct and Manage Project Work - OSC delegates and oversees progress 4.4 Monitor & Control Project Work 4.5 Perform Integrated Change Control - OSC receives updates from staff - SITL provides ongoing SITREPs 4.6 Close Project or Phase - Follow established DMOB process - Schedule AAR meeting Project Scope Management 5.1 Plan Scope mgmt 5.2 Collect Requirements 5.3 Define scope 5.4 WBS - Identify issues - Create objectives - Strategies - Tactics 5.5 Validate Scope 5.6 Control Scope - Re-validate or change objectives each ops period - Expand or contract Ops org and assignments as needed Project Time Management 6.1 Plan Schedule mgmt 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule - Set ops periods - Tactics Mtg - Define Ops org - Complete ICS 215s - Set meeting schedules - Set PAR schedules - Set IAP form due times 6.7 Control Schedule - Adjust Ops periods based on conditions - Alter scheduling based on conditions and status updates - Monitor work/rest ratios Project Cost Management 7.1 Plan Cost Mgmt 7.2 Estimate Costs 7.3 Determine Budget - Work to AHJ & agency guidelines - FSC burn rate & budget 7.4 Control Costs - Release personnel & equipment when possible
  • 2. Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017 2 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes Project Quality Management 8.1 Plan Quality Mgmt - All monitor staff productivity - OSC monitor progress 8.2 Perform Quality Assurance - OSC makes resource adjustments based on progress - FOBs provide ongoing information 8.43 Control Quality - Request completion of ICS 214s for AAR - Monitor field activity Project Human Resource Management 9.1 Plan HR Mgmt - RESL, LSC, FSC establish ordering process based off ICS 215 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team - RESL advises OSC on potential issues with resources - Supervisors aware of their personnel’s work Project Communications Management 10.1 Plan Comms Mgmt - COML create ICS 205 from Tactics Mtg -LOFR create ICS 205A - PIO creates media release plan 10.1 Manage Comms - ICC monitors communicatio ns - GIS or other tracking resources - PIO provides scheduled media briefings 10.3 Control Comms - Monitor and regulate traffic - No 10 codes - Dedicated channels - JIS and JIC coordinate - Rumor control Project Risk Management 11.1 Plan Risk Mgmt 11.2 ID Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses - SOFR create message per Tactics Mtg - MEDL creates medical contingencies - Ongoing safety and health monitoring - Develop overall contingency plans 11.6 Control Risks - Staff with enough SOFRs or assistants - Re-validate safety and medial planning - Adjust contingency plans as needed
  • 3. Developed by: Kevin Pannell, VaPEM, NREMT, PSC3 August 2017 3 *Sections filled in gray had no deliverables identified by the project areas and were not matched with all-hazard products or processes Project Procurement Management 21.1 Plan Procurement Mgmt - FSC and LSC monitor contracts and ongoing costs 12.2 Conduct Procurements - LSC arranges ongoing feeding, housing, & other costs 12.3 Control Procurements - Ensure all requests move through approved processes, e.g. RESL, LSC, and FSC 12.4 Close Procurements - FSC closes out financials - DOCL closes out documentatio n package Project Stakeholder Management 31.1 ID Stakeholders - Identify IC/UC - Speak with AA/Org Reps - Speak with AHJ 31.2 Plan Stakeholder Mgmt - IC, LOFR, PSC stay aware of VIP, AA/Org, AHJ issues - Stand up policy group 13.3 Manage Stakeholder Engagement - IC, LOFR, PSC actively engage VIP, AA/Org, AHJ 13.4 Control Stakeholder Engagement - IC, LOFR, PSC provide regular updates to VIP, AA/Org, AHJ